Task Assignment Notification Summary
This Task Assignment Notification Form is a contract document issued by the Florida Department of Environmental Protection (FDEP) to DRMP, Inc., a consulting firm, for professional design and engineering services related to water system upgrades at Suwannee River State Park in Suwannee County, Florida. The contract is identified as FDEP Agreement CN225, Task Assignment TA50, with Project Number 61547C. The FDEP Contract Manager is Ralph Perkins, and the consultant representative is Paul Benvie, P.E. The project manager for FDEP is Richard Marcil. Additional sub-consultants involved include Russell Johnson Architect and ECS Florida, LLC for geotechnical and hazardous materials consulting.
The scope of services encompasses comprehensive pre-design, design, permitting, and construction administration services for replacing and upgrading the potable water system at the park, including well system replacements, new structures, and water line improvements. The contract is structured as a fixed-price agreement totaling $78,207.05, with an additional $500.00 in reimbursable costs, bringing the total task amount to $78,707.05. Reimbursable expenses include permit fees of $100.00 for the Water Management District exemption and $400.00 for the FDEP water use permit application. Services are scheduled to commence upon execution with a completion date of April 29, 2025, with all subtasks including a two-week review period from the client built into the estimated 26-week timeline. The contract includes seven major subtasks: topographic survey ($11,126.00), geotechnical investigation ($8,054.28), 60% design ($15,298.99), 90% design ($12,016.29), 100% design ($7,108.16), regulatory permitting ($5,988.54), and construction administration services ($15,205.39).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN225 TA50 FDEP 61547C
Suwannee River State Park Water System Upgrades
DRMP, Inc.
Paul Benvie, P.E. 239-206-5107 pbenvie@drmp.com
Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov
To replace and upgrade the potable water system at Suwannee River State Park, per the attached proposal dated January 23, 2024.
Richard Marcil
Upon execution $ 78,207.05 04/29/2025 $ 500.00
$ 78,707.05
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.02.05 11:32:12 -05'00'
Richard Marcil Richard Rene Marcil, III
Digitally signed by Richard Rene Marcil, III Date: 2024.02.05 12:47:13 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.02.05 15:52:24 -05'00'
Paul Benvie, P.E. Paul Benvie Digitally signed by Paul Benvie Date: 2024.02.06 12:38:21 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2024.02.09 16:34:21 -05'00'
61547C 37502000073 080039/24 675002 U3200 134000 XR $ 78,707.05
$ 78,707.05
1625 Summit Lake Drive, Tallahassee FL,32317 Phone: 850.562.9600 | Fax: 850.575.5544
January 23, 2024 DRMP Proposal #: 14-0210.050
Rene Marcil Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520
Subject: Suwannee River State Park – Water System Upgrades FDEP Agreement #CN225 – Task Assignment #50 Proposal for Professional Services
Dear Mr. Marcil:
Our understanding of the project is improvements to the potable water system within the park. This includes the replacement of the main well system and well house, replacement of the back-up well and new pole barn, replace the existing water line from the main well to the campground loop, and connection of the back-up well to the main system. For your review, DRMP, Inc., has provided a proposal summary and man-hour documentation for the services task identified below:
Please review the attached Proposal Summary and Deliverables.
Sincerely, Benjamin Lennon Benjamin Lennon, P.E.
Senior Project Manager
Attachment(s): DRMP, Inc. Proposal
CC: Paul Benvie, DRMP Randall Jernigan, DRMP
Suwannee River State Park – Water System Upgrades - Suwannee County, Florida FDEP Agreement #CN225 – Task Assignment #50 Proposal for Professional Services
Background and Purpose The purpose of this project is to replace and upgrade the potable water system at the park. The system consists of two wells – a main and back-up well. The main well pressure tank is leaking.
Improvements include
Replacement of the main well pump, treatment system, pressure tank Demo old well house, design New well house (similar size, materials) Replacement of the back-up well pump, treatment system, and larger pressure tank New pole barn to cover the back-up well, existing back-up has no structure over it Replace the galvanized piping with PVC from the main well to the campground loop New piping from the back-up well to the campground loop All applicable design will be per the Florida Building Code, 8th Edition Sub-consultants include Russell Johnson Architect and ECS Florida, LLC (ECS) Geotechnical Engineering and Hazardous Materials Consulting
Subtask 1: Pre-design Services Subtask 1a: Topographic Survey
Description: DRMP Inc., will provide labor, material, equipment, transportation, and incidentals necessary to perform a topographic survey in support of well site improvements. The two survey areas are depicted in electronic file “Suwannee Google Earth.pdf”. Said file is referenced as an attachment to this proposal.
Elements include:
Elevations at distances not to exceed 25 feet.
Horizontal location of visible above ground features and improvements.
Elevations at significant breaks in grade.
Horizontal location and species identification (common name) of trees larger than 8” (dbh).
Horizontal location of utilities from visible above ground indicators of utilities.
Horizontal location of water line from Quality Level “B” utility investigation Mapping contours at 1’ intervals.
Mapping in AutoCad Civil 3D.
Establish a minimum of Two (2) project benchmarks established from an identifiable and published benchmark.
Elevations referenced to NAVD 88.
Survey referenced horizontally to Florida State Plane Coordinate System, NAD83/2011, Florida West Zone.
Deliverable: The Consultant shall provide one (1) Topographic Survey (.pdf and .dwg format) to the Department Project Manager.
Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall begin the Survey on the subject property complete Subtask 1 within 4 weeks after the start of the project.
Subtask 1b: Geotechnical Investigation
Description: The Consultant and its sub consultant, ECS will coordinate to perform a subsurface soil investigation to aid the design team in the structural design.
Elements of the work include:
Two standard penetration test borings to a depth of 20 feet Perform soil index testing, including:
o percent fines content (ASTM D1140) o natural moisture content (ASTM D2216) o Atterberg Limits (ASTM D4318)
Written engineering report that presenting findings and recommendations, including:
o Observations from site reconnaissance including current site conditions, surface drainage features, and surface topographic conditions.
o A review of the published soil survey information and/or geologic conditions.
o A subsurface characterization and a description of the field exploration and laboratory tests performed. Groundwater concerns relative to the planned construction, if any, will be summarized.
o Final logs of the soil borings and records of the field exploration prepared in accordance with the standard practice for geotechnical engineering. A boring location plan will be included, and the results of the laboratory tests will be plotted on the final boring logs or included on a separate test report sheet.
o Recommended allowable soil bearing pressure(s) for conventional shallow foundations (spread footings) and estimates of predicted foundation settlement. If required, recommendations for suitable intermediate foundations/ground improvement options or deep foundations in the event estimated settlements of shallow foundations are not tolerable.
o Recommendations for slab-on-grade construction, including recommendations for subgrade improvements and under slab subdrainage recommendations, if necessary.
o Evaluation of the on-site soil characteristics encountered in the soil borings.
Specifically, the suitability of the on-site materials for reuse as engineered fill to support grade slabs.
o Compaction requirements and suitable material guidelines.
o Recommendations for the required site preparation and earthwork construction.
o Recommendations for additional testing and/or consultation that might be required to complete the geotechnical assessment and related engineering for this project
Deliverable: The Consultant shall provide the department with one (1) geotechnical report in electronic (.pdf) format.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost DRMP Project Manager $159.52 4 $638.08 DRMP Senior Project Surveyor $138.71 5 $693.55 DRMP Project Surveyor $110.01 7 $770.07 DRMP Survey Technician $55.81 30 $1,674.30 DRMP 3 Man Survey Crew $150.00 49 $7,350.00
$11,126.00
Subtask 1a: Topographic Survey
SUBTASK 1a TOTAL:
Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall begin the Survey on the subject property complete Subtask 1 within 6 weeks after the start of the project.
Fee:
Subtask 2: 60% Design
Description: The Consultant and their sub-consultant Russel Johnson Architect shall perform engineering services pertinent to 60% plans. The proposed scope of services shall include the following components:
Detailed construction drawings and specifications. Our services will include Demolition Plan, Site Plan, Utility Plans, Structural Plans, Electrical Plans, layout of water equipment, and details pertinent to 60% design. Electrical plans shall include: all demo of existing, new service/meter, panels, control panels, electrical circuitry, generator(s), connection of pumps/motors, basic controls, & lighting.
Structural design include: 1) Structural Design Plans: a) Foundation plan including interior and perimeter foundations, footings, piles, caissons, and grade beams as needed. b) Framing plans for all floors, roof, and ancillary structures including major member sizes noted or scheduled. c) Locate columns, beams, purlins, joists, etc. 2) Structural Specifications relating to the design elements noted above. 3) Structural wall sections detailing framing conditions, connections, etc.
unique to location. 4) Specific and typical construction details relating to the materials and construction disciplines utilized for the project.
Note: all applicable design will be per the Florida Building Code, 8th Edition.
Deliverable: The Consultant shall deliver 60% design plans and opinion of probable construction costs in .pdf format to the Department Project Manager.
Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall complete the services under Subtask 2 within 10 weeks of the start of the project.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost DRMP Project Manager $159.52 6 $957.12 ECS Principal Engineer/Geologist/Industrial Hygienist $253.89 4 $1,015.56 ECS Senior Project Engineer/Geologist/Industrial Hygienist $194.70 10 $1,947.00 ECS Project Engineer/Geologist/Industrial Hygienist $191.28 20 $3,825.60 ECS Administrative/Clerical $77.25 4 $309.00
$8,054.28
Subtask 1b: Geotechnical Investigation
SUBTASK 1b TOTAL:
Subtask 3: 90% Design
Description: Based on the FDEP review of Subtask 2 (60% Design) deliverables, the Consultant and their sub-consultant Russel Johnson Architect shall prepare detailed 90% construction drawings and specifications. Our services will include Demolition Plan, Site and Utility Plans, Structural Plans, Electrical Plans, layout of water equipment, and Details to best describe the proposed work for construction.
Deliverable: The Consultant shall deliver 90% design plans and technical specifications, and opinion of probable construction costs in .pdf format to the Department Project Manager.
Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall complete the services under Subtask 3 within 5 weeks of the completed review of the 60% design deliverables.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 8 $1,276.16 DRMP Senior Project Engineer PE $141.12 10 $1,411.20 DRMP Project Engineer PE $110.01 20 $2,200.20 DRMP Staff Engineer EI $81.79 20 $1,635.80 DRMP CADD Designer $105.23 40 $4,209.20 DRMP Secretary $47.83 4 $191.32 RJA Principal Architect $174.99 6 $1,049.94 RJA CADD Designer $75.01 7 $525.07 RJA Administrative $50.00 1 $50.00 RJA Structural Engineer $174.99 3 $524.97 RJA Structural Cadd Technician $75.01 4 $300.04 RJA Electrical Principal Engineer $174.99 3 $524.97 RJA Electrical Project Engineer $125.01 6 $750.06 RJA Electrical CAD technician $75.01 6 $450.06 RJA Electrical Administrative $50.00 4 $200.00
$15,298.99
Subtask 2: 60% Design
SUBTASK 2 TOTAL:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 8 $1,276.16 DRMP Senior Project Engineer PE $141.12 10 $1,411.20 DRMP Project Engineer PE $110.01 8 $880.08 DRMP Staff Engineer EI $81.79 8 $654.32 DRMP CADD Designer $105.23 28 $2,946.44 DRMP Secretary $47.83 1 $47.83 RJA Principal Architect $174.99 2 $349.98 RJA CADD Designer $75.01 4 $300.04 RJA Administrative $50.00 1 $50.00 RJA Structural Engineer $174.99 2 $349.98 RJA Structural Cadd Technician $75.01 2 $150.02 RJA Electrical Principal Engineer $174.99 4 $699.96 RJA Electrical Project Engineer $125.01 12 $1,500.12 RJA Electrical CAD technician $75.01 16 $1,200.16 RJA Electrical Administrative $50.00 4 $200.00
$12,016.29
Subtask 3: 90% Design
SUBTASK 3 TOTAL:
Subtask 4: 100% Design
Description: Based on the FDEP review of Subtask 5 90% Design deliverables, the Consultant and their sub-consultant Russel Johnson Architect shall perform final engineering analysis and prepare detailed construction drawings and technical specifications.
Deliverable: The Consultant shall deliver digitally signed and sealed 100% design plans and technical specifications to the Department Project Manager. The deliverable shall include digital PDFs of the construction drawings, technical specifications, Engineer’s Estimate of Quantities, opinion of probable construction costs, and Autocad (.dwg) file of the plans.
Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall complete the services under Subtask 4 within 4 weeks of the completed review of the 90% design deliverables.
Subtask 5: Regulatory Permitting
Subtask 5A: WMD Exemption
Description: The project is expected to be exempt from Suwannee River Water Management District permitting and a Request for Verification for Exemption will submitted online to the WMD.
The Consultant will pay all permit fees to be reimbursed directly up to a limiting amount of $100.00.
Additional fees beyond this allowance will require additional fee or be paid the to the review agency directly or to the consultant via a supplemental agreement. Building permit fees will be the responsibility of the Contractor.
Deliverable: The Consultant will electronically deliver a copy (.pdf) of the Water Management District Exemption to the Department Project Manager. The Consultant shall provide receipts for permit fees in .pdf format to the department manager upon invoicing.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall complete the services under Subtask 5A within 4 weeks of Subtask 3.
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 8 $1,276.16 DRMP Senior Project Engineer PE $141.12 4 $564.48 DRMP Project Engineer PE $110.01 6 $660.06 DRMP CADD Designer $105.23 7 $736.61 DRMP Secretary $47.83 2 $95.66 RJA Principal Architect $174.99 2 $349.98 RJA CADD Designer $75.01 1 $75.01 RJA Administrative $50.00 1 $50.00 RJA Structural Engineer $174.99 1 $174.99 RJA Electrical Principal Engineer $174.99 3 $524.97 RJA Electrical Project Engineer $125.01 12 $1,500.12 RJA Electrical CAD technician $75.01 12 $900.12 RJA Electrical Administrative $50.00 4 $200.00
$7,108.16SUBTASK 4 TOTAL:
Subtask 4: 100% Design
Fixed Price Cost:
Reimbursable Cost:
Total for Subtask 5A: $578.56
Subtask 5B: Water Use Permit
Description: If required, DRMP shall the submit a FDEP/SRWMD water use permit application and supporting documentation for the water system improvements. DRMP will complete the application and submit it along with an Engineering Report, cuts sheets for the equipment shown on the drawings and submit it along with the design plans to the agency. The Consultant will pay all permit fees to be reimbursed directly up to a limiting amount of $400.00.
Additional fees beyond this allowance will require additional fee or be paid the to the review agency directly or to the consultant via a supplemental agreement. Building permit fees will be the responsibility of the Contractor.
Deliverable: The Consultant will electronically deliver the application package (.pdf) to the Department Project Manager. The Consultant shall provide receipts for permit fees in .pdf format to the department manager upon invoicing.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall complete the services under Subtask 5B within 4 weeks of Subtask 3.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 3 $478.56
Subtask 5A: WMD Exemption
WMD Exemption Application Fee $100.00 Postage $0.00 Printing $0.00 Overnight Travel (if applicable) $0.00 Mileage (@ $0.445 per mile) $0.00 Reimbursable Total Cost $100.00
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 6 $957.12 DRMP Senior Project Engineer PE $141.12 12 $1,693.44 DRMP Project Engineer PE $110.01 8 $880.08 DRMP CADD Designer $105.23 16 $1,683.68 DRMP Secretary $47.83 2 $95.66
Subtask 5B: FDEP Permit
Reimbursable Cost:
Total for Subtask 5B: $5,709.98
Subtask 6: Pre-Demolition Asbestos and Lead-in-paint Assessment
Description: Based on our understanding of the subject property and plans for future activities The Consultant and its sub consultant, ECS will coordinate to perform assessments of existing materials for the presence of asbestos-containing materials and lead paint.
Asbestos Containing Materials The scope of work outlined herein will be conducted in general accordance with US EPA National Emission Standard for Hazardous Air Pollutants (NESHAP) Regulations (40 CFR 61 Subpart M) and OSHA Standard 29CFR 1926.1101 Inspection Protocol, by an EPA accredited asbestos inspector. The report will be reviewed by a Florida Licensed Asbestos Consultant (LAC), as required by statute. A comprehensive asbestos survey for asbestos-containing Materials (ACMs) and lead-based paint (LBP) will generally consist of the following items:
1. Review of previous records, if available.
2. Visual observations of friable and non-friable suspect ACMs.
3. Bulk sampling.
4. Laboratory analysis.
5. Recommendations and conclusions.
The assessment includes the collection of bulk samples of friable (easily crumbled under hand pressure) and non-friable materials suspected as containing asbestos for laboratory testing.
Multiple samples of thermal system and surfacing materials (e.g., pipe insulation, wall plaster, fireproofing, textured coatings, etc.) may be required based on OSHA and EPA regulations.
Lead in Paint and Other Surface Coatings ECS will visually observe the buildings for painted or coated surfaces. If such surfaces are observed then representative paint-chip samples will be collected to assess the potential presence of LBP hazards that may exist in the building.
Sampling activities will be performed in general accordance with FDEP/SOP FS 8100 for Contaminated Surface Sampling and ASTM E 1729 Standard Practice for Field Collection of Dried Paint Samples for Subsequent Lead Determination. The process typically involves, wearing a new pair of disposable surgical gloves, utilizing a clean chisel or equivalent sampling device to scrap and/or chip an area of the painted or coated surface, horizontally and vertically down to the substrate. The sample is then placed into a new or pre-cleaned container (such as a zip-lock bag or glass jar), sealed, labelled and sent under chain of custody to the laboratory.
Deliverable: One NESHAP Pre-Demolition Survey report for the subject property, in PDF format.
FDEP Water Use Application Fee $400.00 Postage $0.00 Printing $0.00 Overnight Travel (if applicable) $0.00 Mileage (@ $0.445 per mile) $0.00 Reimbursable Total Cost $400.00
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Schedule: The Consultant shall complete the services under this Subtask within 4 weeks of the completion of Subtask 1.
Fixed Price Cost:
Subtask 7: Construction Administration Services
Subtask 7A: Bidding Support Description: The Consultant shall answer bid questions provided by the Department and issue any Addenda needed for issuance. The Consultant or respective Subconsultants shall not answer any bid questions directly from Contractors, subcontractors or vendors and will direct all questions to the Purchasing Agent at the Department.
Subtask 7B: Shop Drawings and RFI’s Description: The Consultant shall review shop drawings pertaining to Site/Civil work and verify their accuracy with the plans and documents. The Consultant shall respond to the contractor with red line mark ups if the shop drawings are not in accordance with the plans. Markups may be approved as noted or require resubmittal. All shop drawings shall be returned to the Department for concurrence. The Consultant shall respond to contractor related questions and requests for information pertaining to Site/Civil work and verify their accuracy with the plans and documents. The Consultant shall respond to the contractor requests for information (RFI) in writing and provide this to BDC for concurrence.
Subtask 7C: Construction Phase Site Visit Description: The Consultant shall make a site visit at the 50% phase of construction or as requested by the FDEP project manager to observe as an experienced and qualified design professional the progress and quality of the executed work and to determine in general if the work is proceeding in accordance with the contract documents and permit conditions for the site work.
Subtask 7D: Construction Phase Site Visit Description: The Consultant shall make a site visit at the 75% phase of construction or as requested by the FDEP project manager to observe as an experienced and qualified design professional the progress and quality of the executed work and to determine in general if the work is proceeding in accordance with the contract documents and permit conditions for the site work.
Subtask 7E: Substantial Completion Site Visit and As-built Review Description: The Consultant will review contractor provided as-built construction survey completed by a registered surveyor and mapper in the State of Florida, for conformance to
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 4 $638.08 ECS Principal Engineer/Geologist/Industrial Hygienist $253.89 2 $507.78 ECS Senior Project Engineer/Geologist/Industrial Hygienist $194.70 4 $778.80 ECS Project Engineer/Geologist/Industrial Hygienist $191.28 8 $1,530.24 ECS Administrative/Clerical $77.25 2 $154.50
$3,609.40
Subtask 6: Pre-Demolition Asbestos Survey
6A TOTAL:
the permitted construction plans. This survey must be signed and sealed by a State of Florida Professional Surveyor and Mapper. As-Built plans shall be submitted prior to the Substantial completion site review. The Consultant shall attend the inspection for substantial completion when requested by the contractor and prepare a punch list of those items not completed and that do not meet the intent of the plans and technical specifications or need minor adjustment. The Consultant shall sign the DEP certification of substantial completion for setting forth the date of substantial completion for this project. If a water use permit is required, DRMP shall submit the Certification Of Construction Completion And Request For Clearance To Place Permitted PWS Components Into Operation form.
Deliverable(s): (These are payment triggers – what items will consultant provide to FDEP, including format, size, number, minimum content, due date, etc.)
Subtask 7A: Bidding - Documentation of any responses to RFI’s (.pdf format).
Subtask 7B: Shop Drawings and RFI’s – Copies of Stamped Shop Drawings and Documentation of any RFI’s (.pdf format).
Subtask 7C: Construction Site Visit – Observation Report of the Site Visit (.pdf format).
Subtask 7D: Construction Site Visit – Observation Report of the Site Visit (.pdf format).
Subtask 7E: Substantial Completion Site Visit – Written Summary of the As-built Review, Meeting and Certification and punch list (.pdf format).
Performance Measure: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.
Total for Subtask 7: $15,205.39
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost DRMP Project Manager $159.52 4 $638.08 DRMP Project Engineer PE $110.01 3 $330.03
RJA Electrical Project Engineer $125.01 4 $500.04
SUBTASK 7A TOTAL: $1,468.15
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 8 $1,276.16 DRMP Sr Project Engineer PE $141.12 1 $141.12 DRMP Project Engineer PE $110.01 10 $1,100.10 DRMP Staff Engineer EI $81.79 6 $490.74 DRMP Secretary $47.83 2 $95.66 RJA Principal Architect $174.99 3 $524.97 RJA Structural Engineer $174.99 3 $524.97 RJA Electrical Project Engineer $125.01 8 $1,000.08
SUBTASK 7B TOTAL: $5,153.80
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 10 $1,595.20 RJA Electrical Project Engineer $125.01 8 $1,000.08
SUBTASK 7C TOTAL: $2,595.28
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 10 $1,595.20 RJA Electrical Project Engineer $125.01 8 $1,000.08
SUBTASK 7D TOTAL: $2,595.28
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
DRMP Project Manager $159.52 15 $2,392.80 RJA Electrical Project Engineer $125.01 8 $1,000.08
SUBTASK 7E TOTAL: $3,392.88
Subtask 7: Construction Administration Services Subtask 7A - Bidding
Subtask 7B: Shop Drawings and RFI’s
Subtask 7D: Construction Phase Site Visit
Subtask 7C: Construction Phase Site Visit
Subtask 7E: Substantial Completion Site Visit & As-Built Review
NOTE: Should work effort vary from proposed professional services / anticipated agency requirements, the Consultant shall submit an additional services proposal for the Department Project Manager’s consideration to modify the agreed upon task assignment (scope of services, schedule, and fees) accordingly.
Reimbursable
Subtask 5A: WMD Exemption $100.00 $400.00
Subtask 5A: WMD Exemption Subtask 5B: FDEP Permit
N/A
4 weeks from Subtask 3 4 weeks from Subtask 3 5 weeks from Subtask 1
$3,609.40
All Subtasks with Predecessors Include 2 Week Review Period from Client Built in to Duration Total Estimated time = 26 weeks
Subtask:
Subtask 6: Pre-Demolition Asbestos Survey Subtask 7: Construction Administration Services
Summary of Fees Subtask: Fixed Price Cost
Subtask 1a: Topographic Survey
Total Reimbursable Cost: $500.00
Subtask 7: Construction Administration Services $15,205.39 Subtask 6: Pre-Demolition Asbestos Survey
Subtask 3: 90% Design $12,016.29 Subtask 4: 100% Design $7,108.16
$78,707.05
Subtask 1a: Topographic Survey $11,126.00
Subtask 2: 60% Design $15,298.99
Subtask 2: 60% Design Subtask 3: 90% Design Subtask 4: 100% Design
Project Schedule Duration 4 weeks from Start
10 weeks from Start 5 weeks from Subtask 2 4 weeks from Subtask 3
GRAND TOTAL:
Subtask 5B: FDEP Permit $5,309.98
Total Fixed Price Cost: $78,207.05
$478.56
Subtask 1b: Geotechnical Investigation $8,054.28
Subtask 1b: Geotechnical Investigation 6 weeks from Start