This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under indefinite delivery vehicle Contract CN225, Task Assignment No. 38. The project involves DRMP, Inc. (the consultant) and Madison County (project location at Ichetucknee Springs State Park). The consultant is represented by Benjamin Lennon, P.E., and FDEP's contract manager is Jeffrey Whitfield. Additional subconsultants include JBrown Professional Group, NOVA Engineering, Wastewater Technologies Inc., Tomahawk, BFBS, KeverMcKee, and WTI for specialized services including surveying, geotechnical engineering, architectural design, and construction administration.

The contract scope encompasses professional engineering services for the design and permitting of a new restroom facility at Ichetucknee Springs State Park, with a total task amount of $90,561.33, comprising $87,861.33 in fixed price costs and $2,700.00 in reimbursable permit fees. The work is structured in seven major subtasks: topographic survey ($5,608.24), geotechnical investigation ($4,404.16), 30% design ($9,714.96), 90% design ($25,338.81), 100% design ($3,743.49), regulatory permitting ($8,705.94), and construction administration services ($19,845.64). The project schedule extends approximately 32 weeks from the start date of upon execution through June 30, 2023, with each design phase incorporating two-week review periods. Services include site surveying, soil testing, preparation of construction documents at three design stages, permit applications to the Suwannee River Water Management District, Department of Health, and State Fire Marshal, and construction phase support including shop drawing review and site inspections.

View the file

Other files

File Type Posted
CN-370000-CN225-A1.pdf PDF
CN-370000-CN225-T10CO1.pdf PDF
CN-370000-CN225-T12.pdf PDF
CN-370000-CN225-T13.pdf PDF
CN-370000-CN225-T14.pdf PDF
CN-370000-CN225-T14CO1.pdf PDF
CN-370000-CN225-T14CO2.pdf PDF
CN-370000-CN225-T15.pdf PDF
CN-370000-CN225-T15CO3.pdf PDF
CN-370000-CN225-T15CO5.pdf PDF
CN-370000-CN225-T16.pdf PDF
CN-370000-CN225-T16CO1.pdf PDF
CN-370000-CN225-T17CO1.pdf PDF
CN-370000-CN225-T17CO2.pdf PDF
CN-370000-CN225-T18CO1.pdf PDF
CN-370000-CN225-T23.pdf PDF
CN-370000-CN225-T24CO2.pdf PDF
CN-370000-CN225-T27CO1.pdf PDF
CN-370000-CN225-T28CO1.pdf PDF
CN-370000-CN225-T32CO2.pdf PDF
CN-370000-CN225-T32CO5.pdf PDF
CN-370000-CN225-T34CO2.pdf PDF
CN-370000-CN225-T39.pdf PDF
CN-370000-CN225-T4.pdf PDF
CN-370000-CN225-T44.pdf PDF
CN-370000-CN225-T45.pdf PDF
CN-370000-CN225-T48.pdf PDF
CN-370000-CN225-T51.pdf PDF
CN-370000-CN225-T53.pdf PDF
CN-370000-CN225-T54.pdf PDF
CN-370000-CN225-T54CO1.pdf PDF
CN-370000-CN225-T56.pdf PDF
CN-370000-CN225-T5CO1.pdf PDF
CN-370000-CN225-T6CO1.pdf PDF
CN-370000-CN225-T6CO2.pdf PDF
CN-370000-CN225-T9.pdf PDF
CN-370000-CN225-TA1.pdf PDF
CN-370000-CN225-TA14CO4.pdf PDF
CN-370000-CN225-TA27.pdf PDF
CN-370000-CN204-TA7CO1.pdf PDF
CN-370000-CN225-CMC4.pdf PDF
CN-370000-CN225-T11.pdf PDF
CN-370000-CN225-T15CO2.pdf PDF
CN-370000-CN225-T19.pdf PDF
CN-370000-CN225-T22.pdf PDF
CN-370000-CN225-T28.pdf PDF
CN-370000-CN225-T29.pdf PDF
CN-370000-CN225-T30.pdf PDF
CN-370000-CN225-T32.pdf PDF
CN-370000-CN225-T36.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN225 38 FDEP 61363C

Ichetucknee Springs State Park Replace Restroom

DRMP

Benjamin Lennon PE 850.692.5659 blennon@drmp.com

Jeffrey Whitfield 850-245-2630 Jeffrey.Whitfield@FloridaDEP.gov

Consultant to professional engineering services needed to design and permit the construction of a new restroom at Ichetucknee Springs State Park as per proposal dated 01/18/22.

Wayne Thomas

Upon Execution $ 87,861.33 6/30/2023 $ 2,700.00

$ 90,561.33

Diane Langston A Diane Langston Digitally signed by A Diane Langston Date: 2022.02.15 08:55:05 -05'00'

Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2022.02.22 09:49:41 -05'00'

Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.02.22 10:26:58 -05'00'

Benjamin R. Lennon PE Benjamin R Lennon

2022.02.23 15:03:43-05'00'

Michael W. Foster Jr, P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2022.03.04 15:56:21 -05'00'

61363C 37502000086 080039/22 423001 U3100 131200 QK $ 90,561.33

$ 90,561.33

2882 Remington Green Circle, Tallahassee, Florida 32308 Phone: 850.562.9600 | Fax: 850.575.5544

DRMP, INC.

PRINCIPALS

Lawrence L. Smith, Jr.

Donaldson K. Barton, Jr.

Glenn J. Lusink

Jon S. Meadows

Mark D. Prochak

Mark E. Puckett

OFFICES

Asheboro, North Carolina

Boca Raton, Florida

Cary, North Carolina

Charlotte, North Carolina

Chipley, Florida

DeLand, Florida

Fort Myers, Florida

Gainesville, Florida

Jacksonville, Florida

Lakeland, Florida

Melbourne, Florida

Merritt Island, Florida

Orlando, Florida

Panama City Beach, Florida

Pensacola, Florida

Stockbridge, Georgia

Tallahassee, Florida

Tampa, Florida

Troutman, North Carolina

1.833.811.3767 www.DRMP.com

January 18, 2022 DRMP Proposal #: 14-0210.M38

Wayne Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520

Subject: Ichetucknee Springs State Park – Restroom Addition

FDEP Agreement #CN225 – Task Assignment #38 Proposal for Professional Services

Dear Mr. Thomas:

Our understanding of the project is for the design and permitting of a new restroom at Ichetucknee Springs State Park. For your review, DRMP, Inc., has provided a proposal summary and man-hour documentation for the services task identified below:

Please review the attached Proposal Summary and Deliverables.

Sincerely, Benjamin Lennon____ 1/18/2021

Benjamin Lennon, P.E. Date Project Engineer

Attachment(s): DRMP, Inc. Proposal

CC: Bryant King, P.E.

Mr. W. Thomas

Ichetucknee Springs State Park Restroom Addition- Columbia County, Florida FDEP Agreement #CN225 – Task Assignment #38

Proposal for Professional Services

Background and Purpose The purpose of this project is to provide professional engineering services needed to design the following elements at Ichetucknee Springs State Park in Madison County, Florida:

• New restroom – similar to Rainbow Springs with 5 changing rooms, 4 toilets per side

• Potential additional Family Restroom

• Block wall and metal trusses – similar to South Restroom

• Floor to have “shark” coating – will not wear or chip

• DRMP to review existing drainfield for capacity

• Any new or additional drainfield to be beside existing

• Will need advanced treatment unit (ATU) for sewage

• FDEP to provide the geo survey (check for sinkholes)

Subtask 1: Topographic Survey

Description: The Consultant, through their subconsultant JBrown Professional Group, shall provide a topographic survey in order to facilitate engineering the project site. The Topographic Survey shall be prepared in accordance with the State of Florida Standards of Practice, Chapter 5J-17, Florida Administrative Code, as set forth by the Board of Professional Surveyors and Mappers, pursuant to Section 472.027, Florida Statues.

This survey information will be tied to the NAD83 horizontal datum and NAVD88 Vertical Datum Using GPS techniques. Spot elevations will be on a 50’ grid. Contours will be drawn to 1’ intervals. Trees larger than 8” DBH will also be located. Only utilities accessible from above ground access points will be located. As part of this survey JBPro will specifically locate approximate area of the Existing drain field within the survey area.

Deliverable: The Consultant shall provide one (1) Topographic Survey (.pdf and dwg format) to the Department Project Manager.

Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.

Schedule: The Consultant shall submit the survey within 4 weeks of the start of the project.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

DRMP Project Manager $159.52 5 $797.60

JBPro Senior Project Surveyor $103.97 1 $103.97

JBPro Senior Survey Technician $61.37 15 $920.55

JBPro 2 Man Survey Crew $105.17 36 $3,786.12

$5,608.24

Subtask 1: Topographic Survey

SUBTASK 1 TOTAL:

Subtask 2: Geotechnical Investigation

Description: The Consultant shall perform geotechnical engineering services through their subconsultant NOVA Engineering. The proposed scope of services shall include the following components:

FIELD – Mobilize to site to perform four (4) 20’ SPT borings within the restroom building pad footprint.

LABORATORY – budget includes (4) wash #200 sieve tests and (4) water content tests and (2) Atterberg Limits test.

REPORT – will include design considerations for the proposed building pad.

Deliverable: The Consultant shall provide one signed and sealed geotechnical report in .pdf format to the department manager.

Schedule: The Consultant shall complete the services under Subtask 2 within 4 weeks of the start of the project.

Subtask 3: 30% Design

Description: Upon completion of the topographic survey the Consultant shall prepare and deliver a 30% design submittal. Our services will include preliminary Layout, Grading, and Details to best describe the proposed work for permitting and construction. The submittal shall include the following components:

The proposed scope of services shall include the following components:

• Cover Sheet

• Existing Conditions Sheet

• Demolition Plan

• Site Plan

• Grading and Drainage Plan

Deliverable: • At a minimum, the deliverables shall include the following:

Electronic copies of the 30% Construction Document drawings in PDF file format. The documents shall be formatted for reproduction on 22x34 paper or half size at 11x17 paper.

Electronic copies of the 30% estimate of probable construction cost in PDF file format. The documents shall be formatted for reproduction on 8-1/2”x11” paper.

Electronic copies of all additional materials required to convey the 30% design intent.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 3.5 $558.32

NOVA Staff Engineer $78.03 16 $1,248.48

NOVA Project Manager $96.32 8 $770.56

NOVA Project Engineer $96.32 6 $577.92

NOVA Senior Project Engineer $141.61 8 $1,132.88

NOVA Administrator $58.00 2 $116.00

$4,404.16

Subtask 2: Geotechnical Engineering

SUBTASK 2 TOTAL:

Schedule: The Consultant shall complete the services under Subtask 3 within 4 weeks of the completion of Subtask 1.

Subtask 4: 90% Design

Description: Based on the FDEP review of Subtask 3 (30% Design) deliverables, the Consultant shall prepare detailed construction drawings and specifications.

The proposed scope of services shall include the following components:

• Cover Sheet

• General Notes

• Demolition Plan

• Layout/Site Plan

• Details

Deliverable: The Consultant shall deliver 90% design plans and technical specifications, and opinion of probable construction costs in .pdf format to the Department Project Manager.

Schedule: The Consultant shall complete the services under Subtask 4 within 4 weeks of the completed review of the 30% design deliverables.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 4 $638.08

DRMP Senior Project Engineer PE $141.12 0.5 $70.56

DRMP Project Engineer PE $110.01 2 $220.02

DRMP Staff Engineer EI $81.79 6 $490.74

DRMP CADD Designer $105.23 16 $1,683.68

Tomahawk Registered Engineer $135.00 1 $135.00

Tomahawk Graduate Engineer $110.00 16.5 $1,815.00

Tomahawk CAD Technician/Drafting $80.00 1.5 $120.00

BFBS Partner $108.55 8 $868.40

BFBS CAD Manager $69.24 32.5 $2,250.30

BFBS Office Manager $48.10 1.5 $72.15

KeverMcKee Project Manager $155.76 2 $311.52

KeverMcKee Senior Project Engineer $155.76 4.5 $700.92

KeverMcKee Staff Engineer $72.10 2 $144.20

KeverMcKee CAD Technician $40.50 4 $162.00

KeverMcKee Clerical $32.39 1 $32.39

$9,714.96

Subtask 3: 30% Design

SUBTASK 3 TOTAL:

Subtask 5: 100% Design

Description: Based on the FDEP review of Subtask 4 (90% Design) deliverables, the Consultant shall perform final engineering analysis and prepare detailed construction drawings and technical specifications.

Deliverable: The Consultant shall deliver digitally signed and sealed 100% design plans and technical specifications to the Department Project Manager. The deliverable shall include digital PDFs of the construction drawings, technical specifications, Engineer’s Estimate of Quantities, opinion of probable construction costs, and Autocad (.dwg) file of the plans.

Schedule: The Consultant shall complete the services under Subtask 5 within 4 weeks of the completed review of the 90% design deliverables.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 10 $1,595.20

DRMP Senior Project Engineer PE $141.12 1 $141.12

DRMP Project Engineer PE $110.01 3 $330.03

DRMP Staff Engineer EI $81.79 8 $654.32

DRMP CADD Designer $105.23 30 $3,156.90

Tomahawk Principle Engineer $150.00 3 $450.00

Tomahawk Registered Engineer $135.00 5 $675.00

Tomahawk Graduate Engineer $110.00 24.5 $2,695.00

Tomahawk CAD Technician/Drafting $80.00 3.5 $280.00

BFBS Partner $108.55 18 $1,953.90

BFBS CAD Manager $69.24 110.5 $7,651.02

BFBS Interior Designer $55.38 26.5 $1,467.57

BFBS Office Manager $48.10 1.5 $72.15

KeverMcKee Project Manager $155.76 6 $934.56

KeverMcKee Senior Project Engineer $155.76 9 $1,401.84

KeverMcKee Staff Engineer $72.10 2 $144.20

KeverMcKee CAD Technician $40.50 12 $486.00

WTI Engineer/Construction Inspector $125.00 10 $1,250.00

$25,338.81

Subtask 4: 90% Design

SUBTASK 4 TOTAL:

Subtask 6: Regulatory Permitting

Subtask 6A: WMD Exemption

Description: The project is expected to be exempt from Suwannee River Water Management District permitting and a Request for Verification for Exemption will submitted online to the WMD.

Deliverable: The Consultant will electronically deliver a copy (.pdf) of the Water Management District Exemption to the Department Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Schedule: The Consultant shall complete the services under Subtask 6A within 4 weeks of Subtask 4.

Subtask 6B: Department of Health

Description: The Consultant and subconsultant Wastewater Technologies, Inc. will permit the wastewater disposal system through the Madison County Department of Health. This system includes the advanced treatment system, tanks, pumps, and drainfield.

Deliverable: The Permit will be delivered in hard copy or digital format consistent with the issuance policy of the regulatory agency.

Schedule: The permits will be delivered within 4 weeks of the 90% Design Documents.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 2 $319.04

DRMP Senior Project Engineer PE $141.12 0.5 $70.56

DRMP Project Engineer PE $110.01 1 $110.01

DRMP Staff Engineer EI $81.79 2 $163.58

DRMP CADD Designer $105.23 2 $210.46

BFBS Partner $108.55 1 $108.55

BFBS CAD Manager $69.24 15.5 $1,073.22

BFBS Interior Designer $55.38 6.5 $359.97

BFBS Office Manager $48.10 1 $48.10

WTI Principal/Professional Engineer $175.00 4 $700.00

WTI Engineer/Construction Inspector $125.00 2 $250.00

WTI CAD, Wastewater Systems As-builts $95.00 3 $285.00

WTI Administration/Clerical $45.00 1 $45.00

$3,743.49

Subtask 5: 100% Design

SUBTASK 5 TOTAL:

Subtask 6C: State Fire Marshall

Description: The Consultant, through the architectural design team, wills submit plans to the State Fire Marshall for review and approval. This task includes preparation of the application, submittal and response to all comments.

Deliverable: The Permit will be delivered in hard copy or digital format consistent with the issuance policy of the regulatory agency.

Schedule: The permits will be delivered within 4 weeks of the 90% Design Document submittal.

Subtask 6D: Permit Fees

Description: The Consultant will pay all permit fees to be reimbursed directly up to a limiting amount of $2,700.00.

We estimate the following allowances:

• SRWMD $100

• Department of Health $600

• State Fire Marshal $2000

Additional fees beyond this allowance will require additional fee or be paid the to the review agency directly or to the consultant via a supplemental agreement. Building permit fees will be the responsibility of the

Contractor.

Deliverable: The Consultant shall provide receipts for permit fees upon invoicing

Schedule: N/A

Subtask 7: Construction Administration Services

Subtask 7A: Bidding Support

Description: The Consultant shall answer bid questions provided by the Department and issue any Addenda needed for issuance. The Consultant or respective Subconsultants shall not answer any bid questions directly from Contractors, subcontractors or vendors and will direct all questions to the Purchasing Agent at the Department.

Subtask 7B: Shop Drawings and RFI’s

Total Fixed Price

Cost

DRMP Project Manager $159.52 3 $478.56

$478.56

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 4 $638.08

DRMP Project Engineer PE $110.01 1 $110.01

DRMP Staff Engineer EI $81.79 16 $1,308.64

WTI CAD, Wastewater Systems As-builts $95.00 13 $1,235.00

$3,291.73

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 3 $478.56

BFBS Partner $108.55 4 $434.20

BFBS CAD Manager $69.24 1 $69.24

BFBS Interior Designer $55.38 1 $55.38

BFBS Office Manager $48.10 1 $48.10

Tomahawk Registered Engineer $135.00 3 $405.00

Tomahawk Graduate Engineer $110.00 1.5 $165.00

Tomahawk CAD Technician/Drafting $80.00 0.5 $40.00

KeverMcKee Project Manager $155.76 2 $311.52

KeverMcKee Senior Project Engineer $155.76 1 $155.76

KeverMcKee CAD Technician $40.50 1 $40.50

KeverMcKee Clerical $32.39 1 $32.39

$2,235.65

Firm Name Expense Type Unit Price Quantity Total NTE Cost

DRMP Permit Fee(s) - Not to Exceed $2,700.00 NTE $2,700.00

$2,700.00

$2,700.00

$8,705.94

Subtask 6: Regulatory Permitting

Subtask 6A: WMD Exemption

6C TOTAL:

Subtask 6D: Permit Fees

REIMBURSABLE EXPENSE SUBTOTAL:

SUBTASK 6D Total:

SUBTASK 6 Grand Total:

6A TOTAL:

Subtask 6B: Department of Health

6B TOTAL:

Subtask 6C: State Fire Marshall

Description: The Consultant shall review shop drawings pertaining to Site/Civil work and verify their accuracy with the plans and documents. The Consultant shall respond to the contractor with red line mark ups if the shop drawings are not in accordance with the plans. Markups may be approved as noted or require resubmittal. All shop drawings shall be returned to the Department for concurrence. The Consultant shall respond to contractor related questions and requests for information pertaining to Site/Civil work and verify their accuracy with the plans and documents. The Consultant shall respond to the contractor requests for information (RFI) in writing and provide this to BDC for concurrence.

Subtask 7C: Construction Phase Site Visit

Description: The Consultant shall make a site visit during construction (likely at the 50% phase of construction) or as requested by the FDEP project manager to observe as an experienced and qualified design professional the progress and quality of the executed work and to determine in general if the work is proceeding in accordance with the contract documents and permit conditions for the site work.

Subtask 7D: Substantial Completion Site Visit and As-built Review

Description: The Consultant will review contractor provided as-built construction survey completed by a registered surveyor and mapper in the State of Florida, for conformance to the permitted construction plans. This survey must be signed and sealed by a State of Florida Professional Surveyor and Mapper. As-Built plans shall be submitted prior to the Substantial completion site review. The Consultant shall attend the inspection for substantial completion when requested by the contractor and prepare a punch list of those items not completed and that do not meet the intent of the plans and technical specifications or need minor adjustment. The Consultant shall sign the DEP certification of substantial completion for setting forth the date of substantial completion for this project.

Subtask 7E: Additional Site Visit

Description: The Consultant shall attend the inspection as needed when requested in writing by the DEP project manager to observe as an experienced and qualified design professional the progress and quality of the executed work and to determine in general if the work is proceeding in accordance with the contract documents and permit conditions for the site work.

Deliverable(s) & Schedule: (These are payment triggers – what items will consultant provide to FDEP, including format, size, number, minimum content, due date, etc.)

• Subtask 8A: Bidding - Documentation of any responses to RFI’s (.pdf format).

• Subtask 8B: Shop Drawings and RFI’s – Copies of Stamped Shop Drawings and Documentation of any RFI’s (.pdf format). Reviews and Responses will be returned within 7 days of receipt.

• Subtask 8C: Construction Site Visit – Observation Report of the Site Visit (.pdf format). Report will be submitted within 7 days of the site visit.

• Subtask 8D: Substantial Completion Site Visit – Written Summary of the As-built Review, Meeting and Certification and punch list (.pdf format). Report will be submitted within 7 days of the site visit and receipt of as-builts.

• Subtask 8E: Additional Site Visit – Observation Report of the Site Visit (.pdf format). Report will be submitted within 7 days of the site visit.

Performance Measure: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.

Cost

DRMP Project Manager $159.52 6 $957.12

Tomahawk Registered Engineer $135.00 4.5 $607.50

KeverMcKee Senior Project Engineer $155.76 2.5 $389.40

BFBS Partner $108.55 22 $2,388.10

SUBTASK 7A TOTAL: $4,342.12

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

DRMP Sr Project Engineer PE $141.12 2 $282.24

DRMP Project Engineer PE $110.01 8 $880.08

DRMP Staff Engineer EI $81.79 4 $327.16

DRMP Secretary $47.83 2 $95.66

Tomahawk Registered Engineer $135.00 2 $270.00

Tomahawk Graduate Engineer $110.00 0.5 $55.00

Tomahawk Intern $80.00 0.5 $40.00

Tomahawk CAD Technician/Drafting $80.00 0.75 $60.00

Tomahawk Clerical Support $60.00 2 $120.00

BFBS Partner $108.55 36 $3,907.80

BFBS CAD Manager $69.24 9 $623.16

BFBS Interior Designer $55.38 4 $221.52

BFBS Office Manager $48.10 2 $96.20

KeverMcKee Project Manager $155.76 1 $155.76

KeverMcKee Senior Project Engineer $155.76 6 $934.56

KeverMcKee Staff Engineer $72.10 3 $216.30

KeverMcKee Clerical $32.39 2 $64.78

WTI Engineer/Construction Inspector $125.00 5 $625.00

SUBTASK 7B TOTAL: $10,251.38

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

Tomahawk Registered Engineer (Mechanical & Elec) $135.00 9.5 $1,282.50

BFBS Partner $108.55 8 $868.40

BFBS Office Manager $48.10 1 $48.10

KeverMcKee Project Manager $155.76 6.5 $1,012.44

KeverMcKee Clerical $32.39 1 $32.39

SUBTASK 7C TOTAL: $4,519.99

Subtask 7: Construction Administration Services

Subtask 7A - Bidding

Subtask 7B: Shop Drawings and RFI’s

Subtask 7C: Construction Phase Site Visit

Cost

DRMP Project Manager $159.52 8 $1,276.16

Tomahawk Registered Engineer (Mechanical & Elec) $135.00 9.5 $1,282.50

BFBS Partner $108.55 10 $1,085.50

BFBS Office Manager $48.10 1 $48.10

WTI Principal/Professional Engineer $175.00 4 $700.00

WTI Engineer/Construction Inspector $125.00 4 $500.00

KeverMcKee Project Manager $155.76 6.5 $1,012.44

KeverMcKee Clerical $32.39 1 $32.39

SUBTASK 7D TOTAL: $5,937.09

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

Tomahawk Registered Engineer (Mechanical & Elec) $135.00 9.5 $1,282.50

BFBS Partner $108.55 8 $868.40

BFBS Office Manager $48.10 1 $48.10

SUBTASK 7E TOTAL: $3,475.16

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

Tomahawk Registered Engineer (Mechanical & Elec) $135.00 9.5 $1,282.50

BFBS Partner $108.55 8 $868.40

BFBS Office Manager $48.10 1 $48.10

KeverMcKee Project Manager $155.76 6.5 $1,012.44

KeverMcKee Clerical $32.39 1 $32.39

SUBTASK 7F TOTAL: $4,519.99

Subtask 7D: Substantial Completion Site Visit & As-built Review

Subtask 7E: Final Site Visit

Subtask 7F: Additional Construction Phase Site Visit

NOTE: Should work effort vary from proposed professional services / anticipated agency requirements, the Consultant shall submit an additional services proposal for the Department Project Manager’s consideration to modify the agreed upon task assignment (scope of services, schedule, and fees) accordingly.

Reimbursable

Subtask 6A: WMD Exemption

Subtask 6B: Department of Health

$2,700.00

4 weeks from Subtask 4

Subtask 6C: State Fire Marshall 4 weeks from Subtask 4

N/A

Subtask 7A - Bidding N/A

Subtask 7B: Shop Drawings and RFI’s N/A

Subtask 7C: Construction Phase Site Visit N/A

Subtask 7D: Substantial Completion Site Visit & As-built Review

Subtask 7E: Final Site Visit

Subtask 7F: Additional Construction Phase Site Visit

All Subtasks with Predecessors Include 2 Week Review Period from Client Built in to Duration

Total Estimated time = 32 weeks

Subtask 7F: Additional Construction Phase Site Visit $4,519.99

N/A

Summary of Fees

Subtask: Fixed Price Cost

Subtask 1: Topographic Survey $5,608.24

Subtask 5: 100% Design $3,743.49

$478.56

$3,291.73

Subtask 6C: State Fire Marshall $2,235.65

Subtask 2: Geotechnical Engineering $4,404.16

Subtask 3: 30% Design $9,714.96

Subtask 4: 90% Design $25,338.81

Subtask 7C: Construction Phase Site Visit $4,519.99

Subtask 7D: Substantial Completion Site Visit & As-built Review $5,937.09

Subtask 7E: Final Site Visit $3,475.16

Subtask 6D: Permit Fees

Subtask 7A - Bidding $4,342.12

Subtask 7B: Shop Drawings and RFI’s $10,251.38

Project Schedule

Subtask: Duration

Subtask 1: Topographic Survey 4 weeks from Start

Subtask 2: Geotechnical Engineering 4 weeks from Start

Total Fixed Price Cost: $87,861.33

Total Reimbursable Cost: $2,700.00

GRAND TOTAL COST: $90,561.33

Subtask 6A: WMD Exemption 4 weeks from Subtask 4

Subtask 6B: Department of Health

Subtask 6D: Permit Fees

N/A

N/A

Subtask 3: 30% Design 8 weeks from Start

Subtask 4: 90% Design 6 weeks from Subtask 3

Subtask 5: 100% Design 6 weeks from Subtask 4