This is a Task Assignment Change Order Form (Change Order No. 01) issued by the Florida Department of Environmental Protection (FDEP) for the Honeymoon Island State Park Septic to Sewer Project. The change order involves FDEP, the consultant George & Associates, Consulting Engineers, Inc., and the subconsultant CPH, LLC. The contract is identified as FDEP Contract No. CN214, Task Assignment No. 40, and Project No. 6A008, with an original task execution date of July 29, 2022, and task end date of September 15, 2024.
The change order authorizes gopher tortoise survey services consisting of two subtasks: Subtask 5a, a 100% Gopher Tortoise Survey of the project area with deliverables including field maps, burrow location maps in PDF format, and GIS shapefiles, with a fixed price cost of $7,941.98 and reimbursable costs of $578.00 for a subtask total of $8,519.98; and Subtask 5b, a re-survey of gopher tortoise burrows approximately 90 days prior to construction commencement with identical deliverables, with a fixed price cost of $4,844.38 and reimbursable costs of $578.00 for a subtask total of $5,422.38. The overall total cost for the change order is $13,942.36, comprising total fixed costs of $12,786.36 and total reimbursable costs of $1,156.00. Payment is contingent upon FDEP approval of deliverables for each subtask. The change order does not modify the task timeline, with a net change of zero days from the original end date.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN214 40 01 6A008
Honeymoon Island Septic to Sewer
George & Associates
Robert George, PE 850.521.0344 rgeorge@gaceng.net
Ralph Perkins Ralph Perkins ralph.perkins@floridadep.gov
Gopher Tortoise Services per the attached proposal dated 2/2/2023.
$ 728.66 $ 113,689.34 $ 114,418.00 $ 728.66 $ 113,689.34 $ 114,418.00
$ 1,156.00 $ 12,786.36 $ 13,942.36 $ 1,884.66 $ 126,475.70 $ 128,360.36
7/29/2022
9/15/2024
9/15/2024
9/15/2024
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.03 09:59:52 -05'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.02.03 10:19:24 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.03 10:46:13 -05'00'
Robert George PE Robert D George Digitally signed by Robert D George Date: 2023.02.03 11:07:21 -05'00' 2/3/2023
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.02.07 10:44:13 -05'00'
6A008 CSFRF 37504008120 085154/22 000286 U3100 131500 AD $ 13,942.36
$ 13,942.36
1967 COMMONWEALTH LANE, SUITE 200 - TALLAHASSEE, FLORIDA 32303
PHONE 850-521-0344 - FAX 850-521-0345
www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION
February 2, 2023
Ms. Theresa Carron Florida Department of Environmental Protection Division of Recreation & Parks Bureau of Design and Construction Project Manager 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: CN214 TA40: TACO#1
Honeymoon Island State Park Septic to Sewer
Dear Ms. Carron:
For your review, George & Associates, Consulting Engineers, Inc. has prepared a Task Assignment Change Order #1, for the Honeymoon Island State Park Septic to Sewer Project.
Upon conducting the on site review, G&A observed gopher tortoises and burrows within the project area. Park staff also provided information of known gopher tortoise locations. It was determined that a gopher tortoise survey would be necessary to provide accurate and thorough design documents for this project. Our office has obtained a fee proposal from CPH, LLC. to complete the gopher tortoise survey.
Please review the attached Proposal Summary and deliverables.
Sincerely, Robert D. George George & Associates, Consulting Engineers, Inc.
Honeymoon Island State Park Honeymoon Island State Park Septic to Sewer
TACO#1
CN214 TA40
Subtask 5a: Gopher Tortoise Survey Description: G&A and its subconsultant CPH, LLC. will conduct a 100% Gopher Tortoise Survey of the proposed project area. Gopher tortoise burrows will be flagged and numbered in the field and located with a hand held GPS. A map of the burrow locations including the coordinates and status (potentially occupied or abandoned) of each burrow.
ArcGIS shapefiles will also be provided.
Deliverables:
Field maps and notes, if requested Burrow location map in pdf format GIS shapefiles of surveyed areas, transect, and burrow locations
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 5a � Gopher Tortoise Survey
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC
Principal Environmental Scientist
$120.51 4 $482.04
CPH, LLC Senior Environmental Scientist $101.64 36 $3,659.04 CPH, LLC Environmental Scientist $71.45 20 $1,429.00 CPH, LLC GIS Analyst $76.67 20 $1,533.40 George & Associates Project Manager $129.00 6.5 $838.50
Fixed Price Total Cost: $ 7,942.02
Reimbursable Cost:
Overnight Travel (if applicable)
$400.00
Mileage (400 @ $0.445/mile) $178.00
Reimbursable Total Cost $578.00 Total for Subtask 5a: $8,520.02 Subtask 5b: Re Survey for Gopher Tortoise Burrows Description: G&A and its subconsultant CPH, LLC. will re survey the project area approximately 90 days prior to construction commencement. The survey will confirm that there arte no burrows within 25 feet of the proposed construction or, if there are burrows within 25 feet of the proposed construction, the re survey will be used for the Florida Fish and Wildlife Conservation Commission (FFWCC) permitting. The burrow locations and status will be updated on the burrow location map.
$7,941.98
8,519.98 are
Deliverables:
Field maps and notes, if requested
Burrow location map in pdf format GIS shapefiles of surveyed areas, transect, and burrow locations.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 5b � Gopher Tortoise Survey
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Senior Environmental Scientist $101.64 24 $2,439.36 CPH, LLC Environmental Scientist $71.45 20 $1,429.00 CPH, LLC GIS Analyst $76.67 6 $460.02 George & Associates Project Manager $129.00 4 $516.00
Fixed Price Total Cost: $4,844.38
Reimbursable Cost:
Overnight Travel (if applicable)
$400.00
Mileage (400 @ $0.445/mile) $178.00
Reimbursable Total Cost $578.00 Total for Subtask 5b: $5,422.38
Project Schedule:
Activity Duration (calendar days)
Dates
Gopher Tortoise Survey 21 Within 3 weeks after notice to proceed
Burrow Location Map and Shapefiles 14 Within 2 weeks after completion of survey
Re Survey 14 Approximately 90 days prior to construction. Within 2 weeks of notification by client
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 5a � Gopher Tortoise Survey $7,942.02 $578.00
Subtask 5b � Re survey for Gopher Tortoise Burrows $4,844.38 $578.00
Total Fixed Cost: $12,786.40
Total Reimbursable Cost $1,156.00
Overall Total Cost: $13,942.40
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
$7,941.98