CN-370000-CN214-T24.pdf
PDF 297 KB Posted
- Contract number
- CN214
- Issued by
- Florida
About this file
This Task Assignment Notification Form (CN214-TA24) represents an indefinite delivery task assignment issued by the Florida Department of Environmental Protection (FDEP) to George & Associates Consulting Engineers, Inc. for inspection and permitting services related to the Port B Restoration project at Dagny Johnson Key Largo Hammock Botanical State Park. The consultant representative is Robert George, while the FDEP Contract Manager is Mae Roth and the Project Manager is Paul Rice. The task assignment was executed on December 29, 2017, with a completion date of June 30, 2018.
The scope of work consists of four subtasks: pre-construction meeting preparation, on-site field inspections during the main construction phase (4 weeks), on-site field inspections during the final construction phase (4 weeks), and an end-of-project summary report. The contract employs a fixed-price structure for labor combined with reimbursable expenses. The total task amount is $27,784.32, comprising a fixed price cost of $26,621.22 and cost reimbursement not to exceed $1,163.10. Cost breakdown by subtask includes: Subtask 1 at $1,610.76 (fixed price $1,558.38 plus reimbursables $52.38); Subtask 2 at $15,629.76 (fixed price $14,935.56 plus reimbursables $694.20); Subtask 3 at $9,078.60 (fixed price $8,662.08 plus reimbursables $416.52); and Subtask 4 at $1,465.20 (fixed price only). Reimbursable expenses include mileage at $0.445 per mile, printing, and related travel costs. Payment is to be made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Em·ironmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature FDEP Contract No.: I Task Assignment No.: Owner's Name: ! Project No.: CN214 TA24 FDEP-D5-JPCRSP 50423-190A Project Location: Project Name: Dagny Johnson Key Largo Hammock Botanical State Park Port B Restoration Consultant Name:
George & Associates Consulting Engineers, Inc.
Consultant Representative: Phone: Email : Robert George 850-521-0344 rgeorge@gaceng.net FDEP Contract Manager: Phone: Email: Mae Roth 850-245-2781 mae.roth@dep.state.tl.us Description of Task:
Provide inspection and permitting services for Port B Restoration at Dagny Johnson Key Largo Hammock Botanical State Park. See consultant's proposal dated - 12/11/2017.
Project Manager: Paul Rice
Start Date: I Upon execution Completion Date: I June 30, 2018
Beth Haslage
Budget Representative, FDEP
Paul Rice
Project Manager, FDEP
Mae Roth
Contract Manager, FDEP Robe11 George
Consultant
Michael W. Foster, Jr. P.E.
Contract Authority, FDEP
Proiect # Grant# 50423
29 digit FLAIR Code:
Or2 Code 37505018190
Sclte<lule Fixed Price Cost: $26,621.22
Cost Reimbursement not to exceed: $1,163.10 Total Task Amount: $27,784.32
Approval Sig11atures:
Beth Haslage DigitallyslgnedbyBethHaslage Date: 2017.12.2914:51 :42-05'00'
Signature
Paul Rice Signature
Dig,lally signed by Paul Rice Dale. 2017 1213 15 18.28-05'00'
Mae Roth D1grtaiy slgned by Mae Roth Dale: 2017.12 29 14·57 58-05'00'
Signa~ ~
Sit fe
Date
Date
Date olte 1
Cat/Year Fund Module Object Code EO
080039/16 423001 U3200 134000 QK
Total:
Amount $27,784.32
$ 0.00
Page I of I
December 11, 2017
Paul Rice, Park Manager John Pennekamp Coral Reef State Park
George & Associates Consulting Engineers, Inc.
Dagny Johnson Key Largo Hammock Botanical State Park
P.O. Box 370487 Key Largo FL 33037
RE: CN214-TA24
Dagny Johnson Key Largo Hammock
Botanical State Park - Port B Restoration (50423-190A)
Dear Paul;
For your review, George & Associates, Consulting Engineers, Inc. is submitting Task Assignment
No. 24 for Dagny Johnson Key Largo Hammock Botanical State Park - Port B Restoration.
Attached is the proposal summary and man-hour documentation for the services identified below.
Please review the attached Proposal Summary and deliverables.
r
One Source. Many Solutions.
1967 COMMONWEAL TH LANE, SUITE 200, TALLAHASSEE, FLORIDA 32303 • PHONt: 850.521.0344 • FAX 850.521.0345 Cl\·11. t'."iGINEERING • f.N\·1RONMF.NTAL ENGINF:t:fllNG • TIIANSf'ORTATION F.NGINl'.r:Kl'1G • ~Y~Tt:MS !'LANNING • 1.A;>iD·U!x: 1'1.l\''li'11NG
Port B Restoration Dagny Johnson Key Largo State Park
CN214-TA24
Subtask 1: Pre-Construction Meeting
Description: Preparation for and attendance for pre-bid meeting including creating copies of reference documents and minor support documents.
Deliverables: George & Associates Consulting Engineers, Inc. will provide electronic documentation of scope of work, project maps, photos, meeting minutes, and sign-in sheets.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1 Flrm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Metric Engineering, Inc. Sr. Environmental $180.30 1 $180.30
Construction Administrator Metric Engineering, Inc. Environmental Construction $66,36 8 $530.88
Inspector II Metric Engineering, Inc. Environmental Construction $73.65 8 $589.20
Inspector I George & Associates Project Manager $129.00 2 $258.00 Consulting Engineers, Inc.
Fixed Price Total Cost: $1558.38
Reimbursable Cost
Postage N/A Printing 100 sheets at $0.15/sheet = $15 Overnight Travel N/A (if applicable) Mileage(@ $0.445 per mile) 84 miles {42 miles each way to Pennekamp) x 1 trip =$37.38 Reimbursable Total Cost $52.38
Total for Subtask 1: $1,610.76
Subtask 2: On-site field inspections and reporting (Main Construction Phase - 4 weeks) Description: Daily inspection/monitoring of restoration activities (removal of buildings, fill, and asphalt, vegetation trimming and planting as needed) for compliance with the contract and governing laws/permits, providing summary logs/reports of contractor activities. Assumes a maximum of 20 days of construction inspection (4 weeks at 5 work days per week, 8 hours of on-site work per day, 9 hours per day total including travel) .
One Source. Many Solutions.
Deliverable: Weekly summary of restoration activities, end of project summary report.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2 Firm Name Position Classification Hourly Hours Total Fixed
Rate Price Cost
Metric Sr. Environmental $180.30 4 $721.20
Construction Administrator {1/week}
Metric Sr. Environmental $111.18 16 $1,778.88 Construction Inspector {4/week}
Metric Environmental Construction $73.65 36 $2,651.40
Inspector I (9/week)
Metric Environmenta I Construction $66.36 128 $8,494.08
Inspector II {32/week)
George & Associates, Project Manager $ 129.00 10 $1,290.00
Consulting Engineers, Inc.
Fixed Price Total Cost: $14,935.56
Reimbursable Cost: (if applicable - provide for each task in which reimbursables are required)
Postage N/A Printing N/A Overnight Travel N/A Mileage(@ $0.445 per mile} 39 miles/direction = 78 miles round-trip, x 20 trips = 1,560 miles
Reimbursable Total Cost $694.20
Total for Subtask 2: $15,629.76 (Fixed Price Cost+ Reimbursable)
Subtask 3: On-site field inspections and reporting (Final Construction Phase - 4 weeks)
Description: Inspection/monitoring of restoration activities {removal of buildings, fill, and asphalt, vegetation trimming and planting as needed) for compliance with the contract and governing laws/permits, providing summary logs/reports of contractor activities. Assumes a maximum of 12 days of construction inspection (4 weeks at 3 work days per week, 8 hours of on-site work per day, 9 hours per day total including travel}.
Deliverable: Weekly summary of restoration activities, end of project summary report.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost·
Subtask 3 Firm Name Position Classification Hourly Hours Total Fixed
Rate Price Cost Metric Sr. Environmental $180.30 4 $721.20
Construction Administrator (1/week) Metric Environmental Construction $66.36 108 $7,166.88
Inspector II (27/week) George & Associates, Project Manager $ 129.00 6 $ 774.00 Consulti~g Engineers, Inc.
Fixed Price Total Cost: $8,662.08
Reimbursable Cost· (if applicable - provide for each task in which reimbursables are required}
Postage N/A Printing N/A Overnight Travel N/A Mileage(@ $0.445 per mile) 39 miles/direction = 78 miles round-trip, x 12 trips = 936 miles Reimbursable Total Cost $416.52
Total for Subtask 3: $ 9,078.60 (Fixed Price Cost+ Reimbursable)
Subtask 4: End of Project Summary Report Description: Creation of a report that documents contractor activities throughout the project to demonstrate compliance with contract documents and depict the final results including photo documentation, along with a punch-list of any items remaining for project close-out.
Deliverable: End of Project Summary Report (delivered electronically)
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4 Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost - ·- Metric Sr. Environmental $180.30 2 $360.60
Construction Administrator Metric Sr. Environmental $111.18 4 $444.72
Construction Inspector Metric E nvironmenta I Construction $66.36 8 $530.88
Inspector II George & Associates, Project Manager $ 129.00 1 $129.00 Consulting Engineers, Inc.
Fixed Price Total Cost: $1,465.20 Total for Subtask 4: $1,465.20
One Source. Many Solulions.
Project Schedule:
Activity Duration (Calendar Days) Dates
Subtask 1: Pre-Construction 1 TBD
Meeting
Subtask 2: On-site Inspection 28 (4 weeks) TBD
Main construction phase
Subtask 3: On-site Inspection 28 (4 weeks) TBD
Final construction phase
Subtask 4: Summary Report 5 TBD
Summarv of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1: Pre-Construction $1,558.38 $ 52.38
Meeting
Subtask 2: On-site Inspection $14,935.56 $694.20
Main constr~~tion phase Subtask 3; On-site Inspection $8,662.08 $416.52
Final construction phase
Subtask 4: Summary Report $1,465.20 $0
Total Fixed Price Cost: $26,621.22 Total Reimbursable Cost: $1,163.10
Overall Total Cost: $27,784.32 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.