CN-370000-CN214-T37.pdf
PDF 2 MB Posted
- Contract number
- CN214
- Issued by
- Florida
About this file
Document Summary
This is a Task Assignment Notification Form (Task Assignment No. 37) under Florida Department of Environmental Protection (FDEP) Contract CN214, executed between FDEP and George & Associates Consulting Engineers, Inc. The contract is managed by FDEP's Bureau of Design and Construction, with project oversight by Wayne Thomas (Project Manager) and Alyssa Skehan (FDEP Contract Manager). The project is located at Florida Caverns State Park in Florida, with coordination involving the City of Marianna Planning & Zoning Department and Water/Wastewater Division, as well as subcontractor Community Trail Design, LLC.
The contract tasks involve providing conceptual planning and design services for a new 90-unit RV campground and mountain bike trail at Florida Caverns State Park. Services are organized into five subtasks: (1A) on-site project review and preliminary site investigations ($5,769.57); (1B) infrastructure review and assessment ($6,245.10); (1C) conceptual planning with three proposed layouts and trail alignments ($28,447.66); (1D) preferred conceptual plan development and 90% mountain bike trail alignment ($14,305.58); and (1E) final design report and 100% mountain bike trail plans ($17,015.06 fixed price plus $1,070.00 reimbursable costs for travel, mileage, and permitting). The total contract value is $72,852.97, comprised of $71,782.97 in fixed price costs and $1,070.00 in reimbursable expenses. The project execution commenced upon contract signature in November 2021, with a completion date of June 30, 2023. Payment is contingent upon FDEP approval of deliverables for each subtask. The scope explicitly excludes full design plans (60%, 90%, and 100% drawings), additional professional services (survey, civil, structural, geotechnical, environmental, architectural, mechanical, electrical, and plumbing design), and permitting coordination beyond the initial exemption request.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN214 37 FDEP 61351C
Florida Caverns State Park New Campground
George & Associates Consulting Engineers
Brian Miller, PE 850-521-0344 bmiller@gaceng.net
Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov
Consultant to provide conceptual planning and design services for a new campground and mountain bike trail to be located at Florida Caverns State Park as per proposal dated 10/26/21.
Wayne Thomas
Upon Execution $ 71,782.97 6/30/2023 $ 1,070.00
$ 72,852.97
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.11.08 16:51:22 -05'00'
Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2021.11.09 08:25:59 -05'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.11.09 08:40:49 -05'00'
Robert George Robert D George Digitally signed by Robert D George Date: 2021.11.30 10:29:17 -05'00'
11/30/2021
Michael W. Foster Jr., P.E. Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2021.12.02 15:16:45 -05'00'
61351C 37501000025 080039/22 423001 U3200 131500 QK $ 72,852.97
$ 72,852.97
1967 COMMONWEALTH LANE, SUITE 200 - TALLAHASSEE, FLORIDA 32303
PHONE 850-521-0344 - FAX 850-521-0345
www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION
October 26, 2021
Mr. Wayne Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: CN214‐TA37: Florida Caverns State Park – New Campground + Mountain Bike Trail
Dear Mr. Thomas:
For your review, George & Associates, Consulting Engineers, Inc. has prepared a fee proposal summary and man‐hour documentation for the proposed Conceptual Planning services for the Florida Caverns State
Park – New Campground + Mountain Bike Trail. Tasks include on‐site reviews, preliminary investigations, infrastructure review and assessment, conceptual level planning, project coordination with Mountain Bike
Consultant, recommendation of preferred conceptual plan, meetings with the Department, initial conceptual cost estimating, and final Mountain Bike Trail alignment with plans and scope of work suitable for bidding.
Please review the attached Proposal Summary and deliverables.
Sincerely, Robert George, P.E.
George & Associates, Consulting Engineers, Inc.
Florida Caverns State Park
New Campground & Mountain Bike Trail
CN214‐TA37
Subtask 1A: On‐Site Project Review Preliminary Site Investigations
Description: George & Associates, Consulting Engineers, Inc. (G&A) will conduct a site visit with Florida
Park Service personnel to verify existing site conditions. Prior to the meeting G&A developing GIS base file, LiDAR, and aerial exhibits for review during the meeting. G&A will prepare the kickoff meeting agenda with sign‐in sheet and discussion points to be reviewed during the meeting.
On‐site project review will consist of observing the proposed RV campground site, mountain bike trail, potential trailhead locations, and ingress/egress locations for the recreational vehicles and day‐trip mountain bike trail users.
Upon completion of site visit the consultant will document the meeting minutes and summarize the findings of the field review. Also included will be establishing the next steps moving forward with the project, the critical path elements from a scheduling standpoint, and any outstanding action items.
Deliverable:
Site visit meeting minutes, pdf
Preliminary Investigation Report, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A ‐ On‐Site Project Review Preliminary Site Investigations
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
George & Associates Chief Engineer $203.43 7 $1,424.01
George & Associates Project Manager $129.00 15 $1,935.00
George & Associates Project Engineer II $76.44 24 $1,834.56
George & Associates Sr. Engineering Technician $72.00 8 $576.00
Fixed Price Total Cost: $5,769.57
Total for Subtask 1A: $5,769.57
Subtask 1B: Infrastructure Review and Assessment
Description: G&A will perform an onsite review and assessment of existing infrastructure. This will help to determine if initial infrastructure is adequate or what additional upgrades will be required. G&A will coordinate with the City of Marianna Planning & Zoning department for the proposed project. G&A will also reach out to the City of Marianna Water / Wastewater Division to review water/sewer infrastructure in the area and confirm that the City’s utilities have sufficient capacity to handle the proposed improvements.
The site visit will include fire flow testing of the existing potable watermain to verify available water pressure and flows, and review of available fire flow. G&A will confirm the availability of sanitary sewage collection systems for both gravity and pressure force main within and outside the park. This will include performing pump station drawdowns to determine current inflows and pump flow rates.
G&A will confirm available electrical power supply and coordinate with the provider which is believed to be Florida Public Utilities. Additional items to be documented include stormwater requirements, verify existing turn lane requirements on SR 71, and review adequacy of existing ranger station vehicular access and queue lengths.
Deliverable: Infrastructure Review and Assessment Report, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost
Subtask 1B ‐ Infrastructure Review and Assessment
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
George & Associates Chief Engineer $203.43 2 $406.86
George & Associates Project Manager $129.00 18 $2,322.00
George & Associates Project Engineer II $76.44 46 $3,516.24
George & Associates Sr. Engineering Technician $72.00 0 $0.00
Fixed Price Total Cost: $6,245.10
Total for Subtask 1B: $6,245.10
Subtask 1C: Conceptual Planning 90 Unit RV Park and Mountain Bike Trail Alignment
Description: G&A will prepare a total of three conceptual site plans that incorporate comments from the
On‐Site Project Review Meeting and data collected from the Infrastructure Review & Assessment. The proposed conceptual site plans will vary in configuration. Up to three conceptual campground layouts will be reviewed. It is anticipated layouts for up to 90 campsites with the following configurations will be provided:
1. 3‐30 RV site campground loops with three ‘Intermediate’ size bathhouses
2. 2‐45 RV site campground loops with two ‘Large’ size bathhouses
3. 2‐30 RV site campground loops, and 15‐30 smaller pop‐up and/or tent sites. Three
‘Intermediate’ size bathhouses or two ‘Large’ size bathhouses can be proposed as requested by the FPS.
Conceptual campground configurations may be mixed and matched at the request of the Florida Park
Service. Conceptual site plans will be based off field review information and other free available information such as LiDAR and aerial imaging.
Upon completion of the conceptual site planning phase, the design team will meet with the Bureau of
Design and Construction to review all three conceptual site plans. The design charrette will provide the opportunity to discuss advantages and disadvantages of each site plan. Upon completion of the design charrette, the preferred site plan will be identified with the understanding that modifications and additional details will be required.
Community Trail Design, LLC (CTD) will develop three (3) high‐level conceptual trail alignments for
Florida Caverns State Park in and around the proposed campground. This will include remotely developing three (3) digital cartographic map sets featuring illustrations of the development site, terrain and topography, aerial imagery and conceptual trail alignments with annotations, legends, and labeling.
Trailheads for the mountain bike alignment will be reviewed, including proximity and ease to which proposed campers can access the trail.
Deliverable:
Three conceptual campground site plans, identifying the preferred site plan, pdf
Three conceptual mountain bike trail alignment map sets, pdf
Meetings minutes summarizing the preferred site plan with recommended modifications, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost
Subtask 1C ‐ Conceptual Planning 90 Unit RV Park and Mountain Bike Trail Alignment
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
George & Associates Chief Engineer $203.43 2 $406.86
George & Associates Project Manager $129.00 50 $6,450.00
George & Associates Project Engineer II $76.44 70 $5,350.80
George & Associates Sr. Engineering Technician $72.00 170 $12,240.00
George & Associates Engineer Technician $45.00 0 $0.00
Community Trail Design Professional Trail Consultant
(PTBA)
$100.00 40 $4,000.00
Fixed Price Total Cost: $28,447.66
Total for Subtask 1C: $28,447.66
Subtask 1D: Preferred Conceptual Plan & 90% Mountain Bike Trail Alignment
Description: G&A will revise the preferred conceptual plans based off feedback received during the
Design Charrette for the preferred conceptual campground layout. Services will include layout of conceptual campground including more detailed: campsites, bathhouses, roadway, utility main alignment corridors, and sidewalks/walking paths. We will coordinate with CTD for connectivity from campground to proposed mountain bike trail. A detailed engineer’s opinion of probable cost will be provided for the preferred conceptual campground layout.
CTD will refine the selected high‐level conceptual trail alignment for Florida Caverns State Park to a 90% phase. This will be accomplished by remotely developing one (1) digital cartographic map set featuring illustrations of the development site, terrain and topography, aerial imagery and conceptual trail alignment with annotations, legend, and labeling. Map set will indicate major points of connectivity, intersections, control points, and experiential characteristics such as surface course material or special features for the trail. A detailed cost analysis will be provided.
Deliverable:
Conceptual campground site plan preference, pdf
90% Mountain Bike Trail alignment map set, pdf
Opinion of Probable Cost for the preferred campground layout and 90% Mountain Bike Trail alignment, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost
Subtask 1D ‐ Preferred Conceptual Plan and 90% Mountain Bike Trail Alignment
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
George & Associates Chief Engineer $203.43 2 $406.86
George & Associates Project Manager $129.00 22 $2,838.00
George & Associates Project Engineer II $76.44 38 $2,904.72
George & Associates Sr. Engineering Technician $72.00 78 $5,616.00
George & Associates Engineer Technician $45.00 12 $540.00
Community Trail Design Project Manager $100.00 20 $2,000.00
Fixed Price Total Cost: $14,305.58
Total for Subtask 1D: $14,305.58
Subtask 1E: Conceptual Campground Final Design Report & 100% Mountain Bike Trail Alignment Plans
Description: G&A will provide a Final Design Report summarizing the stakeholders input, infrastructure review, preferred conceptual campground layout, and engineers’ opinion of probable cost. G&A will apply for a Request for Verification of an Exemption from the NWFWMD for the Mountain Bike Trail, and provide communication from the City of Marianna regarding permitting requirements for the Trail or Campground.
G&A will assist CTD with putting together mountain bike trail documents sufficient to advertise the project for bidding and construction. This will include implementing ground‐level trail corridor design with intervisible flagging. Stakeout and flag all major infrastructure including bridges, culverts, intersections, and trailheads. Collect final corridor with GPS. Trail alignment in either GPX, SHP, or KML file. Update conceptual cartographic map set with final GPS alignment of trail corridor.
Deliverable:
Preferred Conceptual Campground Layout Final Design Report, pdf
Biddable Mountain Bike Trail set of plans, pdf
Scope of Work for Mountain Bike Trail, pdf
Table of Cost Items for Mountain Bike Trail, pdf
NWFWMD Request for Verification of an Exemption 62‐330.050(1), pdf
Communication/Mountain Bike Trail approval from the City of Marianna, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost
Subtask 1E ‐ Conceptual Campground Final Design Report & 100% Mountain Bike Trail Alignment Plans
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
George & Associates Chief Engineer $203.43 2 $406.86
George & Associates Project Manager $129.00 28 $3,612.00
George & Associates Project Engineer II $76.44 55 $4,204.20
George & Associates Sr. Engineering Technician $72.00 11 $792.00
Community Trail Design Project Manager $100.00 80 $8,000.00
Fixed Price Total Cost: $17,015.06
Reimbursable Cost:
NWFWMD Request for Verification of an Exemption 62‐330.050(1)
$125.00
Overnight Travel $500.00 5 nights at $100/night
Mileage (@ $0.445 per mile) $445.00 (1000 miles @ 0.445 per mile)
Reimbursable Total Cost $1,070.00
Total for Subtask 1E: $18,085.06
Notes: The intent of this Task Assignment is to:
1. Provide conceptual campground recommendations and determine a preferred campground layout.
2. Design a mountain bike trail that will mesh with the preferred campground layout and produce construction documents for the mountain bike trail suitable for bidding.
Additional services will be required to complete the design and permitting of the preferred campground layout. Items excluded from this scope of work, but intended to be included in future services consist of:
Full design plans expected to consist of 60%, 90%, and 100% drawings
Additional professional services, as applicable, such as survey, civil, structural, geotechnical, environmental, architectural, mechanical, electrical, and plumbing design
Permitting coordination and submittals for required permits
Final cost estimate
Project Schedule:
Activity Duration (calendar days)
Dates
Subtask 1A ‐ On‐Site Project Review Preliminary Site Investigations
14 Upon execution
Subtask 1B ‐ Infrastructure Review and Assessment 14 Upon On‐Site Project
Review
Subtask 1C ‐ Conceptual Planning 90 Unit RV Park and Mountain Bike Trail Alignment
Upon Infrastructure
Review
Subtask 1D ‐ Preferred Conceptual Plan and 90% Mountain Bike Trail Alignment
Upon Conceptual
Planning
Subtask 1E ‐ Final Design Report & 100% Mountain Bike Trail Alignment Plans
Upon Preferred
Conceptual Plan and 90% Mountain Bike Plans
* ‐ assumed minimum 2‐week review phase by BDC between each construction document submittal.
Next phase would not begin until comments are received from BDC unless directed otherwise.
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 1A ‐ On‐Site Project Review Preliminary Site Investigations $5,769.57
Subtask 1B ‐ Infrastructure Review and Assessment $6,245.10
Subtask 1C ‐ Conceptual Planning 90 Unit RV Park and Mountain Bike Trail Alignment
$28,447.66
Subtask 1D ‐ Preferred Conceptual Plan and 90% Mountain Bike Trail Alignment
$14,305.58
Subtask 1E ‐ Final Design Report & 100% Mountain Bike Trail Alignment Plans
$17,015.06 $1,070.00
Total Fixed Cost: $71,782.97
Total Reimbursable Cost $1,070.00
Overall Total Cost: $72,852.97
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
File details come from the government source that posted it. Updated .