CN-370000-CN210-T38.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CN210|c74bacc1301afbdccbbd4f57e12bda99
Contract number
CN210
Issued by
Florida

About this file

This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) Bureau of Design and Construction for the St Andrews State Park Lagoon Concessions Building project. The document establishes Task Assignment No. 38 under FDEP Contract No. CN210 with CPH Inc. serving as the consultant. The project is located at St Andrews State Park, and key FDEP personnel include Project Manager Theresa Carron and Contract Manager Ralph Perkins, with Jason Toole, P.E. serving as the consultant representative.

Subtask 1 requires CPH Inc. to prepare up to four conceptual plans for the placement of the Lagoon Concession Building, including two initial options and two revisions or new concept options as requested. The deliverable consists of PDFs of the concept plans, to be completed within 30 calendar days. The fixed price cost for this task is $3,060.16, comprised of labor from a Principal ($712.92), Project Engineer ($880.44), and Senior Design Technician ($1,466.80). There are no reimbursable costs. The overall task amount is $3,060.16, with payment due upon FDEP approval of deliverables. The completion date is December 12, 2025, and the work commenced upon contract execution on December 13, 2022.

View the file

Other files

File Type Posted
CN-370000-CN210-A1.pdf PDF
CN-370000-CN210-CMC2.pdf PDF
CN-370000-CN210-CMC3.pdf PDF
CN-370000-CN210-CMC4.pdf PDF
CN-370000-CN210-CMC5.pdf PDF
CN-370000-CN210-T14CO3.pdf.crdownload CRDOWNLOAD file
CN-370000-CN210-T18CO3.pdf PDF
CN-370000-CN210-T1CO2.pdf PDF
CN-370000-CN210-T23.pdf PDF
CN-370000-CN210-T23CO3.pdf PDF
CN-370000-CN210-T25.pdf PDF
CN-370000-CN210-T3.pdf PDF
CN-370000-CN210-T30CO1.pdf PDF
CN-370000-CN210-T30CO2.pdf PDF
CN-370000-CN210-T31.pdf PDF
CN-370000-CN210-T32.pdf PDF
CN-370000-CN210-T35CO1.pdf PDF
CN-370000-CN210-T36CO1.pdf PDF
CN-370000-CN210-T37CO2.pdf PDF
CN-370000-CN210-T39.pdf PDF
CN-370000-CN210-T4.pdf PDF
CN-370000-CN210-T40.pdf PDF
CN-370000-CN210-T41CO1.pdf PDF
CN-370000-CN210-T42.pdf PDF
CN-370000-CN210-T43CO1.pdf PDF
CN-370000-CN210-T44CO2.pdf PDF
CN-370000-CN210-T44CO4.pdf PDF
CN-370000-CN210-T45.pdf PDF
CN-370000-CN210-T47CO1.pdf PDF
CN-370000-CN210-T4CO1.pdf PDF
CN-370000-CN210-T4CO6.pdf PDF
CN-370000-CN210-TA29.pdf PDF
CN-370000-GC920-T9.pdf PDF
CN-370000-CN210-T13.pdf PDF
CN-370000-CN210-T14.pdf PDF
CN-370000-CN210-T14CO2.pdf PDF
CN-370000-CN210-T15.pdf PDF
CN-370000-CN210-T22.pdf PDF
CN-370000-CN210-T23CO1.pdf PDF
CN-370000-CN210-T25CO1.pdf PDF
CN-370000-CN210-T26.pdf PDF
CN-370000-CN210-T33.pdf PDF
CN-370000-CN210-T35.pdf PDF
CN-370000-CN210-T35CO2.pdf PDF
CN-370000-CN210-T35CO3.pdf PDF
CN-370000-CN210-T35CO5.pdf PDF
CN-370000-CN210-T38CO2.pdf PDF
CN-370000-CN210-T41.pdf PDF
CN-370000-CN210-T43.pdf PDF
CN-370000-CN210-T44.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN210 38 FDEP-BDC 61441C

St Andrews State Park Lagoon Concessions Building

CPH Inc.

Jason Toole, PE 850.563.1490 x4801 jtoole@cphcorp.com

Ralph Perkins 850.245.2460 ralph.perkins@floridadep.gov

New task assignment per the attached conceptual phase proposal dated 12/2/2022.

Theresa Carron upon execution $ 3,060.16 12/12/2025

$ 3,060.16

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2022.12.13 12:23:44 -05'00'

Theresa Carron T.Carron Digitally signed by T.Carron Date: 2022.12.13 12:50:16 -05'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.12.13 14:29:14 -05'00'

Jason Toole, PE Digitally signed by Jason L Toole DN: C=US, O=Florida, dnQualifier=A01410C0000017E5468FDBE00018735, CN=Jason L Toole Reason: I am the author of this document Location: your signing location here Date: 2022.12.14 12:44:44-06'00' Foxit PhantomPDF Version: 10.1.0

Jason L Toole

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2022.12.15 16:21:52 -05'00'

61441C 37501000067 080039/23 000286 U3100 131500 AD $ 3,060.16

$ 3,060.16

December 2nd, 2022

Theresa Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399

RE: St Andrews Lagoon Concession

Dear Theresa;

For your review, CPH LLC, has provided a proposal summary and man-hour documentation for the services tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, Jason Toole, P.E.

CPH, LLC

Williams_BrD Text Box

CN210 TA38

St Andrews Lagoon Concession St Andrews State Park

CN 210, Task Assignment Number

Subtask 1: Conceptual Plan Preparation Description:

1 – CPH will prepare up to 4 conceptual plans for the placement of the Lagoon Concession Building. CPH first proposes to have a conference call with the team to discuss potential locations. CPH will then provide 2 options for initial review and then also provide 2 revisions or new concept options as requested.

Deliverable:

1 – PDFs of the Concept Plans

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1 Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost CPH, LLC Principal $178.23 4 $712.92 CPH, LLC Project Engineer $73.37 12 $880.44 CPH, LLC Senior Design Technician $73.34 20 $1466.80

Total for Subtask 2: $3,060.16

Project Schedule:

Activity Duration (Calendar Days) Subtask 1: Conceptual Plans 30

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1: Conceptual Plans $3,060.16 Total Fixed Price Cost: $3,060.16

Total Reimbursable Cost: $0

Overall Total Cost: $3,060.16

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.