This federal contract opportunity is a solicitation to restore the Dorchester Heights Monument and hardscapes. The National Park Service is seeking bids to restore the monument and surrounding areas under solicitation number 140P2023R0023. Bids are due by March 10, 2022 to restore the monument and hardscapes located in Boston, Massachusetts. The selected contractor will be responsible for restoration work that preserves the historic integrity of the monument and surrounding grounds. This is a fixed-price contract with an anticipated period of performance from June 2022 to December 2022.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Boston National Historical Park
SOLICITATION #--
REHABILITATE DORCHESTER HEIGHTS HARDSCAPE
PMIS NO. BOST 227374
DORCHESTER HEIGHTS MONUMENT RESTORATION
PMIS NO. BOST 254798
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
FINAL CONSTRUCTION DOCUMENTS
1/21/2022
BOST – 227374 & BOST – 254798 TOC-1
TABLE OF CONTENTS
HARDSCAPE
PROJECT
BOST 227374
MONUMENT
RESTORATION
BOST 254798
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK * *
01 26 01 CONTRACT MODIFICATION PROCEDURES * *
01 22 00 UNIT PRICES *
01 27 00 DEFINITION OF CONTRACT LINE ITEMS * *
01 31 00 PROJECT MANAGEMENT & COORDINATION * *
01 32 16 CONSTRUCTION SCHEDULE * *
01 32 33 PHOTOGRAPHIC DOCUMENTATION * *
01 33 23 SUBMITTAL PROCEDURES * *
01 35 13.22 ARCHEOLOGICAL PROTECTION * *
01 35 23 SAFETY REQUIREMENTS * *
01 35 73 DELEGATED DESIGN REQUIREMENTS AND
PROCEDURES
01 35 91 HISTORICAL TREATMENT PROCEDURES * *
01 40 00 QUALITY REQUIREMENTS * *
01 40 00A ACCESSIBILITY INSPECTION REPORT FORM * *
01 42 00 REFERENCE STANDARDS * *
01 50 00 TEMPORARY FACILITIES AND CONTROLS * *
01 56 26 TEMPORARY FENCING * *
01 56 39 TREE AND PLANT PROTECTION * *
01 57 19.12 NOISE & ACOUSTICS MANAGEMENT * *
01 57 23 TEMPORARY STORM WATER POLLUTION
PREVENTION
01 67 00 PRODUCT REQUIREMENTS * *
01 73 29 CUTTING AND PATCHING * *
01 73 40 EXECUTION * *
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 77 00 CLOSEOUT PROCEDURES * *
01 89 00 SITE CONSTRUCTION PERFORMANCE
REQUIREMENTS
DIVISION 02 – EXISTING CONDITIONS
02 41 00 HARDSCAPE DEMOLITION *
02 42 96 MONUMENT HISTORIC REMOVAL AND
DISMANTLING
02 81 13 MONUMENT MISCELLANEOUS HAZARDOUS
MATERIALS *
02 82 13 MONUMENT ASBESTOS ABATEMENT *
02 83 13 MONUMENT LEAD IN CONSTRUCTION *
02 87 13 MONUMENT BIRD EXCREMENT REMOVAL *
BOST – 227374 & BOST – 254798 TOC-2
DIVISION 03 – CONCRETE
03 30 00 HARDSCAPE CAST-IN-PLACE CONCRETE *
03 30 00 MONUMENT CAST-IN-PLACE CONCRETE *
03 35 43 MONUMENTAL POLISHED CONCRETE *
03 53 00 MONUMENT CONCRETE TOPPING *
DIVISION 04 – MASONRY
04 01 10 MONUMENT MASONRY CLEANING *
04 01 20 HARDSCAPE MASONRY CLEANING AND
RESTORATION *
04 01 20.91 MONUMENT BRICK MASONRY RESTORATION *
04 01 40.91 MONUMENT STONE MASONRY RESTORATION *
04 10 10 HARDSCAPE SITE STONE *
04 20 00 MONUMENT UNIT MASONRY *
04 25 00 HARDSCAPE SITE UNIT MASONRY *
DIVISION 05 – METALS
05 03 71 HARDSCAPE RESTORATION OF DECORATIVE
METAL *
05 03 73 MONUMENTAL HISTORIC DECORATIVE METAL
REFINISHING *
05 12 00 MONUMENT STRUCTURAL STEEL FRAMING *
05 31 00 MONUMENT STEEL DECKING *
05 50 00 HARDSCAPE AND MONUMENT METAL
FABRICATIONS * *
05 51 16 MONUMENTAL METAL FLOOR PLATE STAIRS *
05 52 00 HARDSCAPE MISCELLANEOUS SITE METALS *
05 52 13 MONUMENT PIPE AND TUBE RAILINGS *
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES (NOT USED)
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 11 13 HARDSCAPE BITUMINOUS DAMPPROOFING *
07 56 00 MONUMENT COLD LIQUID APPLIED MEMBRANE *
07 61 00 MONUMENT SHEET METAL ROOFING *
07 62 00 MONUMENT SHEET METAL FLASHING AND TRIM *
07 92 00 MONUMENT JOINT SEALANTS *
DIVISION 08 - OPENINGS
08 71 11 MONUMENT DOOR HARDWARE (DESCRIPTIVE
SPECIFICATION) *
08 91 19 MONUMENT FIXED LOUVERS *
BOST – 227374 & BOST – 254798 TOC-3
DIVISION 09 – FINISHES
09 91 13 HARDSCAPE EXTERIOR PAINT COATINGS *
09 96 00 MONUMENT HIGH-PERFORMANCE COATINGS *
DIVISION 10 – SPECIALTIES
10 81 13 MONUMENT BIRD CONTROL DEVICES *
10 81 19 HARDSCAPE RODENT CONTROL *
DIVISIONS 11 – 14 (NOT USED)
DIVISION 26 – ELECTRICAL
26 01 00 MONUMENT BASIC ELECTRICAL REQUIREMENTS *
26 05 19 HARDSCAPE AND MONUMENT LOW-VOLTAGE
ELECTRICAL POWER CONDUCTORS AND CABLES * *
26 05 26 HARDSCAPE AND MONUMENT GROUNDING AND
BONDING FOR ELECTRICAL SYSTEMS * *
26 05 29 MONUMENT HANGERS AND SUPPORTS FOR
ELECTRICAL SYSTEMS
26 05 33 MONUMENT RACEWAYS AND BOXES FOR
ELECTRICAL SYSTEMS
26 05 43 HARDSCAPE UNDERGROUND DUCTS AND
RACEWAYS FOR ELECTRICAL SYSTEMS *
26 05 44 MONUMENT SLEEVES AND SLEEVE SEALS FOR
ELECTRICAL RACEWAYS AND CABLING
26 05 53 MONUMENT IDENTIFICATION FOR ELECTRICAL
SYSTEMS
26 05 73 MONUMENT POWER SYSTEM STUDIES *
26 09 23 MONUMENT LIGHTING CONTROL DEVICES *
26 09 26 MONUMENT LIGHTING CONTROL PANELBOARD *
26 27 26 MONUMENT WIRING DEVICES *
26 28 16 MONUMENT ENCLOSED SWITCHES AND CIRCUIT
BREAKERS
26 33 23.11 MONUMENT EMERGENCY LIGHTING INVERTER *
26 41 13 MONUMENT LIGHTNING PROTECTION FOR
STRUCTURES
26 56 19 HARDSCAPE AND MONUMENT LED LIGHTING * *
DIVISION 31 – EARTHWORK
31 05 10 HARDSCAPE SOILS AND AGGREGATES FOR
EARTHWORK *
31 10 00 HARDSCAPE EARTHWORK *
31 11 00 HARDSCAPE CLEARING AND GRUBBING *
31 14 13 HARDSCAPE STRIPPING AND STOCKPILING OF
TOPSOIL *
31 23 23.43 HARDSCAPE GEOFOAM *
31 25 00 HARDSCAPE EROSION AND SEDIMENTATION
CONTROLS *
BOST – 227374 & BOST – 254798 TOC-4
31 25 50 HARDSCAPE MUD AND OTHER SOIL DEBRIS *
31 50 00 HARDSCAPE EXCAVATION SUPPORT AND
PROTECTION *
31 63 33 HARDSCAPE DRILLED MICROPILES *
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 13 13 HARDSCAPE AND MONUMENT REINFORCED
CONCRETE PAVEMENT * *
32 30 00 HARDSCAPE SITE FURNISHINGS *
32 32 32 HARDSCAPE GRANITE CURBS, PIERS AND
PAVEMENT BANDS *
32 84 00 HARDSCAPE IRRIGATION *
32 91 13 HARDSCAPE PLANTING SOILS *
32 91 19 HARDSCAPE LANDSCAPE GRADING *
32 92 00 HARDSCAPE SEEDED TURF *
32 92 50 HARDSCAPE SOD *
32 93 00 HARDSCAPE PLANTING *
DIVISION 33 – UTILITIES
33 05 05 HARDSCAPE SELECTIVE SITE UTILITY
DEMOLITION *
33 40 00 HARDSCAPE STORM DRAINAGE UTILITIES *
APPENDIX A
1. Geotechnical Report, Proposed Improvements, Thomas Park, Dorchester Heights, Boston Massachusetts; Prepared by Lahlaf Geotechnical Consulting, Inc., November 19, 2018.
2. Soil Test Report: Prepared by the Soil and Plant Nutrient Testing Laboratory, University of Massachusetts; August 10, 2020.
3. Test Boring Log and Plan: Prepared by Northeast Geotechnical, Inc. and New England Boring Contractors, Boston, MA; July 29, 2021.
4. Geotechnical Engineering Report: Prepared by Northeast Geotechnical, Inc., Providence, RI;
August 12, 2021.
5. Hazardous Building Materials Survey Report: Prepared by TRC Environmental Corporation, Woburn, MA; June 7, 2021.
6. Hazardous Building Materials Survey Report: Prepared by Maxximus Environmental, Inc., Rockville, MD; December 2, 2021.
7. Existing Irrigation System Plan & Details: Rehabilitate Landscape Features at Dorchester Heights, Bost National Historical Park, May 1, 2013
8. Emergency Stabilization Stone Storage Plan: Grande Masonry LLC, December 2, 2021.
BOST - 227374 & BOST - 254798 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Contractor use of premises.
5. Public use of site.
6. Work Restrictions.
7. Special Construction Requirements.
8. Geotechnical Report.
9. Soil Test Report
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Dorchester Heights NHS, Boston National Historical Park, Boston, MA
B. The Work consists of the following:
1. The Work for the Hardscape Project (BOST 227374) includes:
a. Replacement of deteriorated concrete hardscape throughout the park, including walkways, stairs, ramps and retaining walls, including regrading of existing hardscape elements to meet current accessibility standards. New handrails, at stairs and ramps and modifications to existing entrance area fencing.
b. Retrofitting existing pole light fixtures with new luminaires.
c. Replacement of selected trees and protection of existing trees to remain.
2. The Work for the Monument Restoration Project (BOST 254798) includes the following:
a. Repair of foundations and superstructure
b. Replacement of structural floor framing and topping slabs at Level 1, Level 3, and
Level 4.
c. Replacement of concrete topping slab at Level 2
d. Repair, restoration, cleaning, and re-pointing of existing brick and marble masonry
e. Replacement of existing plinth paving to promote positive drainage and provide waterproofing of nearby crawl space.
f. Replacement of existing lead-coated copper roofing and flashing
g. Repair and restoration of existing steel stairs
h. Replacement in-kind of existing Level 3 steel drum enclosure at spiral stair
i. Repair and restoration of Level 1 entry door with integral louvers for ventilation
j. Replacement of existing Level 2 metal doors and steel lintels with integral louvers for ventilation
k. Replacement of existing Level 3 doors with metal bird screen door.
l. Replacement of existing skylight at Lantern with gravity ventilator.
m. Replacement of existing tie rod within the Lantern
n. Repair and select replacement of stone slabs below Level 4 structural framing.
o. Hazardous material identification, removal, and remediation.
BOST - 227374 & BOST - 254798 01 11 00 - 2
1.3 WORK PHASES
A. The Work shall be conducted in a single contract for both the Hardscape Project (BOST 227374) and the Monument Restoration Project (BOST 254798).
B. Phased Substantial Completion & Inspections: Given the anticipated constraints in accessing all areas of the Monument through the duration of construction, the Contractor shall provide a phased plan for the inspection of completed work as part of the Monument Restoration Project (BOST 254798). Incremental inspections of areas difficult to access will be required to fulfill the requirements for Substantial Completion and Closeout. Prior to scaffold being dismantled, the Construction Manager Representative (CMR), employed by the National Park Service, will provide bi-weekly inspections (or at alternate intervals as determined by the project construction schedule) to verify completeness of the Work. Bi-weekly reports with photographic documentation of completed areas of work will be provided by the Contractor and approved by the CMR. Inspections will include documentation of all structural steel and supports, masonry reinstallation, and masonry cleaning.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Storage of Materials: Confine storage of materials to staging areas within the construction area as approved by the Contracting Officer.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Construction Camp: Establishment of a camp within the park will not be permitted.
E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
1.5 PUBLIC USE OF SITE
A. The construction area will be closed to the public during construction.
1.6 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
BOST - 227374 & BOST - 254798 01 11 00 - 3
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 24 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:30 a.m. to 5:30 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Not allowed except as approved by the Contracting Officer
2. Early Morning Hours: Not allowed except as approved by the Contracting Officer.
3. Hours for excavation and other noisy heavy equipment operation: Limit to normal work hours, but operations may be prohibited on specific times and days as directed by the Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.9 GEOTECHNICAL AND SOIL TEST REPORT
A. A Geotechnical Report has been included at the end of this specification. It is based on site borings and test pits completed on two separate dates: July 20, 2018 and August 20, 2018.
1. Geotechnical Report, Proposed Improvements, Thomas Park, Dorchester Heights, Boston
Massachusetts; Prepared by Lahlaf Geotechnical Consulting, Inc., November 19, 2018.
B. A Soil Test Report has been included in Section 31 14 13 –Stripping and Stockpiling of Topsoil.
1. Soil Test Report: Prepared by the Soil and Plant Nutrient Testing Laboratory, University of Massachusetts; August 10, 2020.
C. A Geotechnical and Concrete Boring Report was completed for three (3) locations at the Monument plinth in July 2021.
1. Test Boring Log and Plan: Prepared by Northeast Geotechnical, Inc., Providence, RI, and
New England Boring Contractors, Boston, MA; July 29, 2021.
2. Geotechnical Engineering Report: Prepared by Northeast Geotechnical, Inc., Providence, RI; August 12, 2021.
BOST - 227374 & BOST - 254798 01 11 00 - 4
1.10 HAZARDOUS MATERIAL REPORT
A. Hazardous Material Reports are provided for reference.
1. Hazardous Building Materials Survey Report: Prepared by TRC Environmental Corporation, Woburn, MA; June 7, 2021.
2. Hazardous Building Materials Survey Report: Prepared by Maxximus Environmental, Inc., Rockville, MD; December 2, 2021.
1.11 MISCELLANEOUS REPORTS
A. Other reports and documentation provided for reference.
1. Existing Irrigation System Plan & Details: Rehabilitate Landscape Features at Dorchester Heights, Bost National Historical Park, May 1, 2013
2. Emergency Stabilization Stone Storage Plan: Grande Masonry LLC, December 2, 2021.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
BOST - 227374 & BOST - 254798 01 22 00 - 1
UNIT PRICES
SECTION 012200 - UNIT PRICES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
B. Related Requirements:
1. Section 01 26 01 "Contract Modification Procedures" for procedures for submitting and handling Change Orders.
2. Section 01 40 00 "Quality Requirements" for field testing by an independent testing agency.
1.3 DEFINITIONS
A. Unit price is an amount incorporated into the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.
1.4 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
C. The Contracting Officer (CO) reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government's expense, by an independent surveyor acceptable to Contracting Officer (CO).
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the Part 3 "Schedule of Unit Prices" Article contain requirements for materials described under each unit price.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF UNIT PRICES
A. Unit Price No. 1: Provide Route and Fill Crack Repair in Marble (Restoration Drawings, M1 & General Note #10)
1. Unit of Measurement: Lineal Feet (assume 12 inches each).
2. Amount: $ ____________
B. Unit Price No. 2: Face Pin Marble Unit Along Crack Length and Patch Crack (Restoration Drawings, M2)
BOST - 227374 & BOST - 254798 01 22 00 - 2
UNIT PRICES
C. Unit Price No. 3: Blind Pin Marble Unit Along Crack Length and Patch Crack (Restoration Drawings, M3)
D. Unit Price No. 4: Install Marble Dutchman (Restoration Drawings, M4)
1. Unit of Measurement: Square Feet
E. Unit Price No. 5: Remove Exterior Face Stone and Reset (General Note #10 in Restoration Drawings, M8)
F. Unit Price No. 6: Replace Stone Unit (Restoration Drawings, M10)
END OF SECTION 01 22 00
BOST - 227374 & BOST - 254798 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
BOST - 227374 & BOST - 254798 01 26 01 - 2
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums http://en.wikipedia.org/wiki/Employee
BOST - 227374 & BOST - 254798 01 26 01 - 3
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
F. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
G. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the
Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
BOST - 227374 & BOST - 254798 01 26 01 - 4
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
BOST - 227374 & BOST - 254798 01 26 01 - 5
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………6.8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 26 01
BOST - 227374 & BOST - 254798 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 - DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. CONTRACT LINE ITEM NO. 1 - BOST 227374 HARDSCAPE PROJECT
1. This item consists of all scope of the plans and specifications, except work included in other contract line items or options. The project is intended to refurbish the park within the property line fence, including additional improvements of sidewalk and roadways on City of Boston property at the north and south gate areas. The refurbishment scope includes reconstruction of all existing concrete structures, stairs ramps and pavements, along with associated metal railings, light fixtures and other work as indicated. The scope also includes regrading of ramps and paths to comply with accessibility standards and restoration of landscaped areas, along with protection of trees and landscaped areas as indicated.
2. Payment will be made at the contract lump sum price.
B. CONTRACT LINE ITEM NO. 2 - BOST 227374 HARDSCAPE PROJECT MICROPILES
1. This item consists of providing micropiles as indicated in the structural drawings and specifications. The drawings include a total of 348 micropile units, each with the assumed length of 32 feet from bottom of pile cap to bottom of pile (per Detail A on drawing S6.00 - Structural Details), for a total assumed micropile length of 11,136 feet.
2. Measurement for payment will be based on the final total installed micropile length meeting the specified requirements.
3. Payment will be made at the contract price per linear foot.
C. CONTRACT LINE ITEM NO. 3 - BOST 254798 MONUMENT RESTORATION
PROJECT
1. This item consists of all scope of the plans and specifications, except work included in other contract line items or options.
The Base Bid scope of work primarily focuses on, but is not limited to, the most urgent needs of deferred maintenance, structural deficiencies, and unsupported masonry identified in September 2021 during selective probes. The primary focus of this scope of work requires the structural repairs and replacement and associated masonry rebuilding of the upper levels of the Monument from the Level 3 structural framing to the spire and weathervane at the top of the Monument.
BOST - 227374 & BOST - 254798 01 27 00 - 2
In lieu of Option 9, the Base Bid includes treatment of the historic steel structural framing of the Level 1 floor assembly and repair of the existing brick vaults and concrete slab. Repair to the floor assembly will include removal of the existing floor grate and installation of a new floor grate as indicated in the drawings.
2. Payment will be made at the contract lump sum price.
D. CONTRACT LINE ITEM NO. 4 – OPTION B
BOST 254798 MONUMENT RESTORATION PROJECT
Interior Masonry Repairs & Repointing
1. The scope of work under this option includes interior masonry and select exterior masonry work to address deferred maintenance but was determined to be less critical to the structural stability of the Monument.
The interior masonry work includes interior brick masonry repairs, select replacement and resetting of brick masonry, removal of ferrous metal anchors, and repointing required at the interior of the Monument below the Level 3 structural framing.
Select exterior repairs include removal of ferrous metal anchors, limited quantity of dutchman repairs to marble, and limited removal and resetting of exterior marble face stone.
2. Payment will be made at the contract lump sum price.
E. CONTRACT LINE ITEM NO. 5 – OPTION C
BOST 254798 MONUMENT RESTORATION PROJECT
Exterior Masonry Restoration Below Level 2 Balconies
1. The scope of work under this option includes masonry work below the Level 2 Balconies to address repairs to cracked masonry, pinning and securing of face stones, dutchman repairs to select marble face stone, removal of ferrous metal anchors, removal and resetting of face stones, select replacement if face stone where required, removal of metallic staining, and complete re-pointing of this lower half of the Monument.
2. Payment will be made at the contract lump sum price.
F. CONTRACT LINE ITEM NO. 6 - OPTION A
BOST 227374 HARDSCAPE PROJECT
Granite Stair Treads
1. This item consists of providing granite stair treads in lieu of cast-in-place concrete treads at all new stairs. Refer to details 3 and 4 on Drawing L29.
2. Payment will be made at the contract lump sum price.
G. CONTRACT LINE ITEM NO. 7 – OPTION D
BOST 254798 MONUMENT RESTORATION
Bronze Entry Door Cleaning & Restoration, including Locking Repairs
1. The scope of work under this option includes the removal of the bronze entry door for repair and restoration off-site. The work required includes removal of paint coatings, patching and repair to the metal components to remove inoperable locking devices, patching holes and missing sections of the bronze, cleaning, and re-patination of the historic bronze. Work includes installation of new hardware and heavy-duty locking hardware. The existing temporary louver will be removed from the top panel of the door and a custom bronze storm resistant louver installed within the historic door.
BOST - 227374 & BOST - 254798 01 27 00 - 3
H. CONTRACT LINE ITEM NO. 8 – OPTION E
BOST 254798 MONUMENT RESTORATION
Exterior Railing and Decorative Gate Restoration
1. The scope of work under this option includes the removal of paint and coatings and refinishing of the existing galvanized steel railing at the perimeter of the Monument plinth and the decorative gate at the west stairs. The work includes the replacement of a missing finial at the west gate.
2. Payment will be made at the contract lump sum price.
I. CONTRACT LINE ITEM NO. 9 – OPTION F
BOST 254798 MONUMENT RESTORATION
Cleaning and Refinishing of Square Steel Stair
1. The scope of work under this option includes the cleaning and refinishing of the “square” steel stair at the interior of the Monument which connects Level 1 to Level 2. Select repairs to be provided to the metal stair stringers.
2. Payment will be made at the contract lump sum price.
J. CONTRACT LINE ITEM NO. 10 – OPTION G
BOST 254798 MONUMENT RESTORATION
Modification of Square Steel Stair Railing
1. The scope of work under this option includes the modification of the railing at the “square” steel stair to provide a code compliant guardrail and handrail. The existing railing will be removed, and the rail cap salvaged for reinstallation on a new railing with proper picket spacing. A new handrail will be installed along the interior of this guardrail and along the outside of the stair at the existing brick wall.
2. Payment will be made at the contract lump sum price.
K. CONTRACT LINE ITEM NO. 11 – OPTION H
BOST 254798 MONUMENT RESTORATION
Cleaning and Refinishing of Spiral Steel Stair
1. The scope of work under this option includes the cleaning and refinishing of the historic spiral steel stair at the interior of the Monument which connects Level 2 to Level 3.
2. Payment will be made at the contract lump sum price.
L. CONTRACT LINE ITEM NO. 12 – OPTION J
BOST 254798 MONUMENT RESTORATION
Plinth Paving
1. The scope of work under this option includes the removal of the existing paving around the perimeter of the monument and installation of a new split slab with waterproofing membrane at the plinth level of the Monument. The new slab will be set on granular fill at the existing grade at the plinth level.
2. Payment will be made at the contract lump sum price.
M. CONTRACT LINE ITEM NO. 13 – OPTION K
BOST 254798 MONUMENT RESTORATION
Level 01 Structural Framing & Floor Replacement
1. The scope of work under this option includes the removal and replacement of the Level 1 structural framing and floor assembly. The new structural framing system will consist of concrete on metal deck supported by new structural steel framing. The new floor assembly will accommodate a new metal floor grate to promote passive ventilation of this space and provide access to the crawl space below.
BOST - 227374 & BOST - 254798 01 27 00 - 4
2. Payment will be made at the contract lump sum price
N. CONTRACT LINE ITEM NO. 14 – OPTION L
BOST 254798 MONUMENT RESTORATION
Electrical Service Wire Replacement
1. The scope of work under this option includes the replacement of service wiring within existing conduit infrastructure from main service panel inside the structure to the existing padmount utility transformer.
END OF SECTION 01 27 00
BOST - 227374 & BOST - 254798 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC SharePoint Project Website.
7. Project meetings.
8. Environmental Coordination.
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor's construction schedule.
2. Section 01 35 73 "Delegated Design Requirements and Procedures"
3. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
4. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits - Contractor Provided
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
http://www.nps.gov/dscw/definitionsdc_a.htm http://www.nps.gov/dscw/definitionsdc_c.htm
BOST - 227374 & BOST - 254798 01 31 00 - 2
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman's compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
11. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued.
BOST - 227374 & BOST - 254798 01 31 00 - 3
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select
"CMR" in the drop-down of the "Send to" box.
3. Enter the details of the question and attach related documents.
4. Select "Submit Form" at the bottom of the page.
D. Contracting Officer's Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Contracting Officer (CO)'s actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
BOST - 227374 & BOST - 254798 01 31 00 - 4
1.6 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Schedule of Values
9. Payments to Contractor.
10. Payroll reports.
http://www.nps.gov/dscw/precon_spproj.htm
BOST - 227374 & BOST - 254798 01 31 00 - 5
11. Contract time.
12. Liquidated damages.
13. Contractor Performance Evaluation.
14. Display of Hotline posters.
15. Notice to proceed.
16. Correspondence procedures.
17. NPS/DSC SharePoint Project website.
18. Acceptance/rejection of work.
19. Progress meetings.
20. Submittal procedures.
21. NPS Final Accessibility Inspection.
22. Environmental requirements.
23. Permit requirements.
24. As-constructed drawings/operation and maintenance (O&M) manuals.
25. Saturday, Sunday, holiday and night work.
26. Reference materials.
27. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery…