Addendum_D_Summary_Memo_2022-0712_NPS_BOST_254798_DD_CD_-__0002.pdf
PDF 163 KB Posted
- Solicitation number
- 140P2023R0023
About this file
This addendum memo revises specifications for a project to restore the Dorchester Heights Monument and hardscapes in Boston National Historical Park. The National Park Service is seeking a contractor to perform design development and construction documents for coating the monument with high-performance coatings per the revised Section 09 96 00 specification. Solicitation number 140P2023R0023 has been issued for this BOST 254798 project with an opportunity description of restoring the Dorchester Heights Monument and hardscapes. No other details regarding response dates, pricing terms, or federal agencies involved are provided in the document.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM
www.smithgroup.com
PROJECT BOST 254798: Dorchester Heights Monument Restoration Design Development & Construction Documents
ADDENDUM
NUMBER
D
PROJECT NO. 13188 DATE 7/12/2022
PROJECT
LOCATION
Boston National Historical Park Thomas Park, Boston, MA
OWNER National Park Service
PREPARED BY Susan Pommerer, AIA
DISTRIBUTION
NAME COMPANY EMAIL PHONE
Tracy McConner NPS, Denver Service
Center (DSC) Tracy_mcconner@nps.gov
Jon Mitchell NPS, Denver Service Center (DSC)
Jon_mitchell@nps.gov
Dave Gustavson NPS, Denver Service Center (DSC)
Dave_Gustavson@contractor.nps.gov
This Addendum is issued pursuant to the Instructions to Bidders and/or Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form.
PART 1 - NEW DOCUMENTS ISSUED WITH THIS DOCUMENT
1.1 NEW PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS
A. Section 07 18 00, “MONUMENT TRAFFIC COATINGS”
1.2 NEW DRAWING SHEETS
A. None.
1.3 NEW SKETCHES
A. None.
PART 2 - DOCUMENTS DELETED BY THIS DOCUMENT
2.1 DELETE THE FOLLOWING FROM THE PROJECT MANUAL
A. None.
2.2 DELETE THE FOLLOWING DRAWING SHEETS
A. None.
ADDENDUM
www.smithgroup.com
PART 3 - REVISED DOCUMENTS ISSUED WITH THIS DOCUMENT
3.1 REVISED PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS
A. Section 09 96 00, “MONUMENT HIGH-PERFORMANCE COATINGS”
3.2 REVISED DRAWING SHEETS
A. None.
PART 4 - PROPOSED CHANGES IN THE WORK
4.1 None.
PART 5 - CLARIFICATIONS
5.1 None.
| PART 1 - NEW DOCUMENTS ISSUED WITH THIS DOCUMENT |
| 1.1 NEW PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS |
| A. Section 07 18 00, “MONUMENT TRAFFIC COATINGS” |
| 1.2 NEW DRAWING SHEETS |
| A. None. |
| 1.3 NEW SKETCHES |
| A. None. |
| PART 2 - DOCUMENTS DELETED BY THIS DOCUMENT |
| 2.1 DELETE THE FOLLOWING FROM THE PROJECT MANUAL |
| A. None. |
| 2.2 DELETE THE FOLLOWING DRAWING SHEETS |
| A. None. |
| PART 3 - REVISED DOCUMENTS ISSUED WITH THIS DOCUMENT |
| 3.1 REVISED PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS |
| A. Section 09 96 00, “MONUMENT HIGH-PERFORMANCE COATINGS” |
| 3.2 REVISED DRAWING SHEETS |
| A. None. |
| PART 4 - PROPOSED CHANGES IN THE WORK |
| 4.1 None. |
| PART 5 - CLARIFICATIONS |
| 5.1 None. |