Addendum_A_Drawings_2022-0610_NPS_BOST_254798_DD___CD_0002.pdf
PDF 22 MB Posted
- Solicitation number
- 140P2023R0023
About this file
This document provides details on a federal contract opportunity for restoration work. The National Park Service is soliciting proposals under solicitation number 140P2023R0023 to restore the Dorchester Heights Monument and hardscapes in Boston, Massachusetts. Interested vendors should respond by the deadline of January 10, 2023. The selected contractor will be awarded a firm fixed price contract to repair and restore the monument and surrounding areas. The restoration work should be completed by June 30, 2023. The National Park Service is the contracting agency overseeing this project.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS PROJECT
HARDSCAPE PROJECT
(BOST 227374)
MONUMENT
RESTORATION
PROJECT
(BOST 254798)
THIS PROJECT
PMIS/PKG NO.
DRAWING NO.
SHEET
CONSULTANT:
TITLE OF DRAWING
OF
BUILDING
CONSERVATION
ASSOCIATES
BOSTON, MA
LOCATION WITHIN PARK
NAME OF PARK
COUNTY STATEREGION
NATIONAL PARK SERVICE
UNITED STATES
DEPARTMENT OF THE INTERIOR
STRUCTURAL:
SILMAN
BOSTON, MAWASHINGTON, DC
smithgroup.com
PRIME/ARCH:
SMITHGROUP
SMITHGROUP Mark Sheet(s) REVISION Date Initial
APPROVED:
Regional Director Date
Superintendent Date
RECOMMENDED:
RECOMMENDED:
Project Manager Date
:2 :3
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
MONUMENT AND HARDSCAPE
RESTORATION
254798
165882
681SUFFOLK
DORCHESTER HEIGHTS
DORCHESTER HEIGHTS MONUMENT
NE MA
FINAL CONSTRUCTION DOCUMENTS
BOSTON NATIONAL HISTORICAL SITE
(BOST)
DRAWING LIST
SHEET # OF # SUBSHEET SHEET TITLE
GENERAL
2 OF 68 G0.1 ABBREVIATIONS AND SYMBOLS
3 OF 68 G0.2 SITE STAGING AND ACCESS PLAN
4 OF 68 G1.0 PROJECT NARRATIVE & BUILDING CODE SUMMARY
ARCHITECTURAL DEMOLITION
5 OF 68 AD2.1 CRAWL SPACE AND LEVEL 1 DEMOLITION FLOOR PLANS
6 OF 68 AD2.2 LEVEL 2, LEVEL 3, AND LANTERN DEMOLITION FLOOR PLANS
7 OF 68 AD3.1 CRAWL SPACE AND LEVEL 1 DEMOLITION REF CEILING PLANS
8 OF 68 AD3.2 LEVEL 2, LEVEL 3, AND LANTERN DEMOLITION REF CEILING PLANS
9 OF 68 AD4.1 BUILDING DEMOLITION SECTIONS
10 OF 68 HD1.0 HAZMAT ABATEMENT SITE PLAN
11 OF 68 HD1.1 HAZMAT ABATEMENT FLOOR PLAN & BUILDING SECTION
ARCHITECTURAL
12 OF 68 A1.1 ARCHITECTURAL SITE PLAN
13 OF 68 A2.1 CRAWL SPACE AND LEVEL 1 FLOOR PLANS
14 OF 68 A2.2 LEVEL 2, LEVEL 3, AND LANTERN FLOOR PLANS
15 OF 68 A3.1 CRAWL SPACE AND LEVEL 1 REF CEILING PLANS
16 OF 68 A3.2 LEVEL 2, LEVEL 3, AND LANTERN REF CEILING PLANS
17 OF 68 A4.1 WEST ELEVATION
18 OF 68 A4.2 NORTH ELEVATION
19 OF 68 A4.3 EAST ELEVATION
20 OF 68 A4.4 SOUTH ELEVATION
21 OF 68 A4.5 EAST-WEST SECTION
22 OF 68 A4.6 NORTH-SOUTH SECTION
23 OF 68 A5.1 LEVEL 2 & LEVEL 3 SECTION DETAILS
24 OF 68 A5.2 LEVEL 3 SECTION DETAILS
25 OF 68 A5.3 LEVEL 4, DRUM, AND LANTERN SECTION DETAILS
26 OF 68 A5.4 ENLARGED ROOF PLAN DETAILS
27 OF 68 A5.5 ENLARGED ROOF PLAN DETAILS
28 OF 68 A5.6 ENLARGED ROOF PLAN DETAILS
29 OF 68 A5.7 ROOFING AND FLASHING DETAILS
30 OF 68 A6.1 CRAWL SPACE AND PLINTH SLAB
31 OF 68 A6.2 LEVEL 1 FLOOR GRATE DETAILS
32 OF 68 A6.3 ENTRY DOOR DETAILS
33 OF 68 A6.4 "SQUARE" STAIR ELEVATIONS
34 OF 68 A6.5 "SQUARE" STAIR ELEVATIONS
35 OF 68 A6.6 "SQUARE" STAIR DETAILS
36 OF 68 A6.7 LEVEL 2 AND LEVEL 3 DOOR DETAILS
37 OF 68 A6.8 LEVEL 2 AND LEVEL 3 DOOR DETAILS
38 OF 68 A6.9 LEVEL 3 FLASHING AND LANTERN WATERPROOFING & FLASHING DETAILS
39 OF 68 A6.10 LEVEL 3 SPIRAL STAIR ENCLOSURE DETAILS
40 OF 68 A6.11 LEVEL 3 SPIRAL STAIR ENCLOSURE DETAILS
MASONRY RESTORATION
41 OF 68 R1.1 MASONRY RESTORATION WEST ELEVATION
42 OF 68 R1.2 MASONRY RESTORATION NORTH ELEVATION
43 OF 68 R1.3 MASONRY RESTORATION EAST ELEVATION
44 OF 68 R1.4 MASONRY RESTORATION SOUTH ELEVATION
45 OF 68 R1.5 MASONRY RESTORATION WEST INTERIOR
46 OF 68 R1.6 MASONRY RESTORATION NORTH INTERIOR
47 OF 68 R1.7 MASONRY RESTORATION EAST INTERIOR
48 OF 68 R1.8 MASONRY RESTORATION SOUTH INTERIOR
49 OF 68 R1.9 MASONRY RESTORATION QUANTITY SCHEDULE - BASE BID
50 OF 68 R1.10 MASONRY RESTORATION QUANTITY SCHEDULE - OPTIONS
51 OF 68 R1.11 MASONRY RESTORATION DETAILS
STRUCTURAL
52 OF 68 S0.1 GENERAL STRUCTURAL NOTES AND LEGEND
53 OF 68 S0.2 DESIGN PARAMETERS AND LOAD SCHEDULE
54 OF 68 S2.1 FOUNDATION PLAN AND FRAMING PLANS
55 OF 68 S4.1 SECTIONS
56 OF 68 S4.2 SECTIONS
57 OF 68 S5.1 TYPICAL DETAILS
58 OF 68 S5.2 TYPICAL DETAILS
ELECTRICAL
59 OF 68 E0.1 ELECTRICAL ABBREVIATIONS AND SYMBOLS
60 OF 68 E1.1 ELECTRICAL SITE POWER AND LIGHTING PLAN
61 OF 68 E1.2 ELECTRICAL SITE UTILITY PLAN
62 OF 68 ED2.1 ELECTRICAL CRAWL SPACE AND LEVEL 1 DEMOLITION FLOOR PLANS
63 OF 68 ED2.2 ELECTRICAL LEVEL 2, LEVEL 3, AND LANTERN DEMOLITION FLOOR PLANS
64 OF 68 E2.1 ELECTRICAL CRAWL SPACE AND LEVEL 1 POWER AND LIGHTING PLANS
65 OF 68 E2.2 ELECTRICAL LEVEL 2, LEVEL 3, AND LANTERN POWER AND LIGHTING PLANS
66 OF 68 E6.0 ELECTRICAL DETAILS
67 OF 68 E6.1 ELECTRICAL DETAILS
68 OF 68 E7.0 ELECTRICAL SCHEDULES
VICINITY MAP (NOT TO SCALE) LOCATION PLAN (NOT TO SCALE)
DRAWING LIST
SHEET # OF # SUBSHEET SHEET TITLE
1 OF 92 LP1 LOGISTICS PLAN
(NOT INCLUDED, SEE BOST 254798)
2 OF 92 LN GENERAL NOTES
3 OF 92 LG KEY PLAN
4 OF 92 LA ACCESSIBILITY PLAN
5 OF 92 L1 SITE PREP AND DEMOLITION
6 OF 92 L2 SITE PREP AND DEMOLITION
7 OF 92 L3 SITE PREP AND DEMOLITION
8 OF 92 L4 SITE PREP AND DEMOLITION
9 OF 92 L5 SITE PREP AND DEMOLITION
10 OF 92 L6 SITE PREP AND DEMOLITION
11 OF 92 L7 MATERIALS AND LAYOUT
12 OF 92 L8 MATERIALS AND LAYOUT
13 OF 92 L9 MATERIALS AND LAYOUT
14 OF 92 L10 MATERIALS AND LAYOUT
15 OF 92 L11 MATERIALS AND LAYOUT
16 OF 92 L12 MATERIALS AND LAYOUT
17 OF 92 L13 GRADING AND PLANTING
18 OF 92 L14 GRADING AND PLANTING
19 OF 92 L15 GRADING AND PLANTING
20 OF 92 L16 GRADING AND PLANTING
21 OF 92 L17 GRADING AND PLANTING
22 OF 92 L18 GRADING AND PLANTING
23 OF 92 L19 TREE PROTECTION
24 OF 92 L20 TREE PROTECTION
25 OF 92 L21 TREE PROTECTION
26 OF 92 L22 TREE PROTECTION
27 OF 92 L23 TREE PROTECTION
28 OF 92 L24 TREE PROTECTION
29 OF 92 L25 SITE DETAILS
30 OF 92 L26 SITE DETAILS
31 OF 92 L27 SITE DETAILS
32 OF 92 L28 SITE DETAILS
33 OF 92 L29 SITE DETAILS
34 OF 92 L30 SITE DETAILS
35 OF 92 L31 SITE DETAILS
36 OF 92 L32 IRRIGATION DETAILS
37 OF 92 L33 IRRIGATION DETAILS
38 OF 92 L34 IRRIGATION DETAILS
BOST 254798 - MONUMENT RESTORATION PROJECT BOST 227374 - HARDSCAPE PROJECT
DRAWING LIST
SHEET # OF # SUBSHEET SHEET TITLE
39 OF 92 C000 CIVIL NOTES
40 OF 92 C100 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN
41 OF 92 C101 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN SHEET 1
42 OF 92 C102 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN SHEET 2
43 OF 92 C103 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN SHEET 3
44 OF 92 C104 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN SHEET 4
45 OF 92 C105 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN SHEET 5
46 OF 92 C106 SITE UTILITY DEMOLITION & EROSION
CONTROL PLAN SHEET 6
47 OF 92 C200 SITE LAYOUT PLAN
48 OF 92 C201 SITE LAYOUT PLAN SHEET 1
49 OF 92 C202 SITE LAYOUT PLAN SHEET 2
50 OF 92 C203 SITE LAYOUT PLAN SHEET 3
51 OF 92 C204 SITE LAYOUT PLAN SHEET 4
52 OF 92 C205 SITE LAYOUT PLAN SHEET 5
53 OF 92 C206 SITE LAYOUT PLAN SHEET 6
54 OF 92 C207 UTILITY PROFILE WEST WALL
55 OF 92 C208 UTILITY PROFILE NORTH WALL
56 OF 92 C209 UTILITY PROFILE SOUTH WALL
57 OF 92 C300 EROSION CONTROL DETAILS
58 OF 92 C301 UTILITY DETAILS
59 OF 92 C302 STAIR, RAMP, & WALL ELEVATION VIEWS
DRAWING LIST
SHEET # OF # SUBSHEET SHEET TITLE
60 OF 92 S1.00 GENERAL STRUCTURAL PLAN & NOTES
61 OF 92 S1.01 DEMOLITION PLAN
62 OF 92 S1.02 WALL ALIGNMENT PLAN
63 OF 92 S1.03 WALL ALIGNMENT PLAN
64 OF 92 S2.00 MICROPILE LOCATION PLAN
65 OF 92 S2.01 MICROPILE LOCATION PLAN
66 OF 92 S2.02 MICROPILE LOCATION PLAN
67 OF 92 S2.03 MICROPILE LOCATION PLAN
68 OF 92 S2.04 MICROPILE LOCATION PLAN
69 OF 92 S2.05 MICROPILE LOCATION PLAN
70 OF 92 S2.06 MICROPILE LOCATION PLAN
71 OF 92 S2.07 MICROPILE LOCATION PLAN
72 OF 92 S2.08 MICROPILE LOCATION PLAN
73 OF 92 S2.09 MICROPILE LOCATION PLAN
74 OF 92 S3.00 FOUNDATION & WALL PLAN
75 OF 92 S3.01 FOUNDATION & WALL PLAN
76 OF 92 S3.02 FOUNDATION & WALL PLAN
77 OF 92 S3.03 FOUNDATION & WALL PLAN
78 OF 92 S3.04 FOUNDATION & WALL PLAN
79 OF 92 S3.05 FOUNDATION & WALL PLAN
80 OF 92 S3.06 FOUNDATION & WALL PLAN
81 OF 92 S3.07 FOUNDATION & WALL PLAN
82 OF 92 S3.08 FOUNDATION & WALL PLAN
83 OF 92 S3.09 FOUNDATION & WALL PLAN
84 OF 92 S4.00 WALL PROFILES
85 OF 92 S4.01 WALL PROFILES
86 OF 92 S4.02 ELEVATIONS VIEWS
87 OF 92 S4.03 ELEVATIONS VIEWS
88 OF 92 S4.04 ELEVATIONS VIEWS
89 OF 92 S5.00 SECTION VIEWS
90 OF 92 S5.01 SECTION VIEWS
91 OF 92 S6.00 STRUCTURAL DETAILS
92 OF 92 E1 SITE LIGHTING PLAN
DORCHESTER HEIGHTS MONUMENT AND HARDSCAPE RESTORATION PROJECTS
A2.2, A3.2, A4.1-A4.4, A5.1-A5.7, A6.3, A6.8-A6.11 ADDENDUM A 6/10/22A
A4.6
A4.5
PROVIDE NEW NORMAL WEIGHT
MESH-REINFORCED CAST-IN-
PLACE TOPPING SLAB SLOPED
TO DRAIN; POLISHED CONCRETE
FINISH
REPLACE EXISTING ALUMINUM
DOORS AND FRAMES;
REPLACE STEEL LINTELS
ABOVE MASONRY OPENINGS
PER STRUCTURAL DWGS;
REPLACE EXISTING
BALUSTERS AT EACH
BALCONY WITH NEW
TO MATCH EXISTING
A5.1
A6.7
CLEAN AND RECOAT ALL
EXPOSED SURFACES OF THE
EXISTING STEEL "SQUARE"
STAIR; SAND BLAST IN PLACE
TO REMOVE CORROSION;
TREAT ALL EXPOSED STEEL
SURFACES WITH A PRIMER
AND HIGH-PERFORMANCE
COATING (OPTION F)
GUARDRAIL WITH NEW
PICKETS, RESUSE
EXISTING TOP CAP.
NEW WALL
MOUNTED PAINTED
METAL HANDRAIL
A4.2
A4.4
A4.3
A4.1
A6.7
DOOR 202
TO BE FIXED
IN PLACE
CLEAN AND RECOAT ALL EXPOSED
SURFACES OF THE EXISTING STEEL
SPIRAL STAIR; SAND BLAST IN PLACE
TO REMOVE CORROSION; TREAT ALL
EXPOSED STEEL SURFACES WITH A
PRIMER AND HIGH-PERFORMANCE
COATING (OPTION H)
CONTROL JOINTS IN
CONCRETE SLAB
ROOF 4: TOWER CHAMBER CORNICE
INSTALL 20 OZ. ZINC-TIN COATED
COPPER ROOFING OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
INSTALL NEW NORMAL
WEIGHT CONCRETE FLOOR
PITCHED TO DRAIN; APPLY
PMMA ROOFING MEMBRANE
ON NEW CONCRETE
REINSTALL OBELISKS, CORNER PIERS,
BALUSTRADE, AND RAILINGS THAT WERE
REMOVED DURING PREVIOUS EMERGENCY
STABILIZATION; REFER TO MASONRY
RESTORATION DWGS
A6.7
A4.2
A4.4
A4.3
A4.1
INSTALL BIRD NET
WITHIN ARCHED
MASONRY OPENINGS;
TYPICAL
23'-9"
SLOPE TOPPING SLAB
TO DRAIN TO DOORS
201, 203, AND 204
WITH CRICKETS AT
EACH CORNER TO
DIRECT WATER AWAY
FROM CORNERS AND
OUT THROUGH ARCHED
OPENINGS
A
PROVIDE NEW PAINTED METAL
GRAVITY VENTILATOR SET ON
MANUFACTURER PROVIDED
CURB IN PLACE OF EXISTING
SKYLIGHT AT THE TOP OF
THE LEVEL 3 BELFRY
A5.4
REPLACE EIGHT (8)
LANTERN TIE RODS WITH
NEW STN STL TIE RODS;
SEE STRUCTURAL DWGS;
PROVIDE FLUID APPLIED
PMMA FLASHING AT BASE
OF RODS TO ZINC-TIN
COATED COPPER; SEE
STRUCTURAL DWGS
ROOF 1: LANTERN BASE
REPLACE ROOFING WITH NEW
20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS RED
ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT; INSTALL NEW
FLASHING AND COUNTER
FLASHING AT PILASTERS
ROOF 2: URN PLATFORM
INSTALL 20 OZ. ZINC-TIN
COATED COPPER ROOFING
OVER SELF-ADHERED
POLYETHYLENE FACED
UNDERLAYMENT
A
A A
1. DISMANTLING (FOR REASSEMBLY) OF THE UPPER
LEVELS OF THE MONUMENT REQUIRES DETAILED
EXISTING CONDITION DOCUMENTATION, CATALOGING,
AND PROTECTION OF SALVAGE MATERIALS FOR
CONTRACTING OFFICER (CO) APPROVAL BEFORE WORK
CAN BEGIN. CONTRACTOR TO PROVIDE SITE AND
MONUMENT PROTECTION AND LOGISTICAL PLAN FOR
APPROVAL PRIOR TO DISMANTLING ACTIVITIES PER
SPECIFICATIONS.
2. PROTECT EXISTING TO REMAIN MASONRY STRUCTURES
AND SURROUNDING LANDSCAPE AND HARDSCAPE
WITHIN THOMAS PARK.
3. ASSUME ALL SCOPE IS INCLUDED IN THE BASE BID
UNLESS NOTED AS AN OPTION. SEE SHEET G1.0 FOR
LIST OF ALL BID OPTIONS.
4. CAREFULLY DISMANTLE MASONRY WALL AS INDICATED.
TAKE CARE TO SALVAGE EXISTING MARBLE AND
BRICKS FOR REUSE PER SPECIFICATIONS.
5. REFER TO SHEET G1.0 FOR LIST OF ALL ITEMS TO
BE SALVAGED.
6. REFER TO THE RESTORATION SERIES DRAWINGS FOR
SCOPE OF BRICK MASONRY REBUILDING, REPAIR, AND
CLEANING.
7. REFER TO THE STRUCTURAL SERIES DRAWINGS FOR
ALL STRUCTURAL STABILIZATION OF MASONRY.
8. REFER TO THE STRUCTURAL SERIES DRAWINGS FOR
ALL STRUCTURAL SUPPORT AND DETAILS.
4 4 80
SCALE OF FEET
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :1
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
S J P
LEVEL 2, LEVEL 3, AND
LANTERN FLOOR PLANS
254798A2.2
SJP
SJP
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA2.2
1 LEVEL 2 FLOOR PLAN
SCALE AA2.2
2 LEVEL 3 FLOOR PLAN
SCALE AA2.2
3 LANTERN FLOOR PLAN
GENERAL SHEET NOTES
A4.6
A4.5
A4.2
A4.4
A4.3
A4.1
OPENING OF
CIRCULAR DRUM
ABOVE
REPLACE
CANTILEVERED
LIMESTONE SLABS
AT BASE OF
LEVEL 4 FRAMING
R 2' - 3"R 2' - 9"
S1
INSTAL SURFACE
MOUNTED LIGHT
FIXTURE AT CEILING
OF STAIR ENCLOSURE
PER LIGHTING PLANS
A4.6
A4.5
METAL DOOR WITH GLAZED
PANELS AND PASSIVE
VENTILATION LOUVERS
REPLACE EXISTING STEEL
STAIR ENCLOSURE AT LEVEL
3 TO PROVIDE OPERABLE
DOOR AND WEATHER TIGHT
ENCLOSURE; SEE SHEET
A6.10 & A6.11 FOR DETAILS
METAL DOOR WITH GLAZED
PANELS AND PASSIVE
VENTILATION LOUVERS
METAL DOOR WITH GLAZED
PANELS AND PASSIVE
VENTILATION LOUVERS
METAL DOOR WITH
GLAZED PANELS AND
PASSIVE VENTILATION
LOUVERS; DOOR 202
TO BE FIXED IN
PLACE
A4.2
A4.4
A4.3
A4.1 202
RECONSTRUCT STEEL
BEAMS AND VAULTED
BRICK FLOOR
ASSEMBLY TO MATCH
ORIGINAL CONSTRCTION;
SEE STRUCTURAL DWGS
EXG
BRICK
ARCH
EXG
BRICK
ARCH
EXG
BRICK
ARCH
EXG
BRICK
ARCH
EXG
BRICK
ARCH
EXG
BRICK
ARCH
EXG
BRICK
ARCHEXG
BRICK
ARCH
1. DISMANTLING (FOR REASSEMBLY) OF THE UPPER
LEVELS OF THE MONUMENT REQUIRES DETAILED
EXISTING CONDITION DOCUMENTATION, CATALOGING,
AND PROTECTION OF SALVAGE MATERIALS FOR
CONTRACTING OFFICER (CO) APPROVAL BEFORE WORK
CAN BEGIN. CONTRACTOR TO PROVIDE SITE AND
MONUMENT PROTECTION AND LOGISTICAL PLAN FOR
APPROVAL PRIOR TO DISMANTLING ACTIVITIES PER
SPECIFICATIONS.
2. PROTECT EXISTING TO REMAIN MASONRY STRUCTURES
AND SURROUNDING LANDSCAPE AND HARDSCAPE
WITHIN THOMAS PARK.
3. ASSUME ALL SCOPE IS INCLUDED IN THE BASE BID
UNLESS NOTED AS AN OPTION. SEE SHEET G1.0 FOR
LIST OF ALL BID OPTIONS.
4. CAREFULLY DISMANTLE MASONRY WALL AS INDICATED.
TAKE CARE TO SALVAGE EXISTING MARBLE AND
BRICKS FOR REUSE PER SPECIFICATIONS.
5. REFER TO SHEET G1.0 FOR LIST OF ALL ITEMS TO
BE SALVAGED.
6. REFER TO THE RESTORATION SERIES DRAWINGS FOR
SCOPE OF BRICK MASONRY REBUILDING, REPAIR, AND
CLEANING.
7. REFER TO THE STRUCTURAL SERIES DRAWINGS FOR
ALL STRUCTURAL STABILIZATION OF MASONRY.
8. REFER TO THE STRUCTURAL SERIES DRAWINGS FOR
ALL STRUCTURAL SUPPORT AND DETAILS.
A5.3
REPLACE LANTERN TIE
RODS WITH NEW
STAINLESS STEEL TIE
RODS; PROVIDE FLUID
APPLIED PMMA FLASHING
AT BASE OF RODS TO
ZINC-TIN COATED
COPPER; SEE
STRUCTURAL DWGS
CENTRAL TIE ROD
SECURING SPIRE
AND DOME ABOVE;
SEE STRUCTURAL
DWGS
MARBLE BASE OF
DOME ABOVE
A
4 4 80
SCALE OF FEET
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :1
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
S J P
LEVEL 2, LEVEL 3, AND
LANTERN REFLECTED
CEILING PLANS 254798A3.2
SJP
SJP
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA3.2
2 LEVEL 3 REFLECTED CEILING PLAN
SCALE AA3.2
1 LEVEL 2 REFLECTED CEILING PLAN
GENERAL SHEET NOTES
SCALE AA3.2
4 LANTERN REFLECTED CEILING PLAN
LEVEL 1
EL +0' - 0"
LEVEL 3
EL +56' - 8"
LOUVER OPENINGS
EL +36' - 1 1/2"
B.O. LANTERN
EL +79' - 6"
B.O. DOME
EL +87' - 11"
T.O. SPIRE/ B.O.
WEATHERVANE
EL +104' - 8"
TOP OF WEATHERVANE
EL +114' - 9"
REPAINT AND RE-GILD
EXISTING WEATHERVANE;
SEE RESTORATION DWGS
ROOF 1: 20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS RED ROSIN
PAPER OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
PROVIDE PAINTED METAL
GRAVITY VENTILATOR SET ON
MANUFACTURER PROVIDED
CURB IN PLACE OF EXISTING
SKYLIGHT AT THE TOP OF
THE LEVEL 3 BELFRY
RESET STONES AND FOUR (4) URNS
THAT WERE REMOVED DURING PREVIOUS
EMERGENCY STABILIZATION; REFER TO
MASONRY RESTORATION DWGS
ROOF 2 & 3: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS RED
ROSIN PAPER OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
REINSTALL OBELISKS, CORNER PIERS,
BALUSTRADE, AND RAILINGS THAT
WERE REMOVED DURING PREVIOUS
EMERGENCY STABILIZATION; REFER TO
MASONRY RESTORATION DWGS
N S
EXISTING PASSIVE
VENTILATION LOUVERS IN
SLOT WINDOWS TO REMAIN
REPLACE SELECT BALUSTERS
AT BALCONIES; REFER TO
RESTORATION DWGS
LEVEL 4
EL +72' - 4"
W E A T H E R V A N E
S P
IR
E
D O M E
L A N T E R N
C
IR
C U L A R
D R U M
B E L F R Y
R E B U
IL
D
U P P E R
L E V E L S
O F
M O N U M E N T
F R O M
L E V E L
S T R U C T U R E
T O
T H E
T O P
O F
S P
IR
E
INSTALL BIRD NETTING
BEHIND LANTERN ARCHES
C
IR
C U L A R
D R U M
MAINTAIN 1" UNDERCUT
BELOW BALUSTRADE
PROVIDE CONDUIT PATHWAY WITHIN
STEEL PIPE BEHIND BIRD NET FOR
FUTURE USE BY NPS
PROVIDE GUARDRAIL AT LEVEL 3
ARCHED OPENINGS; INSTALL BIRD NET
ON EXTERIOR SIDE OF GUARDRAIL
REMOVE AND RESET
ARCHITRAVE STONE; REFER
TO RESTORATION DWGS
T O W E R
C H A M B E R
T O W E R
S T A
IR
W A Y
ROOF 4: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
REPLACE EXISTING TIE-RODS
NEW STAINLESS-STEEL RODS.
A
A
A
1. PROTECT EXISTING TO REMAIN
MASONRY STRUCTURES AND
SURROUNDING LANDSCAPE AND
HARDSCAPE WITHIN THOMAS PARK.
2. ASSUME ALL SCOPE IS INCLUDED IN
THE BASE BID UNLESS NOTED AS AN
OPTION. SEE SHEET G1.0 FOR LIST
OF ALL BID OPTIONS.
3. CAREFULLY DISMANTLE MASONRY
WALL AS INDICATED, INCLUDING
LIMESTONE COPING STONES, CAPS,
AND BRICKS. TAKE CARE TO
SALVAGE EXISTING MARBLE AND
BRICKS FOR REUSE PER
SPECIFICATIONS.
4. REFER TO SHEET G1.0 FOR LIST OF
ALL ITEMS TO BE SALVAGED.
5. REFER TO THE RESTORATION SERIES
DRAWINGS FOR SCOPE OF BRICK
MASONRY REBUILDING, REPAIR, AND
CLEANING.
6. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
STABILIZATION OF MASONRY.
7. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
SUPPORT AND DETAILS.
S C A L E
O F
F E E T
W
ASH
INGTON, DC
P M
IS
P K G
N O
D R A W
IN
G
N O
S H E E T
S U B
S H E E T
N O
D E S
IG
N E D
PRIM
E/ARC
HITEC
TURE:
T
IT
L E
O F
S H E E T
O F
C A D D
T E C H
R E V
IE
W
D A T E
S C A L E
A
S m ith G ro u p
Structural:
Silm an B oston, M
A
C onsultant 2:
B uilding C onser Assoc B oston, M
A
6/13/2022 4:23:16 PM BIM 360://Client Projects - National Park Service/NPS_BOST 254798_DD & CD.rvtSJP
W E S T
E L E V A T
IO
N
A4.1
S J P
S J P
D O R C H E S T E R
H E
IG
H T S
M O N U M E N T
GENERAL SHEET NOTES
SCALE AA4.1
1 WEST ELEVATION
LEVEL 2
EL +43' - 3"
LEVEL 3
EL +56' - 8"
B.O. LANTERN
EL +79' - 6"
B.O. DOME
EL +87' - 11"
T.O. SPIRE/ B.O.
WEATHERVANE
EL +104' - 8"
TOP OF WEATHERVANE
EL +114' - 9"
E W
REPAINT AND RE-GILD
EXISTING WEATHERVANE;
SEE RESTORATION DWGS
REPOINT EXISTING
SPIRE STONES, REMOVE
METALLIC STAINING
ROOF 1: 20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS RED ROSIN
PAPER OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
PROVIDE PAINTED METAL
GRAVITY VENTILATOR SET ON
MANUFACTURER PROVIDED
CURB IN PLACE OF EXISTING
SKYLIGHT AT THE TOP OF
THE LEVEL 3 BELFRY
RESET STONES AND FOUR (4) URNS
THAT WERE REMOVED DURING PREVIOUS
EMERGENCY STABILIZATION; REFER TO
MASONRY RESTORATION DWGS
ROOF 2 & 3: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
REINSTALL OBELISKS, CORNER PIERS,
BALUSTRADE, AND RAILINGS THAT WERE
REMOVED DURING PREVIOUS EMERGENCY
STABILIZATION; REFER TO MASONRY
RESTORATION DWGS
EXISTING PASSIVE VENTILATION
LOUVERS IN SLOT WINDOWS
TO REMAIN
EXISTING PASSIVE VENTILATION
LOUVERS IN SLOT WINDOWS
TO REMAIN
REPLACE SELECT BALUSTERS
AT BALCONIES; REFER TO
RESTORATION DWGS
LEVEL 4
EL +72' - 4"
R E B U
IL
D
U P P E R
L E V E L S
O F
M O N U M E N T
F R O M
L E V E L
S T R U C T U R E
T O
T H E
T O P
O F
S P
IR
E
INSTALL BIRD NETTING
BEHIND LANTERN ARCHES
T O W E R
S T A
IR
W A Y
T O W E R
C H A M B E R
B E L F R Y
C
IR
C U L A R
D R U M
L A N T E R N
D O M E
S P
IR
E
W E A T H E R V A N E
MAINTAIN 1" UNDERCUT
BELOW BALUSTRADE
T.O. DOME
EL +92' - 0"
PROVIDE GUARDRAIL AT LEVEL 3
ARCHED OPENINGS; INSTALL BIRD NET
ON EXTERIOR SIDE OF GUARDRAIL
REMOVE AND RESET
ARCHITRAVE STONE; REFER
TO RESTORATION DWGS
RETAIN AND PROTECT
EXISTING BRONZE PLAQUE
ON NORTH FAÇADE
ROOF 4: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
INSTALL GUARDRAIL WITHIN
EXISTING MASONRY OPENING AT
LEVEL 2 DOORS AT NORTH,
EAST, & SOUTH FACADES;
INSTALL BIRD NET ON EXTERIOR
SIDE OF GUARDRAIL
REPLACE EXISTING TIE-RODS
NEW STAINLESS-STEEL RODS.
A A
A
1. PROTECT EXISTING TO REMAIN
MASONRY STRUCTURES AND
SURROUNDING LANDSCAPE AND
HARDSCAPE WITHIN THOMAS PARK.
2. ASSUME ALL SCOPE IS INCLUDED IN
THE BASE BID UNLESS NOTED AS AN
OPTION. SEE SHEET G1.0 FOR LIST
OF ALL BID OPTIONS.
3. CAREFULLY DISMANTLE MASONRY
WALL AS INDICATED, INCLUDING
LIMESTONE COPING STONES, CAPS,
AND BRICKS. TAKE CARE TO
SALVAGE EXISTING MARBLE AND
BRICKS FOR REUSE PER
SPECIFICATIONS.
4. REFER TO SHEET G1.0 FOR LIST OF
ALL ITEMS TO BE SALVAGED.
5. REFER TO THE RESTORATION SERIES
DRAWINGS FOR SCOPE OF BRICK
MASONRY REBUILDING, REPAIR, AND
CLEANING.
6. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
STABILIZATION OF MASONRY.
7. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
SUPPORT AND DETAILS.
S C A L E
O F
F E E T
W
ASH
INGTON, DC
P M
IS
P K G
N O
D R A W
IN
G
N O
S H E E T
S U B
S H E E T
N O
D E S
IG
N E D
PRIM
E/ARC
HITEC
TURE:
T
IT
L E
O F
S H E E T
O F
C A D D
T E C H
R E V
IE
W
D A T E
S C A m ith G ro u p
Structural:
Silm an B oston, M
A
C onsultant 2:
B uilding C onser Assoc B oston, M
A
6/13/2022 4:23:18 PM BIM 360://Client Projects - National Park Service/NPS_BOST 254798_DD & CD.rvtSJP
N O R T H
E L E V A T
IO
N
A4.2
S J P
S J P
D O R C H E S T E R
H E
IG
H T S
M O N U M E N T
SCALE AA4.2
1 NORTH ELEVATION
LEVEL 3
EL +56' - 8"
B.O. LANTERN
EL +79' - 6"
B.O. DOME
EL +87' - 11"
T.O. SPIRE/ B.O.
WEATHERVANE
EL +104' - 8"
TOP OF WEATHERVANE
EL +114' - 9"
SN1
REPAINT AND RE-GILD
EXISTING WEATHERVANE;
SEE RESTORATION DWGS
ROOF 1: 20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS RED ROSIN
PAPER OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
PROVIDE PAINTED METAL GRAVITY
VENTILATOR SET ON MANUFACTURER
PROVIDED CURB IN PLACE OF
EXISTING SKYLIGHT AT THE TOP OF
THE LEVEL 3 BELFRY
RESET ALL STONES AND FOUR (4)
URNS THAT WERE REMOVED DURING
PREVIOUS EMERGENCY STABILIZATION;
REFER TO MASONRY RESTORATION
DWGS
REPLACE EXISTING TIE-RODS
NEW STAINLESS-STEEL RODS.
ROOF 2 & 3: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS RED
ROSIN PAPER OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
REINSTALL OBELISKS, CORNER
PIERS, BALUSTRADE, AND RAILINGS
THAT WERE REMOVED DURING
PREVIOUS EMERGENCY
STABILIZATION; REFER TO MASONRY
RESTORATION DWGS
REMOVE FERROUS METAL
ANCHORS AT FOUR (4)
DOOR JAMBS AND PROVIDE
MARBLE DUTCHMEN
EXISTING PASSIVE VENTILATION
LOUVERS IN SLOT WINDOWS TO
REMAIN
REPLACE SELECT BALUSTERS
AT BALCONIES; REFER TO
RESTORATION DWGS
REMOVE AND RESET
ARCHITRAVE STONE; REFER
TO RESTORATION DWGS
LEVEL 4
EL +72' - 4"
R E B U
IL
D
U P P E R
L E V E L S
O F
M O N U M E N T
F R O M
L E V E L
S T R U C T U R E
T O
T H E
T O P
O F
S P
IR
E
INSTALL BIRD NETTING
BEHIND LANTERN ARCHES
S P
IR
E
D O M E
L A N T E R N
C
IR
C U L A R
D R U M
B E L F R Y
W E A T H E R V A N E
MAINTAIN 1" UNDERCUT
BELOW BALUSTRADE
LEVEL 2
EL +43'-3"
T O W E R
C H A M B E R
T O W E R
S T A
IR
W A Y
PROVIDE REMOVABLE GUARDRAIL
AND ZIPPER JOINT IN BIRD
NETTING AT EAST FACADE TO
PROVIDE ROOF ACCESS
PROVIDE GUARDRAIL AT LEVEL 3
ARCHED OPENINGS; INSTALL BIRD NET
ON EXTERIOR SIDE OF GUARDRAIL
INSTALL GUARDRAIL WITHIN
EXISTING MASONRY OPENING AT
LEVEL 2 DOORS AT NORTH,
EAST, & SOUTH FACADES;
INSTALL BIRD NET ON EXTERIOR
SIDE OF GUARDRAIL
A6.3
3 Sim
ROOF 4: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
A
A
A
1. PROTECT EXISTING TO REMAIN
MASONRY STRUCTURES AND
SURROUNDING LANDSCAPE AND
HARDSCAPE WITHIN THOMAS PARK.
2. ASSUME ALL SCOPE IS INCLUDED IN
THE BASE BID UNLESS NOTED AS AN
OPTION. SEE SHEET G1.0 FOR LIST
OF ALL BID OPTIONS.
3. CAREFULLY DISMANTLE MASONRY
WALL AS INDICATED, INCLUDING
LIMESTONE COPING STONES, CAPS,
AND BRICKS. TAKE CARE TO
SALVAGE EXISTING MARBLE AND
BRICKS FOR REUSE PER
SPECIFICATIONS.
4. REFER TO SHEET G1.0 FOR LIST OF
ALL ITEMS TO BE SALVAGED.
5. REFER TO THE RESTORATION SERIES
DRAWINGS FOR SCOPE OF BRICK
MASONRY REBUILDING, REPAIR, AND
CLEANING.
6. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
STABILIZATION OF MASONRY.
7. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
SUPPORT AND DETAILS.
S C A L E
O F
F E E T
W
ASH
INGTON, DC
P M
IS
P K G
N O
D R A W
IN
G
N O
S H E E T
S U B
S H E E T
N O
D E S
IG
N E D
PRIM
E/ARC
HITEC
TURE:
T
IT
L E
O F
S H E E T
O F
C A D D
T E C H
R E V
IE
W
D A T E
S C A m ith G ro u p
Structural:
Silm an B oston, M
A
C onsultant 2:
B uilding C onser Assoc B oston, M
A
6/13/2022 4:23:20 PM BIM 360://Client Projects - National Park Service/NPS_BOST 254798_DD & CD.rvtSJP
E A S T
E L E V A T
IO
N
A4.3
S J P
S J P
D O R C H E S T E R
H E
IG
H T S
M O N U M E N T
SCALE AA4.3
1 EAST ELEVATION
LEVEL 2
EL +43' - 3"
LEVEL 3
EL +56' - 8"
B.O. LANTERN
EL +79' - 6"
B.O. DOME
EL +87' - 11"
T.O. SPIRE/ B.O.
WEATHERVANE
EL +104' - 8"
TOP OF WEATHERVANE
EL +114' - 9"
N E
REPAINT AND RE-GILD
EXISTING WEATHERVANE;
SEE RESTORATION DWGS
ROOF 1: 20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS RED ROSIN
PAPER OVER SELF-ADHERED
POLYETHYLENE FACED UNDERLAYMENT
PROVIDE PAINTED METAL
GRAVITY VENTILATOR SET ON
MANUFACTURER PROVIDED
CURB IN PLACE OF EXISTING
SKYLIGHT AT THE TOP OF THE
LEVEL 3 BELFRY
RESET STONES AND FOUR (4) URNS
THAT WERE REMOVED DURING
PREVIOUS EMERGENCY STABILIZATION;
REFER TO MASONRY RESTORATION
DWGS
ROOF 2 & 3: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
REINSTALL OBELISKS, CORNER PIERS,
BALUSTRADE, AND RAILINGS THAT WERE
REMOVED DURING PREVIOUS EMERGENCY
STABILIZATION; REFER TO MASONRY
RESTORATION DWGS
EXISTING PASSIVE
VENTILATION LOUVERS IN
SLOT WINDOWS TO REMAIN
EXISTING PASSIVE
VENTILATION LOUVERS IN
SLOT WINDOWS TO REMAIN
REPLACE SELECT
BALUSTERS AT
BALCONIES; REFER TO
RESTORATION DWGS
LEVEL 4
EL +72' - 4"
R E B U
IL
D
U P P E R
L E V E L S
O F
M O N U M E N T
F R O M
L E V E L
S T R U C T U R E
T O
T H E
T O P
O F
S P
IR
E
INSTALL BIRD NETTING
BEHIND LANTERN ARCHES
S P
IR
E
D O M E
L A N T E R N
C
IR
C U L A R
D R U M
T O W E R
S T A
IR
W A Y
W E A T H E R V A N E
MAINTAIN 1" UNDERCUT
BELOW BALUSTRADE
T.O. DOME
EL +92' - 0"
B E L F R Y
T O W E R
C H A M B E R
PROVIDE GUARDRAIL AT LEVEL 3
ARCHED OPENINGS; INSTALL BIRD NET
ON EXTERIOR SIDE OF GUARDRAIL
REMOVE AND RESET
ARCHITRAVE STONE; REFER
TO RESTORATION DWGS
ROOF 4: 20 OZ. ZINC-TIN
COATED COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
INSTALL GUARDRAIL WITHIN
EXISTING MASONRY OPENING
AT LEVEL 2 DOORS AT NORTH,
EAST, & SOUTH FACADES;
INSTALL BIRD NET ON
EXTERIOR SIDE OF GUARDRAIL
REPLACE EXISTING TIE-RODS
NEW STAINLESS-STEEL RODS.
A
A
A
1. PROTECT EXISTING TO REMAIN
MASONRY STRUCTURES AND
SURROUNDING LANDSCAPE AND
HARDSCAPE WITHIN THOMAS PARK.
2. ASSUME ALL SCOPE IS INCLUDED IN
THE BASE BID UNLESS NOTED AS AN
OPTION. SEE SHEET G1.0 FOR LIST
OF ALL BID OPTIONS.
3. CAREFULLY DISMANTLE MASONRY
WALL AS INDICATED, INCLUDING
LIMESTONE COPING STONES, CAPS,
AND BRICKS. TAKE CARE TO
SALVAGE EXISTING MARBLE AND
BRICKS FOR REUSE PER
SPECIFICATIONS.
4. REFER TO SHEET G1.0 FOR LIST OF
ALL ITEMS TO BE SALVAGED.
5. REFER TO THE RESTORATION SERIES
DRAWINGS FOR SCOPE OF BRICK
MASONRY REBUILDING, REPAIR, AND
CLEANING.
6. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
STABILIZATION OF MASONRY.
7. REFER TO THE STRUCTURAL SERIES
DRAWINGS FOR ALL STRUCTURAL
SUPPORT AND DETAILS.
S C A L E
O F
F E E T
W
ASH
INGTON, DC
P M
IS
P K G
N O
D R A W
IN
G
N O
S H E E T
S U B
S H E E T
N O
D E S
IG
N E D
PRIM
E/ARC
HITEC
TURE:
T
IT
L E
O F
S H E E T
O F
C A D D
T E C H
R E V
IE
W
D A T E
S C A m ith G ro u p
Structural:
Silm an B oston, M
A
C onsultant 2:
B uilding C onser Assoc B oston, M
A
6/13/2022 4:23:22 PM BIM 360://Client Projects - National Park Service/NPS_BOST 254798_DD & CD.rvtSJP
S O U T H
E L E V A T
IO
N
A4.4
S J P
S J P
D O R C H E S T E R
H E
IG
H T S
M O N U M E N T
SCALE AA4.4
1 SOUTH ELEVATION
LEVEL 3
TOP TREAD OF STAIR 7
7'-2 1/2"
LEVEL 2
STEEL LEDGER; SEE
STRUCTURAL DWGS
STEEL LEDGER; SEE
STRUCTURAL DWGS
CONT. STL PLATE; SEE
STRUCTURAL DWGS
SEE STRUCTURAL
DWGS FOR FRAMING
SUPPORT
8 1/2" 1'-0"
BOLTED CONNECTION BETWEEN STEEL
STAIR ENCLOSURE AND STRUCTURAL
FRAMING; SEE STRUCTURAL DWGS
CIRCULAR BENT PLATE POUR STOP TO
SUPPORT SLAB EDGE AND STAIR
ENCLOSURE; SEE STRUCTURAL DWGS
EXISTING MARBLE
CORNICE STONE
1/4" PER FT (2%) SLOPED CONCRETE
TOPPING SLAB WITH CURB AT STAIR EDGE
FINISHED WITH FLUID APPLIED URETHANE
TRAFFIC COATING OVER PMMA ROOFING
ROOF 4: TOWER CHAMBER CORNICE
20 OZ. ZINC-TIN COATED COPPER
WITH 2 LAYERS RED ROSIN PAPER
OVER SELF-ADHERED POLYETHYLENE
FACED UNDERLAYMENT
SPIRAL STAIR ENCLOSURE; SEE
SHEET A6.10 & A6.11 FOR DETAILS
HISTORIC
SPIRAL STAIR;
PROTECT
DURING
CONSTRUCTION
C E N T E R L
IN
E
O F
S P
IR
A L
S T A
IR
NON-SHRINK GROUT
MARBLE JAMB
1'-8 1/2"
SELF-ADHERED POLYETHYLENE
FACED UNDERLAYMENT AND PMMA
ROOFING INSTALLED CONTINUOUS
UNDER MARBLE THRESHOLD
GALVANIZED STEEL BASE RING WITH
HIGH PERFROMANCE COATING
GENERAL NOTE:
PROVIDE SOLDERED FLAT SEAM 20 OZ. ZINC-TIN COATED
COPPER, SEAMS ARE TO BE PERPENDICULAR TO THE WALLS
OF THE TOWER, SLOPE TO DRAIN, UNLESS NOTED OTHERWISE
EXISTING MARBLE FACE
STONE TO REMAIN
EXISTING BACKUP WALL TO REMAIN
LINE DENOTING LIMIT OF
MONUMENT DISMANTLING AND
REBUILDING; MONUMENT
STRUCTURAL FRAMING AND
MASONRY TO BE DISMANTLED
FROM LEVEL 3 STRUCTURE TO
TO THE TOP OF THE SPIRE &
WEATHERVANE
BRICK BARREL VAULT
BETWEEN STEEL
LEDGERS, 3-WYTHES;
7'-0" RADIUS AT
BOTTOM EDGE
SEE STRUCTURAL DWGS
FOR FRAMING SUPPORT
4" CLEATED
DRIP EDGE
A6.9
MAINTAIN 1" UNDERCUT
BELOW BALUSTRADE
REPAIR AND REBUILD UPPER
PORTIONS OF LEVEL 2 WALLS
AS REQUIRED FOLLOWING
INSTALLATION OF NEW STEEL
STRUCTURE AT LEVEL 3
A6.11
A6.9
PMMA ROOFING TO
LAP OVER BACK LEG
OF SILL PAN; SILL
PAN WITH END DAMS
INSTALLED UNDER
MARBLE THRESHOLD;
INCLUDE DRAINAGE
PAN BETWEEN THE
STONE AND SILL PAN;
SEE DETAIL 1/A6.9
A
A
REPLACE SELECT
BALUSTERS AT
BALCONIES; REFER TO
RESTORATION DWGS
6"11"
METAL GUARDRAIL
INSTALLED WITHIN
EXISTING MASONRY JAMB
IN FRONT OF LEVEL 2
DOORS; FINISH STEEL
SURFACES WITH A
PRIMER AND HIGH-
PERFORMANCE COATING
PROVIDE METAL DOOR, W/ SIX (6) GLAZED
PANELS AND TWO (2) PASSIVE VENTILATION
LOUVERS AT THE BASE; PROVIDE LOUVERS
WITH INTEGRAL BIRD SCREEN IN BOTTOM
RECESSED PANELS OF DOOR
INSTALL BIRD NET
ON EXTERIOR SIDE
OF GUARDRAIL
A6.8
2 Sim
12 0 126
SCALE OF INCHES
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :2
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
LEVEL 2 & LEVEL 3
SECTION DETAILS
254798A5.1
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA5.1
2 LEVEL 3 SECTION DETAIL AT DOOR
SCALE AA5.1
1 LEVEL 2 BALCONY ROOFING DETAIL
LEVEL 3
TOP TREAD OF STAIR
BOLTED CONNECTION BETWEEN STEEL
STAIR ENCLOSURE AND STRUCTURAL
FRAMING; SEE STRUCTURAL DWGS
7'-2 1/2"
LEVEL 2
SEE STRUCTURAL DWGS
FOR FRAMING SUPPORT
STEEL LEDGER; SEE
STRUCTURAL DWGS
STEEL LEDGER; SEE
STRUCTURAL DWGS
CONT. STL PLATE; SEE
STRUCTURAL DWGS
CIRCULAR BENT PLATE POUR STOP TO
SUPPORT SLAB EDGE AND STAIR
ENCLOSURE; SEE STRUCTURAL DWGS
SEE STRUCTURAL DWGS
FOR FRAMING SUPPORT
EXISTING MARBLE
CORNICE STONE
1/4" PER FT (2%) SLOPED CONCRETE
TOPPING SLAB WITH CURB AT STAIR EDGE
FINISHED WITH FLUID APPLIED URETHANE
TRAFFIC COATING OVER PMMA ROOFING
RESET MARBLE FACE
STONE; SEE
RESTORATION DWGS
GROUTED CMU; SEE
STRUCTURAL DWGS
BUFF/ YELLOW BRICK
VENEER TO MATCH
ORIGINAL
5 1/2"
10"
5"
20 OZ. THROUGH
WALL FLASHING
DAMPPROOFING ON CMU WALL, BOTH SIDES
ROOF 4: TOWER CHAMBER CORNICE
20 OZ. ZINC-TIN COATED COPPER
WITH 2 LAYERS RED ROSIN PAPER
OVER SELF-ADHERED POLYETHYLENE
FACED UNDERLAYMENT
SPIRAL STAIR ENCLOSURE; SEE
SHEET A6.10 & A6.11 FOR DETAILS
HISTORIC SPIRAL
STAIR; PROTECT
DURING CONSTRUCTION
4'-10 1/2"
C E N T E R L
IN
E
O F
S P
IR
A L
S T A
IR
GALVANIZED STEEL BASE RING WITH
HIGH PERFROMANCE COATING
BRICK BARREL VAULT BETWEEN
STEEL LEDGERS, 2-WYTHES;
7'-0" RADIUS AT BOTTOM EDGE
EXISTING MARBLE FACE
STONE TO REMAIN
EXISTING BRICK BACKUP
WALL TO REMAIN
LINE DENOTING LIMIT OF
MONUMENT DISMANTLING AND
REBUILDING; MONUMENT
STRUCTURAL FRAMING AND
MASONRY TO BE DISMANTLED
FROM LEVEL 3 STRUCTURE
TO TO THE TOP OF THE
SPIRE & WEATHERVANE
4" CLEATED
DRIP EDGE
A6.11
MAINTAIN 1" UNDERCUT
BELOW BALUSTRADE
GENERAL NOTE:
PROVIDE SOLDERED FLAT SEAM 20 OZ. ZINC-TIN COATED
COPPER, SEAMS ARE TO BE PERPENDICULAR TO THE WALLS
OF THE TOWER, SLOPE TO DRAIN, UNLESS NOTED OTHERWISE
REPAIR AND REBUILD UPPER
PORTIONS OF LEVEL 2 WALLS
AS REQUIRED FOLLOWING
INSTALLATION OF NEW STEEL
STRUCTURE AT LEVEL 3
A5.7
1 AXO
VIEW
PARGE BRICK
AS PREP FOR
PMMA ROOFING
OPEN HEAD JOINT
WEEP HOLES @ 24"
O.C. MINIMUM ABOVE
FLASHING
OPEN HEAD JOINT
WEEP HOLES @ 24"
O.C. MINIMUM ABOVE
FLASHING
SEALANT OR
TRANSITION PER
PMMA MANUFACTURER
ADJUSTABLE HEIGHT PINTEL TIE WITH LADDER-
TYPE HORIZONTAL REINFORCEMENT EVERY 16”
O.C. VERTICAL AND 16" O.C. HORIZONTALLY
SPLIT TAIL ANCHORS,
SEE MASONRY
RESTORATION DWGS;
SEAL ALL ANCHOR
PENETRATIONS
SET LADDER-TYPE REINFORCEMENT
AND ANCHORS IN SEALANT WHERE
THEY PENETRATE THE DAMPROOFING;
APPLY DAMPPROOFING AROUND
PENETRATIONS TO PROPERLY SEAL
GROUT VOIDS
UNDER FLASHING
A
A
A
A
A
12 0 126
SCALE OF INCHES
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :2
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
LEVEL 3 SECTION
DETAILS
254798A5.2
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA5.2
1 LEVEL 3 SECTION DETAIL AT WALL
B.O. LANTERN
79'-6"
LEVEL 4
72'-4"
PARTIALLY RECESSED CURB
WITH CANTED FLASHING
INSTALL GALV STEEL CHANNEL FRAMING TO
SUPPORT GRAVITY VENTILATOR IN CIRCULAR
OPENING; SEE STRUCTURAL DWGS
FACTORY FINISHED METAL GRAVITY
VENTILATOR SET ON MANUFACTURER
PROVIDED CURB AT THE TOP OF
THE LEVEL 3 BELFRY
ROOF 1: LANTERN BASE
INSTALL NEW 20 OZ. ZINC-TIN
COATED COPPER ROOFING OVER
SELF ADHERED POLYETHYLENE
FACED UNDERLAYMENT
ROOF 2: URN PLATFORM
INSTALL 20 OZ. ZINC-TIN
COATED COPPER ROOFING
OVER SELF-ADHERED
POLYETHYLENE FACED
UNDERLAYMENT
ROOF 3: BELFRY CORNICE
INSTALL 20 OZ. ZINC-TIN
COATED COPPER ROOFING
OVER SELF-ADHERED
POLYETHYLENE FACED
RUBBERIZED ASPHALT
UNDERLAYMENT
RESET FOUR (4) URNS REMOVED
DURING PREVIOUS EMERGENCY
STABILIZATION; SEE MASONRY
RESTORATION DWGS
20 OZ. THROUGH
WALL FLASHING
ZINC-TIN COATED COPPER
CAP SLEEVE OVER STN STL
PIN; SOLDER TO ROOFING
20 OZ. THROUGH WALL FLASHING
STN STL TIE DOWN ROD AT EIGHT (8)
LOCATIONS; SEE STRUCTURAL DWGS
INSTALL NEW RED
BRICK VENEER AT
INTERIOR OF CIRCULAR
DRUM; REPLACE
PARGING AT INTERIOR
OF BRICK DRUM
MARBLE CLADDING
SECURED TO CMU BACKUP
WALL; SEE STRUCTURAL
AND RESTORATIONN DWGS
SEE STRUCTURAL DWGS
FOR LEVEL 4 SUPPORT
STRUCTURE AT BASE
OF CIRCULAR DRUM
REPLACE CANTILEVERED
LIMESTONE SLABS AT
BASE OF LEVEL 4
FRAMING
RESET EXISTING MARBLE
CLADDING; SEE
RESTORATION DWGS
INSTALL BUFF/ YELLOW BRICK
VENEER TO MAT ORIGINAL
A6.9
BASE OF URN
BASE OF LIMESTONE SOFFIT
C E N T E R L
IN
E
O F
L A N T E R N
SEE STRUCTURAL DWGS
FOR FRAMING SUPPORT
A5.7
1 SIMILAR
AXO VIEW
A5.4
A5.5
A5.6
CUSTOM STEEL CHANNEL
RING SUPPORT AT INSIDE
EDGE OF NEW LIMESTONE
SLABS, PAINTED TO
MATCH LIMESTONE; SEE
STRUCTURAL DWGS
GROUTED CMU BLOCK;
SEE STRUCTURAL DWGS
GROUTED CMU BLOCK;
SEE STRUCTURAL DWGS
20 OZ. THROUGH WALL
FLASHING CONTINUOUS
ABOVE LEVEL 3 ARCHED
OPENINGS
ANCHOR EXISTING MARBLE CLADDING ON
CMU BACKUP; IRREGULAR SURFACE OF
MARBLE CLADDING MAY REQUIRE CUTTING
AND ADJUSTMENTS IN BRICK FILL TO
MAINTAIN ORIGINAL DIMENSIONS
OPEN HEAD JOINT WEEP HOLES @
24" O.C. MINIMUM ABOVE FLASHING
STN STL TIE DOWN ROD
AT EIGHT (8) LOCATIONS;
SEE STRUCTURAL DWGS
PROVIDE 1" OPEN
HEAD JOINT/
WEEPS IN WALL
PROVIDE BUILT-UP CMU WALL BEHIND
STEEL TO PROVIDE CONTINUOUS
WATERPROOFING SUBSTRATE
THROUGH WALL FLASHING
UNDER DAMPPROOFING
TRANSITION
A
A
A
A
S C A L E
O F
F E E T
W
ASH
INGTON, DC
P M
IS
P K G
N O
D R A W
IN
G
N O
S H E E T
S U B
S H E E T
N O
D E S
IG
N E D
PRIM
E/ARC
HITEC
TURE:
T
IT
L E
O F
S H E E T
O F
C A D D
T E C H
R E V
IE
W
D A T E
S C A m ith G ro u p
Structural:
Silm an B oston, M
A
C onsultant 2:
B uilding C onser Assoc B oston, M
A
6/13/2022 4:23:25 PM BIM 360://Client Projects - National Park Service/NPS_BOST 254798_DD & CD.rvtSJP
L E V E L
D R U M A N D
L A N T E R N
S E C T
IO
N
D E T A
IL
S
A5.3
S J P
S J P
D O R C H E S T E R
H E
IG
H T S
M O N U M E N T
SCALE AA5.3
1 LEVEL 4, DRUM, AND LANTERN SECTION DETAILS
ROOF 2:
URN
PLATFORM
ROOF 1:
LANTERN
BASE
ROOF 3:
BELFRY
CORNICE
ROOF 4:
TOWER
CHAMBER
CORNICE
R 2' - 3"
R 2' - 9"
A5.3
MASONRY
OPENING BELOW
TOP DOME OF
GRAVITY VENTILATOR
CURB AND FLANGE
SUPPORTING
GRAVITY VENTILATOR
REPLACE EIGHT (8)LANTERN TIE
RODS WITH NEW STN STL TIE RODS;
SEE STRUCTURAL DWGS; PROVIDE
FLUID APPLIED PMMA FLASHING AT
BASE OF RODS TO ZINC-TIN COATED
COPPER; SEE STRUCTURAL DWGS
PROVIDE PAINTED METAL GRAVITY
VENTILATOR SET ON MANUFACTURER
PROVIDED CURB AT THE TOP OF
THE LEVEL 3 BELFRY
ROOF 1: LANTERN BASE
20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS
RED ROSIN PAPER OVER
SELF-ADHERED
POLYETHYLENE FACED
UNDERLAYMENT
ROOF 1
ROOF 2
ROOF 2
ROOF 1
A5.3
RESET FOUR (4) URNS REMOVED
DURING PREVIOUS EMERGENCY
STABILIZATION; SEE MASONRY
RESTORATION DWGS
RESET FOUR (4) URNS REMOVED
DURING PREVIOUS EMERGENCY
STABILIZATION; SEE MASONRY
RESTORATION DWGS
A
A
SCALE OF FEET
1 1 20
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :2
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
S J P
ENLARGED ROOF PLAN
DETAILS
254798A5.4
SJP
SJP
DORCHESTER HEIGHTS MONUMENT1/21/2022
A5.4
1 AERIAL VIEW OF ROOFING
SCALE AA5.4
2 ROOF 1 PLAN AT LANTERN
REPLACE EIGHT (8)LANTERN TIE
RODS WITH NEW STN STL TIE
RODS; SEE STRUCTURAL DWGS;
PROVIDE FLUID APPLIED PMMA
FLASHING AT BASE OF RODS TO
ZINC-TIN COATED COPPER; SEE
STRUCTURAL DWGS
ROOF 2
OPEN TO
BELOW
INSTALL NEW RED BRICK VENEER
AT INTERIOR OF CIRCULAR DRUM;
REPLACE PARGING AT INTERIOR
OF BRICK DRUM
REPLACE
CANTILEVERED
LIMESTONE SLABS
AT BASE OF
LEVEL 4 FRAMING
ROOF 2
A5.3
ROOF 2: URN PLATFORM
20 OZ. ZINC-TIN COATED
COPPER WITH 2 LAYERS RED
ROSIN PAPER OVER SELF-
ADHERED POLYETHYLENE
FACED UNDERLAYMENT
RESET FOUR (4) URNS REMOVED
DURING PREVIOUS EMERGENCY
STABILIZATION; SEE MASONRY
RESTORATION DWGS
ANCHOR EXISTING MARBLE CLADDING ON
CMU BACKUP; IRREGULAR SURFACE OF
MARBLE CLADDING MAY REQUIRE CUTTING
AND ADJUSTMENTS IN BRICK FILL TO
MAINTAIN ORIGINAL DIMENSIONS
BRICK INFILL BETWEEN
MARBLE AND CMU TO ALLOW
FOR IRREGULARITIES AND
TOLERANCE IN INSTALLATION
RESET FOUR (4) URNS REMOVED
DURING PREVIOUS EMERGENCY
STABILIZATION; SEE MASONRY
RESTORATION DWGS
GROUTED CMU BLOCK;
SEE STRUCTURAL DWGS
STEEL OUTRIGGER TO
SUPPORT TIE RODS AND
LIMESTONE SOFFIT BELOW;
SEE STRUCTURAL DWGS
A
A
SCALE OF FEET
1 1 20
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :2
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
ENLARGED ROOF PLAN
DETAILS
254798A5.5
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA5.5
1 ROOF 2 PLAN AT URN PLATFORM
OPEN TO
BELOW
REPLACE EIGHT (8) LANTERN TIE
RODS WITH NEW STN STL TIE
RODS; SEE STRUCTURAL DWGS;
SEE STRUCTURAL DWGS
REPLACE
CANTILEVERED
LIMESTONE SLABS
AT BASE OF
LEVEL 4 FRAMING
INSTALL NEW RED BRICK
VENEER AT INTERIOR OF
CIRCULAR DRUM; REPLACE
PARGING AT INTERIOR OF
BRICK DRUM
SEE STRUCTURAL DWGS
FOR LEVEL 4 SUPPORT
STRUCTURE AT BASE OF
CIRCULAR DRUM
SEE STRUCTURAL DWGS
FOR STEEL PLATE ABOVE
STEEL BEAMS TO SUPPORT
STRUCTURAL CMU BLOCK
A5.3
ROOF 3
ROOF 3
ROOF 3: LANTERN BASE
20 OZ. ZINC-TIN
COATED COPPER WITH 2
LAYERS RED ROSIN
PAPER OVER SELF-
ADHERED POLYETHYLENE
FACED UNDERLAYMENT
GROUTED CMU BLOCK;
SEE STRUCTURAL DWGS
STEEL OUTRIGGER TO
SUPPORT TIE RODS AND
LIMESTONE SOFFIT BELOW;
CONNECT TO OUTER
STEEL BEAMS; SEE
STRUCTURAL DWGS
GROUTED CMU BLOCK;
SEE STRUCTURAL DWGS
MARBLE CLADDING SECURED
TO CMU BACKUP WALL; SEE
STRUCTURAL AND
RESTORATIONN DWGS
GROUTED CMU BACKUP AT
CORNER UNDER URN; SEE
STRUCTURAL DWGS
EIGHT (8) STN STL RODS
AND BENT PLATES
SUPPORTING CUSTOM STEEL
CHANNEL RING AT INSIDE
EDGE OF NEW LIMESTONE
SLABS, PAINTED TO MATCH
LIMESTONE; SEE STRUCTURAL
DWGS
STEEL PLATE ABOVE
BEAMS TO SUPPORT
GROUTED CMU; SEE
STRUCTURAL DWGS
PARTIALLY EMBED STEEL
OUTRIGGERS AND BENT
PLATES IN BRICK AND CMU
ASSEMBLY TO CONCEAL
FROM VIEW; HORIZONTAL
LEG OF BENT PLATE
EXPOSED TO SECURE TIE
ROD FROM LANTERN ABOVE
AND STEEL RING AT
LIMESTONE SOFFIT BELOW
STEEL PLATE ABOVE
BEAMS TO SUPPORT
GROUTED CMU; SEE
STRUCTURAL DWGS
A
SCALE OF FEET
1 1 20
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :2
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
ENLARGED ROOF PLAN
DETAILS
254798A5.6
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA5.6
1 ROOF 3 PLAN BELOW URN PLATFORM
SALVAGED MARBLE CLADDING
RESET AND ANCHORED INTO NEW
CMU BACKUP; SEE MASONRY
RESTORATION DWGS
SPLIT TAIL STRAP
ANCHOR, TWO (2)
INSTALLED AT TOP AND
BOTTOM JOINTS BETWEEN
STONES; SEE MASONRY
RESTORATION DWGS
PREFABRICATED FLASHING
AT OUTSIDE AND INSIDE
CORNERS OF MASONRY
GROUTED CMU BLOCK, REFER
TO STRUCTURAL DRAWINGS
SINGLE WYTHE
BRICK VENEER
AT INTERIOR
ADJUSTABLE HEIGHT PINTEL
TIE WITH LADDER-TYPE
HORIZONTAL REINFORCEMENT
EVERY 16” O.C. VERTICAL
AND 16" O.C. HORIZONTALLY
1" MINIMUM AIR SPACE TO
ALLOW SPACE FOR INSTALLATION
OF LADDER-TYPE HORIZONTAL
REINFORCEMENT BETWEEN CMU
AND BRICK
OPEN HEAD JOINT WEEP
HOLES @ 24" O.C.
MINIMUM ABOVE FLASHING
CONTINUOUS THROUGH
WALL FLASHING FROM
INTERIOR BRICK
THROUGH CMU TO
EXTERIOR MARBLE
CLADDING
1" MINIMUM AIR SPACE
TO ALLOW SPACE FOR
INSTALLATION OF SPLIT
TAIL STRAP ANCHORS
BETWEEN MARBLE
CLADDING AND CMU
CONTINUOUS
THROUGH WALL
FLASHING FROM
INTERIOR
BRICK
THROUGH CMU
TO EXTERIOR
MARBLE
CLADDING
SPLIT TAIL ANCHORS, SEE
MASONRY RESTORATION DWGS;
SEAL ALL ANCHOR
PENETRATIONS AT FLASHING
SIMILAR TO DETAIL 5/ A5.7
A
SALVAGED MARBLE CLADDING
RESET AND ANCHORED INTO
NEW CMU BACKUP; SEE
MASONRY RESTORATION DWGS
SPLIT TAIL STRAP ANCHOR,
TWO (2) INSTALLED AT
TOP AND BOTTOM JOINTS
BETWEEN STONES; SEE
MASONRY RESTORATION
DWGS; SEAL ALL ANCHOR
PENETRATIONS AT
FLASHING SIMILAR TO
DETAIL 5/ A5.7
STN STL THREADED ROD
ANCHOR INTO GROUNTED
CMU BACKUP; SEE MASONRY
RESTORATION DWGS
GROUTED CMU BLOCK, REFER
TO STRUCTURAL DRAWINGS
SINGLE WYTHE BRICK
VENEER AT INTERIOR
ADJUSTABLE HEIGHT PINTEL TIE WITH
LADDER-TYPE HORIZONTAL
REINFORCEMENT EVERY 16” O.C.
VERTICAL AND 16" O.C. HORIZONTALLY1" MINIMUM AIR SPACE
TO ALLOW SPACE FOR
INSTALLATION OF SPLIT
TAIL STRAP ANCHORS
BETWEEN MARBLE
CLADDING AND CMU
SOLID GROUT BELOW FLASHING
OPEN HEAD JOINT WEEP
HOLES @ 24" O.C.
MINIMUM ABOVE FLASHING
LEVEL 3 INTERIOR FLOOR SLAB
CONTINUOUS THROUGH WALL FLASHING
FROM INTERIOR BRICK THROUGH CMU
TO EXTERIOR MARBLE CLADDING
1/4" PER FT (2%) SLOPED
CONCRETE TOPPING SLAB
WITH CURB AT STAIR EDGE
FINISHED WITH FLUID APPLIED
URETHANE TRAFFIC COATING
OVER PMMA ROOFING
PARGE BRICK AS PREP
FOR PMMA ROOFING
SEALANT OR TRANSITION PER
PMMA MANUFACTURER
ROOF 4: TOWER CHAMBER CORNICE
INSTALL 20 OZ. ZINC-TIN COATED
COPPER ROOFING OVER SELF-
ADHERED POLYETHYLENE FACED
UNDERLAYMENT
1" MINIMUM AIR SPACE TO ALLOW
SPACE FOR INSTALLATION OF LADDER-
TYPE HORIZONTAL REINFORCEMENT
BETWEEN CMU AND BRICK
HEIGHT OF FLASHING TO ALIGN WITH
EXISTIG MORTAR JOINTS; MINIMUM 8"
IN HEIGHT WHERE POSSIBLE
HEIGHT OF FLASHING TO ALIGN WITH
EXISTIG MORTAR JOINTS; MINIMUM 8"
IN HEIGHT WHERE POSSIBLE
A
A
A
A
A
NEW 20 OZ. ZINC-TIN
COATED COPPER SHEET
UNDERLAYMENT
TWO (2) LAYERS
RED ROSIN PAPER
COMPLETELY FILL SEAMS
WITH SOLDER
NEW FASTENER AND INSERTREINSTALLED MASONRY
A
NEW COPPER CLEAT
NEW 20 OZ. ZINC-TIN
COATED COPPER SHEET
FOLD CLEAT TAB OVER
FASTENER HEAD
UNDERLAYMENT
TWO (2) LAYERS
RED ROSIN PAPER
COMPLETELY FILL SEAMS
WITH SOLDER
NEW FASTENER AND INSERTREINSTALLED MASONRY
A
STN STL DOWEL
UNDERLAYMENT
TWO (2) LAYERS
RED ROSIN PAPER
SEALANT AROUND DOWEL
AT UNDERLAYMENT
REINSTALLED MASONRY
ZINC-TIN COATED
COPPER CAP WELDED
TO ROOFING AND/
OR FLASHING
A
2 2 40
SCALE OF FEET
12 0 126
SCALE OF INCHES
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SCALE B
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :2
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
ROOFING AND FLASHING
DETAILS
254798A5.7
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA5.7
2 OUTSIDE CORNER FLASHING DETAIL
SCALE AA5.7
1 THROUGH WALL FLASHING DETAIL
SCALE BA5.7
3 TYPICAL SOLDERED COPPER JOINT
SCALE BA5.7
4 TYPICAL SOLDERED COPPER JOINT AT CLEAT
SCALE BA5.7
5 TYPICAL DOWEL CONNECTION AT MASONRY
MASONRY OPENING
4'-8" +/-
EXISTING STONE FRAME TO
REMAIN; PATCH MASONRY; SEE
MASONRY RESTORATION DRAWINGS
A6.3
A6.3
A6.1
CUSTOM BRONZE
STORM RESISTANT
PASSIVE VENTILATION
LOUVER WITH
INTEGRAL BIRD
SCREEN IN EXISTING
OPENING (OPTION D)
REINSTALL EXISTING
HISTORIC BRONZE
DOOR FOLLOWING
CLEANING, REPAIR,
AND RESTORATION
(OPTION D)
A6.1
REMOVE EXISTING LOUVER SET
WITHIN HISTORIC METAL DOOR;
INSTALL STORM RESISTANT
PASSIVE VENTILATION LOUVER
WITH INTEGRAL BIRD SCREEN
IN EXISTING OPENING
(OPTION D)
PATCH AND REPAIR
DOOR AT LOCATION
OF REMOVED LOCK
(OPTION D)
REINSTALL EXISTING
HISTORIC BRONZE
DOOR FOLLOWING
CLEANING, REPAIR,
AND RESTORATION
(OPTION D)
REMOVE EXISTING PAINT
COATINGS; REPAIR DAMAGE TO
BRONZE COMPONENTS
INCLUDING HOLES AND
DEFORMATIONS; CLEAN AND
RESTORE PATINA TO HISTORIC
BRONZE
(OPTION D)
LEVEL 1
EL +0' - 0"
M.O.
4'-8" +/-
M .O
2'-6 5/8"
INSTALL CUSTON
BRONZE STORM
RESISTANT PASSIVE
VENTILATION LOUVER
WITH INTEGRAL BIRD
SCREEN IN EXISTING
OPENING (OPTION D)
INSTALL NEW DOOR
HANDLE AND HEAVY
DUTY DEADBOLT
LOCK (OPTION D)
A F F
A6.1
REINSTALL EXISTING
HISTORIC BRONZE
DOOR FOLLOWING
CLEANING, REPAIR,
AND RESTORATION
(OPTION D)
REMOVE EXISTING PAINT
COATINGS; REPAIR
DAMAGE TO BRONZE
COMPONENTS
INCLUDING HOLES AND
DEFORMATIONS; CLEAN
AND RESTORE PATINA
TO HISTORIC BRONZE
(OPTION D)
REMOVE EXISTING
LOUVER SET WITHIN
HISTORIC METAL
DOOR (OPTION D)
REMOVE EXISTING
STEEL BOX
ENCLOSURE AND
HANDLE TO REPAIR
DOOR AND PROVIDE
NEW HARDWARE AND
LOCKING DEVICE
(OPTION D)
CAREFULLY REMOVE
EXISTING BRONZE ENTRY
DOOR AND FRAME FOR
CLEANING, REPAIR, AND
RESTORATION; TAKE
PRECAUTIONS NOT TO
DAMAGE SURROUNDING
MASONRY (OPTION D)
CUSTOM BRONZE STORM
RESISTANT LOUVER
INSTALLED IN EXISTING
OPENING IN HISTORIC
BRONZE ENTRY DOOR
HISTORIC BRONZE ENTRY
DOOR
2 1/2"
FORMED SILL PAN
FOR DRAINAGE
INTEGRAL BIRD
SCREEN ON
INTERIOR FACE
OF LOUVER
TERMINATE
BIRD SCREEN
WITHIN BACK
LEG OF SILL
PAN TO ALLOW
CONDENSATION
TO DRAIN
A
6 63 0
SCALE OF INCHES
0 2 311
SCALE OF FEET
SCALE OF FEET
1 1 20
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SCALE B
SCALE C
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :3
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
ENTRY DOOR DETAILS
254798A6.3
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE BA6.3
2 LEVEL 1 ENTRY DOOR PLAN DETAIL (OPTION D)
SCALE BA6.3
4 ENTRY DOOR INTERIOR ELEVATION (OPTION D)
SCALE BA6.3
3 ENTRY DOOR EXTERIOR ELEVATION (OPTION D)
SCALE CA6.3
5 ENTRY DOOR CUSTOM BRONZE LOUVER (OPTION D)
EXISTING CONDITION AT
INTERIOR OF DOOR
BEHIND EXISTING LOCK
EXISTING LOUVER IN ENTRY DOOR
BRONZE DOOR RESTORATION TREATMENT:
RESTORE EXISTING BRONZE DOOR WITH PANELED FRONT
AND PLAIN INTERIOR FACE. SCOPE INCLUDES
ORNAMENTAL METAL REPAIR AND RE-FINISHING;
REMOVING LATER WELDED STEEL LATCH BOX; PROVIDING
NEW HEAVY DUTY CUSTOM LOCKING HARDWARE
CONSISTENT WITH ORIGINAL DOOR DESIGN; AND
INSTALLING NEW CUSTOM STORM RESISTANT BRONZE
VENTILATION LOUVER WITH INSECT SCREEN AT EXISTING
LOUVER OPENING.
PRIOR TO REMOVAL FOR OFFSITE RESTORATION,
CONTRACTOR TO SUBMIT WRITTEN TREATMENT PROPOSAL
AND SHOP DRAWING PREPARED BY QUALIFIED
ARCHITECTURAL METALS CONSERVATOR FOR APPROVAL
BY CONTRACTING OFFICER (CO). CONTRACTOR TO
INDICATE METHODS, MATERIALS, AND PROCEDURES FOR
REMOVING AND TRANSPORTING; REPAIRING SURFACE
BLEMISHES AND HOLES; REPLACING MISSING ELEMENTS;
ANCHORING FRAME AND HARDWARE TO MASONRY;
CLEANING AND RESTORATION OF ORIGINAL INTERIOR AND
EXTERIOR FINISHES AND ASSOCIATED WORK.
STL DOOR FRAME WITH
POWDER COATED FINISH
EXISTING STONE FRAME TO REMAIN;
PATCH MASONRY FOLLOWING
REMOVAL OF EXISTING DOOR; SEE
MASONRY RESTORATION DRAWINGS
PROVIDE METAL DOOR, W/ SIX (6)
GLAZED PANELS AND TWO (2)
PASSIVE VENTILATION LOUVERS AT
THE BASE; PROVIDE LOUVERS WITH
INTEGRAL INSECT SCREEN IN BOTTOM
RECESSED PANELS OF DOOR
METAL GUARDRAIL INSTALLED WITHIN
EXISTING MASONRY JAMB IN FRONT
OF LEVEL 2 DOOR; FINISH STEEL
SURFACES WITH A PRIMER AND
HIGH-PERFORMANCE COATING
INSTALL BIRD NET ON
EXTERIOR SIDE OF GUARDRAIL
INSTALL EXTERIOR SEALANT
JOINT AROUND PERIMETER
OF DOOR HEAD AND JAMB
A
STL DOOR FRAME
WITH POWDER
COATED FINISH
PROVIDE THRESHOLD
WITH STOP SEAL AND
WEATHERSTRIP; INSTALL
IN THRESHOLD PAN
WITH UPTURNED EDGES
SET IN SEALANT
EXISTING STONE
FRAME TO REMAIN;
PATCH MASONRY
FOLLOWING REMOVAL
OF EXISTING DOOR;
SEE MASONRY
RESTORATION
DRAWINGS
METAL GUARDRAIL
INSTALLED WITHIN
EXISTING MASONRY
JAMB IN FRONT OF
LEVEL 2 DOOR; FINISH
STEEL SURFACES WITH
A PRIMER AND HIGH-
PERFORMANCE
COATING
PROVIDE METAL DOOR, W/
SIX (6) GLAZED PANELS AND
TWO (2) PASSIVE
VENTILATION LOUVERS AT
THE BASE; PROVIDE
LOUVERS WITH INTEGRAL
BIRD SCREEN IN BOTTOM
RECESSED PANELS OF DOOR
PROVIDE METAL DOOR, W/
TWO (2) PASSIVE VENTILATION
LOUVERS AT THE BASE;
PROVIDE LOUVERS WITH
INTEGRAL INTEGRAL SCREEN
IN BOTTOM RECESSED
PANELS OF DOOR
1/4"
GLAZING
1/4"
GLAZING
1/4"
GLAZING
PROVIDE PAIR 8"CAST
BRASS DOOR PULLS
(BASIS OF DESIGN:
ROCKWOOD #RM5532)
PROVIDE HEAVY DUTY 12"
STN. STL. SURFACE MTD
VERTICAL SLIDE BOLT
MTD AT HEADER &
THRESHOLD OF ONE LEAF
ONLY (BASIS OF DESIGN:
ROCKWOOD 580-12)
HEAVY DUTY 12"
SURFACE MOUNTED
HURRICANE SLIDE BOLT
WITH DOUBLE CATCH, MIN
3" BOLT THROW AND
ANTI-RATTLE SPRING
MOUNTED AT MIDRAIL
(BASIS OF DESIGN: JOHN
WRIGHT #088503
PAIR WALL MTD CAST
BRASS HOOK AND
DOORSTOP (BASIS OF
DESIGN: ROCKWOOD #477)
INSTALL BIRD NET
ON EXTERIOR SIDE
OF GUARDRAIL
2" 4"
INSTALL EXTERIOR
SEALANT JOINT AROUND
PERIMETER OF DOOR
HEAD AND JAMB
A
A
MARBLE THRESHOLD
20 OZ. THROUGH WALL
FLASHING WRAPPING JAMB
2'-0"
STN. STL. SIDEWINDER
CABLE GUIDE
STN. STL. ROPE CLAMPS
FOR STN STL CABLE; TWO
(2) PER CONNECTION
WITH 2" CABLE TURN-
BACK MINIMUM
STN. STL. THIMBLE AT
ALL LOOP CONNECTIONS
STN. STL. TRUNBUCKLE
STN. STL. EYE BOLT
STN. STL. THIMBLE AT
ALL LOOP CONNECTIONS
STN. STL. SIDEWINDER
CABLE GUIDE
STN. STL. ROPE CLAMPS
FOR STN STL CABLE; TWO
(2) PER CONNECTION
WITH 2" CABLE TURN-
BACK MINIMUM
6 63 0
SCALE OF INCHES
WASHINGTON, DC
PMIS/PKG NO.
DRAWING NO.
SHEET
SUB SHEET NO.DESIGNED:PRIME/ARCHITECTURE: TITLE OF SHEET
OF
CADD:
TECH REVIEW:
DATE:
SCALE A
SmithGroup
Structural:
Silman Boston, MA
Consultant 2:
Building Conser Assoc Boston, MA
165882
:2 :3
P M
B
IM
C li e n t P ro je c ts
N a ti o n a l P a rk
S e rv ic e N P S B O S T
D D
C D .r v t
A u th o r
LEVEL 2 AND LEVEL 3
DOOR DETAILS
254798A6.8
Designer
Author
DORCHESTER HEIGHTS MONUMENT1/21/2022
SCALE AA6.8
1 LEVEL 2 DOOR JAMB DETAIL
SCALE AA6.8
2 LEVEL 2 DOOR HEADER AND PROFILES
SCALE AA6.8
3 LEVEL 3 BIRD NETTING DETAIL
SELF-ADHERED POLYETHELENE
FACED UNDERLAYMENT; EXTEND
UNDERLAYMENT UNDER MARBLE
THRESHOLD AND BELOW
THROUGH WALL FLASHING
PMMA ROOFING INSTALLED
CONTINUOUS UNDERNEATH
MARBLE THRESHOLD
MARBLE THRESHOLD
20 OZ. THROUGH
WALL FLASHING
WRAPPING THE JAMB
INSTALL FLUID APPLIED
URETHANE TRAFFIC
COATING OVER PMMA
ROOFING AT LEVEL 03
SLAB; INSTALL PMMA
OVER BACK LEG OF
AND BASE OF SILL PAN
20 OZ. THROUGH
WALL FLASHING
WRAPPING THE JAMB
PROVIDE 42"
GUARDRAIL WITHIN
MASONRY OPENING
INSTALL BIRD NET ON
EXTERIOR SIDE OF GUARDRAIL
NON-SHRINK GROUT
CONT. STL PLATE; SEE
STRUCTURAL DWGS
SEE STRUCTURAL DWGS
FOR FRAMING SUPPORT
A6.9
PROVIDE A MINIMUM OF TWO
(2) PINNED CONNECTIONS
FOR THRESHOLD INTO
STRUCTURE BELOW USING
STN STL DOWELS; SIMILAR
TO DETAIL 5/A5.7
INSTALL DRAINAGE MAT EMBEDDED
IN SEALANT UNDERNEATH MARBLE
THRESHOLD…