This addendum memo provides clarification and revisions to construction documents for the restoration of the Dorchester Heights Monument located in Boston National Historical Park. The project involves masonry restoration, structural reinforcement, and rebuilding portions of the monument up to the top of the spire. The addendum includes one new demolition details drawing sheet showing existing condition photographs and revisions to multiple drawing sheets providing additional details on demolition scope, building sections, elevations, and stone pinning requirements. It clarifies but does not change the scope of work. The related federal contract opportunity is a competitive solicitation by the National Park Service seeking restoration of the Dorchester Heights Monument and hardscapes with an estimated value over $25,000.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM
www.smithgroup.com
PROJECT BOST 254798: Dorchester Heights Monument Restoration Design Development & Construction Documents
ADDENDUM
NUMBER
B
PROJECT NO. 13188 DATE 6/22/2022
PROJECT
LOCATION
Boston National Historical Park Thomas Park, Boston, MA
OWNER National Park Service
PREPARED BY Susan Pommerer, AIA
DISTRIBUTION
NAME COMPANY EMAIL PHONE
Tracy McConner NPS, Denver Service
Center (DSC) Tracy_mcconner@nps.gov
Jon Mitchell NPS, Denver Service Center (DSC)
Jon_mitchell@nps.gov
Dave Gustavson NPS, Denver Service Center (DSC)
Dave_Gustavson@contractor.nps.gov
This Addendum is issued pursuant to the Instructions to Bidders and/or Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form.
PART 1 - NEW DOCUMENTS ISSUED WITH THIS DOCUMENT
1.1 NEW PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS
A. None.
1.2 NEW DRAWING SHEETS
A. Drawing Sheet AD4.2 – DEMOLITION DETAILS
• Additional demolition details sheet included to provide select photographs from Probe #1 and Probe #4 from the Emergency Stabilization Phase to assist the Contractor with understanding existing conditions.
1.3 NEW SKETCHES
A. None.
PART 2 - DOCUMENTS DELETED BY THIS DOCUMENT
2.1 DELETE THE FOLLOWING FROM THE PROJECT MANUAL
A. None.
2.2 DELETE THE FOLLOWING DRAWING SHEETS
A. None.
PART 3 - REVISED DOCUMENTS ISSUED WITH THIS DOCUMENT
3.1 REVISED PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS
A. None.
3.2 REVISED DRAWING SHEETS
A. COVER SHEET
• New drawing sheet “AD4.1 – BUILDING DEMOLITION SECTON” was included in the drawings set. This increases total drawing count to 69 sheets.
B. Drawing Sheet AD4.1 – BUILDING DEMOLITION SECTON
• Enlarged building section representing Level 3 to the top of the spire to further explain existing conditions of portions of the monument to be rebuilt. The background used in this drawings detail was taken from the 1994-1997 As-built documentation provided by the National Park Service.
C. Drawing Sheet A1.1 – ARCHITECTURAL SITE PLAN
• Adjustment of viewport provide notes and details regarding plinth fence and gate restoration.
D. Drawing Sheet A5.2 – LEVEL 3 SECTION DETAILS
• Clarification of demolition of the existing structure to be dismantled to allow removal of the Level 3 structural framing.
• Refinement of the detail to depict stone which form the Level 3 cornice.
E. Drawing Sheet R1.1 – MASONRY RESTORATION WEST ELEVATION
• Description of pinning required between Level 3 cornice stones and adjacent stones above and below.
• Description of pinning required between Level 4 cornice stones and adjacent stones above and below.
F. Drawing Sheet R1.2 – MASONRY RESTORATION NORTH ELEVATION stones above and below.
G. Drawing Sheet R1.3 – MASONRY RESTORATION EAST ELEVATION stones above and below.
H. Drawing Sheet R1.4 – MASONRY RESTORATION SOUTH ELEVATION
I. Drawing Sheet S4.1 – SECTION
• Revised Section 1 to indicate rebuilt portion at top of existing masonry wall below cornice.
• Added Elevation 2 to indicate pinning of stone units at top of tower.
PART 4 - PROPOSED CHANGES IN THE WORK
4.1 None.
PART 5 - CLARIFICATIONS
5.1 None.
| PART 1 - NEW DOCUMENTS ISSUED WITH THIS DOCUMENT |
| 1.1 NEW PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS |
| A. None. |
| 1.2 NEW DRAWING SHEETS |
| A. Drawing Sheet AD4.2 – DEMOLITION DETAILS |
| Additional demolition details sheet included to provide select photographs from Probe #1 and Probe #4 from the Emergency Stabilization Phase to assist the Contractor with understanding existing conditions. |
| 1.3 NEW SKETCHES |
| A. None. |
| PART 2 - DOCUMENTS DELETED BY THIS DOCUMENT |
| 2.1 DELETE THE FOLLOWING FROM THE PROJECT MANUAL |
| A. None. |
| 2.2 DELETE THE FOLLOWING DRAWING SHEETS |
| A. None. |
| PART 3 - REVISED DOCUMENTS ISSUED WITH THIS DOCUMENT |
| 3.1 REVISED PROJECT MANUAL DOCUMENTS AND SPECIFICATIONS |
| A. None. |
| 3.2 REVISED DRAWING SHEETS |
| A. COVER SHEET |
| New drawing sheet “AD4.1 – BUILDING DEMOLITION SECTON” was included in the drawings set. This increases total drawing count to 69 sheets. |
| B. Drawing Sheet AD4.1 – BUILDING DEMOLITION SECTON |
| Enlarged building section representing Level 3 to the top of the spire to further explain existing conditions of portions of the monument to be rebuilt. The background used in this drawings detail was taken from the 1994-1997 As-built documentation ... |
| C. Drawing Sheet A1.1 – ARCHITECTURAL SITE PLAN |
| Adjustment of viewport provide notes and details regarding plinth fence and gate restoration. |
| D. Drawing Sheet A5.2 – LEVEL 3 SECTION DETAILS |
| Clarification of demolition of the existing structure to be dismantled to allow removal of the Level 3 structural framing. |
| Refinement of the detail to depict stone which form the Level 3 cornice. |
| E. Drawing Sheet R1.1 – MASONRY RESTORATION WEST ELEVATION |
| Description of pinning required between Level 3 cornice stones and adjacent stones above and below. |
| Description of pinning required between Level 4 cornice stones and adjacent stones above and below. |
| F. Drawing Sheet R1.2 – MASONRY RESTORATION NORTH ELEVATION |
| Description of pinning required between Level 3 cornice stones and adjacent stones above and below. |
| Description of pinning required between Level 4 cornice stones and adjacent stones above and below. |
| G. Drawing Sheet R1.3 – MASONRY RESTORATION EAST ELEVATION |
| Description of pinning required between Level 3 cornice stones and adjacent stones above and below. |
| Description of pinning required between Level 4 cornice stones and adjacent stones above and below. |
| H. Drawing Sheet R1.4 – MASONRY RESTORATION SOUTH ELEVATION |
| Description of pinning required between Level 3 cornice stones and adjacent stones above and below. |
| Description of pinning required between Level 4 cornice stones and adjacent stones above and below. |
| I. Drawing Sheet S4.1 – SECTION |
| Revised Section 1 to indicate rebuilt portion at top of existing masonry wall below cornice. |
| Added Elevation 2 to indicate pinning of stone units at top of tower. |
| PART 4 - PROPOSED CHANGES IN THE WORK |
| 4.1 None. |
| PART 5 - CLARIFICATIONS |
| 5.1 None. |