This document contains questions and answers regarding Solicitation Number 140P2023R0023 to restore the Dorchester Heights Monument and hardscapes. The National Park Service is seeking to replace or restore existing light poles and globes to match existing character, provide revised specification documents that were included in prior addenda, and confirm that new light poles may be provided in lieu of restoring existing poles for cost savings. Clarification is also provided on including additional specification documents with the forthcoming Amendment 002.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P2023R0023 1/13/22
Q&A
Discipline Spec Offeror Questions Technical Response Addressed By
1 General The previous solicitation of this project included Addenda A thru E from Smithgroup, issued under various Amendments to the NPS Solicitation. These Addenda included revised drawings and specifications. These previous Addenda are not included in the current solicitation, only the Summary Memo for Addendum F. Please provide all documents associated with Addenda A thru E, and the revised specification from Addendum F.
Addendum A thru F included in Amendment 002
CO/CS
2 General Attachment 8;
Attachment 4
Attachment 8, Addendum F Summary Memo, indicates that Specification Section 02 83 13 - Monument Lead in Construction was revised. However, when comparing Specification Section 02 83 13 contained within Attachment 4-Final Specs with the version of 02 83 13 which was included with the previous Solicitation, they are both the same. It appears that the Amended version of 02 83 13 was not included in the Solicitation package, only the summary memo was.
Please provide the revised Specification 02 83 13
Updated Addendum F 02 83 13 included in Amendment 002
CO/CS
3 General Attachment 7 The Solicitation posted to SAM.gov did not include Attachment 7, Addendum F Monument Lead in Construction. Please provide this document
Attachment 7, Addendum F will be include in Amendment 002
CO/CS
4 Electrical General note 3.1 on drawing E1 states the following "pole restoration process shall be performed by iron fabricator, with multi-step process to remove existing finish, clean and prepare pole to receive prime and final powder coat finish". Is it acceptable to provide new poles to match existing in lieu of restoration process as the cost for new is less expensive?
The light poles may be replaced with a matching profile and factory applied primer and powder coasting black finish.
The glass globes are to match the existing character and the luminaires must also match the specification and be dark sky compliant.
D&C