This document contains questions and answers regarding solicitation number 140P2022R0049 to restore the Dorchester Heights Monument and hardscapes. The solicitation is seeking proposals from contractors to complete the restoration project, involving both hardscape and monument aspects. Key details include that 11x17 size paper may be used for charts and graphics but will count as one page; schedules can be presented on 11x17 paper; either MS Project or Primavera P6 software is acceptable for the Gantt chart; the schedule narrative is limited to 25 pages; relevant projects from the last 6-8 years will be considered due to the complexity of restoring both hardscape and monument aspects; previously completed past performance questionnaires within the last 12 months are acceptable; and there is no form for proposed equals as referenced in the solicitation. The National Park Service is the contracting agency for this opportunity.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P2022R0049 Perini Question Set #1
6/6/2022
Q&A
Discipline Sheet Detail Spec Description Tech response
1 Contracting Solicitation Factor 1 Page 49 of 57 Is 11x17 size paper allowable for representations of charts and/or graphics in the technical approach? If so, will it count as 1 page or 2 pages.
11x17 size paper for charts and/or graphics, shall be considered as 1 page.
Applicants should limit the use of 11x17 paper. The techical approach narrative shall be on 8.5x11 only.
2 Contracting Solicitation Factor 2 Page 49 of 57 Please confirm the use of 11x17 size paper is allowable for the schedule. Schedules may be presented on 11x17.
3 Contracting Solicitation Factor 2 Page 49 of 57 The Schedule requirements in the solicitation states that we should submit a schedule in MS
Project Gantt Chart Format. Is a Gantt Chart meeting all of the solicitation requirements prepared using Primavera P6 in lieu of MS Project acceptable?
Applicant may use any Software to develop a Gantt chart. Primavera P6 is acceptable.
4 Contracting Solicitation Factor 2 Page 49 of 57 What is the page limit for the schedule narrative?
The schedule narrative shall not exceed 25 pages including the schedule.
5 Contracting Solicitation Factor 3 Page 49 of 57 Due to the complexity of the project involving both hardscape and monument aspects, we respectfully request the allowance of projects completed in the last 8 years.
Relevant projects in the last 6 years will be considered. Project should be of similar scope and magnitude to this solicitation.
6 Contracting Solicitation Factor 5 Page 51 of 57 Will the Government accept previously completed PPQs? Yes, if it is within the last twelve (12) months.
7 Contracting Solicitation Proposed
Equals Page 51 of 57 Please provide Proposed Equals form referenced in solicitation.
There is no form, administrative error, this will be removed from the solicitation.
8 Contracting Amendment 0002 The NPS issued a revised document titled "BO8_SOL_140P2022R0049_Rev1_0004" on 5/26 without including an SF 30 form stating whether this was Amendment 0001 or not. Then, the NPS issued Amendment 0002 with an SF 30 form on 5/31. To help us track changes to the RFP, we respectfully request the NPS issue an SF 30 form for the revised solicitation issued on 5/26 and please confirm whether this was meant to be Amendment 0001.
This will annotated on a forthcoming amendment
9 Contracting Please provide site visit attendees list Issued