70T05026R5900N005 Questions and Answers Set 6.pdf
PDF 507 KB Posted
- Solicitation number
- 70T05026R5900N005
About this file
This document is a Questions and Answers (Q&A) Set 6 for the Gold+ federal contract opportunity, contract number 70T05026R5900N005.
The Q&A addresses clarifications regarding submission requirements for an IDIQ (Indefinite Delivery/Indefinite Quantity) contract with two separate evaluation tracks. Question 1 concerns the placement of signed SF1449 forms and SF30 acknowledgments, with TSA clarifying that these documents should be included in Volume VI (Financial Capability & Business Stability) for Phase 2 candidates, which has no page limits. Question 2 addresses misalignment between proposal volume descriptions and detailed requirements sections, clarifying that Phase 2 Track 1 Volume 1 consists of the Cost Efficiency and Compliance proposal (including compliance documentation per Section I.3.1.1) used in conjunction with Phase 1 evaluations to determine IDIQ award recipients, while Phase 2 Track 2 Volume 1 requirements comprise proposal responses to sections 1.2.7.2 through 1.2.7.8, with evaluations determining which offerors receive Task Order awards for specified airports. The document provides authoritative guidance to resolve ambiguities between the original RFP and subsequent amendments regarding the structural organization of proposal submissions across both phases and tracks.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Number
RFP Section
RFP
Paragraph
RFP Page Number
RFP Question TSA Response
Amend 003
SF1449, SF30s In Amend 003, QA set #5, instructs Offerors to include SF1449 and SF30s in their Phase 1 and Phase 2 proposal submittals. Q6 asked if Phase II/Track 1 was required for the IDIQ submission. The answer was no.
QUESTION: If Track 1 Volume I Cost Efficiency and Compliance (Factor 1)(mandatory) is not due now where are we to insert signed SF1449s and SF30s?
Table I.2.5.2 – VOLUME DESCRIPTIONS & REQUIREMENTS Volume VI – Financial Capability & Business Stability has been revised "to include SF1449 and SF30 Acknowledgements and I.2.4.5 Sensitive Security Information Phase 2 candidates", this volume has no page limits.
Amend
Cost Efficiency Track 1 and Track 2:
The revised Table in I.2.5.3 Phase 2 Volume Descriptions and Requirements (pg 46 & 47) does not align with the detailed corresponding sections in I.2.7 Phase 2 General Volume Requirements (pg 53).
I.2.7.1 I.2.7.1 Track 1 Volume I Cost Efficiency and Compliance (Factor 1) (mandatory) (pg. 52-
53) is a carry over from original RFP with the addition of a last line NOTE: Please refer to section I.3.1.1 for complete compliance documentation requirements.
You then include Track 2 First Task Order: Airport 1 I.2.7.2 Volume I: Cost Efficiency (Factor 1) (pg 53)
QUESTION: Please clarify the Track 1 Volume 1 and Track 2 Volume 1 requirements for Phase 1 and 2
Phase 2 Track 1 Volume 1 consists only of the I.2.7.1 Track 1 Volume I Cost Efficiency and Compliance (Factor 1) proposal. This includes the Volume 1 Cost Efficiency proposal as well as the Compliance Documentation detailed in Section I.3.1.1.
This will be used in conjunction with the Phase 1 evaluations to determine which offerors receive IDIQ awards.
Phase 2 Track 2 Volume 1 requirements are the proposal responses for 1.2.7.2 through
1.2.7.8. the evaluations of these will determine which offerors receives a Task Order award for the specified airport(s).
Gold+ 70T05026R5900N005 Questions and Answers Set 6
File details come from the government source that posted it. Updated .