15 Attachment F - TSE RMA Metrics.pdf

PDF 152 KB Posted

Attached to
TSA Gold+ COMMERCIAL SERVICES IDIQ CONTRACT SOLICITATION
Solicitation number
70T05026R5900N005
Issued by

About this file

This is a Data Item Description (DID) template for the Transportation Security Equipment (TSE) Reliability, Maintainability, and Availability (RMA) Metrics Report, identified as APM-ILS-018. The document specifies the format and content requirements for monthly maintenance metrics reporting that TSA uses to monitor TSE and contractor performance against maintenance objectives.

The report must be submitted in Microsoft Project (MSP) format and contain sufficient data to allow independent recomputation of both low-level and high-level metrics. Required identification information includes the preparing activity, name and title of the MSP official certifying accuracy, and Sensitive Security Information (SSI) statements when applicable. Contractors must report thirteen low-level M-Values for each maintenance activity: M1 (Initial Call Center Interaction Time), M2 (Technician Dispatch Time), M3 (Technician Diagnosis Time), M4 (Part Request Time), M5 (Part Fulfillment Time), M6 (Local Logistics Time), M7 (Technician Repair Time), M8 (Technician Testing Time), M9 (TSA Signoff Time), M10 (Time to Repair), M11 (Depot Turnaround Time), M12 (Uncrate/Setup at Location Time), and M13 (Telephone Customer Support). The report must also include five RMA metrics—Mean Time Between Critical Failures (MTBCF), Mean Up Time (MUT), Mean Downtime (MDT), Mean Time to Repair (MTTR), and Operational Availability (Ao)—calculated monthly by airport and by technology. Additionally, Service Level Agreement (SLA) Performance Metrics must be calculated and reported to evaluate the maintenance service provider's responsiveness and logistics support effectiveness. The report must list all TSE serial numbers and locations used in calculations, noting dates when units were added to or removed from the contract during the reporting period, with appendices included as applicable.

View the file

Other files

File Type Posted
70T05026R5900N005 Questions and Answers Set 8.pdf PDF
70T05026R5900N005 AMD 0004.pdf PDF
70T05026R5900N005 Questions and Answers Set 6.pdf PDF
70T05026R5900N005 Questions and Answers Set 5.pdf PDF
70T05026R5900N005 AMD 0003.pdf PDF
70T05026R5900N005 AMD 0002.pdf PDF
AMD 0001 REVISION SUMMARY.pdf PDF
1 Gold_CM Req_Attachment_7.16.26.pdf PDF
70T05026R5900N005 Questions and Answers Set 3.pdf PDF
70T05026R5900N005 Questions and Answers Set 1.pdf PDF
70T05026R5900N005.pdf PDF
22 PGDS v8.0 Appendices.pdf PDF
19 Attachment D - ITAR_Terms-Conditions GOLD.pdf PDF
17 Gold_Maintenance Req_Attachment_4.13.26.pdf PDF
31 TSA MD 1900.18, FINAL, eff 24.12.04.pdf PDF
35 SAFETY ACT BLOCK DESIGNATION NOTICE.pdf PDF
11 Attachment B - TSE Metrics Terms and Definitions and RMA Metrics.pdf PDF
25 Attachment H - TSA Handbook 1100.73-2, FINAL, 201218.pdf PDF
39 ACRONYMS AND DEFINITIONS.pdf PDF
27 OD-400-50-1-5H Reporting Customer Thruput-Wait_Times_111220_FINAL_sig.pdf PDF
28 TSA MD 200.51, FINAL, 171114.pdf PDF
5 L004 - Request for Deviation.pdf PDF
12 Attachment C - Failure Mode Indicator Codes.pdf PDF
Attachment 1 Performance Work Statement.pdf PDF
41 Gold Performance Metrics.xlsx XLSX spreadsheet
40 - DHS Form 700-23.pdf PDF
23 PGDS v8.0 Main.pdf PDF
1 Gold_CM Req_Attachment_4.13.26.pdf PDF
36 ESTIMATED CONSUMABLES LIST.pdf PDF
32 TSA MD1900.8, FINAL, 231025, eff231105.pdf PDF
38 SUITABILITY DETERMINATIONS.pdf PDF
2 L001 - Configuration Management Plan.pdf PDF
16 Attachment G - TSA Media Sanitization Certificate.pdf PDF
29 TSA MD 200.52, FINAL, 2, 160829.pdf PDF
13 Attachment D - TSE Database.pdf PDF
6 L005 - Request for Waiver.pdf PDF
21 checkpoint-requirements-and-planning-guide.pdf PDF
20.1 Attachment E - cap_acceptable_capability_list _R.pdf PDF
14 Attachment E -SLA Performance Metrics.pdf PDF
9 L009 - Configuration Audit Summary Report.pdf PDF
37 TRAINING REQUIREMENTS.pdf PDF
4 L003 - Engineering Change Proposal.pdf PDF
7 L007 - Configuration Status Accounting Report.pdf PDF
42 Airport Task Order Summary - Sample.docx DOCX document
24 Attachment G - TSA T and E Guidebook Rev 6 - Final.pdf PDF
18 Attachment C - SSI Policies and Procedures Handbook.pdf PDF
33 TSA-RTWT-Requirements_Final_2026-04-27.pdf PDF
30 TSA MD 1000.15, FINAL, 221118, 508C.pdf PDF
10 Attachment A - Radiation Survey and Radioactive Leak Test Rec.pdf PDF
3 L002 - Master Configuration Item List.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment F – TSE RMA Metrics

1. TITLE 2. IDENTIFICATION NUMBER

TSE RMA Metrics Report N/A

3. DESCRIPTION/PURPOSE

3.1. The Transportation Security Equipment (TSE) Reliability, Maintainability, & Availability (RMA) Metrics Report documents the status of contract efforts towards achieving contract maintenance objectives. It is used by TSA to monitor TSE and Contractor performance.

4. APPROVAL DATE (YYMMDD) 5. OFFICE OF PRIMARY RESPONSIBILITY (OPR) 6a. DTC APPLICABLE 6b. GIDEP APPLICABLE

7. APPLICATION/INTERRELATIONSHIP

7.1. This attachment contains the format and content preparation instructions for the maintenance metrics report.

8. APPROVAL LIMITATION 9a. REFERENCES 9b. AMSC NUMBER

10. Preparation Instructions

10.1. FORMAT. The monthly TSE RMA Metrics Report may be in MSP format. It shall contain the data and information specified in the following monthly metric report subparagraphs. The contractor shall change the report format when requested by the Contractor.

10.2. CONTENT. The data delivered in accordance with this attachment shall contain sufficient information to allow the low-level and high-level metrics to be independently recomputed by the Contractor (or TSA).

10.2.1. IDENTIFICATION. The submittal will contain the information listed below:

a. Preparing activity and name/title of MSP official certifying accuracy of the report

b. Sensitive Security Information (SSI) statement applied when required

10.2.2. Low Level Metrics (M-Values). Provide a list of all work order numbers, criticality, relevancy, and low-level metrics (M-Values) making appropriate adjustments as required for high level metrics submitted as identified in this DID. This work order information should correlate with the M-Values derived for the same work order number as documented in the TSE Database, adjusted as required for metrics calculations. Metrics calculation information is included in Attachment B, TSE Metrics Terms and Definitions and RMA Metrics, and Attachment E, Service Level Agreement Performance Metrics. The following M-Values will be reported for each maintenance activity, as applicable, as specified for a TSE or MSP performance metric:

a. M1 – Initial Call Center Interaction Time

b. M2 – Technician Dispatch Time

c. M3 – Technician Diagnosis Time

d. M4 – Part(s) Request Time

e. M5 – Part(s) Fulfillment Time

f. M6 – Local Logistics Time

g. M7 – Technician Repair Time

h. M8 – Technician Testing Time

i. M9 – TSA Signoff Time

j. M10 – Time to Repair

k. M11 – Depot Turnaround Time

l. M12 – Uncrate/Setup at Location Time

m. M13 – Telephone Customer Support

DATA ITEM DESCRIPTION APM-ILS-018

10. Preparation Instructions (Continued)

10.2.3. RMA Metrics. RMA metrics submitted on the RMA Metrics Report will be used to evaluate the operational performance of deployed TSE as specified in the contract in 1.13, Maintenance Services SLA Performance Requirements. The metrics will be calculated monthly by airport and by technology. Definitions and calculation of RMA metrics can be found in Attachment B. The maintenance activities and maintenance action M-Values should be counted as specified in Attachment B. The following are the RMA metrics identified in Attachment B:

• Mean Time Between Critical Failures (MTBCF)

• Mean Up Time (MUT)

• Mean Downtime (MDT)

• Mean Time to Repair (MTTR)

• Operational Availability (Ao)

10.2.4. Service Level Agreement (SLA) Performance Metrics. The Contractor will use MSP performance metrics in the contract to evaluate maintenance service performance against the SLA requirements specified in 1.13, Maintenance Services SLA Performance Requirements. These metrics focus on the MSP’s responsiveness in returning TSE to full operational capability and the effectiveness of their logistics support structure. The Contractor must calculate all the SLA performance metrics as specified in Attachment E, SLA Performance Metrics and report these metrics in the TSE RMA Metrics Report. These metrics will include the same supporting data as specified in paragraph 10.2.2.

10.2.5. Units Counted. The report will include a list of all TSE serial numbers and locations on the Contract that are used to calculate the reporting period’s metrics. If a unit was added to or deleted from the Contract during the reporting period, the list will include the date on which that action occurred.

10.2.7. Appendices. Appendices, where applicable, for tables, references, charts, or other descriptive material. Each appendix will be identified and referenced in the appropriate area of the report.

11. DISTRIBUTION STATEMENT

DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.

Attachment F – TSE RMA Metrics
1. TITLE
2. IDENTIFICATION NUMBER
3. DESCRIPTION/PURPOSE
4. APPROVAL DATE (YYMMDD)
5. OFFICE OF PRIMARY RESPONSIBILITY (OPR)
6a. DTC APPLICABLE
6b. GIDEP APPLICABLE
7. APPLICATION/INTERRELATIONSHIP
8. APPROVAL LIMITATION
9a. REFERENCES
9b. AMSC NUMBER
11. DISTRIBUTION STATEMENT