5-EJCDC - Bid Form for Construction Contracts 00300 (003).pdf
PDF 247 KB Posted
- Solicitation number
- US.255952
- Issued by
- Lehigh County, Pennsylvania
About this file
This is a Bid Form for Construction Contracts (EJCDC 00300) related to the Electrical Substation Replacement Project – Equipment Procurement Phase managed by Lehigh County Authority in Pennsylvania. Online sealed bids will be received via the PennBid electronic bidding service until 11:00 a.m. on Wednesday, October 28, 2026, at which time bids will be publicly opened and read. No pre-bid meeting will be held; however, site visits are available on a self-guided basis and can be scheduled by email with Charles Volk, P.E., Chief Capital Works Officer, at charlesvolk@lehighcountyauthority.org. All bidding documents are available at no cost through PennBid (www.PennBid.net). Bids shall remain open for 60 days from the date of bid opening, and bid results will be made available through PennBid following the opening.
Each bid must be accompanied by bid security in the form of a certified check, bank check, or bid bond in the required form equal to 10 percent of the bid total. After bid opening, bids may be withdrawn only in compliance with Commonwealth of Pennsylvania laws and regulations as outlined in the Instructions to Bidders. Lehigh County Authority reserves the right to reject any and all bids and to waive any omissions, errors, mistakes, defects, or irregularities in any submitted bid.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELECTRICAL SUBSTATION #2 AND #4 PROCUREMENT
BID FORM
EJCDC C-410 Suggested Bid Form for Construction Contracts
With Changes by Lehigh County Authority as Indicated
00300-i
Supplemental Provisions, which are revisions by Lehigh County Authority to the original EJCDC form, are indicated.
ELECTRICAL SUBSTATION PROCUREMENT
Contract No. 1: General Construction
TABLE OF ARTICLES
Page
Article 1 – Bid Recipient 1
Article 2 – Bidder’s Acknowledgements 1
Article 3 – Bidder’s Representations 1
Article 4 – Further Representations 2
Article 5 – Basis of Bid 2
Article 6 – Time of Completion 5
Article 7 – Attachments To This Bid 5
Article 8 – Defined Terms 5
Article 9 – Bid Submittal 5
00300-1
ARTICLE 1 – BID RECIPIENT
1.01 This Bid is submitted, via PennBid, to:
Lehigh County Authority
P.O. Box 3348, 1053 Spruce Street
Allentown (Wescosville), PA 18106-0348
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the
Bidding Documents.
ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS
2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for sixty (60) days after the Bid opening; for up to one hundred twenty (120) days if the award is delayed by the required approval of another government agency, the sale of bonds or the award of a grant; or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 – BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the
Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged.
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in §4.02 of the General
Conditions, and (2) reports and drawings that have been identified in §4.06 of the General Conditions.
E. Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.
00300-2
F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the
Work as indicated in the Bidding Documents.
H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the
Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.
I. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
K. Bidder will submit written evidence of its authority to do business in Pennsylvania not later than the date of its execution of the Agreement.
ARTICLE 4 – FURTHER REPRESENTATIONS
4.01 Bidder further represents that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.
ARTICLE 5 – BASIS OF BID (BASE BID)
5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
(numerals)
(words)
00300-3
Item
No. Description Unit
Estimated
Quantity Bid Unit Price
Bid Price in Words
Bid Price in Figures
1 Bonds, Insurance, and Mobilization LS 1 $ __
2 Substation #2 equipment, as indicated in the attached bid documents, including, but not limited to, the MV switchgear, transformer, and LV switchgear, together with all associated connections, shall be provided as a single assembly. Assembly to be delivered at site. Refer to contract specifications and drawings attached for full scope.
EA 1
3 Substation #4 equipment, as indicated in the attached bid documents, including, but not limited to, the MV switchgear, transformer, and LV switchgear, together with all associated connections, shall be provided as a single assembly. Assembly to be delivered at site. Refer to contract specification and drawings attached for full scope.
EA 1 $ __
4 ALLOWANCE ITEM: Local permitting allowance $500
Total of All Base Bid Prices (Items 1-4) $______________
A1: Alternate 1 Bid Items
Alternate 1 Bid Item
A1-1 Extended warranty of 12 months, in addition to the manufacturer's standard 24-month warranty, for the
Substation #2 equipment assembly, as specified in the attached bid documents.
EA 1 $_______
A1-2 Extended warranty of 12 months, in addition to the manufacturer's standard 24-month warranty, for the
Substation #4 equipment assembly, as specified in the attached bid documents.
EA 1 $_______
Alternate 1 Bid Item
A1-3 Extended warranty of 24 months, in addition to the manufacturer's standard 24-month warranty, for the
Substation #2 equipment assembly, as specified in the attached bid documents.
EA 1 $_______
A1-4 Extended warranty of 24 months, in addition to the manufacturer's standard 24-month warranty, for the
Substation #4 equipment assembly, as specified in
00300-4
Alternate 1 Bid Item
A1-5 Extended warranty of 36 months, in addition to the manufacturer's standard 24-month warranty, for the
Substation #2 equipment assembly, as specified in the attached bid documents.
EA 1 $_______
A1-6 Extended warranty of 36 months, in addition to the manufacturer's standard 24-month warranty, for the
Substation #4 equipment assembly, as specified in
A2: Alternate 2 Bid Items
Equipment Delivery Lead-Time Expediting Alternate 2 Bid Items
All Bidders shall provide a separate line-item price as an alternate 2 for expediting the manufacturer’s standard equipment delivery lead time. The alternate price shall represent the additional cost required to reduce the standard delivery lead time and expedite delivery of the equipment to the Project site, thereby allowing the equipment to be delivered earlier and potentially allowing the Project to achieve Substantial Completion earlier than the maximum
650-calendar-day period specified below.
The Base Bid shall be based on the Manufacturer’s/Bidder’s standard equipment delivery lead time. The expedited delivery alternate shall identify the additional cost and the corresponding reduction in delivery time from the standard lead time.
Under no circumstances shall the Substantial Completion date exceed 650 calendar days from the date the
Agreement is approved by the Comptroller. Acceptance of the expediting alternate may be considered by the
Owner to facilitate an earlier Substantial Completion date.
Bidders shall clearly identify the following information in their bid:
1. Additional Cost for Expediting Equipment Delivery: $____________
2. Number of Calendar Days Saved by Expediting: __________ days
3. Manufacturer’s/Bidder’s Standard Equipment Delivery Lead Time Included in Base Bid: __________ days
The standard delivery lead time identified above shall be the basis of the Bidder’s original/base bid price. The expedited delivery cost shall be provided separately as an alternate/additive cost and shall not be included in the
Base Bid.
Bidder acknowledges that final payment for all work will be based on actual performed/installed unit price work, as determined during construction. Quantities are not guaranteed, and Owner reserves the right to adjust quantities as site conditions allow.
00300-5
5.02 ALTERNATES
Bidders are requested to provide Alternate pricing, to be performed by Bidder or Bidder’s subcontractor. Owner reserves the right to award Base Bid only, or Base Bid plus Alternate A1 AND A2
ARTICLE 6 – TIME OF COMPLETION
6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 14.07.B of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the Contract Times.
ARTICLE 7 – ATTACHMENTS TO THIS BID
7.01 The following documents are attached to and made a condition of this Bid:
A. Required Bid security in the form of either a bid bond or cashier’s check in the amount of ten (10%) percent of the total bid amount
B. List of Proposed Subcontractors
C. Certificate as to Corporate Principal
D. Required Bidder Qualification Statement with Supporting Data: An Experience Questionnaire will be required to document information regarding similar projects and other evidence of qualifications. (Pertinent information regarding similar projects and other evidence of qualification; as well as evidence that Subcontractors and
Suppliers are qualified to do business in the Commonwealth of Pennsylvania or covenant to obtain such qualification prior to and as a condition of award of a Contract.)
E. Affidavit of Non-Collusion
F. Agreement of Surety
G. List of Proposed Major Equipment Manufacturers
H. Experience Questionnaire
I. [List other documents as pertinent]
ARTICLE 8 – DEFINED TERMS
8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders and the
General Conditions, as amended by the Supplementary Conditions.
ARTICLE 9 – BID SUBMITTAL
9.01 This Bid submitted by:
Bidder’s Business address: _______________________________________________________________
Phone: ________________________________ Facsimile: ___________________________________
00300-6
Submitted on ______________________________, 20_____.
State Contractor License No. ________________. (If applicable)
If Bidder is:
An Individual
Name (typed or printed): ________________________________________________________________
By: _________________________________________________________________________________ (SEAL)
(Individual’s signature)
Doing business as: _____________________________________________________________________
A Partnership
Partnership Name: _____________________________________________________________________ (SEAL)
By: _________________________________________________________________________________
(Signature of general partner – attach evidence of authority to sign)
A Corporation
Corporation Name: _____________________________________________________________________ (SEAL)
State of Incorporation: ___________________
Type (General Business, Professional, Service, Limited Liability): ________________________________
(Signature – attach evidence of authority to sign)
Title: ________________________________________________________________________________
Attest: _______________________________________________________________________________
(Signature of Corporate Secretary)
Date of Qualification to do business in Pennsylvania is ____/____/____.
A Joint Venture
Name of Joint Venturer: _________________________________________________________________
First Joint Venturer Name: _______________________________________________________________ (SEAL)
(Signature of first joint venture partner – attach evidence of authority to sign)
00300-7
Second Joint Venturer Name: _____________________________________________________________ (SEAL)
(Signature of second joint venture partner – attach evidence of authority to sign)
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)
| Article 1 – Bid Recipient |
| 1.01 This Bid is submitted, via PennBid, to: |
| 1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and wit... |
| Article 2 – Bidder’s Acknowledgements |
| 2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for sixty (60) days after the Bid opening; ... |
| Article 3 – Bidder’s Representations |
| 3.01 In submitting this Bid, Bidder represents that: |
| A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged. |
| B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, and performance of the Work. |
| C. Bidder is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress and performance of the Work. |
| D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to t... |
| E. Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground ... |
| F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance wit... |
| G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents. |
| H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, st... |
| I. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder. |
| J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted. |
| K. Bidder will submit written evidence of its authority to do business in Pennsylvania not later than the date of its execution of the Agreement. |
| Article 4 – Further Representations |
| 4.01 Bidder further represents that: |
| A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; |
| B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; |
| C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and |
| D. Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner. |
| Article 5 – Basis of Bid (BASE Bid) |
| 5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s): |
| Equipment Delivery Lead-Time Expediting Alternate 2 Bid Items |
| All Bidders shall provide a separate line-item price as an alternate 2 for expediting the manufacturer’s standard equipment delivery lead time. The alternate price shall represent the additional cost required to reduce the standard delivery lead time ... |
| The Base Bid shall be based on the Manufacturer’s/Bidder’s standard equipment delivery lead time. The expedited delivery alternate shall identify the additional cost and the corresponding reduction in delivery time from the standard lead time. |
| Under no circumstances shall the Substantial Completion date exceed 650 calendar days from the date the Agreement is approved by the Comptroller. Acceptance of the expediting alternate may be considered by the Owner to facilitate an earlier Substantia... |
| Bidders shall clearly identify the following information in their bid: |
| 1. Additional Cost for Expediting Equipment Delivery: $____________ |
| 2. Number of Calendar Days Saved by Expediting: __________ days |
| 3. Manufacturer’s/Bidder’s Standard Equipment Delivery Lead Time Included in Base Bid: __________ days |
The standard delivery lead time identified above shall be the basis of the Bidder’s original/base bid price. The expedited delivery cost shall be provided separately as an alternate/additive cost and shall not be included in the Base Bid.
| 5.02 ALTERNATES |
| Bidders are requested to provide Alternate pricing, to be performed by Bidder or Bidder’s subcontractor. Owner reserves the right to award Base Bid only, or Base Bid plus Alternate A1 AND A2 |
| Article 6 – Time of Completion |
| 6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 14.07.B of the General Conditions on or before the dates or within the number of calendar days indicated in ... |
| 6.02 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the Contract Times. |
| Article 7 – Attachments To This Bid |
| 7.01 The following documents are attached to and made a condition of this Bid: |
| A. Required Bid security in the form of either a bid bond or cashier’s check in the amount of ten (10%) percent of the total bid amount |
| B. List of Proposed Subcontractors |
| C. Certificate as to Corporate Principal |
| D. Required Bidder Qualification Statement with Supporting Data: An Experience Questionnaire will be required to document information regarding similar projects and other evidence of qualifications. (Pertinent information regarding similar projects a... |
| E. Affidavit of Non-Collusion |
| F. Agreement of Surety |
| G. List of Proposed Major Equipment Manufacturers |
| H. Experience Questionnaire |
| I. [List other documents as pertinent] |
| Article 8 – Defined Terms |
| 8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders and the General Conditions, as amended by the Supplementary Conditions. |
| Article 9 – Bid Submittal |
| 9.01 This Bid submitted by: |