This is a specification document for secondary unit substation equipment procurement issued by Lehigh County Authority in Allentown, Pennsylvania. The project encompasses the furnishing and installation of two new secondary unit substations at Substation #2 and Substation #4, located at 7676 Industrial Blvd., Allentown, PA 18106. Each substation shall be a complete assembly from incoming line terminals to outgoing line terminals, configured with Secondary Selective Type distribution and main-tie-main setup with electrical interlocks. The substations will operate as two electrically independent units with approximately half the total load on each bus, allowing automatic failover with outage duration limited to a few seconds. Sealed bids will be received through the PennBid electronic bidding service until 11:00 a.m. on Wednesday, October 28, 2026, with results made available through PennBid. Site visits are self-guided and can be scheduled via email with Charles Volk, P.E., Chief Capital Works Officer. Bids must remain open for 60 days from the opening date, and all bidding documents are available at no cost through PennBid.
Each bid must include bid security in the form of a certified check, bank check, or bid bond equal to 10 percent of the total bid amount. The manufacturer of the unit substation must furnish and coordinate all major components, including primary equipment, transformers, and secondary equipment, with a single warranty covering all assemblies and components plus an extended 36-month warranty. The manufacturer must be ISO 9001 or 9002 certified and must have produced similar electrical equipment for a minimum of five years. The specification requires comprehensive factory testing, field quality control with a qualified manufacturer's representative for 8 working days, training for up to five owner representatives for one workday, and manufacturer's certification of proper installation and testing. Lehigh County Authority reserves the right to reject any and all bids and to waive any omissions, errors, mistakes, defects, or irregularities in any bid.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Substation #2, #4 Procurement 7676 Industrial Blvd.
Allentown, PA 18106 September 15, 2026
26 11 16.11-1
SECTION 26 11 16.11
SECONDARY UNIT SUBSTATIONS – SECONDARY LESS THAN 1000 V
PART 1 GENERAL
1.01 SCOPE
A. The Contractor shall furnish and install two new secondary unit substation(s) at Substation #2 and Substation #4 complete from the incoming line terminals to the outgoing line terminals as specified herein and as shown on the contract drawings.
Each substation shall follow the Secondary Selective Type of distribution which shall be normally operated as two electrically independent unit substations, with bus tie breaker (T) open, and with approximately half of the total load on each bus.
In case of failure of either primary incoming circuit, only one bus is affected, and service can be promptly restored by opening main breaker (M) on the dead bus and closing tie breaker (T). This operation shall be made automatic, with duration of outage on either bus limited to a few seconds. The main-tie-main setup shall include electrical interlocks.
B. Each secondary unit substation shall consist of primary equipment, transformers and secondary equipment as specified below. The manufacturer of the unit substation shall furnish and coordinate all major components of the substations, including incoming primary equipment section, transformer and low-voltage section, as well as circuit breakers, fusible switches, and metering components.
Provide a single warranty covering all substation assemblies, transformers and components. Also included in this contract is an extended warranty for 36 months.
C. Connections between the primary device and transformer shall be cable, and between the transformer and secondary shall be flexible bus braid.
D. Outdoor primary and secondary equipment where specified shall be of weatherproof construction, rodent proof and shall contain 120-volt space heaters, receptacles and lighting as required.
1.02 RELATED SECTIONS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
B. Section 26 12 13.01 – Substation Transformers – Liquid-Filled
C. Section 26 13 26.11 – Metal Clad Medium Voltage Arc Resistant Switchgear
D. Section 26 23 00.16 – Arc Resistant Metal Enclosed Drawout Switchgear Low Voltage
1.03 REFERENCES
A. The secondary unit substation shall be designed, assembled, tested and installed in accordance with latest applicable standards of NEMA, IEEE and ANSI, applicable to its three major sections:
1. MV Metal-Clad Switchgear – NEMA SG4, SG5; ANSI C37
2. MV Metal-Enclosed Switchgear – NEMA SG4, SG5; ANSI C37
3. MV Load Interrupter Switchgear – NEMA SG4, SG5; ANSI C37
Allentown, PA 18106 September 15, 2026
26 11 16.11-2
4. MV Motor Controllers – ANSI/NEMA ICS-3-Part 2, UL347
5. Secondary Substation Transformers – NEMA 210, IEEE 100, ANSI C57
6. LV Metal-Enclosed Switchgear – ANSI C37, UL 1558
7. LV Distribution Switchboards – NEMA PB-2, UL 891
1.04 SUBMITTALS – FOR REVIEW/APPROVAL
A. The following information shall be submitted to the Engineer:
1. Master drawing index
2. Front view elevation
3. Floor plan
4. Single line
5. Schematic diagram
6. Nameplate schedule
7. Component list
8. Conduit entry/exit locations
9. Assembly ratings including:
a. Short-circuit rating
b. Voltage
c. Continuous current
d. Basic Impulse level for equipment over 600 volts
e. kVA
10. Major component ratings including:
a. Voltage
b. Continuous current
c. Interrupting ratings
11. Cable terminal sizes
12. Connection details between close-coupled assemblies
13. Composite front view and floor plan of close-coupled assemblies
14. Impedance for transformers
15. Product data sheets
B. Where applicable, the following additional information shall be submitted to the Engineer:
1. Busway connection
2. Key interlock scheme drawing and sequence of operation
Allentown, PA 18106 September 15, 2026
26 11 16.11-3
1.05 SUBMITTALS – FOR CONSTRUCTION
A. The following information shall be submitted for record purposes:
1. Final as-built drawings and information for items listed Paragraph 1.04, and shall incorporate all changes made during the manufacturing process
2. Wiring diagrams
3. Certified production test reports
4. Installation information
5. Seismic certification as specified
1.06 QUALIFICATIONS
A. The manufacturer of the assembly shall be the manufacturer of the major components within the assembly.
B. For the equipment specified herein, the manufacturer shall be ISO 9001 or 9002 certified.
C. The manufacturer of this equipment shall have produced similar electrical equipment for a minimum period of five (5) years. When requested by the Engineer, an acceptable list of installations with similar equipment shall be provided demonstrating compliance with this requirement.
1.07 REGULATORY REQUIREMENTS
A. Certified copies of production test reports shall be supplied demonstrating compliance with these standards when requested by the engineer.
1.08 DELIVERY, STORAGE AND HANDLING
A. Equipment shall be handled and stored in accordance with manufacturer's instructions. One (1) copy of these instructions shall be included with the equipment at time of shipment.
1.09 OPERATION AND MAINTENANCE MANUALS
A. Equipment operation and maintenance manuals shall be provided with each assembly shipped and shall include instruction leaflets, instruction bulletins, and renewal parts lists where applicable for the complete assembly and each major component.
PART 2 A PRODUCTS – PRIMARY EQUIPMENT
Metal Clad Medium Voltage Arc Resistant Switchgear Section 26 13 26.11
B PRODUCTS – TRANSFORMERS
Substation Transformers – Liquid-Filled Section 26 12 13.01
C PRODUCTS – SECONDARY EQUIPMENT
Allentown, PA 18106 September 15, 2026
26 11 16.11-4
Arc Resistant Metal Enclosed Drawout Switchgear LV Section 26 23 00.16
PART 3 EXECUTION
3.01 FACTORY TESTING
A. Standard factory tests shall be performed on the primary equipment provided under this section. All tests shall be in accordance with the latest version of ANSI and NEMA standards.
B. The following factory tests shall be made on all transformers. All tests shall be in accordance with the latest revision of ANSI and NEMA standards.
1. Resistance measurements of all windings on the rated voltage connection of each unit and at the tap extremes of one unit only of a given rating on this project
2. Ratio tests on the rated voltage connection and on all tap connections
3. Polarity and phase-relation tests on the rated voltage connections
4. No-load loss at rated voltage on the rated voltage connection
5. Exciting current at rated voltage on the rated voltage connection
6. Impedance and load loss at rated current on the rated voltage connection of each unit and on the tap extremes of one unit only of a given rating on this project
7. Applied potential test
8. Induced potential tests
9. Temperature test(s) shall be made on all. When a transformer is supplied with auxiliary cooling equipment to provide more than one kVA rating, temperature tests as listed above shall be made on the lowest kVA OA or AA rating and the highest kVA FA rating
10. ANSI impulse test on all primary windings
C. The following standard factory tests shall be performed on the secondary equipment provided under this section. All tests shall be in accordance with the latest version of ANSI and NEMA standards.
1. The switchgear shall be completely assembled, wired, adjusted and tested at the factory. After assembly, the complete switchgear shall be tested to ensure the accuracy of the wiring and the functioning of all equipment. The main bus system shall be given a dielectric test of 2200 volts for one minute between live parts and ground and between opposite polarities
2. The wiring and control circuits shall be given a dielectric test of 1500 volts for one minute or 1800 volts for one second between live parts and ground, in accordance with ANSI C37.20.1
D. The manufacturer shall provide three (3) certified copies of factory test reports.
E. Factory tests as outlined above shall be witnessed by the owner's representative.
1. The manufacturer shall notify the owner two (2) weeks prior to the date the tests are to be performed
Allentown, PA 18106 September 15, 2026
26 11 16.11-5
2. The manufacturer shall include the cost of transportation and lodging for up to three (3) owner's representatives. The cost of meals and incidental expenses shall be the owner's responsibility
3.02 FIELD QUALITY CONTROL
A. Provide the services of a qualified factory-trained manufacturer's representative to assist the Contractor in installation and startup of the equipment specified under this section for a total period of 8 working days covering installation checks, testing and commissioning for Substation #2 and Substation #4. The manufacturer's representative shall provide technical direction and assistance to the contractor in general assembly of the equipment, connections and adjustments, and testing of the assembly and components contained herein.
B. The Contractor shall provide three (3) copies of the manufacturer's field startup report.
3.03 MANUFACTURER'S CERTIFICATION
A. A qualified factory-trained manufacturer's representative shall certify in writing that the equipment has been installed, adjusted and tested in accordance with the manufacturer's recommendations.
B. The Contractor shall provide three (3) copies of the manufacturer's representative's certification.
3.04 TRAINING
A. The Contractor shall provide a training session for up to five (5) owner's representatives for 1 normal workdays at a job site location determined by the owner.
B. The training session shall be conducted by a manufacturer's qualified representative. The training program shall include instructions on the assembly including primary equipment, transformer, and secondary equipment. All circuit breakers, protective devices and other major components shall be included.
3.05 INSTALLATION
A. The contractor shall install all equipment per the manufacturer’s recommendation and the contract drawings.
B. All necessary hardware to secure the assembly in place shall be provided by the contractor.
3.06 FIELD ADJUSTMENTS
A. Any adjustments required based on field conditions, shall be made by the contractor st the field in line with manufacturer requirements for a code compliant installation. All changes shall be documented in the As-built Drawings.
3.07 FIELD TESTING
A. Engage qualified medium-voltage and low-voltage electrical testing and inspection agency to administer and perform tests and inspections.
| part 1 General |
| 1.01 Scope |
| A. The Contractor shall furnish and install two new secondary unit substation(s) at Substation #2 and Substation #4 complete from the incoming line terminals to the outgoing line terminals as specified herein and as shown on the contract drawings. Eac... |
| B. Each secondary unit substation shall consist of primary equipment, transformers and secondary equipment as specified below. The manufacturer of the unit substation shall furnish and coordinate all major components of the substations, including inco... |
| C. Connections between the primary device and transformer shall be cable, and between the transformer and secondary shall be flexible bus braid. |
| D. Outdoor primary and secondary equipment where specified shall be of weatherproof construction, rodent proof and shall contain 120-volt space heaters, receptacles and lighting as required. |
| 1.02 Related Sections |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| B. Section 26 12 13.01 – Substation Transformers – Liquid-Filled |
| C. Section 26 13 26.11 – Metal Clad Medium Voltage Arc Resistant Switchgear |
| D. Section 26 23 00.16 – Arc Resistant Metal Enclosed Drawout Switchgear Low Voltage |
| 1.03 References |
| A. The secondary unit substation shall be designed, assembled, tested and installed in accordance with latest applicable standards of NEMA, IEEE and ANSI, applicable to its three major sections: |
| 1. MV Metal-Clad Switchgear – NEMA SG4, SG5; ANSI C37 |
| 2. MV Metal-Enclosed Switchgear – NEMA SG4, SG5; ANSI C37 |
| 3. MV Load Interrupter Switchgear – NEMA SG4, SG5; ANSI C37 |
| 4. MV Motor Controllers – ANSI/NEMA ICS-3-Part 2, UL347 |
| 5. Secondary Substation Transformers – NEMA 210, IEEE 100, ANSI C57 |
| 6. LV Metal-Enclosed Switchgear – ANSI C37, UL 1558 |
| 7. LV Distribution Switchboards – NEMA PB-2, UL 891 |
| 1.04 Submittals – for review/Approval |
| A. The following information shall be submitted to the Engineer: |
| 1. Master drawing index |
| 2. Front view elevation |
| 3. Floor plan |
| 4. Single line |
| 5. Schematic diagram |
| 6. Nameplate schedule |
| 7. Component list |
| 8. Conduit entry/exit locations |
| 9. Assembly ratings including: |
| a. Short-circuit rating |
| b. Voltage |
| c. Continuous current |
| d. Basic Impulse level for equipment over 600 volts |
| e. kVA |
| 10. Major component ratings including: |
| a. Voltage |
| b. Continuous current |
| c. Interrupting ratings |
| 11. Cable terminal sizes |
| 12. Connection details between close-coupled assemblies |
| 13. Composite front view and floor plan of close-coupled assemblies |
| 14. Impedance for transformers |
| 15. Product data sheets |
| B. Where applicable, the following additional information shall be submitted to the Engineer: |
| 1. Busway connection |
| 2. Key interlock scheme drawing and sequence of operation |
| 1.05 Submittals – for CONSTRUCTION |
| A. The following information shall be submitted for record purposes: |
| 1. Final as-built drawings and information for items listed Paragraph 1.04, and shall incorporate all changes made during the manufacturing process |
| 2. Wiring diagrams |
| 3. Certified production test reports |
| 4. Installation information |
| 5. Seismic certification as specified |
| 1.06 Qualifications |
| A. The manufacturer of the assembly shall be the manufacturer of the major components within the assembly. |
| B. For the equipment specified herein, the manufacturer shall be ISO 9001 or 9002 certified. |
| C. The manufacturer of this equipment shall have produced similar electrical equipment for a minimum period of five (5) years. When requested by the Engineer, an acceptable list of installations with similar equipment shall be provided demonstrating c... |
| 1.07 Regulatory Requirements |
| A. Certified copies of production test reports shall be supplied demonstrating compliance with these standards when requested by the engineer. |
| 1.08 Delivery, Storage and Handling |
| A. Equipment shall be handled and stored in accordance with manufacturer's instructions. One (1) copy of these instructions shall be included with the equipment at time of shipment. |
| 1.09 Operation and Maintenance Manuals |
| A. Equipment operation and maintenance manuals shall be provided with each assembly shipped and shall include instruction leaflets, instruction bulletins, and renewal parts lists where applicable for the complete assembly and each major component. |
| part 2 A Products – Primary equipment |
| B Products – Transformers |
| C products – Secondary equipment |
| part 3 execution |
| 3.01 factory testing |
| A. Standard factory tests shall be performed on the primary equipment provided under this section. All tests shall be in accordance with the latest version of ANSI and NEMA standards. |
| B. The following factory tests shall be made on all transformers. All tests shall be in accordance with the latest revision of ANSI and NEMA standards. |
| 1. Resistance measurements of all windings on the rated voltage connection of each unit and at the tap extremes of one unit only of a given rating on this project |
| 2. Ratio tests on the rated voltage connection and on all tap connections |
| 3. Polarity and phase-relation tests on the rated voltage connections |
| 4. No-load loss at rated voltage on the rated voltage connection |
| 5. Exciting current at rated voltage on the rated voltage connection |
| 6. Impedance and load loss at rated current on the rated voltage connection of each unit and on the tap extremes of one unit only of a given rating on this project |
| 7. Applied potential test |
| 8. Induced potential tests |
| 9. Temperature test(s) shall be made on all. When a transformer is supplied with auxiliary cooling equipment to provide more than one kVA rating, temperature tests as listed above shall be made on the lowest kVA OA or AA rating and the highest kVA FA ... |
| 10. ANSI impulse test on all primary windings |
| C. The following standard factory tests shall be performed on the secondary equipment provided under this section. All tests shall be in accordance with the latest version of ANSI and NEMA standards. |
| 1. The switchgear shall be completely assembled, wired, adjusted and tested at the factory. After assembly, the complete switchgear shall be tested to ensure the accuracy of the wiring and the functioning of all equipment. The main bus system shall be... |
| 2. The wiring and control circuits shall be given a dielectric test of 1500 volts for one minute or 1800 volts for one second between live parts and ground, in accordance with ANSI C37.20.1 |
| D. The manufacturer shall provide three (3) certified copies of factory test reports. |
| E. Factory tests as outlined above shall be witnessed by the owner's representative. |
| 1. The manufacturer shall notify the owner two (2) weeks prior to the date the tests are to be performed |
| 2. The manufacturer shall include the cost of transportation and lodging for up to three (3) owner's representatives. The cost of meals and incidental expenses shall be the owner's responsibility |
| 3.02 field quality control |
| A. Provide the services of a qualified factory-trained manufacturer's representative to assist the Contractor in installation and startup of the equipment specified under this section for a total period of 8 working days covering installation checks, ... |
| B. The Contractor shall provide three (3) copies of the manufacturer's field startup report. |
| 3.03 manufacturer's certification |
| A. A qualified factory-trained manufacturer's representative shall certify in writing that the equipment has been installed, adjusted and tested in accordance with the manufacturer's recommendations. |
| B. The Contractor shall provide three (3) copies of the manufacturer's representative's certification. |
| 3.04 training |
| A. The Contractor shall provide a training session for up to five (5) owner's representatives for 1 normal workdays at a job site location determined by the owner. |
| B. The training session shall be conducted by a manufacturer's qualified representative. The training program shall include instructions on the assembly including primary equipment, transformer, and secondary equipment. All circuit breakers, protectiv... |
| 3.05 installation |
| A. The contractor shall install all equipment per the manufacturer’s recommendation and the contract drawings. |
| B. All necessary hardware to secure the assembly in place shall be provided by the contractor. |
| 3.06 field adjustments |
| A. Any adjustments required based on field conditions, shall be made by the contractor st the field in line with manufacturer requirements for a code compliant installation. All changes shall be documented in the As-built Drawings. |
| 3.07 field testing |
| A. Engage qualified medium-voltage and low-voltage electrical testing and inspection agency to administer and perform tests and inspections. |