This is a Stipulated Price Agreement form (EJCDC C-520) between Lehigh County Authority and a contractor for Contract One – General Construction related to the Electrical Substation #2 and #4 Procurement project. The work includes all piping, fittings, excavation, demolition of existing sewer main and lateral pipe, temporary pumping and maintenance of sewer service, backfill, restoration, and testing as described in the drawings and specifications. The contractor must furnish all labor, superintendence, services, tools, products, and other utilities necessary to complete the work. Substantial completion must be achieved within 650 days from the contract commencement date, with final completion and readiness for final payment required within 680 days. At least 90 percent of the work must be completed at substantial completion, with surface restoration to be finished within 30 days thereafter. Online sealed bids will be received by Lehigh County Authority via PennBid until 11:00 a.m. on Wednesday, October 28, 2026, with bids remaining open for 60 days following the bid opening. Self-guided site visits can be scheduled via email with Charles Volk, P.E., Chief Capital Works Officer. All bidding documents are available at no cost through PennBid.
The contract price is established as a lump sum amount to be completed in accordance with the contract documents, with all specific cash allowances included in the stated price. Progress payments will be made monthly on or about the 15th of each month, with 90 percent of completed work due to the contractor until 50 percent completion is achieved; thereafter, 95 percent of monthly completed work shall be due. Retainage of 10 percent applies until 50 percent completion, after which retainage is reduced. Liquidated damages are set at $300.00 per day for delays beyond the substantial completion date and per day for delays beyond final completion. All payments not made by the due date will bear interest at 10 percent per annum. Each bid must be accompanied by bid security equal to 10 percent of the bid total in the form of a certified check, bank check, or bid bond. Lehigh County Authority reserves the right to reject any and all bids and to waive any omissions, errors, mistakes, defects, or irregularities in any bid. The contractor must not be under suspension or debarment by the Commonwealth, any other state, or the federal government and must provide written certifications as required.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Electrical Substation #2 And #4 Procurement - Contract One General Construction September 2026
FORM OF AGREEMENT
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
With Amendments by Lehigh County Authority as Indicated
00500
EJCDC
BETWEEN OWNER AND CONTRACTOR FOR
CONSTRUCTION CONTRACT (STIPULATED PRICE)
Supplemental Provisions, which are revisions by Lehigh County Authority to the original EJCDC form, are indicated.
THIS AGREEMENT is by and between
(Owner) and
(Contractor).
Owner and Contractor, in consideration of the mutual covenants set forth herein, agree as follows:
ARTICLE 1 - WORK
1.01 Contractor shall furnish all labor, superintendence, services, tools. Products, and other utilities and facilities to perform all work necessary for or incidental to, and to perform all other obligations imposed by this Contract One - General Construction, entitled “Electrical Substation #2 And #4 Procurement” (collectively referred to herein as the “Work”).
ARTICLE 2 - THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:
A. General Construction: Includes all piping, fittings, excavation, demolition of existing sewer main and lateral pipe, temporary pumping/maintenance of sewer service, backfill, restoration, and testing work as described in the drawings and specifications.
2.02 The Drawings covered under this Agreement consist of the following sheets: Refer to the attached bid documents
ARTICLE 3 – ENGINEER
3.01 The Authority will act as both the Owner and the Engineer.
ARTICLE 4 - CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Days to Achieve Substantial Completion and Final Payment
A. The Work will be substantially completed within 650 days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions and completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions within 680 days after the date when the Contract Times commence to run. In accordance with the definition of Substantial Completion in the
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
General Conditions and by Pennsylvania law, at least ninety percent (90%) of the work on the Project must be completed; in most cases surface restoration will be considered minor items and thus need not be completed at the time of Substantial Completion, however the Contractor must complete the surface restoration within 30 days of the Substantial Completion date.
4.03 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence of this Agreement and that Owner will suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Owner $ 300.00 for each day that expires after the time specified in Paragraph 4.02 for Substantial
Completion until the Work is substantially complete. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time or any proper extension thereof granted by Owner, Contractor shall pay Owner $ 300.00 for each day that expires after the time specified in Paragraph 4.02 for completion and readiness for final payment until the Work is completed and ready for final payment.
The liquidated damages may, solely at the Owner’s choice, be deducted by the Owner from monies due the
Contractor. Should the total amount chargeable as liquidated damages exceed the amount due or payable by the Contractor or, if a default had been declared by the Owner, then such excess shall be paid to the Owner by the Contractor or its Surety. The Owner retains all of its other rights detailed in the Contract Documents when
Contractor is out of compliance with the Contract Documents and, pursuance by the Owner of any other course of action shall not preclude the Authority from obtaining liquidated damages, if applicable.
ARTICLE 5 - CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to Paragraph s 5.01 below:
A. For all Work other than additional as directed Unit Price Work, a Lump Sum of:
(words) (numerals)
All specific cash allowances are included in the above price and have been computed in accordance with paragraph 11.02 of the General Conditions.
ARTICLE 6 - PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 14 of the General
Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s
Applications for Payment on or about the fifteenth (15th) day of each month during performance of the Work as provided in Paragraphs 6.02.A.1 and 6.02.A.2 below. All such payments will be measured by the schedule of
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price) values established as provided in Paragraph 2.07.A of the General Conditions (and in the case of Unit Price
Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Engineer may determine or Owner may withhold, including but not limited to liquidated damages, in accordance with Paragraph 14.02 of the General Conditions:
a. Ninety (90%) percent of the sum determined by Engineer shall be due to the Contractor until fifty (50%) percent of the Work has been completed (with the balance being retainage) ; and
b. If the Work has been fifty (50%) percent completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, Owner, on recommendation of Engineer, may determine that as long as the character and progress of the Work remain satisfactory to them, and there are no specific causes for greater withholding, one -half (½) of the amount retained so far shall be paid to the Contractor. After fifty (50%) percent of the Work has been finished the retainage shall be reduced and thereafter ninety-five (95%) percent of the estimate of that month's completed work shall be due the Contractor
The Owner may withhold payment for deficiency items according to the terms of the Contract;
however, if it does so, Contractor shall be notified of the deficiency item within fifteen (15) calendar days of the date that the application for payment is received.
The Owner shall make payment of the amount due to Contractor within thirty (30) calendar days of the date the application for payment is received. If any progress payment, less the applicable retainage amount, is not made to Contractor by the due date, Contractor shall be entitled to interest at the rate determined by the Commonwealth Secretary of Revenue for interest on payments on overdue or refund of taxes, as provided in §§806 and 806.1 of the Act of April 9, 1929 (P.L. 343, No. 176), known as The Fiscal
Code. If payment is made on or before the fifteenth (15th) calendar day after the thirty (30) day payment date, the interest penalty shall be waived.
When the Owner has more than one contractor involved in the Project and a dispute arises between the Owner and any of the contractors based upon increased costs claimed by one contractor occasioned by delays or other actions of another contractor, additional retainage in the sum of one and one -half times the amount of any possible liability may be withheld. This additional retainage shall be held until:
• final resolution is agreed to by all parties directly or indirectly involved; or
• the contractor causing the additional claim furnishes a bond satisfactory to the Owner to indemnify the Owner against the claim; or
• if the Owner so chooses, until Substantial Completion of the Contract.
2. Within thirty (30) days of receipt of the Contractor's request for final inspection and final payment, the Engineer shall make final inspection. If the Engineer determines that the Work is at the stage of
Substantial Completion, he shall issue a Certificate of Completion. The Owner shall then pay the Contractor any remaining monies due for the Work performed under this Contract within forty-five (45) days; however, the Owner may retain one and one-half (1½) times the cost of any minor items of Work remaining to be completed. This retainage shall be based upon the Engineer's certification detailing each uncompleted item and an estimated reasonable cost for completion of that item; payment for said minor items of Work shall be made upon their completion. After issuance of the Certificate of Completion, amounts due to the Contra ctor until Final Payment shall bear interest at the rate of interest of any bond issue the Owner used to finance the
Project or the rate of ten (10%) percent per annum, whichever is less.
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
In the event that there are any legal and equitable deductions, including liquidated damages, said deductions shall be made as they come due, and in any case prior to or at the time of payment for Substantial
Completion.
B. Any payment or payments to the Contractor by the Owner shall not bind the Owner to the acceptance of the Work performed.
C. If a dispute should arise between the Contractor and the Owner over the payment of such retainages and final payment, such dispute shall be arbitrated in accordance with §3942 of Part II of the Commonwealth
Procurement Code, 62 Pa.C.S.A. §3942.
6.03 Final Payment
A. Upon final completion and acceptance of the Work in accordance with Paragraph 14.07 of the General
Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 14.07.
ARTICLE 7 - INTEREST
7.01 All moneys not paid when due as provided in Article 14 of the General Conditions shall bear interest at the rate of ten (10%) percent per annum.
ARTICLE 8 – CONTRACTOR’S REPRESENTATIONS
8.01 In order to induce Owner to enter into this Agreement Contractor makes the following representations:
A. Contractor has examined and carefully studied the Contract Documents and the other related data identified in the Bidding Documents.
B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to exis ting surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the
Project Manual as provided in Paragraph 4.02 of the General Conditions and (2) reports and drawings of a
Hazardous Environmental Condition, if any, at the Site which has been identified in the Project Manual as provided in Paragraph 4.06 of the General Conditions.
E. Contractor has obtained and carefully studied (or assumes responsibility for doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions
(surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents , and safety precautions and programs incident thereto.
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
F. Contractor does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract Documents.
G. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.
H. Contractor has correlated the information known to Contractor, information and observations obtained from visits to the Site, reports and drawings identified in the Contract Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Contract Documents.
I. Contractor has given Owner and Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by
Engineer is acceptable to Contractor.
J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
K. The Contractor is financially solvent and experienced in and competent to perform the Work.
L. The Contractor is not currently under suspension or debarment by the Commonwealth, any other state or the federal government, and is willing to provide any and all written certifications required under any contractor integrity provisions to the Owner, any government agencies and/or entities providing financing to the Owner. If during the construction period of this Work the Contractor or any subcontractor becomes suspended or debarred by the Commonwealth, any other state or the federal government, the Owner shall have the right to require the Contractor to replace that subcontractor or terminate the Contract. Contractor agrees that it shall be responsible for all necessary and reasonable costs and expenses incurred by the Office of
Inspector General relating to an investigation of the Contractor’s or any subcontractor’s compliance which results in the suspension or debarment of the Contractor or any subcontractor.
ARTICLE 9 - CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement (pages 1 to 8, inclusive).
2. Performance Bond (pages 1 to 2, inclusive).
3. Payment Bond (pages 1 to 2, inclusive).
4. Other bonds (pages to , inclusive).
5. General Conditions (pages 1 to 64, inclusive).
6. Supplementary Conditions (which are reflected as changes in the General Conditions).
7. Specifications and Details as listed in the table of contents of the Pro ject Manual, including attachments and reference drawings.
8. Drawings listed in §2.02 of this Agreement (N/A).
9. Addenda (numbers to , inclusive).
10. Exhibits to this Agreement (enumerated as follows):
a. Contractor’s Bid (pages to , inclusive).
b. Documentation submitted by Contractor prior to Notice of Award (pages to , inclusive).
c. .
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
11. The following which may be delivered or issued on or after the Effective Date of the Agreement and are not attached hereto:
a. Notice to Proceed.
b. Work Change Directives.
c. Change Order(s).
B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
D. The Contract Documents may only be amended, modified, or supplemented as provided in Paragraph
3.04 of the General Conditions.
ARTICLE 10 - MISCELLANEOUS
10.01 Terms
A. Terms used in this Agreement will have the meanings stated in the General Conditions and the
Supplementary Conditions.
B. Terms used in this Agreement and the Contract Documents, regardless of the number and gender specifically used, shall be deemed and construed to include any other number, singular or plural, and any other gender, masculine, feminine, or neuter, as the context requires.
10.02 Assignment of Contract
A. No assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent
(except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.
10.03 Successors and Assigns
A. Owner and Contractor each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or
Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon
Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision. If any provision of the Contract Documents conflicts with a statute, regulation or conditions concerning the receipt of state or federal aid, including reduced interest on loans, the terms of the Contract Documents shall be modified the minimum amount possible to bring them within compliance.
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
10.05 Jurisdiction
A. This Agreement and the Contract Documents will be governed by the Laws and Regulations of the
Commonwealth of Pennsylvania. The Court of Common Pleas of Lehigh County, Pennsylvania, will have exclusive jurisdiction over matters which are not subject to arbitration and over all claims and disputes arising out of, or related to, the Contract Documents.
10.06 Records Access
A. The Owner, or any other governmental entity or agency any way involved in the project, or any of their duly authorized representatives shall at all reasonable times have access to any books, documents, papers and records of the Contractor which are directly pertinent to the Project and Contract Documents for the purpose of making audits, excerpts and transcriptions.
10.07 Non-waiver
A. Indulgences extended by the Owner to the Contractor shall not be construed as a waiver of any breach by the Contractor, nor shall any waiver of one breach be construed as a waiver of any rights or remedies with respect to any subsequent breach.
10.08 Product/Method Substitutions and Product Submittals:
A. Paragraph 6.05C of the General Conditions provides for charging the Contractor for costs associated with any request for substitution made by the Contractor. Section 01330 of the General Requirements provides for charging the Contractor for costs associated with review of any submittals which are classified as excess re -submittals; that is, any re-submittal beyond the second. Contractor agrees to compensate Owner for such charges by allowing deductions from Contractor’s progress payments.
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement in duplicate. One counterpart each has been delivered to Owner and Contractor. All portions of the Contract Documents have been signed or identified by Owner and Contractor or on their behalf.
This Agreement will be effective on ____________, (which is the Effective Date of the Agreement).
OWNER: CONTRACTOR:
By: By:
Title: Title:
[CORPORATE SEAL] [CORPORATE SEAL]
Attest: Attest:
Title: Title:
Address for giving notices: Address for giving notices:
EJCDC C-520 Suggested Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price)
License No.:
(If Owner is a corporation, attach evidence of authority to sign. If Owner is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of Owner-Contractor Agreement.)
(Where applicable)
Agent for service or process:
(If Contractor is a corporation or a partnership, attach evidence of authority to sign.)
END OF AGREEMENT
| EJCDC |
| ARTICLE 1 - WORK |
| ARTICLE 2 - THE PROJECT |
| ARTICLE 3 – ENGINEER |
| ARTICLE 6 - PAYMENT PROCEDURES |
| ARTICLE 7 - INTEREST |
| ARTICLE 8 – CONTRACTOR’S REPRESENTATIONS |
| ARTICLE 9 - CONTRACT DOCUMENTS |
| ARTICLE 10 - MISCELLANEOUS |