Summary: Instructions to Bidders for Electrical Substation #2 and #4 Procurement
This document constitutes the Instructions to Bidders issued by Lehigh County Authority for the Electrical Substation #2 and #4 Procurement project, based on EJCDC C-200 standard form with modifications specific to the Authority. Bidders must obtain complete bidding documents from the PennBid electronic service at no cost and are responsible for examining all documents, site conditions, and related data before submitting bids. No pre-bid conference will be held; site visits are self-guided and may be scheduled with Charles Volk, P.E., Chief Capital Works Officer. Online sealed bids will be received via PennBid until 11:00 a.m. on Wednesday, October 28, 2026, at which time they will be publicly opened and read. Bids shall remain open for 60 days from the bid opening date. Each bid must be accompanied by bid security equal to 10 percent of the bid total in the form of a certified check, bank check, or bid bond. The contract will be awarded to the responsible bidder whose bid is deemed in the best interests of the project, with the Authority reserving the right to reject any or all bids.
Bids must be submitted on a lump sum basis using the electronic bid forms provided through PennBid, with a hard copy of the handwritten, fully executed bid form scanned and submitted alongside uploaded documents. The Authority, as a municipal entity, is exempt from Pennsylvania Sales and Use Tax and will furnish certificates of exemption for applicable materials; however, contractors are responsible for determining tax applicability and shall not include such taxes in their bids. Bidders must comply with the Pennsylvania Prevailing Wage Act, pay workers at rates established by the Secretary of Labor and Industry, and ensure subcontractor compliance. The Pennsylvania Public Works Employment Act requires use of the Federal E-Verify program to confirm employee work authorization. Bidders must list all proposed subcontractors and suppliers with experience statements and evidence of Pennsylvania business qualification or a covenant to obtain such qualification prior to award. The contract is subject to comprehensive state and federal environmental laws, safety regulations, and nondiscrimination requirements in employment.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELECTRICAL SUBSTATION #2 AND #4 PROCUREMENT
INSTRUCTIONS TO BIDDERS
EJCDC C-200 Suggested Instructions to Bidders for Construction Contracts
With Changes by Lehigh County Authority as Indicated
00200 – i
SUGGESTED INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
ARTICLE 1 - DEFINED TERMS
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE
ARTICLE 5 - PRE-BID CONFERENCE
ARTICLE 6 - SITE AND OTHER AREAS
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
ARTICLE 8 - BID SECURITY
ARTICLE 9 - CONTRACT TIMES
ARTICLE 10 - LIQUIDATED DAMAGES
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
ARTICLE 13 - PREPARATION OF BID
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS
ARTICLE 15 - SUBMITTAL OF BID
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
ARTICLE 17 - OPENING OF BIDS
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
ARTICLE 21 - SIGNING OF AGREEMENT
ARTICLE 22 - SALES AND USE TAXES
ARTICLE 23 - RETAINAGE
ARTICLE 24 - CONTRACTS TO BE ASSIGNED
ARTICLE 25 - PARTNERING
ARTICLE 23 – NONDISCRIMINATION IN EMPLOYMENT
ARTICLE 24 – LAWS AND REGULATIONS
00200 – ii
TABLE OF ARTICLES (Alphabetical by Subject)
Subject Article
Award of Contract
Basis of Bid; Comparison of Bids
Bid Security
Bids to Remain Subject to Acceptance
Contract Security and Insurance
Contract Times
Contracts to be Assigned
Copies of Bidding Documents
Defined Terms
Evaluation of Bids and Award of Contract
Examination of Bidding Documents, Other Related Data, and Site
Interpretations and Addenda
Laws and Regulations
Liquidated Damages
Modification and Withdrawal of Bid
Nondiscrimination in Employment
Opening of Bids
Partnering
Pre-Bid Conference
Preparation of Bid
Qualifications of Bidders
Retainage
Sales and Use Taxes
Signing of Agreement
Site and Other Areas
Subcontractors, Suppliers and Others
Submittal of Bid
Substitute and “Or-Equal” Items
00200 – I-1
Supplemental Provisions, which are revisions by Lehigh County Authority to the original EJCDC form, are indicated.
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and
Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office--The Owner’s office/operations center located at 1053 Spruce Street, Wescosville, Pennsylvania, with a postal address of P.O. Box 3348, Allentown, PA 18106-0348, which will be the location from where the bidding procedures are to be administered. Bid documents will not be issued from this location.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents, as stated in the Advertisement or Invitation to Bid, are to be obtained from the PennBid site. Any deposit or fees, if applicable, will not be refunded.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, within five (5) days of Owner’s request, Bidder shall submit written evidence such as financial data, previous experience, present contracts commitments, and such other data as may be called for below.
A. Financial Data
B. Statement of Qualifications and Experience with name of contacts and project names.
C. Current Contacts.
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE
4.01 Subsurface and Physical Conditions
A. The Project Manual identifies:
1. Those reports of explorations and tests of subsurface conditions at or contiguous to the Site that Engineer has used in preparing the Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface and subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made available by Owner to any
Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02 of the General Conditions.
00200 – I-2
Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions or information contained in such reports or shown or indicated in such drawings.
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground
Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Hazardous Environmental Condition
A. The Project Manual identifies those reports and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that Engineer has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in Paragraph 4.03.A will be made available by Owner to any
Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.06 of the General Conditions.
Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions and Underground Facilities, and possible changes in the Bidding
Documents due to differing or unanticipated conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General
Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in
Paragraph 4.06 of the General Conditions.
4.05 On request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.06 Following is a list of other work that may be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents or Work related to on-going services. On request, Owner will provide to each Bidder for examination access to or copies of Contract
Documents (other than portions thereof related to price) for such other work.
A. None
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, the other related data identified in the Bidding
Documents, and any Addenda;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and site conditions that may affect cost, progress, and performance of the Work; this includes verifying depth of existing manholes in order to determine depth of pipeline installation;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the
Site (except Underground Facilities) which have been identified in §4.02 of the General Conditions, and (2) reports and
00200 – I-3 drawings of Hazardous Environmental Conditions at the Site which have been identified in §4.06 of the General
Conditions;
E. obtain and carefully study (or accept consequences of not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and
Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents, and safety precautions and programs incident thereto;
F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. correlate the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents;
I. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to
Bidder; and
J. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the
Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that
Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 - PRE-BID CONFERENCE
5.01 There will be no pre-bid conference. Bidders are responsible to become familiar with the site via self-guided site visits.
ARTICLE 6 - SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to LCA via PennBid.
Interpretations or clarifications considered necessary by LCA in response to such questions will be issued by Addenda
00200 – I-4 mailed or delivered to all parties recorded by Owner and Engineer as having purchased or downloaded the Bidding
Documents and attended the pre-bid conference and site visit. Questions received less than three (3) days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of ten (10%) percent of
Bidder’s maximum Bid price and in the form of a cashier’s check or a Bid bond (on the form attached) issued by a surety meeting the requirements of §§5.01 and 5.02 of the General Conditions.
8.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract
Documents, furnished the required contract security and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within fifteen (15) days after the Notice of Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid security of the three apparent lowest Bidders will be returned upon the signing of the Agreement and furnishing of acceptable bonds and other documents by the successful Bidder.
8.03 Bid security of all Bidders except the three apparent lowest Bidders will be returned within thirty (30) days after the Bid opening.
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which, [Milestones are to be achieved and] the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the
Bidding Documents without consideration of possible substitute or “or-equal” items. Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. Refer to General Conditions Paragraph 6.05 for requirements on substitute and “or equal”.
Bidders shall not rely upon approvals made in any other manner.
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 A list of proposed Subcontractors and Suppliers is required to be submitted to Owner with the bid. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor and Suppliers. Contractor shall also submit evidence that
Subcontractors and Suppliers are qualified to do business in the Commonwealth of Pennsylvania or covenant to obtain
00200 – I-5 such qualification prior to and as a condition of award of a Contract. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, [without an increase in the Bid.]
No substitutions for Subcontractors shown on the list shall be made by Contractor without prior written approval of
Owner or Engineer.
12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors or Suppliers. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.
12.03 Contractor shall not be required to employ any Subcontractor or Supplier against whom Contractor has reasonable objection.
4. Any restrictions or limitations on subcontracting should appear in SC-6.06, and cross references to that location should appear in I-12.
ARTICLE 13 - PREPARATION OF BID
13.01 The Bid Form and required supplements are included with the Bidding Documents. Bids must be submitted through PennBid service using the electronic forms provided. A hard copy of the handwritten fully executed Bid Form shall be scanned and submitted along with the uploaded the bid documents on PennBid.
13.02 All blanks on the Bid Form shall be completed prior to electronic submission of the Bid. A written bid price shall be indicated for each item, or the words “no bid”, “no charge”, or “not applicable” entered.
13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown below the signature.
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown below the signature.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown below the signature.
13.06 A Bid by an individual shall show the Bidder’s name and official address.
13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid Form.
The official address of the joint venture shall be shown below the signature.
13.08 All names shall be typed or printed in ink below the signatures. Proof of a partner’s, or agent’s, authority to obligate the Contractor must be attached to the Bid.
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
00200 – I-6
13.10 The address and telephone number for communications regarding the Bid shall be shown.
13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the Commonwealth of
Pennsylvania or covenant to obtain such qualification prior to award of the Contract. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
13.12 Unless specifically provided in the Contract Documents, bids containing substitutions or combinations of alternates will not be considered unless such substitutions or combinations are specifically authorized by the Owner.
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS
14.01 Lump Sum
A. Bidders shall submit a Bid on a lump sum basis as set forth in the Bid Form.
14.02 The Bid price shall include such amounts as the Bidder deems proper for overhead and profit on account of cash allowances, if any, named in the Contract Documents as provided in Paragraph 11.02 of the General Conditions.
ARTICLE 15 - SUBMITTAL OF BID
15.01 – All Bid Documents are to be acquired through the Penn Bid Service.
15.02 A Bid shall be submitted no later than the date and time prescribed and using the PennBid service as indicated on the Invitation to Bid, and shall be accompanied by the Bid security and other required documents.
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bidder may withdraw his Bid from consideration after the Bid opening without forfeiture of the cashier's check, surety bid bond or other security filed with the Bid if the price bid was submitted in good faith, and the Bidder submits credible evidence that the reason for the price bid being substantially lower was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional and substantial arithmetical error or an unintentional omission of a substantial quantity of work, labor, material or services made directly in the compilation of the Bid.
Withdrawal is allowed only if (i) notice of a claim of the right to withdraw such Bid is made in writing with the Owner within two (2) business days after the opening of Bids; and (ii) the withdrawal of the Bid would not result in the awarding of the contract on another Bid of the same Bidder, his partner, or to a corporation or business venture owned by or in which he has a substantial interest. No Bidder who is permitted to withdraw a Bid shall supply any material or labor to, or perform any subcontract or other work agreement for any person to whom a contract or subcontract is awarded in the performance of the contract for which the withdrawn Bid was submitted, without the written approval of the Owner.
16.02 If a Bid is withdrawn in accordance with the provisions of §16.01, the Owner may award the contract to the next lowest Bidder or reject all Bids and resubmit the project for bidding. In the event the Owner resubmits the project for bidding the withdrawing Bidder shall pay the costs, in connection with the resubmission, of printing new contract document, required advertising, and printing and mailing notices to prospective Bidders, if the Owner finds that such costs would not have been incurred but for such withdrawal. In no event shall the withdrawing Bidder be permitted to resubmit a Bid for the Project.
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will be opened via PennBid at the time indicated in the Advertisement or Invitation to Bid. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of
Bids.
00200 – I-7
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible or responsive. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder.
Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in §12.01.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors and Suppliers to perform the Work in accordance with the Contract Documents.
19.06 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project. The Contractor shall submit an original hard copy of all Bid Documents with the Bid (upload to PennBid site).
19.07 Owner reserves the right to cancel the award of any Contract at any time prior to its execution of the
Agreement by Owner without incurring any liability to any of the Bidders.
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed
Agreement to Owner, it shall be accompanied by such bonds and appropriate insurance certificates.
ARTICLE 21 - SIGNING OF AGREEMENT
21.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the
Agreement as attached thereto. Within fifteen (15) days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten (10) days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.
00200 – I-8
ARTICLE 22 - SALES AND USE TAXES
22.01 Owner, as a municipal authority, is exempt from the Pennsylvania Sales and Use Tax. Certificates of
Exemption will be furnished to the Contractor for its purchase of materials for which the Authority’s exemption is transferable, upon Contractor’s request; however, it is Contractor's responsibility to determine for which materials the tax exemption is applicable prior to submitting its Bid. Said taxes shall not be included in the Bid. Contractor shall pay all other sales, consumer, use and other similar taxes required to be paid by Contractor in accordance with the Laws and Regulations of the Commonwealth of Pennsylvania which are applicable during the performance of the Work. Said taxes shall not be included in the Bid. Refer to Paragraph 6.10 of the General Conditions for additional information, if any.
ARTICLE 23 - NONDISCRIMINATION IN EMPLOYMENT
23.01 Contractor agrees that:
A. In the hiring of employees for the performance of Work under the Contract or any subcontract, no
Contractor, Subcontractor or any person acting on behalf of the Contractor or Subcontractor shall by reason of gender, race, creed or color discriminate against any citizen of this Commonwealth who is qualified and available to perform the Work to which the employment relates.
B. No Contractor or Subcontractor or any person on their behalf shall in any manner discriminate against or intimidate any employee hired for the performance of Work under the Contract on account of gender, race, creed or color.
C. The Contract may be canceled or terminated by the Owner, and all money due or to become due under the
Contract may be forfeited, for a violation of the terms or conditions of these nondiscrimination provisions.
23.02 Contracts for Work under this Bid will obligate the Contractor and Subcontractor to be non-discriminatory in employment practices. Bidders, if requested, must submit with their Bid any information or documents required by state, federal or local statutes or regulations applicable to non-discrimination in employment; including, if necessary, a compliance report concerning their employment practices and policies in order to maintain their eligibility to receive the award of the Contract.
23.03 Bidders must submit a list of all Subcontractors who will perform work on the Project and written signed statements from authorized agents of the labor pools with which it will or may deal for employees on this Work, together with supporting information to the effect that these labor pools will affirmatively cooperate in or offer no hindrance to the recruitment, employment and equal treatment of employees who are seeking employment and are performing work under the Contract. If such agents or labor pools have failed or refused to furnish the necessary statements prior to the award of the Contract, Bidder shall provide certification as to what efforts have been made to secure such statements.
ARTICLE 24 - LAWS AND REGULATIONS
24.01 The Bidder’s attention is directed to the fact that all applicable laws, ordinances, and rules and regulations having jurisdiction over construction of the Project shall apply to the Contract throughout; are the
Bidder’s/Contractor’s responsibility to ascertain; and will be deemed to be included in the Contract the same as though herein written in full, whether or not specified in the Contract Documents.
24.02 PREVAILING WAGE ACT. The Pennsylvania Prevailing Wage Act applies to the work to be performed under the Contract; therefore, the Contractor must pay to its workers the minimum wage rate established by the Secretary of Labor and Industry and specified in the Contract Document - Prevailing Wage Act and Predetermination - and further the Contractor must assure that its Subcontractors also pay the Subcontractor’s workers these same minimum wage rates.
00200 – I-9
24.03 STEEL PRODUCTS PROCUREMENT ACT (N/A). Special attention is drawn to the provisions of Pennsylvania’s
Steel Products Procurement Act, which includes cast iron in the definition of steel products. The Contractor is advised that only steel products as defined in said Act shall be used or supplied in the performance of the Contract
The Act defines Steel Products as "Products rolled, formed, shaped, drawn, extruded, forged, cast, fabricated or otherwise similarly processed, or processed by a combination of two or more of such operations, from steel made in the United States by the open hearth, basic oxygen, electric furnace, Bessemer or other steel making process and shall include cast iron products and shall include machinery and equipment listed in United States Department of
Commerce Standard Industrial Classification 25 (furniture and fixture), 35 (machinery, except electrical) and 37
(transportation equipment) and made of, fabricated from, or containing steel components. If a product contains both foreign and United States steel, such product shall be determined to be a United States steel product only if at least seventy-five (75%) percent of the cost of the articles, materials and supplies have been mined, produced or manufactured, as the case may be, in the United States. Transportation equipment shall be determined to be a
United States steel product if it complies with section 165 of Public Law 97-424 (96 Stat. 2136)".
Contractor shall provide steel origin certifications of compliance in conjunction with shop drawing submittals, which certification shall be on forms to be provided by the Owner.
24.04 PUBLIC WORKS EMPLOYMENT ACT. Pennsylvania’s Public Works Employment Act requires contractors and subcontractors performing work on public works projects in this Commonwealth to comply with the
Federal E-Verify program (the EVP) to ensure employees are authorized to work in the United States. The EVP is a free Internet-based program operated by the United States Department of Homeland Security that compares information from an employee's Form I-9, Employment Eligibility Verification, to data from the United States
Department of Homeland Security and Social Security Administration records to confirm employment eligibility.
As a result, every contractor and subcontractor performing work under a public works contract shall utilize the EVP system to verify the employment eligibility of each new employee hired after January 1, 2013; shall submit the official Public Employment Verification Form to the Authority to ensure compliance with the act; and shall maintain documentation of continued compliance with the act by utilizing the EVP for new employees hired throughout the duration of the public work contract. The Pennsylvania Department of General Services is responsible for administering the program and information, as well as establishing the official Public Works Employment
Verification Form that needs to be completed by contractors and subcontractors, can be obtained on their website.
This has been the appropriate link to that website, although the Authority does not warrant its current accuracy -http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/public_works_employ ment_verification/1357211.
24.05 Environmental Laws. According to the Commonwealth Procurement Code, Act of May 15, 1998, P.L. 358, No. 57, 62 Pa.C.S.A. §3301, all invitations for bids and requests for proposals for construction projects issued by any government agency shall set forth any provision of federal and state statutes, rules and regulations dealing with the prevention of environmental pollution and the preservation of public natural resources that affect the projects.
This is the list entitled Environmental Statement as prepared by the Commonwealth of Pennsylvania, Department of
General Services, 1999 Edition, for its standard contract forms, although revised to eliminate acts which don’t apply because of geographic location.
The Bidder is hereby notified that this project is subject to those statutes, rules and regulations shown on the following list, and the work must be carried out in compliance with these statutes, rules and regulations.
STATE LAW
I. Purdon's Statutes - Title 3 (Agriculture)
• Pennsylvania Fertilizer Law of 1956, Act of May 29, 1956 (P.L. (1955) 1795, §1), as amended, 3 P.S. 68.1 et seq.
• Pennsylvania Pesticide Control Act of 1973, Act of March 1, 1974 (P.L. 90, No. 24), as amended, 3 P.S.
111.21 et seq.
• Agricultural Liming Materials Act, Act of March 17, 1978 (P.L. 15, No. 9), as amended, 3 P.S. 132-1 et seq.
• The Pennsylvania Plant Pest Act of 1992, Act of December 16, 1992 (P.L. 1228, No. 162, §1), as amended, 3
P.S. 258.1 et seq.
http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/public_works_employment_verification/1357211 http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/public_works_employment_verification/1357211
00200 – I-10
• Noxious Weed Control Law, Act of April 7, 1982 (P.L. 228, No. 74), as amended, 3 P.S. 255.1 et seq.
• Soil Conservation Law, Act of May 15, 1945 (P.L. 547, §1), as amended, 3 P.S. 849 et seq.
• (Relating to weather modification), Act of January 19, 1968 (P.L. (1967) 1024, §1), as amended, 3 P.S. 1101 et seq.
II. Purdon's Statutes - Title 16 (Counties)
• (Relating to land use), Act of January 13, 1966 (P.L. (1965) 1292, §1), as amended, 16 P.S. 11941 et seq.
III. Purdon's Statutes - Title 18 (Crimes and Offenses)
• The Crimes Code, Act of December 6, 1972 (P.L. 1482, No. 334), as amended, 18 Pa. C.S.A. 101 et seq.
IV. Purdon's Statutes - Title 24 (Education)
• Public School Code of 1949, Act of March 10, 1949 (P.L. 30, Art. VII, §741), as amended, 24 P.S. 7-741 et seq.
V. Purdon’s Statutes - Title 30 (Fish)
• The Fish and Boat Code, Act of October 16, 1980 (P.L. 996, No. 175), as amended, 30 Pa. C.S.A. 101 et seq.
VI. Purdon's Statutes - Title 32 (Forests, Waters and State Parks)
• (Relating to water power and water supply permits), Act of June 14, 1923 (P.L. 704, §1), as amended, 32 P.S. 591 et seq.
• Water Well Drillers License Act, Act of May 29, 1956 (P.L. (1955) 1840, §1), as amended, 32 P.S. 645.1 et seq.
• (Relating to Flood Control), Act of August 7, 1936 (P.L. 106, 1st Ex. Sess., No. 46), as amended, 32 P.S. 653 et seq.
• Flood Plain Management Act, Act of October 4, 1978 (P.L. 851, No. 166), as amended, 32 P.S. 679.101 et seq.
• Storm Water Management Act, Act of October 4, 1978 (P.L. 864, No. 167), as amended, 32 P.S. 680.1 et seq.
• Dam Safety and Encroachments Act, Act of November 26, 1978 (P.L. 1375, No. 325), as amended, 32 P.S.
693.1 et seq.
• (Relating to Stream Clearance), Act of June 5, 1947 (P.L. 422, §1), as amended, 32 P.S. 701 et seq.
• (Relating to Delaware River pollution), Act of April 19, 1945 (P.L. 272, §1), as amended, 32 P.S. 815.31 et seq.
• Delaware River Basin Compact, Act of July 7, 1961 (P.L. 518, §§1 to 3), as amended, 32 P.S. 815.101 et seq.
• (Relating to Preservation and Acquisition of Land for Open Space Uses), Act of January 19, 1968 (P.L.
(1967) 992, §1), as amended, 32 P.S. 5001 et seq.
• Land and Water Conservation and Reclamation Act, Act of January 19, 1968 (P.L. (1967) 996, §2), as amended, 32 P.S. 5101 et seq.
• Bluff Recession and Setback Act, Act of May 13, 1980 (P.L. 122, No. 48), as amended, 32 P.S. 5201 et seq.
• Wild Resource Conservation Act, Act of June 23, 1982 (P.L. 597, No. 170), as amended, 32 P.S. 5301 et seq.
VII. Purdon's Statutes - Title 34 (Game)
• The Game and Wildlife Code, Act of July 8, 1986 (P.L. 442, No. 93), as amended, 34 Pa. C.S.A. 101 et seq.
VIII. Purdon's Statutes - Title 35 (Health and Safety)
• (Related to public eating and drinking places), Act of May 23, 1945 (P.L. 926, §1), as amended, 35 P.S.
655.1 et seq. Repealed in Part. Section 6(b) of Act 1994, Dec. 12, P.L. 903, NO. 131, repealed this section in so far as it is inconsistent with said act.
• The Public Bathing Law, Act of June 23, 1931 (P.L. 899, §1), as amended, 35 P.S. 672 et seq.
• The Clean Streams Law, Act of June 22, 1937 (P.L. 1987, Art. I, §1), as amended, 35 P.S. 691.1 et seq.
• (Related to Commonwealth Contribution to cost of Abating Pollution) Act of August 20, 1953 (P.L. 1217, §1), as amended, 35 P.S. 701 et seq.
• Pennsylvania Safe Drinking Water Act, Act of May 1, 1984 (P.L. 206, No. 43), as amended, 35 P.S. 721.1 et seq.
00200 – I-11
• Pennsylvania Sewage Facilities Act, Act of January 24, 1966 (P.L. (1965) 1535, §1), as amended, 35 P.S.
750.1 et seq.
• Pennsylvania Solid Waste-Resource Recovery Development Act, Act of July 20, 1974 (P.L. 572, No. 198), as amended, 35 P.S. 755.1 et seq.
• (Related to pollution from abandoned mines), Act of December 15, 1965 (P.L. 1075, §1), as amended, 35
P.S. 760.1 et seq.
• (Related to low-level radioactive waste disposal), Act of February 9, 1988 (P.L. 31, No. 12, §101), as amended, 35 P.S. 7130.101 et seq.
• (Related to Camp Regulation), Act of November 10, 1959 (P.L. 1400 §1), as amended 35 P.S. 3001 et seq.
• Air Pollution Control Act, Act of January 8, 1960 (P.L. (1959) 2119, §1), as amended 35 P.S. 4001 et seq.
• Solid Waste Management Act, Act of July 7, 1980 (P.L. 380, No. 97), as amended, 35 P.S. 6018.101 et seq.
Repealed in Part. Section 905(b) of Act 1988, Feb. 9, P.L. 31, No. 12, the Low-Level Radioactive Waste
Disposal Act (35 P.S. §7130.101 et seq.), repealed this section insofar as it is inconsistent with said act.
• Radiation Protection Act, Act of July 10, 1984 (P.L. 688, No. 147, §101), as amended, 35 P.S. 7110.101 et seq. Repealed in Part. Section 17(b) of Act 1992, Dec. 18, P.L. 1638, No. 180, provides that this section is repealed insofar as it is inconsistent with said act.
• Worker and Community Right-to-Know Act, Act of October 5, 1984 (P.L. 734, No. 159), as amended, 35
P.S. 7301 et seq.
IX. Purdon's Statutes - Title 36 (Highways and Bridges)
• State Highway Law, Act of June 1, 1945 (P.L. 1242, Art. I, §101), as amended, 36 P.S. 670-101 et seq.
Repealed in Part. Section 4 of Act 1985, July 3, P.L. 159, No. 43 repealed this act insofar as it is inconsistent with said act.
• (Related to Junkyards along Highways), Act of July 28, 1966 (P.L. 91, §1, Sp. Sess.), as amended, 36 P.S.
2719.1 et seq.
• Highway Vegetation Control Act, Act of December 20, 1983 (P.L. 293, No. 79), as amended, 36 P.S. 2720.1 et seq.
X. Purdon's Statutes - Title 37 Appendix (Historical and Museum)
• History Code, Act of May 26, 1988 (P.L. 414, No. 72, §1), as amended, 37 Pa.C.S.A. 101 et seq.
XI. Purdon's Statutes - Title 43 (Labor)
• (Related to General Safety), Act of May 18, 1937 (P.L. 654, §1), as amended, 43 P.S. 25-1 et seq.
• Seasonal Farm Labor Act, Act of June 23, 1978 (P.L. 537, No. 93), as amended, 43 P.S. 1301.101 et seq.
XII. Purdon's Statutes - Title 52 (Mines and Mining)
• The Coal Mine Sealing Act of 1947, Act of June 30, 1947 (P.L. 1177, §1), as amended, 52 P.S. 28.1 et seq.
• Coal Refuse Disposal Control Act, Act of September 24, 1968 (P.L. 1040, No. 318), as amended, 52 P.S.
30.51 et seq.
• (Related to Coal Land Improvement), Act of July 19, 1965 (P.L. 216, No. 117), as amended, 52 P.S. 30.101 et seq.
• (Related to Mine Fires and Subsidence), Act of April 3, 1968 (P.L. 92, No. 42), as amended, 52 P.S. 30.201 et seq.
• Pennsylvania Anthracite Coal Mine Act, Act of November 10, 1965 (P.L. 721, No. 346), as amended, 52 P.S.
70-101 et seq.
• (Related to discharge of coal into banks of streams), Act of June 27, 1913 (P.L. 640, §1), as amended, 52 P.S.
631 et seq.
• (Related to Caving-in, Collapse, Subsidence), Act of May 27, 1921 (P.L. 1198, §1), as amended, 52 P.S. 661 et seq.
• (Related to Subsidence), Act of September 20, 1961 (P.L. 1538, §1), as amended, 52 P.S. 672.1 et seq.
00200 – I-12
• Anthracite Strip Mining & Conservation Act, Act of June 27, 1947 (P.L. 1095, §2), as amended, 52 P.S.
681.1 et seq.
• (Related to control and drainage of water from coal formations), Act of July 7, 1955 (P.L. 258, §1), as amended, 52 P.S. 682 et seq.
• Pennsylvania Bituminous Coal Mine Act, Act of July 17, 1961 (P.L. 659, Art. I, §101), as amended, 52 P.S.
701-101 et seq.
• (Related to Abandoned Mines), Act of May 7, 1935 (P.L. 141, §1), as amended, 52 P.S. 809 et seq..
• (Related to maps and plans), Act of June 15, 1911 (P.L. 954, §1), as amended, 52 P.S. 823.
• Surface Mining Conservation and Reclamation Act, Act of May 31, 1945 (P.L. 1198, §1), as amended, 52
P.S. 1396.1 et seq.. Repealed in Part. Section 27 of Act 1984, Dec. 19, P.L. 1093, No. 219, provides that, except as provided in §3304 of this title, this section "is repealed to the extent that it applies to the surface mining of minerals other than bituminous and anthracite coal."
• The Bituminous Mine Subsidence and Land Conservation Act, Act of April 27, 1966 (P.L. 31, 1st Sp. Sess., §1), as amended, 52 P.S. 1406.1 et seq.
• (Related to cave-in or subsidence of surface above mines), Act of July 2, 1937 (P.L. 2787, §1), as amended, 52 P.S. 1407 et seq.
• (Related to coal stripping), Act of June 18, 1941 (P.L. 133, §1), as amended, 52 P.S. 1471 et seq.
• (Related to coal under State Lands), Act of June 1, 1933 (P.L. 1409, §1), as amended, 52 P.S. 1501 et seq.
• (Related to Mining Safety Zones), Act of December 22, 1959 (P.L. 1994, §1), as amended, 52 P.S. 3101 et seq.
• (Related to Coal Mine Subsidence Insurance Fund), Act of August 23, 1961 (P.L. 1068, §1), as amended, 52
P.S. 3201 et seq.
• Interstate Mining Compact, Act of May 5, 1966 (P.L. 40, Sp. Sess. No. 1, §1), as amended, 52 P.S. 3251 et seq.
• Noncoal Surface Mining Conservation and Reclamation Act, Act of December 19, 1984 (P.L. 1093, No.
219), as amended, 52 P.S. 3301 et seq.
XIII. Purdon's Statutes - Title 58 (Oil and Gas)
• Oil and Gas Conservation Law, Act of July 25, 1961 (P.L. 825, §1), as amended, 58 P.S. 401 et seq.
• Pennsylvania Used Oil Recycling Act, Act of April 9, 1982 (P.L. 314, No. 89), as amended, 58 P.S. 471 et seq.
• Coal and Gas Resource Coordination Act, Act of December 18, 1984 (P.L. 1069, No. 214), as amended, 58
P.S. 501 et seq.
• Oil and Gas Act, Act of December 19, 1984 (P.L. 1140, No. 223), as amended, 58 P.S. 601.101 et seq.
XIV. Purdon's Statutes Title 63 (Professions and Occupations)
• Sewage Treatment Plant and Waterworks Operators' Certification Act, Act of November 18, 1968 (P.L.
1052, No. 322), as amended, 63 P.S. 1001 et seq.
XV. Purdon’s Statutes - Title 64 (Public Lands)
• Pennsylvania Appalachian Trail Act, Act of April 28, 1978 (P.L. 87, No. 41), as amended, 64 P.S. 801 et seq.
XVI. Purdon's Statutes - Title 71 (State Government)
• The Administrative Code of 1929, Act of April 9, 1929 (P.L. 177, No. 175), as amended, 71 P.S. 51 et seq.;
Repealed in Part. Section 7 of Act 1991, Dec. 20, P.L. 439, No. 53, repealed the act of April 9, 1929 (P.L.
177, No. 175), known as Administrative Code of 1929 insofar as it is inconsistent with said act.
XVII. Purdon's Statutes - Title 72 (Taxation and Fiscal Affairs)
• Project 70 Land Acquisition and Borrowing Act, Act of June 22, 1964 (P.L. 131, Sp. Sess., No. 8), as amended, 72 P.S. 3946.1 et seq.
• (Related to pollution control services), Act of March 4, 1971 (P.L. 6, No. 2, §602.1, added 1971, Aug. 31, P.L. 362, No. 93, §6), as amended, 72 P.S. 7602.1 et seq.
XVIII. Purdon's Statutes - Title 73 (Trade and Commerce)
00200 – I-13
• Infrastructure Development Act, Act of July 11, 1996 (P.L. 677, No. 116, §1), as amended, 73 P.L. 393.21 et seq.
• (Related to Explosives), Act of July 1, 1937 (P.L. 2681, §1), as amended, 73 P.S. 151 et seq.; 1939, April 27, P.L. 34, No. 29, §1; 1949, May 18, P.L. 1461, §1. Suspended in Part. This section is suspended insofar as it is in conflict with the provisions of Reorganization Plan No. 8 of 1981. See 71 P.S. 5 751-35.
• (Related to Explosives), Act of July 10, 1957 (P.L. 685, §1), as amended, 73 P.S. 164 et seq. Suspended in
Part. Section 164 is suspended insofar as it is in conflict with the provisions of Reorganization Plan No. 8 of
1981. See 71 P.S. 751-35.
• (Related to Black Powder), Act of May 31, 1974 (P.L. 304, No. 96), as amended, 73 P.S. 169 et seq.
• (Related to excavation and demolition), Act of December 10, 1974 (P.L. 852, No. 287), as amended, 73 P.S.
176 et seq.
XIX. Purdon's Statutes - Title 75 (Vehicles)
• Vehicle Code, Act of June 17, 1976 (P.L. 162, No. 81), as amended, 75 Pa. C.S.A. 101 et seq.
• Snowmobile Law, Act of June 17, 1976 (P.L. 162, No. 81), as amended, 75 Pa. C.S.A. 7701 et seq.
• (Related to hazardous materials transport), Act of June 30, 1984 (P.L. 473, No. 99, §4), as amended, 75 Pa.
C.S.A. 8301 et seq.
XX. Purdon's Statutes - Title 77 (Workmen’s Compensation)
• Pennsylvania Workmen's Compensation Act, Act of June 2, 1915 (P.L. 736, Art. 1, §101), as amended, 77
P.S. 1 et seq.
• Pennsylvania Occupational Disease Act, Act of June 21, 1939 (P.L. 566, No. 284, §101), as amended, 77
P.S. 1201 et seq.
XXI. Other Statutes
• (Relating to Medical Waste-Manifesting and Transporter Licensing), Act of July 13, 1988 (P.L. 525, No. 93).
• Municipal Waste Planning, Recycling & Waste Reduction Act, Act of July 28, 1988 (P.L. 556, No. 101).
• Hazardous Sites Cleanup Act, Act of October 18, 1988 (P.L. 756, No. 108).
XXII. Pennsylvania Constitution - Article I, Section 27 (Adopted May 18, 1971)
FEDERAL LAW
• Acid Precipitation Act of 1980 (42 U.S.C. 8901-8912).
• Act to Prevent Pollution from Ships (33 U.S.C. 1901-1912).
• Americans with Disabilities Act, The,
• Asbestos Hazard Emergency Response Act of 1986 [see Toxic Substances Control Act §§201-214 (15 U.S.C.
2641-2654)].
• Atomic Energy Act of 1954 (42 U.S.C. 2014, 2021, 2021a, 2022, 2111, 2113, 2114).
• Aviation Safety and Noise Abatement Act of 1979 (49 App. U.S.C. 2101-2125).
• Clean Air Act (42 U.S.C. 7401-7642).
• Clean Water Act [see Federal Water Pollution Control Act].
• Coastal Zone Management Act of 1972 (16 U.S.C. 1451-1464).
• Comprehensive Environmental Response, Compensation & Liability Act of 1980 (42 U.S.C. 9601-9675).
• Emergency Planning and Community Right-to-Know Act of 1986 (42 U.S.C. 11001-11050).
• Energy Supply and Environmental Coordination Act of 1974 (15 U.S.C. 791-798).
• Environmental Quality Improvement Act of 1970 (42 U.S.C. 4371-4375).
• Federal Insecticide, Fungicide, and Rodenticide Act (7 U.S.C. 136-136v).
• Federal Land Policy and Management Act of 1976 (43 U.S.C. 1701-1784).
00200 – I-14
• Federal Water Pollution Control Act (33 U.S.C. 1251-1387).
• Geothermal Energy Research, Development, and Demonstration Act of 1974 (30 U.S.C. 1101-1164).
• Global Climate Protection Act of 1987 (15 U.S.C. 2901 note).
• Hazardous Substance Response Revenue Act of 1980 (see 26 U.S.C. 4611, 4612, 4661, 4662).
• Low-Level Radioactive Waste Policy Act (42 U.S.C. 2021b-2021d).
• Marine Protection, Research, and Sanctuaries Act of 1972 (33 U.S.C. 1401-1445).
• National Climate Program Act (15 U.S.C. 2901-2908).
• National Environmental Policy Act of 1969 (42 U.S.C. 4321-4370a)
• Noise Control Act of 1972 (42 U.S.C. 4901-4918).
• Nuclear Waste Policy Act of 1982 (42 U.S.C. 10101-10270).
• Outer Continental Shelf Land Act Amendments of 1978 (43 U.S.C. 1801-1866).
• Public Health Service Act (42 U.S.C. 300f-300j-11).
• Safe Drinking Water Act [see Public Health Service Act §§1401-1451 (42 U.S.C. 300f-300j-11)].
• Soil and Water Resources Conservation Act of 1977 (16 U.S.C. 2001-2009).
• Solid Waste Disposal Act (42 U.S.C. 6901-6991i)
• Surface Mining Control and Reclamation Act of 1977 (30 U.S.C. 1201-1328).
• Toxic Substances Control Act (15 U.S.C. 2601-2654).
• Uranium Mill Tailings Radiation Control Act of 1978 (42 U.S.C. 7901-7942).
• Water Resources Research Act of 1984 (42 U.S.C. 10301-10309).
END OF INSTRUCTIONS TO BIDDERS
| SUGGESTED INSTRUCTIONS TO BIDDERS |
| TABLE OF CONTENTS |
| ARTICLE 1 - DEFINED TERMS |
| ARTICLE 2 - COPIES OF BIDDING DOCUMENTS |
| ARTICLE 3 - QUALIFICATIONS OF BIDDERS |
| ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE |
| ARTICLE 5 - PRE-BID CONFERENCE |
| ARTICLE 6 - SITE AND OTHER AREAS |
| ARTICLE 7 - INTERPRETATIONS AND ADDENDA |
| ARTICLE 8 - BID SECURITY |
| ARTICLE 9 - CONTRACT TIMES |
| ARTICLE 10 - LIQUIDATED DAMAGES |
| ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS |