About this file

This document is a Pennsylvania Prevailing Wage Act (PW-1) compliance notice issued by Lehigh County Authority for the Electrical Substation #2 and #4 Procurement project. The file establishes prevailing wage requirements that apply to all work performed by the prime contractor and all subcontractors on this public works project. Sealed bids are due by 11:00 a.m. on Wednesday, October 28, 2026, through the PennBid electronic bidding service. Self-guided site visits may be scheduled via email with Charles Volk, P.E., Chief Capital Works Officer (charlesvolk@lehighcountyauthority.org). No pre-bid meeting is planned. Bid results will be available through PennBid, and bids shall remain open for 60 days from the bid opening date. Each bid must be accompanied by bid security equal to 10 percent of the total bid amount in the form of a certified check, bank check, or bid bond.

The prevailing wage rates, as determined by the Pennsylvania Secretary of Labor and Industry, must be paid to all workmen employed on the project without deduction or rebate, paid at least weekly. Contractors and subcontractors must post wage determinations at the project site, maintain accurate records of worker names, classifications, hours worked, and wages paid (preserved for two years), and submit weekly wage certifications and a final wage certification upon project completion. Apprentices are limited to those enrolled in approved programs registered with the Pennsylvania Apprenticeship and Training Council. Payment on a lump sum, piece work, or price-certain basis is prohibited. Lehigh County Authority reserves the right to reject any and all bids and to waive any omissions, errors, mistakes, defects, or irregularities.

View the file

Other files

File Type Posted
26 11 16.11 - Secondary Unit Substations - Secondary Less Than 1000V.pdf PDF
26 12 13.01 - Liquid-Filled Medium Voltge Unit Substation Transformers.pdf PDF
9-Agreement of Surety Form Contract.pdf PDF
23-EJCDC - Payment Bond (C-620-2002).pdf PDF
1-LCA-ELECTRICAL SUBSTATION PROCUREMENT DWGS.pdf PDF
017716 – CONTRACT CLOSEOUT.pdf PDF
15-Affidavit of Non-Collusion.pdf PDF
21-EJCDC - Performance Bond (C-600-2002).pdf PDF
012977.02 - MEASUREMENT AND PAYMENT.pdf PDF
13-List of Proposed Subcontractors.pdf PDF
26 27 13.11 - Microprocessor-Based Metering Equipment.pdf PDF
017900.01 - VIDEO TRAINING PROGRAMS.pdf PDF
26 23 00.16 - Arc Resistant Metal Enclosed Drawout Switchgear LV.pdf PDF
26 05 73.13 - Short Circuit Studies.pdf PDF
1-TITLE page.pdf PDF
26 13 26.11 - Metal Clad MV Arc Resistent Switchgear.pdf PDF
24-EJCDC - General Conditions (with Supplementary shown).pdf PDF
2-TOC.pdf PDF
011000.03 -SUMMARY OF THE WORK.pdf PDF
26 05 53 - Identification For Electrical Systems.pdf PDF
26 05 73.19 - Arc Flash Hazard Analysis.pdf PDF
26 43 13A - LV Surge Protective Devices For Electrical Distribution Systems.pdf PDF
19-EJCDC - Agreement Stipulated Price (C-520-2002).pdf PDF
5-EJCDC - Bid Form for Construction Contracts 00300 (003).pdf PDF
4-7-EJCDC - Bid Bond, Penal Sum Form (C-430-2002) Revised 10-30-2026.pdf PDF
11-Experience Questionnaire.pdf PDF
013300.0 - SUBMITTALS.pdf PDF
3-Addendum 1 LCA.pdf PDF
4-EJCDC - Instructions to Bidders (C-200-2002).pdf PDF
7-EJCDC - Bid Bond, Penal Sum Form (C-430-2002).pdf PDF
3-00010_Invitation to Bid.pdf PDF
26 05 73.16 - Coordination Studies.pdf PDF
17-CertAsToCorpPrincipal.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ELECTRICAL SUBSTATION #2 AND #4 PROCUREMENT

PENNSYLVANIA PREVAILING WAGE ACT PW-1

00810

PENNSYLVANIA PREVAILING WAGE ACT & PREDETERMINATION

1. The provisions of the Pennsylvania Prevailing Wage Act (the Act), approved August 15, 1961 (Act No. 442), as amended August 9, 1963 (Act No. 342), and the regulations issued pursuant thereto, are hereby incorporated into and made a part of the Contract Documents.

2. Incorporated into the Contract Documents are the following requirements. These requirements shall apply to all Work performed by the Contractor and to all Work performed by all Subcontractors.

2.1. The general prevailing minimum wage rates including contributions for employee benefits as they have been determined by the Secretary of Labor and Industry, the

“Secretary”, must be paid to the workmen employed in the performance of the Contract.

The Contractor shall comply with the conditions of the Act and the regulations issued pursuant thereto, to assure the full and proper payment of said rates.

2.2. These provisions shall apply to all work performed on the Contract by the Contractor and to all work performed on the Contract by all Subcontractors.

2.3. The Contractor shall insert in each of his Subcontracts all of the stipulations contained herein and such other provisions as may be required under applicable law.

2.4. No workmen may be employed on the public work except in accordance with the classifications set forth in the decisions of the Secretary. In the event that additional or different classifications are necessary, the procedure set forth in 34 PA Code 9.107 shall be followed.

2.5. All workmen employed or working on the public work shall be paid unconditionally, regardless of whether any contractual relationship exists or the nature of any contractual relationship which may be alleged to exist between a Contractor, Subcontractor and workmen, not less than once a week without deduction or rebate, on any account, either directly or indirectly, except authorized deductions, the full amounts due at the time of payment, computed at the rates applicable to the time worked in the appropriate classification. Nothing in the Contract, the Act or these Regulations shall prohibit the payment of more than the general prevailing minimum wage rates as determined by the

Secretary to any workman on public work.

2.6. The Contractor and each Subcontractor shall post for the entire period of construction the wage determination decisions of the Secretary, including the effective date of any changes thereof, in a prominent and easily accessible place or places at the site of the work and at such place or places used by them to pay workmen their wages. The posted notice of wage rates must contain 2.62 the following information:

2.6.1. Name of project.

2.6.2. Name of public body for which it is being constructed.

2.6.3. The crafts and classifications of workmen listed in the Secretary’s general prevailing minimum wage rate determinations for the particular project.

PENNSYLVANIA PREVAILING WAGE ACT PW-2

2.6.4. The general prevailing minimum wage rates determined for each craft and classification and the effective date of any changes.

2.6.5. A statement advising workmen that if they have been paid less than the general prevailing minimum wage rate for their job classification or that the Contractor and/or Subcontractor are not complying with the Act or the regulations issued pursuant thereto in any manner whatsoever they may file a protest with the

Secretary. Any workmen paid less than the rate specified in the Contract shall have a civil right of action for the difference between the wage paid and the wages stipulated in the Contract, which right of action must be exercised within six (6) months from the occurrence of the event creating such right.

2.7. The Contractor and all Subcontractors shall keep an accurate record showing the name, craft and/or classification, number of hours worked per day, and the actual hourly rate of wage paid (including employee benefits) to each workman employed by him in connection with the public work and such record must include any deductions from each workman. The record shall be preserved for two years from the date of payment and shall be open at all reasonable hours to the inspection of the public body awarding the

Contract and to the Secretary or his duly authorized representative.

2.8. Apprentices shall be limited to such numbers as shall be in accordance with a bona fide apprenticeship program registered with and approved by the Pennsylvania

Apprenticeship and Training Council and only apprentices whose training and employment are in full compliance with the provisions of the Apprenticeship and

Training Act approved July 14, 1961 (Act No. 304) and the Rules and Regulations issued pursuant thereto shall be employed on the public work project. Any workman using the tools of a craft who does not qualify as an apprentice within the provisions of this subsection shall be paid the rate predetermined for journeymen in that particular craft and/or classification.

2.9. Wages shall be paid without any deductions except authorized deductions. Employers not parties to a contract requiring contributions for employee benefits which the

Secretary has determined to be included in the general prevailing minimum wage rate shall pay the monetary equivalent thereof directly to the workman.

2.10. Payment of compensation to workmen for work performed on public work on a lump sum basis, or a piece work system, or a price certain for the completion of a certain amount of work, or the production of a certain result shall be deemed a violation of the

Act and the regulations issued pursuant thereto, regardless of the average hourly earnings resulting therefrom.

2.11. Each Contractor and each Subcontractor shall file a statement each week and a final statement at the conclusion of the work on the Contract with the Contracting Agency

(herein called the Owner), under oath, and in form satisfactory to the Secretary, certifying that all workmen have been paid wages in strict conformity with the provisions of the contract as prescribed by the Act and the regulations issued pursuant thereto or if any wages remain unpaid to set forth the amount of wages due and owing to each workman, respectively.

PENNSYLVANIA PREVAILING WAGE ACT PW-3

3. Contractor and all Subcontractors are required to file weekly wage certifications with the

Owner.

4. Before final payment is made, Contractor and all Subcontractors are required to submit final wage certifications.

END OF PREVAILING WAGE ACT SUMMARY