011000.03 -SUMMARY OF THE WORK.pdf
PDF 138 KB Posted
- Solicitation number
- US.255952
- Issued by
- Lehigh County, Pennsylvania
About this file
This is a Summary of Work document for the Electrical Substation Replacement Project – Equipment Procurement Phase, a state and local contract opportunity issued by the Lehigh County Authority in Pennsylvania. The project involves the procurement of equipment for an electrical substation replacement initiative. Online sealed bids will be received through the PennBid electronic bidding service until 11:00 a.m. on Wednesday, October 28, 2026, at which time bids will be publicly opened and read. A pre-bid meeting will not be held; however, site visits are available on a self-guided basis and can be scheduled via email with Charles Volk, P.E., Chief Capital Works Officer, at charlesvolk@lehighcountyauthority.org. All bidding documents are available at no cost through PennBid (www.PennBid.net). Bids shall remain open for 60 days from the date of bid opening, and bid results will be made available through PennBid.
Each bid must be accompanied by bid security in the form of a certified check, bank check, or bid bond in the required form equal to 10 percent of the total bid amount. The Lehigh County Authority reserves the right to reject any and all bids and to waive any omissions, errors, mistakes, defects, or irregularities in any bid. No set-asides are identified in this document. After bid opening, bids may be withdrawn only in compliance with Commonwealth of Pennsylvania laws and regulations.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Substation #2, #4 Procurement
7676 Industrial Blvd.
Allentown, PA 18106 September 15, 2026
011000.03-1
SECTION 011000.03
SUMMARY OF THE WORK
PART 1 - GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Lehigh County Authorities Pre-Treatment Plant which houses Substation #2 and Substation#4 is located at 7676 Industrial Drive, Allentown, PA 18106. The Pre-Treatment Plant will be referred to as the “Facility”. This Facility is operated by Jacobs.
B. Type of Contract: Procurement contract with a Fixed price.
C. Procurement of substation equipment assembly for substation# 2 per bid documents including drawings and specifications.
D. Procurement of substation equipment assembly for substation# 4 per bid documents including drawings and specifications.
E. Winning bidder must ship and deliver the equipment and product to a designated site/location at
Lehigh County authority's pretreatment plant at the address in the title block. The equipment delivery shall be coordinated with the installation contractor (To be determined by the authority).
F. The vendor/manufacturer representative shall allow the Lehigh County authority or the contractor hired by the authority to perform inspection at the time of the delivery of the equipment at site.
Vendor/manufacturer needs to make arrangements for the equipment inspection.
G. Include, shipping and labor costs in the procurement bid.
H. The winning vendor/manufacturer shall provide shop drawings of the electrical equipment to the
AHJ, EOR and owner for review and approval prior to fabrication. If required, the winning bidder shall hire a licensed engineer and file with the AHJ to obtain approval prior to fabrication.
I. Winning bidder shall provide power system studies to the EOR including arc flash studies and arc flash labels for the equipment.
J. Include factory acceptance testing in the procurement bid.
K. All bidders are required to provide a list of deviations that they are taking from the contract documents, if no list of deviations are provided it will be assumed that the contractors proposed equipment are in compliance with the contract documents and intent.
L. The Vendor/Procurement Contractor/Manufacturer/Manufacturer’s Authorized Representative shall bear full responsibility for any damage to, or deficiency in, the equipment arising during transportation, loading, or unloading, until the equipment has been delivered to and accepted at the site.
011000.03-2
M. Acceptance of the equipment shall take place upon delivery and shall be conditional on a satisfactory site inspection carried out by LCA's designated representative or by the installation contractor appointed by LCA.
N. Extended Warranty Alternate 1:
All bidders must include a separate line item (alternate 1) for the following extended warranty in addition to the standard 24 months manufacturer warranty.
12 months
24 months
36 months
O. Equipment Delivery Lead-Time Expediting Alternate 2
All Bidders shall provide a separate line-item price as an alternate 2 for expediting the manufacturer’s standard equipment delivery lead time. The alternate price shall represent the additional cost required to reduce the standard delivery lead time and expedite delivery of the equipment to the Project site, thereby allowing the equipment to be delivered earlier and potentially allowing the Project to achieve Substantial Completion earlier than the maximum 650-calendar-day period specified below.
The Base Bid shall be based on the Manufacturer’s/Bidder’s standard equipment delivery lead time. The expedited delivery alternate shall identify the additional cost and the corresponding reduction in delivery time from the standard lead time.
Under no circumstances shall the Substantial Completion date exceed 650 calendar days from the date the Agreement is approved by the Comptroller. Acceptance of the expediting alternate may be considered by the Owner to facilitate an earlier Substantial Completion date.
Bidders shall clearly identify the following information in their bid:
1. Additional Cost for Expediting Equipment Delivery: $____________
2. Number of Calendar Days Saved by Expediting: __________ days
3. Manufacturer’s/Bidder’s Standard Equipment Delivery Lead Time Included in Base Bid:
__________ days
The standard delivery lead time identified above shall be the basis of the Bidder’s original/base bid price. The expedited delivery cost shall be provided separately as an alternate/additive cost and shall not be included in the Base Bid.
The Owner reserves the right to accept or reject the expediting alternate.
1.2 CONCURRENT PROJECTS
A. The following projects will be taking place concurrently with the work of this project:
Construction Work - Installation of the Substation equipment assembly for substations 2 and 4
011000.03-3
B. Coordinate the work of this project, through the Owner’s Representative, to avoid conflicts with concurrent contracts.
1.3 SUBSTANTIAL AND PHYSICAL COMPLETION DATES
A. Equipment delivery date at site shall be determined by the equipment supplier and shall be negotiated and agreed on by the Lehigh County Authority prior to the approval of the agreement.
B. Substantial completion date shall be determined by the equipment supplier and shall be negotiated and agreed on by the Lehigh County Authority prior to the approval of the agreement. Complete the Work within 650 days (final number of days will be determined or directed by the Lehigh
County Authority) after the Agreement is approved by the Comptroller.
1. The time allocated for the performance of work under this contract includes 10 days for notification of the Contractor of the Comptroller’s approval of the Agreement.
2. The approval of the Agreement by the Comptroller constitutes the filing of the Contract
Documents as a public record and notice to the Contractor that a fully executed contract exists between the Contractor and the State.
C. Physically complete the Work within 30 days after the established Substantial Completion date.
1.4 CONTRACT AWARD SUBMITTALS
A. Submittal No. 1: Submit the CONTRACTOR’S LIST OF SUBCONTRACTORS-SUPPLIERS information required not later than 15 days after approval of the Contract by the Authority.
B. Submittal No. 2: Submit Preliminary Project Schedule related information within 15 days after approval of the Contract by the Authority
C. Submittal No. 3: Submit the Submittal Coordinator Qualifications not later than 10 days after
Award. Include resume and references, and other certification, licenses, or other requested information.
1.5 ITEMS NOT INCLUDED
A. The following items shown on the Drawings are not included in this Contract:
1. Items indicated “NIC” (Not in Contract).
2. Installation/demolition work of the substation equipment at site.
1.6 OCCUPANCY
A. This is an occupied Facility. The facility will be occupied and operational during execution of the Work. Ingress to and egress from the facility shall be maintained at all times.
011000.03-4
1.7 CONNECTION TO ELECTRICAL EQUIPMENT OR SYSTEMS
A. Contractor will not be allowed to tie into electrical equipment or systems until the Authority has reviewed and approved the connection.
1.8 CONTRACTOR USE OF PREMISES
A. Work hours shall be as established by the Facility authorities through the Owners’s
Representative.
B. Inform the Owners’s Representative of work area access requirements. The Owner’s
Representative will coordinate and schedule the requirements with Facility staff to obtain and ensure timely availability of work areas.
C. Check in with the Facility Representative, as directed, at the beginning of each workday. Furnish information regarding where employees will be working during the day.
D. Comply with the Facility’s Visitor Identification Policy. A copy of the current policy will be distributed at the initial job meeting.
E. The following items are not allowed on the Site or on Facility premises.
1. Firearms, ammunition, weapons, and dangerous instruments (other than tools required for the Work).
2. Alcoholic beverages and persons under the influence of same.
3. Cannabis and persons under the influence of same. Cannabis, as used herein shall refer to any form of cannabis that has psychoactive properties.
4. Illegal controlled substances and persons under the influence of same.
5. Cameras (except with written permission from the Owner’s Representative).
F. Comply with Facility policies relating to smoking at the Site.
G. Routes of ingress and egress within the facility to the location of the Work shall be as directed by the Owner’s Representative.
H. Store materials and perform the Work so that pedestrian and vehicular traffic is not obstructed.
I. Do not diminish the level of life safety during performance of the Work.
J. Furniture and portable equipment, which interferes with execution of the Work, will be removed, and reset by Facility personnel.
K. Remove furniture and portable equipment, which interferes with the execution of the Work, and store where directed. Reset such items when directed.
L. Utility Outages and Shutdowns: Do not interrupt utility services or branch services within the facility except for the time required to make new connections. Arrange with the Owner’s
Representative for the time and duration of interruptions of services. Provide temporary services required to always maintain the facility’s services other than during scheduled interruptions.
011000.03-5
M. Utility Outages and Shutdowns: Do not interrupt utility services or branch services within the facility. Provide temporary services required to always maintain such services.
N. Utility Outages and Shutdowns: Perform Work which will cause interruptions of utility services or branch services within the facility at such times as directed by the Owner’s Representative, on weekdays between the hours of 6:00 p.m. and 6:00 a.m. or on Saturdays or Sundays.
O. Do not use existing elevators for the Work.
P. Be responsible and accountable for employees, suppliers, subcontractors, and their employees, with regard to their use of the premises. Direct them to comply with the Facility Regulations and with the security and traffic regulations.
Q. Furnish Facility authorities with a telephone number or method to contact the supervisor for the
Work in case of an emergency after work hours, including weekends and holidays.
R. Direct employees to be watchful for people in or near the work area where safety hazards may be present. Notify the Facility Safety/Security Department, if necessary, to remove them from the work area or Site.
S. Report fire and other emergency situations to the Facility Safety/Security Department immediately.
1.9 REFERENCE SPECIFICATIONS AND STANDARDS
A. Comply with the requirements of the various specifications and standards referred to in these
Specifications, except where they conflict with the requirements of these Specifications. Such reference specifications and standards shall be the date of latest revision in effect at the time of receiving bids unless the date is given.
1.10 LAYING OUT
A. Examine the Contract Documents thoroughly and promptly report any errors or discrepancies to the Owner’s Representative before commencing the Work.
B. Lay out the Work in accordance with the Contract Documents.
1.11 SPECIAL INSPECTIONS
A. Special Inspections and tests are required by Chapter 17 of the Pennsylvania Building Code 2021.
Inspections & Testing Services will be provided by the state unless otherwise noted.
B. Contractors are responsible for notifying the Owners’s Representative regarding individual inspections listed in the STATEMENT OF SPECIAL INSPECTIONS. Contractors shall
011000.03-6 cooperate with the inspectors and testing agencies and sufficient notice and lead time (minimum
48 hours) must be allowed for inspection and testing to be performed.
C. Where deficiencies are identified, the contractor must take corrective actions to comply with the contract documents or remedy the deficiencies in accordance with contract.
PART 2 - PRODUCTS : Refer to the contract documents including specification and drawing for each of the products being supplied and delivered at site by this contract.
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
| PART 1 - GENERAL |
| 1.1 WORK COVERED BY CONTRACT DOCUMENTS |
| A. Lehigh County Authorities Pre-Treatment Plant which houses Substation #2 and Substation#4 is located at 7676 Industrial Drive, Allentown, PA 18106. The Pre-Treatment Plant will be referred to as the “Facility”. This Facility is operated by Jacobs. |
| B. Type of Contract: Procurement contract with a Fixed price. |
| C. Procurement of substation equipment assembly for substation# 2 per bid documents including drawings and specifications. |
| D. Procurement of substation equipment assembly for substation# 4 per bid documents including drawings and specifications. |
| E. Winning bidder must ship and deliver the equipment and product to a designated site/location at Lehigh County authority's pretreatment plant at the address in the title block. The equipment delivery shall be coordinated with the installation contra... |
| F. The vendor/manufacturer representative shall allow the Lehigh County authority or the contractor hired by the authority to perform inspection at the time of the delivery of the equipment at site. Vendor/manufacturer needs to make arrangements for t... |
| G. Include, shipping and labor costs in the procurement bid. |
| H. The winning vendor/manufacturer shall provide shop drawings of the electrical equipment to the AHJ, EOR and owner for review and approval prior to fabrication. If required, the winning bidder shall hire a licensed engineer and file with the AHJ to ... |
| I. Winning bidder shall provide power system studies to the EOR including arc flash studies and arc flash labels for the equipment. |
| J. Include factory acceptance testing in the procurement bid. |
| K. All bidders are required to provide a list of deviations that they are taking from the contract documents, if no list of deviations are provided it will be assumed that the contractors proposed equipment are in compliance with the contract document... |
| L. The Vendor/Procurement Contractor/Manufacturer/Manufacturer’s Authorized Representative shall bear full responsibility for any damage to, or deficiency in, the equipment arising during transportation, loading, or unloading, until the equipment has ... |
| M. Acceptance of the equipment shall take place upon delivery and shall be conditional on a satisfactory site inspection carried out by LCA's designated representative or by the installation contractor appointed by LCA. |
| N. Extended Warranty Alternate 1: |
| All bidders must include a separate line item (alternate 1) for the following extended warranty in addition to the standard 24 months manufacturer warranty. |
| 12 months |
| 24 months |
| 36 months |
| O. Equipment Delivery Lead-Time Expediting Alternate 2 |
| All Bidders shall provide a separate line-item price as an alternate 2 for expediting the manufacturer’s standard equipment delivery lead time. The alternate price shall represent the additional cost required to reduce the standard delivery lead time ... |
| The Base Bid shall be based on the Manufacturer’s/Bidder’s standard equipment delivery lead time. The expedited delivery alternate shall identify the additional cost and the corresponding reduction in delivery time from the standard lead time. |
| Under no circumstances shall the Substantial Completion date exceed 650 calendar days from the date the Agreement is approved by the Comptroller. Acceptance of the expediting alternate may be considered by the Owner to facilitate an earlier Substantia... |
| Bidders shall clearly identify the following information in their bid: |
| 1. Additional Cost for Expediting Equipment Delivery: $____________ |
| 2. Number of Calendar Days Saved by Expediting: __________ days |
| 3. Manufacturer’s/Bidder’s Standard Equipment Delivery Lead Time Included in Base Bid: __________ days |
| The standard delivery lead time identified above shall be the basis of the Bidder’s original/base bid price. The expedited delivery cost shall be provided separately as an alternate/additive cost and shall not be included in the Base Bid. |
| The Owner reserves the right to accept or reject the expediting alternate. |
| 1.2 CONCURRENT PROJECTS |
| A. The following projects will be taking place concurrently with the work of this project: |
| B. Coordinate the work of this project, through the Owner’s Representative, to avoid conflicts with concurrent contracts. |
| 1.3 SUBSTANTIAL AND PHYSICAL COMPLETION DATES |
| A. Equipment delivery date at site shall be determined by the equipment supplier and shall be negotiated and agreed on by the Lehigh County Authority prior to the approval of the agreement. |
| B. Substantial completion date shall be determined by the equipment supplier and shall be negotiated and agreed on by the Lehigh County Authority prior to the approval of the agreement. Complete the Work within 650 days (final number of days will be d... |
| 1. The time allocated for the performance of work under this contract includes 10 days for notification of the Contractor of the Comptroller’s approval of the Agreement. |
| 2. The approval of the Agreement by the Comptroller constitutes the filing of the Contract Documents as a public record and notice to the Contractor that a fully executed contract exists between the Contractor and the State. |
C. Physically complete the Work within 30 days after the established Substantial Completion date.
| 1.4 CONTRACT AWARD SUBMITTALS |
| A. Submittal No. 1: Submit the CONTRACTOR’S LIST OF SUBCONTRACTORS-SUPPLIERS information required not later than 15 days after approval of the Contract by the Authority. |
| B. Submittal No. 2: Submit Preliminary Project Schedule related information within 15 days after approval of the Contract by the Authority |
| C. Submittal No. 3: Submit the Submittal Coordinator Qualifications not later than 10 days after Award. Include resume and references, and other certification, licenses, or other requested information. |
| 1.5 ITEMS NOT INCLUDED |
| A. The following items shown on the Drawings are not included in this Contract: |
| 1. Items indicated “NIC” (Not in Contract). |
| 2. Installation/demolition work of the substation equipment at site. |
| 1.6 OCCUPANCY |
| A. This is an occupied Facility. The facility will be occupied and operational during execution of the Work. Ingress to and egress from the facility shall be maintained at all times. |
| 1.7 CONNECTION TO ELECTRICAL EQUIPMENT OR SYSTEMS |
| A. Contractor will not be allowed to tie into electrical equipment or systems until the Authority has reviewed and approved the connection. |
| 1.8 CONTRACTOR USE OF PREMISES |
| A. Work hours shall be as established by the Facility authorities through the Owners’s Representative. |
| B. Inform the Owners’s Representative of work area access requirements. The Owner’s Representative will coordinate and schedule the requirements with Facility staff to obtain and ensure timely availability of work areas. |
| C. Check in with the Facility Representative, as directed, at the beginning of each workday. Furnish information regarding where employees will be working during the day. |
| D. Comply with the Facility’s Visitor Identification Policy. A copy of the current policy will be distributed at the initial job meeting. |
| E. The following items are not allowed on the Site or on Facility premises. |
| 1. Firearms, ammunition, weapons, and dangerous instruments (other than tools required for the Work). |
| 2. Alcoholic beverages and persons under the influence of same. |
| 3. Cannabis and persons under the influence of same. Cannabis, as used herein shall refer to any form of cannabis that has psychoactive properties. |
| 4. Illegal controlled substances and persons under the influence of same. |
| 5. Cameras (except with written permission from the Owner’s Representative). |
| F. Comply with Facility policies relating to smoking at the Site. |
| G. Routes of ingress and egress within the facility to the location of the Work shall be as directed by the Owner’s Representative. |
| H. Store materials and perform the Work so that pedestrian and vehicular traffic is not obstructed. |
| I. Do not diminish the level of life safety during performance of the Work. |
| J. Furniture and portable equipment, which interferes with execution of the Work, will be removed, and reset by Facility personnel. |
| K. Remove furniture and portable equipment, which interferes with the execution of the Work, and store where directed. Reset such items when directed. |
| L. Utility Outages and Shutdowns: Do not interrupt utility services or branch services within the facility except for the time required to make new connections. Arrange with the Owner’s Representative for the time and duration of interruptions of ser... |
| M. Utility Outages and Shutdowns: Do not interrupt utility services or branch services within the facility. Provide temporary services required to always maintain such services. |
| N. Utility Outages and Shutdowns: Perform Work which will cause interruptions of utility services or branch services within the facility at such times as directed by the Owner’s Representative, on weekdays between the hours of 6:00 p.m. and 6:00 a.m.... |
| O. Do not use existing elevators for the Work. |
| P. Be responsible and accountable for employees, suppliers, subcontractors, and their employees, with regard to their use of the premises. Direct them to comply with the Facility Regulations and with the security and traffic regulations. |
| Q. Furnish Facility authorities with a telephone number or method to contact the supervisor for the Work in case of an emergency after work hours, including weekends and holidays. |
| R. Direct employees to be watchful for people in or near the work area where safety hazards may be present. Notify the Facility Safety/Security Department, if necessary, to remove them from the work area or Site. |
| S. Report fire and other emergency situations to the Facility Safety/Security Department immediately. |
| 1.9 REFERENCE SPECIFICATIONS AND STANDARDS |
| A. Comply with the requirements of the various specifications and standards referred to in these Specifications, except where they conflict with the requirements of these Specifications. Such reference specifications and standards shall be the date o... |
| 1.10 LAYING OUT |
| A. Examine the Contract Documents thoroughly and promptly report any errors or discrepancies to the Owner’s Representative before commencing the Work. |
| B. Lay out the Work in accordance with the Contract Documents. |
| 1.11 SPECIAL INSPECTIONS |
| A. Special Inspections and tests are required by Chapter 17 of the Pennsylvania Building Code 2021. Inspections & Testing Services will be provided by the state unless otherwise noted. |
| B. Contractors are responsible for notifying the Owners’s Representative regarding individual inspections listed in the STATEMENT OF SPECIAL INSPECTIONS. Contractors shall cooperate with the inspectors and testing agencies and sufficient notice and le... |
| C. Where deficiencies are identified, the contractor must take corrective actions to comply with the contract documents or remedy the deficiencies in accordance with contract. |
| PART 2 - PRODUCTS : Refer to the contract documents including specification and drawing for each of the products being supplied and delivered at site by this contract. |
| PART 3 - EXECUTION (Not Used) |