24-EJCDC - General Conditions (with Supplementary shown).pdf
PDF 826 KB Posted
- Solicitation number
- US.255952
- Issued by
- Lehigh County, Pennsylvania
About this file
This file is the General and Supplementary Conditions for Contract One—General Construction of the Electrical Substation #2 and #4 Procurement Project by Lehigh County Authority. The document establishes the contractual framework and terms governing the construction work, including definitions of key terms, preliminary matters, contract document requirements, availability of lands and subsurface conditions, bonds and insurance requirements, contractor responsibilities, owner responsibilities, engineer status during construction, changes in work, cost and payment procedures, tests and inspections, suspension and termination provisions, and dispute resolution methods. The contract specifies that the contractor must deliver executed agreements and bonds to the owner, commence work on the thirtieth day after the effective date or upon receipt of a Notice to Proceed, submit preliminary schedules within ten days of the agreement's effective date, and hold a preconstruction conference before work begins. The contractor is responsible for all labor, materials, equipment, and temporary facilities necessary for project completion in accordance with the contract documents. Progress payments are subject to engineer review and acceptance of the contractor's Application for Payment, with retainage provisions and final payment contingent upon substantial completion and engineer certification.
The General Conditions establish that the contractor must furnish performance and payment bonds in an amount equal to the contract price, maintain comprehensive liability insurance with minimum limits of $1,000,000 occurrence and $2,000,000 aggregate for general liability, and purchase builder's risk property insurance covering the full contract price. The contractor bears responsibility for all differing subsurface or physical conditions discovered at the site, with provisions for equitable adjustment to contract price or times if conditions materially differ from those indicated in the contract documents. The contractor must comply with all applicable laws and regulations, including prevailing wage requirements, and is responsible for hazardous environmental conditions created by materials the contractor brings to the site. The supplementary conditions modify the standard EJCDC form to address Lehigh County Authority's specific requirements, including provisions for scheduling, substitutions, inspections, and dispute resolution procedures. The contract contemplates unit price work and allows for change orders and work change directives as needed throughout the project duration.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Electrical Substation #2 And #4 Procurement: Contract One-General Construction
GENERAL AND SUPPLEMENTARY CONDITIONS
EJCDC C-700 Suggested Form of Standard General Conditions of the Construction Contract
With Amendments by Lehigh County Authority as Indicated
00700-i
GENERAL AND SUPPLEMENTARY CONDITIONS
TABLE OF CONTENTS
Supplemental Provisions, which are revisions by Lehigh County Authority to the original EJCDC form, are highlighted.
Page No.
ARTICLE 1 – DEFINITIONS & TERMINOLOGY 1
1.01 Defined Terms 1
1. Addenda 1
2. Agreement 1
3. Application for Payment 1
4. Asbestos 1
5. Bid 1
6. Bidder 1
6a. Bidding Documents 1
7. Bidding Requirements 1
8. Bonds 1
8a. Certificate of Completion 1
8b. Certificate of Payment 1
8c. Certified Check 2
9. Change Order 2
10. Claim 2
10a. Construction Coordinator 2
10b. Consultant 2
11. Contract 2
12. Contract Documents 2
13. Contract Price 2
14. Contract Times 2
15. CONTRACTOR 2
16. Cost of the Work 2
17. Drawings 2
18. Effective Date of the Agreement 2
19. ENGINEER 2
20. ENGINEER'S Consultant 2
20. Field Order 2
21. Final Acceptance Certificate 2
21a. Final Estimate 3
21b. General Conditions 3
22. General Requirements 3
23. Hazardous Environmental Condition 3
24. Hazardous Waste 3
25. Laws and Regulations; Laws or Regulations 3
26. Liens 3
27. Milestone 3
Page No.
28. Notice of Award 3
28a. Notice of Termination for Convenience 3
29. Notice to Proceed 3
30. OWNER 3
31. Partial Utilization 3
32. PCBs 3
32a. Progress Schedule 3
33. Petroleum 3
33a. Product or Products 4
34. Project 4
35. Project Manual 4
36. Radioactive Material 4
36a. Related Entity 4
37. Resident Project Representative 4
38. Samples 4
38a. Schedule of Submittals 4
38b. Schedule of Values 4
39. Shop Drawings 4
40. Site 4
41. Specifications 4
42. Subcontractor 4
43. Substantial Completion 5
43a. Successful Bidder 5
44. Supplementary Conditions 5
45. Supplier 5
46. Underground Facilities 5
47. Unit Price Work 5
48. Work 5
49. Work Change Directive 5
50. Written Amendment 5
1.02 Terminology 5
A. Intent of Certain Terms or Adjectives 5
B. Day 6
C. Defective 6
D. Furnish, Install, Perform, Provide 6
ARTICLE 2 – PRELIMINARY MATTERS 6
2.01 Delivery of Bonds 6
Electrical Substation Procurement: Contract No. 1-General Construction September 2026
00700-ii
2.02 Copies of Documents 7
2.03 Commencement of Contract Times;
Notice to Proceed 7
2.04 Starting the Work 7
2.05 Before Starting Construction 7
A. Preliminary Schedules 7
2.06 Preconstruction Conference 7
2.07 Initial Acceptance of Schedules 7
ARTICLE 3 – CONTRACT DOCUMENTS: INTENT,
AMENDING, REUSE 8
3.01 Intent 8
3.02 Reference to Standards 8
A. Standards, Specifications, Codes, Laws and Regulations 8
3.03 Reporting and Resolving Discrepancies 8
A. Reporting Discrepancies 8
B. Resolving Discrepancies 9
3.04 Amending and Supplementing Contract 9
Documents
3.05 Reuse of Documents 9
3.06 Electronic Data 10
ARTICLE 4 – AVAILABILITY OF LANDS: SUBSURFACE
AND PHYSICAL CONDITIONS; REFERENCE POINTS 10
4.01 Availability of Lands 10
4.02 Subsurface and Physical Conditions 10
A. Reports and Drawings 10
B. Limited Reliance by CONTRACTOR 11
4.03 Differing Subsurface or Physical Conditions 11
A. Notice 11
B. Engineer’s Review 11
C. Possible Price and Times Adjustments 11
4.04 Underground Facilities and Existing Utilities 12
A. Shown or Indicated 12
B. Not Shown or Indicated 12
4.05 Reference Points 13
4.06 Hazardous Environmental Conditions at Site 13
A. Reports & Drawings 13
B. Limited Reliance by Contractor on
Technical Data Authorized 13
ARTICLE 5 – BONDS AND INSURANCE 15
5.01 Performance, Payment and Other Bonds 15
5.02 Licensed Sureties and Insurers 15
5.03 Certificates of Insurance 15
5.04 CONTRACTOR’s Liability Insurance 16
5.05 OWNER’s Liability Insurance 18
5.06 Property Insurance 18
5.07 Waiver of Rights 20
5.08 Receipt and Application of Insurance Proceeds 21
5.09 Acceptance of Bonds and Insurance;
Option to Replace 21
5.10 Partial Utilization, Acknowledgment of 21
Property Owner
5.11 Bonds and Insurance; Changes to
Contract Price or Time 21
ARTICLE 6 – CONTRACTOR’S RESPONSIBILITIES 22
6.01 Supervision and Superintendence 22
6.02 Labor, Working Hours 22
6.03 Services, Materials and Equipment 22
6.04 Progress Schedule 23
6.05 Substitutes and “Or-Equal” 23
A. General 23
1. "Or-Equal" Items 23
2. Substitute Items 23
B. Substitute Construction Methods or Procedures 25
C. ENGINEER's Evaluation 26
D. Special Guarantee 26
E. ENGINEER's Cost Reimbursement 26
E. CONTRACTOR's Expense 26
6.06 Concerning Subcontractors, Suppliers 26
and Others
6.07 Patent Fees and Royalties 28
6.08 Permits 28
6.09 Laws and Regulations 28
6.10 Taxes 29
6.11 Use of Site and Other Areas 29
A. Limitation of Use of Site and Other Areas 29
B. Removal of Debris During Performance of the Work 30
C. Cleaning 30
D. Loading Structures 30
6.12 Record Documents 30
6.13 Safety and Protection 30
6.14 Safety Representative 31
6.15 Hazard Communication Programs 31
6.16 Emergencies 31
6.17 Shop Drawings and Samples 31
A. Submittals 31
B. Work Prior to Approvals 32
00700-iii
C. Submittal Procedures 32
D. ENGINEER's Review 32
E. Resubmittal Procedures 33
6.18 Continuing the Work 33
6.19 CONTRACTOR’s General Warranty and
Guarantee 33
6.20 Indemnification 34
6.21 Delegation of Professional Design Services 35
6.22 Limitations on Actions 35
ARTICLE 7 – OTHER WORK 35
7.01 Related Work at Site 35
7.02 Coordination 36
7.03 Legal Relationship 37
7.04 Other Contractor Damage and Claims 37
ARTICLE 8 – OWNER’S RESPONSIBILITIES 38
8.01 Communications to CONTRACTOR 38
8.02 Replacement of ENGINEER 38
8.03 Furnish Data 38
8.04 Pay Promptly When Due 38
8.05 Lands and Easements; Reports and Tests 38
8.06 Insurance 38
8.07 Change Orders 38
8.08 Inspections, Tests and Approvals 38
8.09 Limitations on OWNER’s Responsibilities 38
8.10 Undisclosed Hazardous Environmental 38
Condition
8.11 Evidence of Financial Arrangements 39
ARTICLE 9 – ENGINEER’S STATUS DURING
CONSTRUCTION 39
9.01 OWNER’s Representative 39
9.02 Visits to Site 39
9.03 Project Representative 39
9.04 Authorized Variations in Work 39
9.05 Rejecting Defective Work 40
9.06 Shop Drawings, Change Orders and Payments 40
9.07 Determinations for Unit Price Work 40
9.08 Decisions on Requirements of Contract
Documents and Acceptability of Work 40
9.09 Limitations on ENGINEER’s Authority
and Responsibilities 40
ARTICLE 10 – CHANGES IN THE WORK 41
10.01 Authorized Changes in the Work 41
10.02 Unauthorized Changes in the Work 41
10.03 Execution of Change Orders 41
10.04 Notification to Surety 42
10.05 Claims and Disputes 42
A. ENGINEER's Decision Required 42
B. Notice 42
C. ENGINEER's Action 42
D. ENGINEER's Failure to Render Decision 42
E. ENGINEER's Action is Final 42
F. Claim Invalidity 42
ARTICLE 11 – COST OF THE WORK; ALLOWANCES;
UNIT PRICE WORK 43
11.01 Cost of the Work 43
A. Costs Included 45
B. Costs Excluded 45
C. CONTRACTOR's Fee 46
D. Documentation 46
11.02 Allowances 46
A. General 46
B. Cash Allowances 46
C. Contingency Allowances 46
D. Prior to Final Payment 46
11.03 Unit Price Work 46
ARTICLE 12 – CHANGE OF CONTRACT PRICE;
CHANGE OF CONTRACT TIMES 47
12.01 Change of Contract Price 47
A. General 47
B. Value of Work Determination 47
C. CONTRACTOR's Fee 47
12.02 Change of Contract Times 48
12.03 Delays 48
ARTICLE 13 – TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE
OF DEFECTIVE WORK 48
13.01 Notice of Defects 49
13.02 Access to Work 49
13.03 Tests and Inspections 49
13.04 Uncovering Work 49
13.05 OWNER May Stop the Work 50
13.06 Correction or Removal of Defective Work 50
00700-iv
13.07 Correction Period 50
13.08 Acceptance of Defective Work 51
13.09 OWNER May Correct Defective Work 51
ARTICLE 14 – PAYMENTS TO CONTRACTOR
AND COMPLETION 52
14.01 Schedule of Values 52
14.02 Progress Payments 52
A. Application for Payments 52
B. Review of Applications 52
C. Payment Becomes Due 54
D. Reduction in Payment 54
14.03 CONTRACTOR’s Warranty of Title 54
14.04 Substantial Completion 55
14.05 Partial Utilization 55
14.06 Final Inspection 56
14.07 Final Application for Payment 56
A. Application for Payment 56
B. ENGINEER's Review of Application & Acceptance 57
C. Payment Becomes Due 57
14.08 Final Completion Delayed 57
14.09 Waiver of Claims 57
ARTICLE 15 – SUSPENSION OF WORK
AND TERMINATION 57
15.01 OWNER May Suspend Work 58
15.02 OWNER May Terminate for Cause 58
15.03 OWNER May Terminate for Convenience 59
15.04 CONTRACTOR May Stop Work or Terminate 59
15.05 Wrongful Termination 59
ARTICLE 16 – DISPUTE RESOLUTION 59
16.01 Methods and Procedures 59
ARTICLE 17 – MISCELLANEOUS 60
17.01 Giving Notice 60
17.02 Computation of Times 60
17.03 Cumulative Remedies 60
17.04 Survival of Obligations 60
17.05 Controlling Law 61
17.06 Headings 61
17.07 Resident Project Representative 61
Responsibilities
A. Schedules 61
B. Conferences and Meetings 61
C. Liaison 61
D. Shop Drawings and Samples 61
E. Review of Work, Rejection of Defective
Work, Inspections and Tests 61
F. Interpretation of Contract Documents 61
G. Modifications 61
H. Records 62
I. Reports 62
J. Payment Requests 62
K. Certificates, Operation and Maintenance
Manuals 62
L. Completion 62
M. Limitations on Authority 62
17.08 Severability and Interpretation 62
00700-1 of 63
GENERAL CONDITIONS
(WITH SUPPLEMENTARY CONDITIONS
INCLUDED AS UNDERLINED LANGUAGE)
GC shall mean General Conditions and SC shall mean
Supplementary Conditions when used herein.
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in the Bidding Requirements or Contract Documents and printed with initial capital letters, terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.
1. Addenda - Written or graphic instruments issued prior to the opening of Bids which clarify, correct or change the Bidding Requirements or the proposed Contract Documents.
2. Agreement - The written instrument which is evidence of the agreement between OWNER and CONTRACTOR covering the Work.
3. Application for Payment - The form accepted by ENGINEER which is to be used by CONTRACTOR during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract
4. Asbestos - Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration.
5. Bid - The offer or proposal of the bidder submitted on the prescribed form setting forth the prices for the Work to be performed.
6. Bidder - The individual or entity who submits a Bid directly to Owner.
6a. Bidding Documents - The Invitation to
Bid, Instructions to Bidders, Bid Form, Bid Bond Form, Experience Questionnaire, List of Proposed Subcontractors, Financial Statement(s), all additional documentation required by Article 7 of the Bid Form, all Addenda, and the proposed Contract
7. Bidding Requirements - The
Advertisement or Invitation to Bid, Instructions to Bidders, Bid security form, if any, and the Bid form with any supplements.
8. Bonds - Performance and Payment bonds and other instruments of security.
8a. Certificate of Completion - The certificate of the Engineer indicating that the work specified and performed under the Contract has reached Substantial Completion. This certificate shall include a list of minor items that remain uncompleted with the reasonable cost of completing each of those items. It shall also state the amount of any legal and equitable deductions, including liquidated damages, which are due the Authority at this time, as well as the retainage of one and one-half (1½) times the cost of the minor items remaining to be completed.
8b. Certificate of Payment - The document issued by the OWNER each time a payment is made to the CONTRACTOR for work performed under the Contract stating the specifics of the payment, retainage, change orders, relationship of the payment to the entire Contract amount and the time period covered by the payment. This certificate will be executed by the ENGINEER and/or his designees.
8c. Certified Check - A certified check drawn upon a solvent clearinghouse bank, 00700-2 of 63 bank cashier’s check, or trust company treasurer’s check.
9. Change Order - A document recommended by ENGINEER, which is signed by CONTRACTOR and OWNER and authorizes an addition, deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Times issued on or after the Effective Date of the Agreement.
10. Claim – A demand or assertion by
Owner or Contractor seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.
10a. Construction Coordinator - The person or entity designated pursuant to Paragraph 7.02 to coordinate the work of all prime contractors on the Project.
10b. Consultant - A person, firm, or corporation having a contract with OWNER or ENGINEER to furnish services as OWNER's or ENGINEER's independent professional associate with respect to the Project and who is identified as such by OWNER.
11. Contract – the entire and integrated written agreement between the OWNER and CONTRACTOR concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral.
12. Contract Documents - Those items so designated in the Agreement. Only printed or hard copies of the items listed in the Agreement are Contract Documents. Approved Shop Drawings, other Contractor’s submittals, and the reports and drawings of subsurface and physical conditions are not Contract
13. Contract Price - The moneys payable by
OWNER to CONTRACTOR for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of paragraph 11.03 in the case of Unit Price Work).
14. Contract Times - The numbers of days or the dates stated in the Agreement to: (i) achieve Milestones, if any, (ii) achieve Substantial Completion, and (iii) complete the Work so that it is ready for final payment as evidenced by ENGINEER's written recommendation of final payment.
15. CONTRACTOR - The individual or entity with whom OWNER has entered into the Agreement.
16. Cost of the Work – See paragraph 11.01.A for definition.
17. Drawings – That part of the Contract
Documents prepared or approved by ENGINEER which graphically shows the scope, extent and character of the Work to be furnished and performed by CONTRACTOR and which have been prepared or approved by ENGINEER and are referred to in the Contract Documents.
Shop Drawings and other CONTRACTOR submittals are not Drawings as so defined.
18. Effective Date of the Agreement - The date indicated in the Agreement on which it becomes effective, but if no such date is indicated it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver.
19. ENGINEER - The individual or entity named as such in the Agreement.
20. Field Order - A written order issued by
ENGINEER which requires minor changes in the Work, but which does not involve a change in the Contract Price or the Contract Times.
21. Final Acceptance Certificate - The document issued when the OWNER has determined that the construction of the CONTRACTOR’s portion of the Project is complete and indicates OWNER’s acceptance of the work. This certification reports the Final Estimate and is used to issue the final payment.
00700-3 of 63
21a. Final Estimate - The estimate made by the ENGINEER of the total contract value (minus legal and equitable deductions) of the construction work performed by the CONTRACTOR. This estimate shall be calculated following completion and acceptance of all work specified and performed under the Contract.
21b. General Conditions - Engineers' Joint
Contract Documents Committee (EJCDC) Document No. 1910-8 (2002 Edition) "Standard General Conditions of the Construction Contract".
22. General Requirements - The General
Requirements pertain to all sections of the Specifications.
23. Hazardous Environmental Condition – The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material in such quantities or circumstance that may present a substantial danger to persons or property exposed thereto in connection with the Work.
24. Hazardous Waste - The term Hazardous
Waste shall have the meaning provided in Section 1004 of the Solid Disposal Waste Act (42 USC Section 6903) as amended from time to time.
25. Laws and Regulations; Laws or Regulations
- Any and all applicable laws, rules, regulations, ordinances, codes and orders of any and all governmental bodies, agencies, authorities and courts having jurisdiction.
26. Liens - Charges, security interests or encumbrances upon real property or personal property.
27. Milestone - A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work.
28. Notice of Award - The written notice by
OWNER to the apparent successful bidder stating that upon timely compliance by the apparent successful bidder with the conditions precedent listed therein, within the time specified, OWNER will sign and deliver the Agreement.
28a. Notice of Termination for Convenience -
The notice given by the OWNER to the CONTRACTOR in accordance with Paragraph
15.03 that the Contract is terminated for convenience in whole or, from time to time, in part; which notice shall specify the extent of and the effective date of the termination.
29. Notice to Proceed - A written notice given by OWNER to CONTRACTOR fixing the date on which the Contract Times will commence to run and on which CONTRACTOR shall start to perform the Work under the Contract
30. OWNER – The Lehigh County
Authority, also referred to as the “Authority” in the Contract Documents and is the entity with whom CONTRACTOR has entered into the Agreement and for whom the Work is to be performed.
31. Partial Utilization - Use by OWNER of a substantially completed part of the Work for the purpose for which it is intended (or a related purpose) prior to Substantial Completion of all the Work.
32. PCBs - Polychlorinated biphenyls.
32a. Progress Schedule - A schedule, prepared and maintained by CONTRACTOR, describing the sequence and duration of the activities comprising the CONTRACTOR’s plan to accomplish the Work within the Contract Times.
33. Petroleum - Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute) such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Wastes and crude oils.
33a. Product or Products - New materials, machinery, components, equipment, fixtures, 00700-4 of 63 systems, and any other item which will become or has become a physical portion of the Work. The term "Products" does not include machinery and equipment used for preparation, fabrication, conveying, or erection of the Work. The term "Products" may include materials, equipment, or components removed from existing facilities that may, if specifically permitted by the Contract Documents, be re-used in the Work.
34. Project - The total construction of which the Work to be performed under the Contract Documents may be the whole, or a part.
35. Project Manual – The bound documentary information, based on the Construction Specifications Institute (CSI) organizational format, prepared for bidding and constructing the Work and includes:
Bidding Requirements (which term refers to the Advertisement or Invitation to Bid, the Instructions, and any Bid Form that may be suggested or prescribed, all of which provide information and guidance for all Bidders) and the Contract Documents (defined in Article 1 of the General Conditions), which include the Agreement, bonds and certificates, the General Conditions, the Supplementary Conditions, the Drawings, and the Specifications.
36. Radioactive Material – Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.
36a. Related Entity - An officer, director, partner, employee, agent, consultant, or subcontractor.
37. Resident Project Representative - A representative of either the OWNER or ENGINEER who may be assigned to the Project site on either a full- or part-time basis. The duties, responsibilities, and limitations on authority of the Resident Project Representative, if used, are specified in SC- 17.07.
38. Samples - Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged.
38a. Schedule of Submittals - A schedule, prepared and maintained by CONTRACTOR, of required submittals and the time requirements to support scheduled performance of related construction activities.
38b. Schedule of Values - A schedule, prepared and maintained by CONTRACTOR, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing CONTRACTOR’s Applications for Payment.
39. Shop Drawings - All drawings, diagrams, illustrations, schedules and other data or information which are specifically prepared or assembled by or for CONTRACTOR and submitted by CONTRACTOR to illustrate some portion of the Work.
40. Site – Lands or areas indicated in the
Contract Documents as being furnished by OWNER upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by OWNER which are designated for the use of CONTRACTOR.
41. Specifications - Those portions of the
Contract Documents consisting of written requirements for materials, equipment, construction systems, standards and workmanship as applied to the Work and certain administrative details applicable thereto.
42. Subcontractor - An individual or entity having a direct contract with CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the Site.
43. Substantial Completion / Substantially
Complete - The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of ENGINEER, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or specified part) can be utilized for the purposes for which it is
00700-5 of 63 intended. The terms "substantially complete" and "substantially completed" as applied to all or part of the Work refer to Substantial Completion thereof. In accordance with the Pennsylvania Public Works Contract Regulation Law, as amended by Act 142, of 1994, in no event will the Work (or a specified part thereof) be certified as substantially complete until at least ninety (90%) percent of the Work (or the specified part thereof) is completed.
43a. Successful Bidder - The Bidder submitting a responsive Bid to whom OWNER makes an award.
44. Supplementary Conditions - The part of the Contract Documents which amends or supplements the General Conditions and is indicated herein as underlined language.
45. Supplier - A manufacturer, fabricator, supplier, distributor, materialman or vendor having a direct contract with CONTRACTOR or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by CONTRACTOR or any Subcontractor.
46. Underground Facilities – All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.
47. Unit Price Work - Work to be paid for on the basis of unit prices.
48. Work - The entire completed construction or the various separately identifiable parts thereof required to be furnished under the Contract Documents.
Work includes and is the result of performing or furnishing labor and furnishing and incorporating materials and equipment into the construction, and performing or furnishing services and furnishing documents, all as required by the Contract Documents.
49. Work Change Directive - A written statement to CONTRACTOR, issued on or after the Effective Date of the Agreement and signed by OWNER and recommended by ENGINEER, ordering an addition, deletion or revision in the Work, or responding to differing or unforeseen physical conditions under which the Work is to be performed or to emergencies. A Work Change Directive will not change the Contract Price or the Contract Times, but is evidence that the parties expect that the change directed or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract Times.
50. Written Amendment - A written amendment of the Contract Documents, signed by the Authority and the Contractor on or after the effective date of the Contract.
1.02 Terminology
The following words or terms are not defined but, when used in the Bidding Requirements or Contract Documents, have the following meaning:
A. Intent of Certain Terms or Adjectives
1. The Contract Documents include the terms “as allowed,” “as approved,” “as ordered’” “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Work. It is intended that such exercise of professional judgment, action or determination will be solely to evaluate, in general, the Work for compliance with the requirements of and information in the Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific
00700-6 of 63 statement indicating otherwise). The use of any such term or adjective is not intended to and shall not be effective to assign to Engineer any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of Paragraph 9.09 or any other provision of the Contract
B. Day
1. The word "day" means a calendar day of
24 hours measured from midnight to the next midnight.
C. Defective.
1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract
Documents, or
b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents, or
c. has been damaged prior to
ENGINEER’s recommendation of final payment (unless responsibility for the protection thereof has been assumed by OWNER at Substantial Completion in accordance with Paragraph 14.04 or 14.05).
D. Furnish, Install, Perform, Provide
1. The word "furnish," when used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.
2. The word "install," when used in connection with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.
3. The word "perform" or "provide," when used in connection with services, materials, or equipment, shall mean to furnish and install said services, materials, or equipment complete and ready for intended use.
4. When "furnish," "install," "perform," or
"provide" is not used in connection with services, materials, or equipment in a context clearly requiring an obligation of CONTRACTOR, "provide" is implied.
Unless stated otherwise in the Contract Documents, words or phrases which have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.
ARTICLE 2 - PRELIMINARY MATTERS
2.01. Delivery of Bonds
A. When CONTRACTOR delivers the executed Agreements to OWNER, CONTRACTOR shall also deliver to OWNER such Bonds as CONTRACTOR may be required to furnish.
B. Evidence of Insurance: Before any Work at the
Site is started, CONTRACTOR shall deliver to OWNER, with copies to each additional insured identified in Article 5, certificates of insurance (and other evidence OWNER may reasonably request) which CONTRACTOR is required to
00700-7 of 63 purchase and maintain in accordance with Article 5.
2.02. Copies of Documents
A. OWNER will furnish to the CONTRACTOR a paper copy of the Contract Documents.
2.03. Commencement of Contract Times; Notice
to Proceed
A. The Contract Times will commence to run on the thirtieth day after the Effective Date of the Agreement, or, if a Notice to Proceed is given, on the day indicated in the Notice to Proceed.
2.04. Starting the Work
A. CONTRACTOR shall start to perform the Work on the date when the Contract Times commence to run. No Work shall be done at the Site prior to the date on which the Contract Times commence to run.
2.05. Before Starting Construction
A. Preliminary Schedules: Within ten (10) days after the Effective Date of the Agreement (unless otherwise specified in the General Requirements), CONTRACTOR shall submit to ENGINEER for review:
1. a preliminary Progress Schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents;
2. a preliminary Schedule of Submittals;
and
3. a preliminary Schedule of Values for all of the Work which will include quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work.
4. A schedule of job classification and wage rates.
2.06. Preconstruction Conference
A. Before any Work at the Site is started, a conference attended by CONTRACTOR, ENGINEER and others, as appropriate, will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2.05A, procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and maintaining required records.
2.07. Initial Acceptance of Schedules
A. At least ten days before submission of the first Application for Payment a conference attended by CONTRACTOR, ENGINEER and others, as appropriate, will be held to review for acceptability to ENGINEER as provided below the schedules submitted in accordance with paragraph 2.05.A. CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until acceptable schedules are submitted to and acceptable to ENGINEER.
1. The Progress Schedule will be acceptable to ENGINEER if it provides an orderly progression of the Work to completion within any specified Milestones and the Contract Times. Such acceptance will not impose on ENGINEER responsibility for the Progress Schedule, for scheduling or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR's full responsibility therefor.
2. CONTRACTOR's schedule of Shop
Drawing and Sample submissions will be acceptable to ENGINEER if it provides a workable arrangement for reviewing and processing the required submittals.
3. CONTRACTOR's Schedule of Values will be acceptable to ENGINEER as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work.
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT,
00700-8 of 63
AMENDING, REUSE
3.01 Intent
A. The Contract Documents are complementary; what is called for by one is as binding as if called for by all.
B. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials or equipment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be provided whether or not specifically called for at no additional cost to Owner.
C. Clarifications and interpretations of the
Contract Documents shall be issued by ENGINEER as provided in Article 9.
D. Each and every provision of law and clause of law required by law to be inserted in these Contract Documents shall be deemed to be inserted herein, and they shall be read and enforced as though they were included herein, and if through mistake or otherwise, any such provision and clause is not referenced or inserted, or is not correctly referenced or inserted, then upon the application of either party, the Contract Documents shall forthwith be physically amended to correctly make such reference or insertion.
3.02. Reference to Standards
A. Standards, Specifications, Codes, Laws and Regulations
1. Reference to standards, specifications.
manuals or codes of any technical society, organization or association, or to the Laws or Regulations, whether such reference be specific or by implication, shall mean the latest standard, specification, manual, code or Laws or Regulations in effect at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision of any such standard, specification, manual or code, or any instruction of a Supplier shall be effective to change the duties or responsibilities of OWNER, CONTRACTOR, or ENGINEER, or any of their subcontractors, consultants, agents, or employees from those set forth in the Contract Documents, nor shall any such provision or instruction be effective to assign to OWNER, ENGINEER, or any Consultants, agents, or employees any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract
3.03. Reporting and Resolving Discrepancies
A. Reporting Discrepancies
1. Contractor’s Review of Contract Documents Before Starting Work: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein and all applicable field measurements. Contractor shall promptly report in writing to Engineer any conflict, error, ambiguity, or discrepancy which Contractor may discover and shall obtain a written interpretation or clarification from Engineer before proceeding with any Work affected thereby.
2. Contractor’s Review of Contract Documents
During Performance of Work: If, during the performance of the Work, CONTRACTOR discovers any conflict, error, ambiguity or discrepancy within the Contract Documents or between the Contract Documents and any provision of any such Law or Regulation applicable to the performance of the Work or of any such standard, specification, manual or code or of any instruction of any Supplier referred to in paragraph 6.03.B, CONTRACTOR shall report it to ENGINEER in writing at once. CONTRACTOR shall not proceed with the Work affected thereby (except in an emergency as authorized by paragraph 6.16A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in paragraph 3.04.
00700-9 of 63
3. CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any such conflict, error, ambiguity or discrepancy unless CONTRACTOR knew or reasonably should have known thereof.
B. Resolving Discrepancies
1. Except as otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the Contract Documents and:
a. the provisions of any standard, specification, manual, code or instruction (whether or not specifically incorporated by reference in the Contract Documents); or
b. the provisions of any Laws or
Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation).
2. If there are any conflicts, errors, ambiguities, or discrepancies within the Contract Documents, the documents shall be interpreted in the order of precedence specified in §17.08 of the General Conditions.
3.04. Amending and Supplementing Contract
Documents
A. The Contract Documents may be amended to provide for additions, deletions and revisions in the Work or to modify the terms and conditions thereof by either a Change Order or a Work Change Directive.
B. The requirements of the Contract
Documents may be supplemented, and minor variations and deviations in the Work may be authorized, in one or more of the following ways:
1. a Field Order;
2. ENGINEER's approval of a Shop Drawing or Sample (Subject to the provisions of
Paragraph 6.17.D.3); or
3. ENGINEER's written interpretation or clarification.
3.05. Reuse of Documents
A. CONTRACTOR, and any Subcontractor or Supplier or other individual or entity performing or furnishing any of the Work under a direct or indirect contract with OWNER shall not:
1. have or acquire any title to or ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER or any Consultant, and
2. shall not reuse any of such Drawings, Specifications, other documents or copies on extensions of the Project or any other project without written consent of OWNER and ENGINEER and specific written verification or adoption by ENGINEER.
B. This prohibition of this Paragraph 3.05 will survive final payment or termination of the Contract. Nothing herein shall preclude CONTRACTOR from retaining copies of the Contract Documents for record purposes.
3.06. Electronic Data
A. Copies of data furnished by OWNER or ENGINEER to CONTRACTOR or CONTRACTOR to OWNER or ENGINEER that may be relied upon are limited to the printed copies (also known as hard copies). Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user’s sole risk. If there is a discrepancy between the electronic files and the hard copies, the hard copies govern.
B. Because data stored in electronic media format can deteriorate or be modified inadvertently or otherwise without authorization of the data’s creator, the party receiving electronic files agrees that it will perform acceptance tests or procedures within sixty (60) days, after which the
00700-10 of 63 receiving party shall be deemed to have accepted the data thus transferred. Any errors detected within the 60-day acceptance period will be corrected by the transferring party.
C. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data’s creator.
ARTICLE 4 - AVAILABILITY OF LANDS: SUBSURFACE
AND PHYSICAL CONDITIONS; HAZARDOUS
ENVIRONMENTAL CONDITIONS; REFERENCE POINTS
4.01. Availability of Lands
A. OWNER shall furnish the Site. OWNER shall notify CONTRACTOR of any encumbrances or restrictions not of general application but specifically related to use of the Site with which CONTRACTOR will have to comply in performing the Work. OWNER will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. If CONTRACTOR and OWNER are unable to agree on entitlement to or the amount or extent of any adjustments in the Contract Price or the Contract Times, or both, as a result of any delay in OWNER's furnishing the Site, CONTRACTOR may make a claim therefor as provided in paragraph 10.05.
B. CONTRACTOR shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment.
C. CONTRACTOR shall be fully responsible for all damage to real estate or personal property of any persons outside the Project Site, caused by CONTRACTOR, its Subcontractor(s), agents, or assignees in performing Work under this contract. CONTRACTOR's duties shall include repairing, replacing or restoring the damaged property to its condition prior to such damage or the payment of money damages equal to the reasonable value of the damage caused to such property. If CONTRACTOR fails to promptly repair or replace damaged property, OWNER may arrange to have the Work performed by others and the cost of such Work will be charged to the CONTRACTOR by deduction from a progress payment.
4.02. Subsurface and Physical Conditions
A. Reports and Drawings: The Project
Manual identifies:
1. those reports of explorations and tests of subsurface conditions at or contiguous to the Site that have been utilized by ENGINEER in preparing the Contract Documents; and
2. those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) that have been utilized by ENGINEER in preparing the Contract Documents.
B. Limited Reliance by CONTRACTOR on
Technical Data Authorized: CONTRACTOR may rely upon the general accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Project Manual. Except for such reliance on such "technical data," CONTRACTOR may not rely upon or make any claim against OWNER, ENGINEER or any Consultants with respect to:
1. the completeness of such reports and drawings for CONTRACTOR's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto, or
2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings, or
3. any CONTRACTOR interpretation of or conclusion drawn from any "technical data" or any such data, interpretations, opinions or information.
00700-11 of 63
4.03. Differing Subsurface or Physical Conditions
A. Notice: If CONTRACTOR believes that any subsurface or physical condition at or contiguous to the Site that is uncovered or revealed either:
1. is of such a nature as to establish that any "technical data" on which CONTRACTOR is entitled to rely as provided in Paragraph
4.02 is materially inaccurate, or
2. is of such a nature as to require a change in the Contract Documents, or
3. differs materially from that shown or indicated in the Contract Documents, or
4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents;
then CONTRACTOR shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as permitted by paragraph 6.16A), notify OWNER and ENGINEER in writing about such condition. CONTRACTOR shall not further disturb such conditions or perform any Work in connection therewith (except as aforesaid) until receipt of written order to do so.
B. ENGINEER's Review: After receipt of written notice as required by paragraph 4.03A, ENGINEER will promptly review the pertinent conditions, determine the necessity of OWNER's obtaining additional exploration or tests with respect thereto and advise OWNER in writing (with a copy to CONTRACTOR) of ENGINEER's findings and conclusions.
C. Possible Price and Times Adjustments:
1. The Contract Price or the Contract Times, or both, will be equitably adjusted to the extent that the existence of such differing subsurface or physical condition causes an increase or decrease in CONTRACTOR's cost of, or time required for performance of, the Work; subject, however, to the following:
a. such condition must meet any one or more of the categories described in paragraph 4.03.A; and
b. with respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of paragraphs
9.08 and 11.03.
2. CONTRACTOR shall not be entitled to any adjustment in the Contract Price or Contract Times if;
a. CONTRACTOR knew of the existence of such conditions at the time CONTRACTOR made a final commitment to OWNER in respect of Contract Price and Contract Times by the submission of a bid or becoming bound under a negotiated contract; or
b. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test or study of the Site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for CONTRACTOR prior to CONTRACTOR's making such final commitment; or
c. CONTRACTOR failed to give the written notice within the time and as required by paragraph 4.0 3 .A.
3. If OWNER and CONTRACTOR are unable to agree on entitlement to or as to the amount or length of any such equitable adjustment in the Contract Price or Contract Times, or both, a Claim may be made therefor as provided in paragraph 10.05.
However, OWNER, ENGINEER and all Consultants shall not be liable to CONTRACTOR for any claims, costs, losses or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all cost or arbitration or other dispute
00700-12 of 63 resolution costs) sustained by CONTRACTOR on or in connection with any other project or anticipated project.
4.04. Underground Facilities and Existing
Utilities
A. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to OWNER or ENGINEER by the owners of such Underground Facilities or by others. Unless it is otherwise expressly provided in the Project Manual:
1. OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or data; and
2. The cost of all of the following will be included in the Contract Price and CONTRACTOR shall have full responsibility for:
a. reviewing and checking all such information and data; or
b. locating all Underground
Facilities shown or indicated in the Contract Documents,
c. coordination of the Work with the owners of such Underground Facilities during construction, and
d. the safety and protection of all such Underground Facilities and repairing any damages thereto resulting from the Work.
B. Not Shown or Indicated
1. If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, CONTRACTOR shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by paragraph 6.16.A), identify the owner of such Underground Facility and give written notice to that owner and to OWNER and ENGINEER. ENGINEER will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence of the Underground Facility. During such time, CONTRACTOR shall be responsible for the safety and protection of such Underground Facility
2. If ENGINEER concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued to reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or Contract Times, or both, to the extent that they are attributable to the existence of any Underground Facility that was not shown or indicated in the Contract Documents and that CONTRACTOR did not know of and could not reasonably have been expected to be aware of or to have anticipated. If OWNER and CONTRACTOR are unable to agree on entitlement to or the amount or length of any such adjustment in Contract Price or Contract Times, OWNER or CONTRACTOR may make a claim therefor as provided in paragraph 10.05.
C. CONTRACTOR shall comply with federal, state, and local regulations relating to the requirement to notify utility companies prior to performing work which has the potential to damage the facilities of such utility companies.
CONTRACTOR shall make arrangements for a utility company representative to locate Underground Facilities prior to initiating excavation work.
D. If any utility company facility is damaged during the Work, CONTRACTOR shall immediately notify the affected utility company.
CONTRACTOR shall be fully responsible for repairing or replacing such damaged facilities in
00700-13 of 63 accordance with utility company's requirements.
If CONTRACTOR fails to promptly repair or replace damaged facilities, OWNER or utility company may arrange to have the required work performed by others and the cost of such work…