This is a Contract Closeout specification document (Section 01 70 00) applicable to the 2026 Bristol Borough CDBG Curb Ramp Program in Pennsylvania, which involves the design and construction of ADA/PennDOT compliant curb ramps with associated sidewalks, curbing, and sign relocation/installation. The specification establishes mandatory closeout procedures that contractors must follow upon project completion, including final cleaning, equipment adjusting, and submission of project record documents. Key closeout deliverables include written certification of work completion, final inspection punchlist completion, final application for payment, final completion photographs, outstanding inspection reports, material testing reports, and CS-4401 forms. Contractors must maintain on-site record documents throughout construction, including marked-up drawings, specifications, shop drawings, addenda, and change orders that accurately reflect all actual installations, substitutions, field changes, and measured locations of utilities and foundations.
The closeout specification requires contractors to submit comprehensive documentation prior to final payment, including payroll certification forms (for contracts exceeding $25,000), waivers of liens from all subcontractors and suppliers, maintenance bonds, any outstanding change orders, applicable liquid fuels and PennDOT compliance certifications, and test or sample results. Final payment is contingent upon final completion and acceptance of all work, completion of the punchlist, and submission of all required record documents to the Owner's Engineer. The specification mandates that all work comply with PennDOT Publication 408 and Borough Standards, with final cleaning including removal of temporary labels, debris, construction facilities, and waste materials from the site, as well as cleaning and adjustment of all operating equipment and fixtures to ensure proper functionality prior to project acceptance.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CLOSEOUT
01 70 00-1
SECTION 01 70 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Closeout procedures.
2. Final cleaning.
3. Adjusting.
4. Project record documents.
5. Operation and maintenance manual.
6. Spare parts and maintenance Products.
7. Other documentation.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning.
1.03 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Owner’s Engineer's review.
B. Owner’s Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph 14.06 of the General Conditions.
C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.
D. Provide submittals to Owner’s Engineer that are required by governing or other authorities.
E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.
F. Final Payment will not be made until final completion and acceptance of the Work.
G. Contractor shall provide final completion photos and any outstanding inspection reports, material testing reports, and final CS-4401 forms.
1.04 FINAL CLEANING
A. Execute final cleaning prior to final Project inspection.
B. Clean interior and exterior glass and surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
C. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
D. Clean or replace filters of operating equipment.
E. Clean debris from roofs, gutters, downspouts, and drainage systems.
01 70 00-2
F. Clean site; sweep paved areas, rake clean landscaped surfaces.
G. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.05 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
1.06 PROJECT RECORD DOCUMENTS
A. Maintain on-site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, Product data, and samples.
6. Manufacturer’s instructions for assembly, installation and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured depth of foundations in relation to finish main floor datum.
2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
4. Field changes of dimension and detail.
5. Details not on original Contract Drawings.
G. Delete Engineer's title block and seal from all documents.
H. Submit documents to Owner’s Engineer with claim for final Application for Payment.
1.07 OTHER DOCUMENTATION
A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:
1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).
2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.
3. Maintenance Bond.
4. Any Change Orders with supporting documentation which remain to be submitted.
01 70 00-3
5. Applicable liquid fuels, PennDOT Compliance Certifications and related documents.
6. Test and/or sample results.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION