34-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf

PDF 97 KB Posted

Attached to
2026 Bristol Borough CDBG Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

About this file

This is a specification document for Section 01 31 00 - Coordination and Meetings, establishing the administrative and procedural framework for the 2026 Bristol Borough CDBG Curb Ramp Program in Pennsylvania. The document outlines the contractor's responsibilities for coordinating scheduling, submittals, and work sequencing to ensure efficient and orderly installation of project elements, including field engineering services, stakeout activities, and verification of setbacks and easements. A mandatory preconstruction meeting must be held at the project site after the effective date of the agreement and before work commences, with required attendance from the owner, owner's engineer, owner's resident project representative, contractor, contractor's superintendent, major subcontractors, contractor's design engineer, and third-party inspection representatives. The preconstruction meeting agenda includes distribution of contract documents, submission of subcontractor lists and schedules, designation of contract personnel, procedures for field decisions and change orders, scheduling discussions, and premises usage guidelines, with meeting minutes to be distributed within seven working days.

Progress meetings shall be scheduled throughout the construction period on an as-needed basis, presided over by the owner's resident project representative, with required attendance from the contractor's superintendent, major subcontractors and suppliers, owner, and owner's engineer. Progress meeting agendas shall address work progress reviews, field observations and problems, submittal status, off-site fabrication and delivery schedules, schedule maintenance, quality standards, and the effects of proposed changes on project coordination and timelines. The contractor bears responsibility for locating and protecting survey control points, establishing field engineering controls based on the design engineer's established datum, and constructing work according to verified elevations, lines, and locations utilizing recognized survey control practices. Meeting minutes from progress meetings must be distributed within five working days to all participants, ensuring comprehensive documentation and communication throughout the project lifecycle.

View the file

Other files

File Type Posted
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
5-Doc 00 91 13 - ADDENDA.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
32-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
26-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
30-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
43-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
58-ADA Curb Ramp Intersections 2026.pdf PDF
35-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
31-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
48-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

1.02 RELATED SECTIONS

A. This section not used.

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial

Completion and for portions of Work designated for Owner’s occupancy.

C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.04 FIELD ENGINEERING

A. Contractor is responsible to locate survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points.

B. Control datum for survey is that established by Design Engineer providing survey.

C. Verify set-backs and easements; confirm drawing dimensions and elevations.

D. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

E. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.

1.05 PRECONSTRUCTION MEETING

A. Owner’s Engineer will schedule a meeting at the Project site after the Effective Date of the

Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Owner’s Engineer, Owner’s Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors, Contractor’s Design Engineer, Contractor’s Third-Party Inspection representative.

COORDINATION AND MEETINGS

01 31 00-2

C. Agenda:

1. Distribution of Contract Documents.

2. Submission of list of subcontractors, list of products, submittals, and progress schedule.

3. Designation of personnel representing the parties in Contract and the OWNER’S

ENGINEER.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

5. Scheduling.

6. Use of premises by OWNER and CONTRACTOR.

D. Owner’s Engineer shall record minutes and distribute copies within seven (7) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Owner’s Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings as necessary.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, and Owner’s Engineer, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Owner’s Resident Project Representative shall record minutes and distribute copies within five

(5) working days after meeting to Owner, Owner’s Engineer and all other participants.

PART 2 - PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 Not Used

END OF SECTION