41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf

PDF 121 KB Posted

Attached to
2026 Bristol Borough CDBG Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

About this file

This is a technical specification document for polymer modified asphalt joint and crack sealing work, prepared in accordance with PennDOT standards and applicable to the Bristol Borough 2026 CDBG Curb Ramp Program in Pennsylvania. The specification covers the cleaning and sealing of pavement surface joints associated with the removal and replacement of concrete curb and curb ramps. The work requires the use of PG 64-22 asphalt cement meeting PennDOT Bulletin 25 requirements, combined with reclaimed granulated rubber at a ratio of two pounds of RGR per gallon of asphalt cement. The mixture must be prepared in an oil-jacketed double wall kettle with indirect heating, maintained at 350°F to 380°F for thirty minutes, with surface temperatures not exceeding 400°F. The specification establishes detailed quality control and certification requirements, including testing and verification of materials, vendor bills of lading documentation, and producer certification signed by responsible company officials. All materials must comply with PennDOT Publication 408 and Borough Standards, with testing results submitted to the Materials Testing Division for verification prior to project use.

The application procedures require joints and adjacent pavement surfaces to be thoroughly cleaned, dried, and free of loose material and debris, with air blasting at minimum 100 psi or hot compressed air lance treatment immediately prior to sealing. Polymer modified asphalt sealing must be applied level with the pavement surface using a wand followed by a standard V-shaped squeegee, with no more than 1/8 inch buildup. Work cannot be performed when air temperatures fall below 40°F or exceed 90°F unless the hot compressed air lance sufficiently warms cracks to ensure proper adhesion. No bituminous overlay may be placed within seventy-two hours of sealing unless authorized by the Engineer. The specification addresses joints ranging from 1/8 inch to one inch in width and requires cleaning of pavement surfaces four to six inches on either side of the joint to ensure proper sealing and adhesion.

View the file

Other files

File Type Posted
5-Doc 00 91 13 - ADDENDA.pdf PDF
47-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
6-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
34-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
21-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
12-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
31-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
15-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
33-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
19-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
28-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
55-Doc 00 73 00 - 08 APPENDIX C Part 1 Contract Language Requirements.pdf PDF
44-Sec 02 41 16 - DEMOLITION.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
43-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
49-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
1-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
7-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
56-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
42-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
32-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
37-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
8-Doc 00 41 00 - BID FORM - EBID.pdf PDF
58-ADA Curb Ramp Intersections 2026.pdf PDF
35-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
30-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
26-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
48-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
9-Doc 00 43 13 - BID BOND.pdf PDF
17-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
57-Doc 00 73 00 - 09 Part 2 Federal Labor Standard Provisions.pdf PDF
25-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
4-Doc 00 73 00 4 - Appendix B - Public Works Employment Verification Form.pdf PDF
13-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
53-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
3-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
20-Doc 00 52 00 - AGREEMENT.pdf PDF
23-Doc 00 01 10-TOC.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
54-Doc 00 73 00 11- CDBG AND STATE REQUIREMENTS.pdf PDF
Show 40 more

Latest 50 of 122 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

POLYMER MODIFIED ASPHALT JOINT AND CRACK SEALING

32 01 17.61-1

SECTION 32 01 17.61

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Asphaltic Joint and Crack Sealing

1.02 DESCRIPTION OF WORK

A. This work is the cleaning and sealing of pavement surface joints associated with the removal and replacement of concrete curb and curb ramps with polymer modified asphalt.

PART 2 PRODUCTS

2.01 ASPHALT CEMENT PG 64-22

A. Obtain material meeting the requirements of PennDOT Bulletin 25 from a producer listed in Bulletin 15.

1. Quality Control Section 01 40 00

2. Certification

a. General

1) When a bituminous material tank is filled, submit a copy of the required test results to the MTD for verification of compliance with Department specifications.

2) Specify the type of material, tank number, and company lot number of the certificate for cross-reference to the bill of lading.

3) Have a responsible company official sign the certificate.

4) Obtain a verification sample from each batch. A batch is a tank completely filled, partially filled, or refilled with a blend of residual and new material.

5) Test one-half (1/2) sample and forward the results to the MTD. Forward the remaining one-half (1/2) sample to the MTD for testing. The MTD will evaluate quality control on the basis of three (3) consecutive verification samples.

b. Levels of Certification

1) Use the same levels of certification as specified in PennDOT Publication 408, Section 701.1(b)2, except substitute the word “batch” for the word “silo.”

c. Handling and Transportation, Section 01 60 00

1) Furnish the vendor’s bill of lading for each shipment (one copy retained by the vendor and one copy included with the shipment to the project). Use a form acceptable to the MTD, containing the following information:

a) Statement that material has been testing and meets Department specifications.

b) Class of Material

c) Tank Number

d) Company Batch Number

e) Date of Shipment

f) Producer’s Name and Location

g) Name and Location of Consignee, (Bituminous Concrete Plant or

Maintenance District)

32 01 17.61-2

h) Mix or Application Temperatures, Minimum and Maximum

i) Viscosity at 140F

j) Penetration at 77F

k) Trailer Number

l) Specific Gravity of Asphalt Cement at 77F

m) Statement that the material is compatible with job aggregate E-4, E-5, E-10, E-11, E-12, MC-400, and MC-800

n) Percent Bitumen Residue by Weight (for liquid bituminous materials only)

o) Quality of Material

p) Statement that the shipment container was determined to be reasonably free of contamination immediately prior to loading

PART 3 EXECUTION

3.01 GENERAL

A. Provide a mixture of asphalt cement and reclaimed granulated rubber, combined to the specified proportions, or furnish a premixed composition as specified in Section 469.2(c) or (d).

3.02 MIXING PROCEDURES

A. Combine the PG 64-22 and reclaimed granulated rubber to obtain a mixture having proportions of two (2 lbs) pounds of RGR per gallon of asphalt cement. Blend the PG 64-22 and reclaimed granulated rubber in an oil-jacketed double wall kettle (indirect hating) equipped with agitator and two (2") inch hot asphalt pump. Provide separate thermometers for oil bath. Heat and agitate the mixture with the temperature range of 350F - 380F for thirty

(30) minutes. Do not allow the operating temperature in the kettle to exceed 400F.

B. For premixed material, as specified in Section 469.2(c) or (d), obtain the safe heating temperature range and recommended pouring temperature from the manufacturer’s shipping container. Place the material within this temperature range, and as close as possible to the recommended pouring temperature. Maintain a safe heating temperature. Do not maintain any single batch of material at the pouring temperature for more than four (4) hours. Reheat only in accordance with manufacturer’s recommendations.

3.03 SURFACE PREPARATION

A. Apply sealer only after joints and adjacent pavement surfaces are clean, dry, and free of any loose material and debris. Clean the pavement for four (4") to six (6") inches on either side of the joint. Air blast joints immediately prior to sealing. Use a compressed air stream of at least 100 psi measured at the source, or use a hot compressed air lance for cleaning and drying damp cracks in the bituminous pavements. Care should be taken to ensure that damage to the surrounding pavement area from overheating does not occur. Seal joints (1/8) to one (1") inch wide with polymer modified asphalt.

3.04 SEALING

A. Apply polymer modified asphalt to prepared joints, level with the pavement surface, using a wand followed by a standard “V” shaped asphalt squeegee. Leave no more than 1/8 inch buildup. Do not place sealer when the air temperature is below 40F or above 90F, unless otherwise permitted by the Engineer if the hot compressed air lance used can sufficiently warm the crack to ensure adhesion between the pavement and the sealer. Do not place bituminous overlay within seventy-two (72) hours of sealing unless permitted by Engineer.

END OF SECTION