This is a Quality Control specification document for the 2026 Bristol Borough CDBG Curb Ramp Program, a comprehensive infrastructure improvement project in Bristol Borough, Pennsylvania, focused on designing and constructing ADA/PennDOT compliant curb ramps. The specification establishes mandatory quality assurance and control procedures covering installation monitoring, tolerance management, reference standards compliance, mock-up testing, testing laboratory services, observation services, and manufacturers' field services. The contractor must comply with manufacturers' instructions and specified standards while maintaining strict tolerance control during fabrication and installation. All work must be performed by qualified personnel, and contractors are required to furnish duplicate certified copies of mill, shop, and factory tests to the Owner's Engineer. Daily construction observation reports including photographs, material testing reports, and quantities must be submitted throughout all phases of construction, including demolition, grading, formwork, concrete placement, and final restoration. The contractor bears full responsibility for all testing and laboratory services costs as specified in individual specification sections.

The Quality Control section establishes that testing and observation services do not relieve the contractor of responsibility for performing work to contract requirements, and any retesting required due to non-conformance must be performed by the same independent testing firm under Owner's Engineer direction. Substrate examination and preparation are mandatory before applying new materials, including cleaning, sealing cracks, and applying manufacturer-required primers or conditioners. The specification requires that contractors verify existing site conditions and substrate capabilities, confirm utility service availability and characteristics, and comply with all reference standards current as of the bid date. Mock-ups, when accepted by the Owner's Engineer and specified for removal, must be cleared from the site when directed. The document references related sections including General Conditions, Supplementary Conditions, Submittals, Material and Equipment requirements, and other technical specifications to ensure comprehensive project compliance with federal CDBG funding requirements and local standards.

View the file

Other files

File Type Posted
55-Doc 00 73 00 - 08 APPENDIX C Part 1 Contract Language Requirements.pdf PDF
37-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
49-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
33-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
7-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
19-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
9-Doc 00 43 13 - BID BOND.pdf PDF
42-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
28-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
44-Sec 02 41 16 - DEMOLITION.pdf PDF
1-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
56-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
5-Doc 00 91 13 - ADDENDA.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
10-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
12-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
22-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
26-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
3-Doc 00 43 13 - BID BOND.pdf PDF
32-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
4-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
46-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
53-Sec 02 41 16 - DEMOLITION.pdf PDF
58-Location Map.pdf PDF
6-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
61-Addendum 1.pdf PDF
62-Addendum 1 Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION (REV).pdf PDF
7-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
8-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY CONTROL

01 40 00-1

SECTION 01 40 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Quality assurance - control of installation.

2. Tolerances.

3. References and standards.

4. Mock-up.

5. Testing laboratory services.

6. Observation services.

7. Manufacturers' field services.

8. Examination.

9. Preparation.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 72 00: General Conditions: References to Standards and Specifications of Technical Societies; Reporting and Resolving Discrepancies.

2. Document 00 73 00: Supplementary Conditions: Duties, Responsibilities and Limitation of Authority of the Resident Project Representative.

3. Section 01 33 00: Submittals: Submission of manufacturer’s instructions and certificates.

4. Section 01 42 13: Organization and Reference Acronyms

5. Section 01 60 00: Material and Equipment: Requirements for material and product quality.

1.03 QUALITY ASSURANCE-CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply fully with manufacturers' instructions, including each step-in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Owner’s Engineer before proceeding.

D. Comply with specified standards as minimum quality for the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion or disfigurement.

1.04 TOLERANCES

A. Monitor fabrication and installation tolerance control of Products to produce acceptable Work.

Do not permit tolerances to accumulate.

01 40 00-2

B. Comply with manufacturers’ tolerances. Should manufacturers’ tolerances conflict with Contract Documents, request clarification from Engineer before proceeding.

C. Adjust Products to appropriate dimensions; position before securing Products in place.

1.05 REFERENCES AND STANDARDS

A. For Products or workmanship specified by association, trade or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date for receiving bids, except where a specific date is established by code.

C. Obtain copies of standards where required by Product specification sections.

D. Should specified reference standard conflict with Contract Documents, request clarification from Owner’s Engineer before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Owner’s Engineer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.06 MOCK-UP

A. Tests will be performed under provisions identified in this section and identified in the respective Product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Owner’s Engineer and is specified in Product specification sections to be removed; remove mock-up and clear area when directed to do so.

1.07 TESTING LABORATORY SERVICES

A. Contractor shall furnish to Owner’s Engineer duplicate certified copies of all routine tests made by the mill, shop or factory at which material or equipment is fabricated or manufactured for the Work when so specified in individual specification sections.

B. An independent firm will perform tests and other services.

C. Testing and source quality control may occur on or off the Project site. Perform off-site testing as required by Owner’s Engineer.

D. Reports will be submitted by the independent firm to Owner’s Engineer, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access and assistance by incidental labor as requested.

1. Notify Owner’s Engineer and independent firm 24 hours prior to expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

F. Testing does not relieve Contractor to perform Work to contract requirements.

G. Retesting required because of non-conformance to specified requirements shall be performed

01 40 00-3 by the same independent firm on instructions by Owner’s Engineer.

H. Contractor shall pay for all testing and laboratory services and/or test reports as are required in individual specification sections.

1.08 OBSERVATION SERVICES

A. The Contractor shall employ and pay for observation services during construction of the Project.

B. Construction observation shall be provided for all aspects of the construction phase including but not limited to demolition, grading and formwork, subbase placement, concrete placement, concrete finishing, and final restoration.

C. Construction observation reports shall be submitted to the Owner’s Engineer on a daily basis and shall include photos, material testing reports, and quantities.

D. Observation does not relieve Contractor to perform Work to contract requirements.

1.09 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers’ written instructions.

C. Refer to Section 01 33 00 - Submittals, Manufacturers’ field reports article.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work.

Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct locations.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

END OF SECTION