About this file
This is a Narrative Construction Schedule specification document for the 2026 Bristol Borough CDBG Curb Ramp Program in Pennsylvania, outlining contractual requirements for schedule preparation and project management. The contractor must prepare, maintain, and revise a detailed construction project schedule based on the anticipated Notice to Proceed date, with an initial schedule submitted prior to construction commencement that identifies the design phase start date and construction phase sequencing for each intersection. The schedule must include minimum required elements: activity descriptions and locations, duration in working days, and start/finish calendar dates for all activities. Additionally, the contractor shall submit a workday calendar specifying work days, non-work days, shift quantities per day, and hours per shift, with sufficient activity detail to demonstrate necessary interdependencies. The Owner's Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt, and the contractor may be required to attend a scheduling meeting if the schedule is not received prior to construction start.
Progress payments may be withheld by the Owner until an acceptable schedule is submitted and approved. The construction schedule specification requires the contractor to provide a narrative description of the schedule incorporating all submitted information and demonstrating project sequencing logic. Failure to submit the schedule prior to construction initiation may delay payment release and require mandatory scheduling meetings with the Owner. This specification is cross-referenced with Section 01 31 00 regarding coordination and meetings, indicating that schedule management is integrated into broader project coordination requirements under the CDBG-funded curb ramp improvement project.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NARRATIVE CONSTRUCTION SCHEDULE
01 32 16-1
SECTION 01 32 16
NARRATIVE CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work Of This Section Includes:
1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 31 00 - Coordination and Meetings
PART 2 – PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CONSTRUCTION SCHEDULE
A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date for the design phase and construction phase. The schedule for the construction phase shall identify the order of completing each intersection. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.
B. Owner’s Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:
Activity description & location;
Duration of activity, in working days; and Start and finish calendar dates of activities.
D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.
E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.
F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.
END OF SECTION