36-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf

PDF 89 KB Posted

Attached to
2026 Bristol Borough CDBG Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

About this file

This is a Narrative Construction Schedule specification document for the 2026 Bristol Borough CDBG Curb Ramp Program in Pennsylvania, outlining contractual requirements for schedule preparation and project management. The contractor must prepare, maintain, and revise a detailed construction project schedule based on the anticipated Notice to Proceed date, with an initial schedule submitted prior to construction commencement that identifies the design phase start date and construction phase sequencing for each intersection. The schedule must include minimum required elements: activity descriptions and locations, duration in working days, and start/finish calendar dates for all activities. Additionally, the contractor shall submit a workday calendar specifying work days, non-work days, shift quantities per day, and hours per shift, with sufficient activity detail to demonstrate necessary interdependencies. The Owner's Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt, and the contractor may be required to attend a scheduling meeting if the schedule is not received prior to construction start.

Progress payments may be withheld by the Owner until an acceptable schedule is submitted and approved. The construction schedule specification requires the contractor to provide a narrative description of the schedule incorporating all submitted information and demonstrating project sequencing logic. Failure to submit the schedule prior to construction initiation may delay payment release and require mandatory scheduling meetings with the Owner. This specification is cross-referenced with Section 01 31 00 regarding coordination and meetings, indicating that schedule management is integrated into broader project coordination requirements under the CDBG-funded curb ramp improvement project.

View the file

Other files

File Type Posted
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
5-Doc 00 91 13 - ADDENDA.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
32-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
34-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
26-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
30-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
43-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
58-ADA Curb Ramp Intersections 2026.pdf PDF
35-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
31-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NARRATIVE CONSTRUCTION SCHEDULE

01 32 16-1

SECTION 01 32 16

NARRATIVE CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work Of This Section Includes:

1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 31 00 - Coordination and Meetings

PART 2 – PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 CONSTRUCTION SCHEDULE

A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date for the design phase and construction phase. The schedule for the construction phase shall identify the order of completing each intersection. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.

B. Owner’s Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:

Activity description & location;

Duration of activity, in working days; and Start and finish calendar dates of activities.

D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.

E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.

F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.

END OF SECTION