37-Sec 01 11 13 - SUMMARY OF WORK.pdf
PDF 105 KB Posted
- Attached to
- 2026 Bristol Borough CDBG Curb Ramp Program
- Solicitation number
- Not on record
- Issued by
- Bucks County, Brodheadsville CDP, Pennsylvania
About this file
This Summary of Work document outlines the scope for the 2026 Bristol Borough CDBG Curb Ramp Program in Bucks County, Pennsylvania, a design-build project requiring the construction and reconstruction of ADA/PennDOT compliant curb ramps and associated sidewalk improvements within the public right-of-way. The contractor must retain a licensed Pennsylvania Professional Engineer to conduct topographic field surveys of all intersections, design ADA/PennDOT compliant curb ramps, and provide survey layout documentation for Owner approval prior to construction. Work includes removal of existing curbs, sidewalks, and curb ramps; placement and compaction of stone base; construction of depressed curbs, vertical curbs, sidewalks, and truncated domes; replacement of removed curbing and sidewalk; concrete finishing; restoration of roadway, grading, and seeding; utility elevation adjustments; and signage relocation. The contractor must maintain continuous accessible pedestrian routes throughout construction and engage a third-party testing and inspection company to provide construction oversight, daily field reports with photographs, material testing documentation, and final certification of compliance. The contractor is responsible for all coordination with utility companies, notification of property owners at least 24 hours before work begins, adherence to OSHA Construction Workplace Safety Standards, and protection of existing utilities in accordance with Pennsylvania Act 287. The work sequence includes field survey, design review, curb ramp construction, as-built plan preparation, final inspection, and project closeout, with the Owner occupying the site during the entire construction period.
The contractor must submit a complete construction schedule prior to beginning work. The Owner will supply no products, and no concurrent work by the Owner or other parties is anticipated during construction. All work must be performed within rights-of-way limits, with the contractor responsible for restoring work areas to at least original conditions and bearing all costs for damage to property outside specified construction limits. Payment shall be withheld until the contractor provides all required information and documentation, including third-party inspection certifications, materials testing results, and as-built plans, which must be accepted by the Owner or Owner's Engineer. The document references compliance with PennDOT Publication 408, current PennDOT standards, municipal requirements, and PROWAG guidelines, though the specific number of intersections, project schedule dates, and financial terms are not detailed in this section.
View the file
Other files
Show 40 more
Latest 50 of 122 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK
01 11 13-1
SECTION 01 11 13
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Description of Work.
2. Work by OWNER.
3. Work by other parties.
4. OWNER supplied Products.
5. CONTRACTOR use of site and premises.
6. Future work.
7. Work sequence of construction.
8. OWNER occupancy.
1.02 DESCRIPTION OF WORK
A. DESIGN/BUILD CURB RAMPS – ALL INTERSECTIONS
The Work includes the construction and/or reconstruction of curb ramps and associated sidewalk improvements within the public right-of-way, in accordance with applicable ADA requirements and as modified by reference to current PennDOT standards, municipal requirements, and PROWAG (or equivalent) guidelines.
The Work to be done under this contract associated with the project consists of the design, construction and third-party observation of Americans with Disabilities Act (ADA) / PennDOT compliant curb ramps. The Contractor shall be responsible for obtaining a Professional Engineer, licensed in the State of Pennsylvania, to conduct topographic field survey of all intersections, design ADA/PennDOT compliant curb ramps per, and provide survey layout for curb ramps. All plans shall be provided to the Owner/Owner’s Engineer for review and approval prior to construction.
Upon approval of the designs, the Contractor shall remove all existing curbs, sidewalks, and/or curb ramps and place and compact the stone base for all curb ramps. The contractor shall maintain continuous accessible pedestrian routes that comply with ADA requirements throughout construction, including the provision of safe, clearly delineated temporary pathways, curb ramps, and appropriate staging measures to ensure uninterrupted access for all users. The Contractor shall provide ADA/PennDOT compliant curb ramps, including, depressed curb, vertical curb, sidewalk, and ADA/PennDOT compliant truncated domes, in accordance with the approved designs. The Contractor is also to replace any curb and sidewalk that are removed to facilitate the construction of compliant curb ramps in accordance with the contract requirements at no additional cost. The Contractor will remove all forms and finish all concrete surfaces. The Contractor will complete restoration of existing features, including roadway restoration, grading and seeding, incidental to items described in the measurement and payment Section 01 22 00. The Contractor will adjust utility elevations to finish grade, as necessary to facilitate the above work in accordance with ADA/PennDOT grading requirements, and coordinate with the appropriate utility company to accomplish this task. The Contractor will also relocate signage as required to facilitate the above work.
01 11 13-2
During construction, the Contractor shall also be responsible for obtaining a third-party testing and inspection company to provide construction oversight services. The inspection company shall observe the demolition and installation of curb ramps to ensure compliance with the design and Borough Standards. The inspection company shall provide daily field reports, with photos, noting all construction activities, provide material mix design and submittals and compaction testing, and at the end of construction certify that work has been completed in accordance with all design requirements. Payments shall be withheld until all information/documentation is provided and accepted by the Owner / Owner’s Engineer.
1.03 WORK BY OWNER
A. No other work is being planned by Owner at the site during construction of the Work under this contract.
1.04 WORK BY OTHER PARTIES
A. No other work by other parties is anticipated in the immediate vicinity during construction of the Work under this contract.
1.05 OWNER SUPPLIED PRODUCTS
A. No products are to be supplied and paid for by OWNER.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. The Work under this contract must be accomplished while the existing roadway and vicinity are utilized by pedestrians and vehicles.
B. Contractor shall confine his operations so that all work is performed within the limits of rights-of-way areas. Written permission is obtained to occupy additional ground. Upon completion of work, the Contractor shall clean-up and restore the area of his operations to a condition at least equal to original conditions. Damage to property outside of specified construction limits shall be the responsibility of the Contractor and restoration of same shall be made at the Contractor’s expense.
C. CONTRACTOR shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, CONTRACTOR shall determine the location of each facility which is questionable. The location of utilities shown on the Drawings represents the best information available;
however, it is the responsibility of CONTRACTOR to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (December 10, 1974) as amended by Act 181 (March 29, 2007) and as may have been further amended.
D. CONTRACTOR will be responsible to notify all property owners and residents at least twenty-four (24) hours prior to the start of construction on or near their properties.
E. CONTRACTOR shall conduct all Work in strict compliance with OSHA Construction
Workplace Safety Standards.
1.07 FUTURE WORK
A. No future work is proposed as part of this contract.
1.08 WORK SEQUENCE OF CONSTRUCTION
01 11 13-3
A. The contractor shall submit a complete construction schedule prior to the start of any construction. The schedule shall include the time required for design and review of the curb ramps.
B. A sample schedule is as follows:
a. Notice to Proceed.
b. Conduct field survey.
c. Construction of curb ramps.
d. Preparation of As-built Plans
e. Owner’s final inspection of work.
f. Project closeout.
1.09 OWNER OCCUPANCY
A. OWNER will occupy the site and premises during the entire period of construction for the conduct of normal operations.
B. Cooperate with OWNER to minimize conflict and to facilitate OWNER's operations.
C. Schedule the Work to accommodate OWNER occupancy.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION