37-Sec 01 11 13 - SUMMARY OF WORK.pdf

PDF 105 KB Posted

Attached to
2026 Bristol Borough CDBG Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

About this file

This Summary of Work document outlines the scope for the 2026 Bristol Borough CDBG Curb Ramp Program in Bucks County, Pennsylvania, a design-build project requiring the construction and reconstruction of ADA/PennDOT compliant curb ramps and associated sidewalk improvements within the public right-of-way. The contractor must retain a licensed Pennsylvania Professional Engineer to conduct topographic field surveys of all intersections, design ADA/PennDOT compliant curb ramps, and provide survey layout documentation for Owner approval prior to construction. Work includes removal of existing curbs, sidewalks, and curb ramps; placement and compaction of stone base; construction of depressed curbs, vertical curbs, sidewalks, and truncated domes; replacement of removed curbing and sidewalk; concrete finishing; restoration of roadway, grading, and seeding; utility elevation adjustments; and signage relocation. The contractor must maintain continuous accessible pedestrian routes throughout construction and engage a third-party testing and inspection company to provide construction oversight, daily field reports with photographs, material testing documentation, and final certification of compliance. The contractor is responsible for all coordination with utility companies, notification of property owners at least 24 hours before work begins, adherence to OSHA Construction Workplace Safety Standards, and protection of existing utilities in accordance with Pennsylvania Act 287. The work sequence includes field survey, design review, curb ramp construction, as-built plan preparation, final inspection, and project closeout, with the Owner occupying the site during the entire construction period.

The contractor must submit a complete construction schedule prior to beginning work. The Owner will supply no products, and no concurrent work by the Owner or other parties is anticipated during construction. All work must be performed within rights-of-way limits, with the contractor responsible for restoring work areas to at least original conditions and bearing all costs for damage to property outside specified construction limits. Payment shall be withheld until the contractor provides all required information and documentation, including third-party inspection certifications, materials testing results, and as-built plans, which must be accepted by the Owner or Owner's Engineer. The document references compliance with PennDOT Publication 408, current PennDOT standards, municipal requirements, and PROWAG guidelines, though the specific number of intersections, project schedule dates, and financial terms are not detailed in this section.

View the file

Other files

File Type Posted
5-Doc 00 91 13 - ADDENDA.pdf PDF
47-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
6-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
34-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
21-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
12-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
31-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
15-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
33-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
19-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
28-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
55-Doc 00 73 00 - 08 APPENDIX C Part 1 Contract Language Requirements.pdf PDF
44-Sec 02 41 16 - DEMOLITION.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
43-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
49-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
1-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
7-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
56-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
42-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
32-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
8-Doc 00 41 00 - BID FORM - EBID.pdf PDF
58-ADA Curb Ramp Intersections 2026.pdf PDF
35-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
30-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
26-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
48-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
9-Doc 00 43 13 - BID BOND.pdf PDF
17-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
57-Doc 00 73 00 - 09 Part 2 Federal Labor Standard Provisions.pdf PDF
25-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
4-Doc 00 73 00 4 - Appendix B - Public Works Employment Verification Form.pdf PDF
13-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
53-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
3-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
20-Doc 00 52 00 - AGREEMENT.pdf PDF
23-Doc 00 01 10-TOC.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
54-Doc 00 73 00 11- CDBG AND STATE REQUIREMENTS.pdf PDF
Show 40 more

Latest 50 of 122 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF WORK

01 11 13-1

SECTION 01 11 13

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Description of Work.

2. Work by OWNER.

3. Work by other parties.

4. OWNER supplied Products.

5. CONTRACTOR use of site and premises.

6. Future work.

7. Work sequence of construction.

8. OWNER occupancy.

1.02 DESCRIPTION OF WORK

A. DESIGN/BUILD CURB RAMPS – ALL INTERSECTIONS

The Work includes the construction and/or reconstruction of curb ramps and associated sidewalk improvements within the public right-of-way, in accordance with applicable ADA requirements and as modified by reference to current PennDOT standards, municipal requirements, and PROWAG (or equivalent) guidelines.

The Work to be done under this contract associated with the project consists of the design, construction and third-party observation of Americans with Disabilities Act (ADA) / PennDOT compliant curb ramps. The Contractor shall be responsible for obtaining a Professional Engineer, licensed in the State of Pennsylvania, to conduct topographic field survey of all intersections, design ADA/PennDOT compliant curb ramps per, and provide survey layout for curb ramps. All plans shall be provided to the Owner/Owner’s Engineer for review and approval prior to construction.

Upon approval of the designs, the Contractor shall remove all existing curbs, sidewalks, and/or curb ramps and place and compact the stone base for all curb ramps. The contractor shall maintain continuous accessible pedestrian routes that comply with ADA requirements throughout construction, including the provision of safe, clearly delineated temporary pathways, curb ramps, and appropriate staging measures to ensure uninterrupted access for all users. The Contractor shall provide ADA/PennDOT compliant curb ramps, including, depressed curb, vertical curb, sidewalk, and ADA/PennDOT compliant truncated domes, in accordance with the approved designs. The Contractor is also to replace any curb and sidewalk that are removed to facilitate the construction of compliant curb ramps in accordance with the contract requirements at no additional cost. The Contractor will remove all forms and finish all concrete surfaces. The Contractor will complete restoration of existing features, including roadway restoration, grading and seeding, incidental to items described in the measurement and payment Section 01 22 00. The Contractor will adjust utility elevations to finish grade, as necessary to facilitate the above work in accordance with ADA/PennDOT grading requirements, and coordinate with the appropriate utility company to accomplish this task. The Contractor will also relocate signage as required to facilitate the above work.

01 11 13-2

During construction, the Contractor shall also be responsible for obtaining a third-party testing and inspection company to provide construction oversight services. The inspection company shall observe the demolition and installation of curb ramps to ensure compliance with the design and Borough Standards. The inspection company shall provide daily field reports, with photos, noting all construction activities, provide material mix design and submittals and compaction testing, and at the end of construction certify that work has been completed in accordance with all design requirements. Payments shall be withheld until all information/documentation is provided and accepted by the Owner / Owner’s Engineer.

1.03 WORK BY OWNER

A. No other work is being planned by Owner at the site during construction of the Work under this contract.

1.04 WORK BY OTHER PARTIES

A. No other work by other parties is anticipated in the immediate vicinity during construction of the Work under this contract.

1.05 OWNER SUPPLIED PRODUCTS

A. No products are to be supplied and paid for by OWNER.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. The Work under this contract must be accomplished while the existing roadway and vicinity are utilized by pedestrians and vehicles.

B. Contractor shall confine his operations so that all work is performed within the limits of rights-of-way areas. Written permission is obtained to occupy additional ground. Upon completion of work, the Contractor shall clean-up and restore the area of his operations to a condition at least equal to original conditions. Damage to property outside of specified construction limits shall be the responsibility of the Contractor and restoration of same shall be made at the Contractor’s expense.

C. CONTRACTOR shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, CONTRACTOR shall determine the location of each facility which is questionable. The location of utilities shown on the Drawings represents the best information available;

however, it is the responsibility of CONTRACTOR to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (December 10, 1974) as amended by Act 181 (March 29, 2007) and as may have been further amended.

D. CONTRACTOR will be responsible to notify all property owners and residents at least twenty-four (24) hours prior to the start of construction on or near their properties.

E. CONTRACTOR shall conduct all Work in strict compliance with OSHA Construction

Workplace Safety Standards.

1.07 FUTURE WORK

A. No future work is proposed as part of this contract.

1.08 WORK SEQUENCE OF CONSTRUCTION

01 11 13-3

A. The contractor shall submit a complete construction schedule prior to the start of any construction. The schedule shall include the time required for design and review of the curb ramps.

B. A sample schedule is as follows:

a. Notice to Proceed.

b. Conduct field survey.

c. Construction of curb ramps.

d. Preparation of As-built Plans

e. Owner’s final inspection of work.

f. Project closeout.

1.09 OWNER OCCUPANCY

A. OWNER will occupy the site and premises during the entire period of construction for the conduct of normal operations.

B. Cooperate with OWNER to minimize conflict and to facilitate OWNER's operations.

C. Schedule the Work to accommodate OWNER occupancy.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION