Concrete Reinforcement Specification for Bristol Borough CDBG Curb Ramp Program

This is a technical specification document for concrete reinforcement materials and installation procedures for the 2026 Bristol Borough CDBG Curb Ramp Program in Bucks County, Pennsylvania. The specification establishes requirements for reinforcing steel bars, wire fabric, and accessories used in cast-in-place concrete work as part of the borough's ADA/PennDOT compliant curb ramp infrastructure project. The specification mandates the use of ASTM A615 deformed billet steel bars with 60 ksi yield grade in unfinished condition and ASTM A185 welded steel wire fabric in flat sheets for reinforcement. All reinforcing steel accessories, including tie wire, chairs, bolsters, and bar supports, must meet specified standards with plastic-coated steel types required for weather-exposed concrete surfaces. Fabrication must comply with the Concrete Reinforcing Steel Institute (CRSI) Manual of Practice, and reinforcement placement, support, and security must strictly conform to design specifications without deviation from required positions, including adherence to ACI 318 code requirements for concrete cover.

Quality assurance requirements mandate that all work be performed in accordance with CRSI standards 63 and 65, ACI 301 and ACI 318 building codes, and that design be conducted under the direct supervision of a Professional Structural Engineer licensed in Pennsylvania. Contractors must provide the engineer with access to fabrication plants for inspection purposes and submit notification of shop fabrication schedules. Welders employed on the project must submit AWS qualification certificates dated within the previous 12 months. Documentation requirements include maintaining copies of applicable standards and codes on site and submitting all required certifications and inspection notifications in advance of construction activities.

View the file

Other files

File Type Posted
5-Doc 00 91 13 - ADDENDA.pdf PDF
47-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
6-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
34-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
21-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
12-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
31-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
15-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
33-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
19-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
28-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
55-Doc 00 73 00 - 08 APPENDIX C Part 1 Contract Language Requirements.pdf PDF
44-Sec 02 41 16 - DEMOLITION.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
43-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
49-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
1-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
7-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
56-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
42-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
32-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
37-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
8-Doc 00 41 00 - BID FORM - EBID.pdf PDF
58-ADA Curb Ramp Intersections 2026.pdf PDF
35-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
30-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
26-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
48-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
9-Doc 00 43 13 - BID BOND.pdf PDF
17-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
57-Doc 00 73 00 - 09 Part 2 Federal Labor Standard Provisions.pdf PDF
25-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
4-Doc 00 73 00 4 - Appendix B - Public Works Employment Verification Form.pdf PDF
13-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
3-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
20-Doc 00 52 00 - AGREEMENT.pdf PDF
23-Doc 00 01 10-TOC.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
54-Doc 00 73 00 11- CDBG AND STATE REQUIREMENTS.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONCRETE REINFORCEMENT

03 20 00-1

SECTION 03 20 00

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Reinforcing steel bars, wire fabric and accessories for cast-in-place concrete.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere.

1. This section not used.

1.03 REFERENCES

A. ACI 301 - Structural Concrete for Buildings.

B. ACI 318 - Building Code Requirements for Reinforced Concrete.

C. ASTM A185 - Welded Steel Wire Fabric for Concrete Reinforcement.

D. ASTM A615 - Deformed and Plain Billet Steel Bars for Concrete Reinforcement.

E. ASTM A775 - Epoxy-Coated Reinforcing Steel Bars.

F. ASTM D3963 - Epoxy-Coated Reinforcing Steel.

G. CRSI - Concrete Reinforcing Steel Institute - Manual of Practice.

H. CRSI 63 - Recommended Practice for Placing Reinforcing Bars.

I. CRSI 65 - Recommended Practice for Placing Bar Supports, Specifications and Nomenclature.

1.04 SUBMITTALS FOR REVIEW

A. Section 01 33 00 - Submittals: Procedures for submittals.

1.05 QUALITY ASSURANCE

A. Perform Work in accordance with CRSI 63, 65 and Manual of Practice, ACI 301, and ACI 318.

Maintain one copy of each document on site.

B. Provide Engineer with access to fabrication plant to facilitate inspection of reinforcement. Provide notification of commencement and duration of shop fabrication in sufficient time to allow inspection.

C. Design reinforcement under direct supervision of a Professional Structural Engineer experienced in design of this Work and licensed in the Commonwealth of Pennsylvania.

D. Welders: Certificates: Submit under provisions of Section 01 40 00 Manufacturer’s Certificates, certifying welders employed on the Work, verifying AWS qualification within the previous 12 months.

PART 2 PRODUCTS

2.01 REINFORCEMENT

A. Reinforcing Steel: ASTM A615, 60 ksi yield grade; deformed billet steel bars, unfinished.

B. Welded Steel Wire Fabric: ASTM A185 Plain Type in flat sheets, unfinished.

2.02 ACCESSORIES

A. Tie Wire: Minimum 16 gage annealed type, epoxy coated.

B. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for strength and support of reinforcement during concrete placement conditions.

C. Special Chairs, Bolsters, Bar Supports, Spacers Adjacent to Weather Exposed Concrete Surfaces:

Plastic coated steel type; size and shape as required.

2.03 FABRICATION

03 20 00-2

A. Fabricate concrete reinforcing in accordance with CRSI Manual of Practice.

B. Locate reinforcing splices not indicated on drawings, at point of minimum stress.

PART 3 EXECUTION

3.01 PLACEMENT

A. Place, support and secure reinforcement against displacement. Do not deviate from required position.

B. Do not displace or damage vapor barrier.

C. Accommodate placement of formed openings.

D. Conform to Act 318 code for concrete cover over reinforcement.

END OF SECTION