39-Sec 01 55 26 - TRAFFIC REGULATION.pdf

PDF 129 KB Posted

Attached to
2026 Bristol Borough CDBG Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

About this file

This is a Traffic Regulation specification document (Section 01 55 26) prepared by Bristol Borough, Pennsylvania for the 2026 CDBG Curb Ramp Program. The specification establishes the contractor's obligations for maintaining safe and efficient traffic movement during construction activities. The contractor must furnish, erect, and maintain traffic control devices including cones, drums, barricades, flashing danger signal lights, directional signs, and trained flagpersons as required by the Borough. Key requirements include developing a Traffic Control Plan compliant with the Borough's Road Opening Permit, providing advance notification to the local Police Department (minimum ten days prior), and notifying affected parties including the Fire Company, School District, Ambulance Service, and residents at least twenty-four hours before any roadway work. The specification mandates that at least one traffic lane remain open during non-working periods, with provisions for emergency vehicle passage at all times.

Additional execution requirements include controlling construction vehicle parking to prevent interference with public traffic and emergency access, designating approved haul routes in consultation with the Owner, installing and relocating traffic signs and signals as work progresses, and maintaining access to adjacent property driveways and entrances. The contractor must provide safe decking using steel plates or equivalent materials over open trenches during non-work periods with sufficient strength to support truck loads. Upon project completion, the contractor is responsible for removing all traffic control equipment and devices, repairing any damage caused by installation, and removing post settings to a depth of two feet. All traffic control signs, signals, cones, drums, flares, lights, and flagperson equipment must be approved by the authority having jurisdiction, whether PennDOT or the local municipality.

View the file

Other files

File Type Posted
50-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
5-Doc 00 91 13 - ADDENDA.pdf PDF
24-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
40-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
41-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
45-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
59-2026 BB CDBG Curb Ramp Program Concept Plans.pdf PDF
32-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
34-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
26-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
30-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
43-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
58-ADA Curb Ramp Intersections 2026.pdf PDF
35-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
31-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
48-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRAFFIC REGULATION

01 55 26-1

SECTION 01 55 26

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. This Section involves the Contractor’s obligations relative to maintaining the safe and efficient movement of traffic in the vicinity of construction.

B. Contractor will be required to furnish, erect, and maintain traffic cones, drums, barricades, flashing danger signal lights, directional signs and provide trained and equipped flagmen as required by the Borough to restrict the movement of traffic within the construction areas and to clearly indicate the restrictions well in advance to vehicular traffic.

1.02 SECTION INCLUDES

A. Traffic Control Plan.

B. Notification.

C. Construction parking controls.

D. Flag persons.

E. Flares and lights.

F. Haul routes.

G. Traffic signs and signals.

H. Other Requirements I. Removal.

1.03 RELATED SECTIONS

A. Section 01 11 13 - Summary of Work B. Section 01 31 00 - Coordination and Meetings: Coordination and Project conditions.

C. Section 01 50 00: Construction Facilities and Temporary Controls: Barriers, access roads and parking.

PART 2 - PRODUCTS

2.01 SIGNS, SIGNALS, AND DEVICES

A. Post Mounted and Wall Mounted Traffic Control and Informational Signs: As approved by the authority having jurisdiction.

B. Traffic Control Signals: As approved by the authority having jurisdiction.

C. Traffic Cones and Drums, Flares and Lights: As approved by the authority having jurisdiction.

D. Flagperson Equipment: As required by the authority having jurisdiction.

PART 3 - EXECUTION

3.01 TRAFFIC CONTROL PLAN

A. Contractor shall implement any Traffic Control Plan requirements imposed by the Road Opening Permit issued by the Borough.

3.02 NOTIFICATIONS

A. Contractor shall provide advance notification to any parties so noted in the local municipal

01 55 26-2

Road Opening Permit in accordance with the required time schedule. In any event, the local municipal Police Department shall be notified at least ten (10) days prior to the date Contractor desires to restrict traffic in or along any highways or roads.

B. The Contractor shall notify the following parties at least twenty-four (24) hours in advance of any work within the roadway:

1. Local Municipal Police

2. Local Fire Company

3. Local School District

4. Local Ambulance Service

5. All affected residents

C. Contractor shall obtain advance approval from the authority having jurisdiction

(PennDOT, local municipality) should it be necessary to restrict traffic in or along any highways or roads, including temporary closure of a road.

D. At least one lane must be open for traffic during non-working periods and Contractor must be prepared to allow passage of emergency vehicles at any time.

3.03 CONSTRUCTION PARKING CONTROLS

A. Control vehicular parking to prevent interference with public traffic and parking, access by emergency vehicles, and Owner's operations.

B. Monitor parking of construction personnel's vehicles. Maintain vehicular access to and through parking areas.

C. Prevent parking on or adjacent to access roads or in non- designated areas.

3.04 FLAG PERSONS

A. Provide trained and equipped flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes.

3.05 HAUL ROUTES

A. Consult with the Owner for routes to be used for haul routes and site access.

B. Confine construction traffic to designated routes.

3.06 TRAFFIC SIGNS AND SIGNALS

A. Install and operate traffic controls to direct and maintain orderly flow of traffic in areas under

Contractor’s control, and areas affected by Contractor’s operations.

B. Relocate as Work progresses, to maintain effective traffic control.

3.07 OTHER REQUIREMENTS

A. Maintain access at all times during non-working periods and to the maximum extent feasible during working periods to all driveways and entrances of adjacent properties. In this regard, use and maintenance of steel plates or other decking across the trench may be necessary to reduce to a minimum interference with access to the adjacent properties.

B. Provide safe decking over open trenches in or along highways or roads during non-work periods by the use and maintenance of steel plates or other decking, which shall have sufficient strength to safely support all traffic including truck loads.

01 55 26-3

3.08 REMOVAL

A. Remove equipment and devices when all work, including repaving, has been completed.

B. Repair damage caused by installation.

C. Remove post settings to a depth of 2 feet.

END OF SECTION