This document is a Drawings section (Section 52 00 00) from the Folsom Warehouse Bridge Crane Replacement federal contract specification, issued under Solicitation No. 140R2026R0017 by the American River Division as Amendment No. 0004. The section establishes the requirements and procedures for managing contract drawings, specifying that the Contractor will receive one set of full-size 22-by-34-inch drawings. When discrepancies, errors, or omissions are discovered on drawings, the Contractor must promptly inform the Contracting Officer (CO) for written determination; any adjustments made without CO approval are at the Contractor's own risk and expense. Written specifications govern over drawings in cases of conflict. Some specification drawings contain details not applicable to the work scope, which the Contractor must disregard, and reference drawings not included in the specifications are not considered necessary for performance.

The document categorizes eleven drawings into three types: General Drawings (1 sheet), Information Drawings (6 sheets), and Standard Drawings (13 sheets). Information Drawings depict existing or future features required for work performance but do not show work to be performed; where jobsite conditions differ from these drawings, the actual jobsite conditions prevail. General drawings include the Site Map and Contractor Use Areas. Information drawings address warehouse plans, elevations, foundations, roof details, electrical installations, and crane modifications. Standard drawings cover electrical grounding details, control and instrument switches, nameplates, transmission line fencing, switchyard identification and safety signs, equipment symbols and designations, and electrical equipment support specifications. All listed drawings are incorporated into Section C (Description/Specifications) of the contract and are made binding contract documents.

View the file

Other files

File Type Posted
Attachment_4_-_Wage_Determination_9_3_2026_0006.pdf PDF
Section_J_10_2_2026_0006.pdf PDF
Section_L_10_2_2026_0006.pdf PDF
Sol_140R2026R0017_Amd_0006.pdf PDF
Attachment_11_-_RFP_Checklist_10_2_2026_0006.pdf PDF
Attachment_14_-_Breaker_10_2_2026_0006.pdf PDF
Amendment_No__5_Questions-Answers_9_25_2026_0005.pdf PDF
Sol_140R2026R0017_Amd_0005.pdf PDF
Folsom_Warehouse_Crane_-_Site_Visit_2_Attendance_0005.pdf PDF
Section_J_9_25_2026_0005.pdf PDF
26_08_00_-_Commissioning_of_Electrical_Equipment_Amend_0004_0004.pdf PDF
25_12_10_-_Programmable_Logic_Controller_Amend_0004_0004.pdf PDF
26_05_02_-_Basic_Electrical_Materials_and_Methods_Amend_0004_0004.pdf PDF
Attachment_13_-_Folsom_Warehouse_Crane_Site_Visit_0004.pdf PDF
00_01_10_-_Table_of_Contents_Amend_0004_0004.pdf PDF
RFQ-140R2026R0017_SF1442_9_2_2026_0004.pdf PDF
25_00_01_-_Automation_Control_System_Amend_0004_0004.pdf PDF
Attachment_2_-_FolsomCraneMod_11x17_Amend_0004_0004.pdf PDF
41_22_14_-_Bridge_Crane_Amend_0004_0004.pdf PDF
01_33_00_-_Submittals_Amend_0004_0004.pdf PDF
41_22_15_-_Bridge_Crane_Electrical_Components_Amend_0004_0004.pdf PDF
Attachment_12_Questions_and_Answers_9_1_2026_0004.pdf PDF
Sol_140R2026R0017_Amd_0004.pdf PDF
41_22_13_-_Removal_of_Existing_Cranes_Amend_0004_0004.pdf PDF
Attachment_11_-_RFP_Checklist_9_1_2026_0004.pdf PDF
C06_01_Attachment_9_-_Pre-Proposal_Meeting_Agenda_8_5_2026_0003.pdf PDF
Sol_140R2026R0017_Amd_0003.pdf PDF
C06_01_Attachment_10_Virtual_Folsom_Dam_Warehouse_Crane_8_5_2026_0003.pdf PDF
Sol_140R2026R0017_Amd_0002.pdf PDF
Sol_140R2026R0017_Amd_0001.pdf PDF
C05_04_Attachment_8_-_RFP_Checklist_7_11_2026.pdf PDF
C05_04_RFP-140R2026R0017_SF1442_7_31_2026.pdf PDF
C05_04__Attachment_1_-_SOW_7_1_2026.pdf PDF
C05_04_Attachment_7_-_PPQ_6_30_2026.docx DOCX document
C05_04_Attachment_3_-_Wage_Determination_6_22_2026.pdf PDF
Sol_140R2026R0017.pdf PDF
C05_04_Attachment_6_-_Risk_Assessment-Value_Add_7_14_2026.docx DOCX document
C05_04_Attachment_5_-_LOS_6_24_2026.xlsx XLSX spreadsheet
C05_04_Attachment_4_-_Release_of_Claims_6_23_2026.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Folsom Warehouse – Bridge Crane Replacement Amendment No. 0004 American River Division Solicitation No. 140R2026R0017 Folsom Unit - Central Valley Project, California Specifications No. 20-C0942

Drawings

Revised 52 00 00 - 1

SECTION 52 00 00

DRAWINGS

PART 1 GENERAL

1.01 DISCREPANCIES, ERRORS, OR OMISSIONS

A. Promptly inform the CO of discrepancies discovered on the drawings. The CO will make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense.

B. Anything mentioned in the written specifications and not shown on the drawings, or shown on the drawings and not mentioned in the written specifications, shall be of like effect as if shown or mentioned in both. In case of differences between drawings and written specifications, the written specifications shall govern.

1.02 SPECIFICATION DRAWINGS

A. Some drawings show details of installation or other details and specifications which are not a part of work under these specifications. Disregard specifications and details shown on these drawings which are not applicable to work under these specifications.

B. Reference drawings referred to on specifications drawings not included in specifications are not considered necessary for contract performance.

1.03 INFORMATION DRAWINGS

A. Drawings marked "For Information Only" in the drawing list are included to show existing future features about which knowledge is required to perform work under this contract. These drawings do not show work to be performed under this contract.

B. If there are differences as determined by the CO between details and dimensions shown on these drawings and those of existing features at jobsite, use details and dimensions of existing features at jobsite.

1.04 COPIES OF DRAWINGS

A. One set of full size 22- by 34-inches drawings will be furnished to the Contractor.

1.05 LIST OF DRAWINGS

A. Drawings listed in Table 52 00 00A - List of Drawings, are made a part of Section C - Description/Specifications.

Revised 52 00 00 - 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Table 52 00 00A - List of Drawings

Sheet No.

Drawing No. Title

General Drawings:

1 485-D-61367 Site Map and Contractor Use Areas

Information Drawings:

2 485-208-85 Folsom Power Plant – Warehouse “A” – Plan, Elevations and Details

3 485-208-86 Folsom Power Plant – Warehouse “A” – Foundation- Concrete Outline and Reinforcement

4 485-208-87 Folsom Power Plant – Warehouse “A” – Roof Plan and Details

5 485-208-91 Folsom Power Plant – Warehouse “A” – Electrical Installation

6 485-208-1009 Folsom Dam – Electrical Modifications to Warehouse A 30-Ton Crane

7 485-208-1010 Folsom Dam – Electrical Modifications to Warehouse A 30-Ton Traveling Crane

Standard Drawings:

8 40-D-4334 Electrical Standards - Typical Grounding Details – Sheet 1 of 2

9 40-D-4335 Electrical Installation - Typical Grounding Details – Sheet 2 of 2

10 40-D-4753

Electrical Installation - Typical Grounding Details for Switchyards and Substations

11 40-D-4874 Electrical Installation - Substation and Switchyard Platforms Grounding Details

Revised 52 00 00 - 3

Table 52 00 00A - List of Drawings

Sheet No.

Drawing No. Title

12 40-D-5324 Electrical Standards – Control and Instrument Switch – Escutcheons and Indicating Lamps

13 40-D-6234 Standard Nameplates

14 40-D-6376 Transmission Lines – Fencing Within Right -of-Way – Typical Grounding Details

15 40-D-7095 Switchyards and Substations – Electrical Installation – Identification, Warning and Safety Signs

16 40-D-7098 Electrical Installation – Equipment, Location and Voltage Symbols Key Lists

17 40-D-7102 Drawing Border, Sample Title Block and Signature Lines

18 104-D-1150 Major Power/Pumping Plants - Electrical Installation Device Designations and Symbols to Be Used on Single-Line and Schematic Diagrams

19 104-D-1165 Main Control Board CSA – Panel 7R – Wiring Diagram

20 40-D-60001 Electrical Equipment Support, Type 1 – Sections and Detail

END OF SECTION