00_01_10_-_Table_of_Contents_Amend_0004_0004.pdf
PDF 96 KB Posted
- Attached to
- Folsom Warehouse Bridge Crane Replacement
- Solicitation number
- 140R2026R0017
About this file
This document is a Table of Contents for Section C (Description/Specifications) of a federal construction solicitation for the Folsom Warehouse Bridge Crane Replacement project. The solicitation, issued by the American River Division of the U.S. Bureau of Reclamation for the Central Valley Project in California, is identified as Solicitation No. 140R2026R0017, Amendment No. 0004, with Specifications No. 20-C0942.
The specifications are organized into nine divisions covering the complete scope of work required for bridge crane replacement. Division 01 addresses general requirements including work summary, site coordination, safety and health protocols, quality procedures, and temporary utilities. Division 02 covers existing conditions including asbestos abatement and hazardous materials removal. Division 03 specifies concrete work for equipment grouting. Division 09 addresses coating finishes. Division 25 establishes automation control system and programmable logic controller requirements. Division 26 details comprehensive electrical work including materials, grounding, raceways, identification systems, and commissioning. Division 41 constitutes the core scope, requiring removal of the existing crane and installation of a new bridge crane with associated electrical components. Division 51 makes available project information including photographs, hazardous materials survey results, and electronic media releases to potential offerors. Division 52 references contract drawings. The table of contents does not provide pricing information, response deadlines, or award dates.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Folsom Warehouse – Bridge Crane Replacement Amendment No. 0004 American River Division Solicitation No. 140R2026R0017 Folsom Unit - Central Valley Project, California Specifications No. 20-C0942
Table of Contents
Revised 00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 12 10 Other Contracts 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 30 Interruption of Service 01 31 22 Coordination Meetings 01 31 30 Contract Document Management System 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 35 50 Site Security 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents 01 79 20 Training
DIVISION 02 - EXISTING CONDITIONS
02 80 10 General Requirements for Asbestos Abatement 02 80 11 General Requirements for Coatings Containing Regulated Metals Abatement 02 82 20 Removal and Disposal of Asbestos Containing Materials 02 83 33 Recycling of Scrap Metal with Coatings Containing Hazardous Materials 02 87 20 Recycling and Disposal of Used Oil
DIVISION 03 – CONCRETE
03 62 20 Non-shrink Grout for Equipment and Metalwork
Folsom Warehouse – Bridge Crane Replacement Amendment No. 0004 American River Division Solicitation No. 140R2026R0017 Folsom Unit - Central Valley Project, California Specifications No. 20-C0942
Table of Contents
Revised 00 01 10 - 2
DIVISION 09 – FINISHES
09 96 20 Coatings
DIVISION 25 – INTEGRATED AUTOMATION
25 00 01 Automation Control System 25 12 10 Programmable Logic Controller
DIVISION 26 - ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 20 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 60 Identification, Warning and Safety Signs 26 05 90 Wiring Checkout and Tests 26 08 00 Commissioning of Electrical Equipment 26 24 42 Distribution Panelboards 26 43 13 Surge Protection Devices for Electrical Circuits
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13 Removal of Existing Crane 41 22 14 Bridge Crane 41 22 15 Bridge Crane Electrical Components Deleted
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Photographs 51 00 50 Electronic Media Release 51 02 82 Hazardous Materials Survey and Analytical Results
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF CONTENTS
File details come from the government source that posted it. Updated .