This is a Task Order Proposal Request (TOPR) for vault toilet and septic pumping services at the Smith River National Recreation Area under the USFS California Regional Vault and Septic Pumping Services Indefinite Delivery Indefinite Quantity (IDIQ) contract.

The contractor shall furnish all labor, equipment, supplies, transportation, supervision, and permits necessary to perform vault toilet pumping, septic tank pumping, debris removal, cleaning, sanitizing, waste hauling, and disposal at 22 identified recreation sites across the Six Rivers National Forest in Del Norte County, California. Project locations include campgrounds, trailheads, day-use areas, boating sites, and remote locations accessible by paved, gravel, or dirt roads. The period of performance runs from August 7, 2026, through August 31, 2027 (not to exceed 365 days). Contractors must provide scheduled service dates within 5 business days of request, begin routine pumping within 72 hours of request, and respond to emergency requests within 48 hours. All work must comply with the parent IDIQ Performance Work Statement and applicable Federal, State, Tribal, and local regulations. Required deliverables include service documentation (pumping logs, volumes, dates/times, debris removal notes), waste manifests and disposal receipts from facilities, and incident or spill reports if applicable. Proposals are due July 26, 2026, by 2359 PST, and must address ability to meet the start date, approach to servicing locations, staffing and equipment availability, and identification of a Task Order point of contact. The Government will evaluate proposals on responsiveness, technical capability, experience and past performance, price, and compliance with representations and bio-based requirements, using best value under FAR 16.505. Travel will be reimbursed according to IDIQ travel tiers based on round-trip frequency proposed by the contractor. Wage determinations applicable to Del Norte County must be identified and complied with, with the contractor responsible for submitting SF-1444 Conformance Requests if required classifications are not available.

View the file

Other files

File Type Posted
C05-1. J37_Q&A_127EAS26R0003, v4, 20260727.pdf PDF
C05-1. J37_Q&A_127EAS26R0003, v3, 20260721.pdf PDF
C05-1. J1_SF1449&TermsB-M_127EAS26R0003, 20260722.pdf PDF
C05-1. J2_PWS v5.1_127EAS26R0003 20260525.pdf PDF
C05-1. J1_SF30_127EAS26R0003, 20260722.pdf PDF
C05-1. J3_SOI 127EAS26R0003, 20260721.xlsx XLSX spreadsheet
C04. J4_Geographic Locations, v4.pdf PDF
C04. J6_Past Performance & Exp Questionnaire.pdf PDF
C04. J15_ Seed TOPR MDF-1171248.pdf PDF
C04. J19_Seed TOPR TNF5 Sierraville-1171357.pdf PDF
C04. J31_Seed TOPR SQF Hume Lake-1171645.pdf PDF
C04. J7_Reps and Certs_52.212-3, 202607.pdf PDF
C04. J8_Contractor Responsibility Cert, 202607.pdf PDF
C04. J10_KeyPersonnel-DesgofReps, 202604.pdf PDF
C04. J11_FS 6300-11_SubkApp, 202602.pdf PDF
C04. J12_SF 1444 - ReqforAuthofAdd'lClassif&Rate.pdf PDF
C04. J14_Seed SOI LNF5-1171338, 20260711.xlsx XLSX spreadsheet
C04. J18_Seed SOI SRF, 20260712.xlsx XLSX spreadsheet
C04. J22_Seed SOI TNF5 N. Yuba-1171347.xlsx XLSX spreadsheet
C04. J25_Seed TOPR SNF5 High Sierra-1171334.pdf PDF
C04. J33_Seed TOPR BDF-1165566.pdf PDF
C04. J3_SOI 127EAS26R0003, 20260711.xlsx XLSX spreadsheet
C04. J9_Biobased-Sustainable Statement.pdf PDF
C04. J13_Seed TOPR LNF5-1171338F, 20260712.pdf PDF
C04. J16_Seed SOI MDF-1171248, 20260711.xlsx XLSX spreadsheet
C04. J30_Seed SOI SNF5 Bass Lake-1171333.xlsx XLSX spreadsheet
C04. J1_SF1449&TermsB-M_127EAS26R0003.pdf PDF
C04. J2_PWS v5_127EAS26R0003 20260525.pdf PDF
C04. J5_Maps.pdf PDF
C04. J20_Seed SOI TNF Sierraville RD.xlsx XLSX spreadsheet
C04. J21_Seed TOPR TNF5 N. Yuba-1171347.pdf PDF
C04. J23_ Seed TOPR TMU, 20260712.pdf PDF
C04. J24_Seed SOI TMU, 20260712.xlsx XLSX spreadsheet
C04. J26_Seed SOI SNF5-1171334, 20260712.xlsx XLSX spreadsheet
C04. J27_Seed TOPR STF-1149457, 20260712.pdf PDF
C04. J28_Seed SOI STF-1149457.xlsx XLSX spreadsheet
C04. J29_Seed TOPR SNF5 BassLake-1171333.pdf PDF
C04. J32_Seed SOI SQF Hume Lake-1171645.xlsx XLSX spreadsheet
C04. J34_Seed SOI BDF-1165566.xlsx XLSX spreadsheet
C04. J35_Seed TOPR LPF, 20260712.pdf PDF
C04. J36_Seed SOI LPF-EVO, 20260712.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA FOREST SERVICE

Task Order Proposal Request (TOPR)

USFS California Regional Vault & Septic Pumping Services IDIQ

TO Solicitation No.: 127EAS26R0003 TO Project Title: SRF FY26 Smith River NRA Vault Pumping Forest: Six Rivers National Forest (SRF) Geographic Zone CA Northern WEST Parent IDIQ No.: TBD TO No.: TBD Contractor: TBD

1. GENERAL INFORMATION

1.1 Scope Summary

The Contractor shall furnish all labor, equipment, supplies, transportation, supervision, and permits necessary to perform vault toilet pumping, septic pumping, debris removal, cleaning, sanitizing, waste hauling, and disposal at the recreation sites identified in this Task Order (TO).

Project locations may include campgrounds, trailheads, day‑use areas, administrative sites, dispersed sites, OHV sites, and remote locations accessed via paved, gravel, or dirt roads. All work shall be performed in accordance with the IDIQ Performance Work Statement (PWS), this TOPR, and all applicable Federal, State, Tribal, and local regulations.

All pumping, cleaning, debris removal, sanitizing, and recharge procedures must comply with IDIQ Attachment J2 (PWS). Deliverables shall be provided as required under IDIQ Section H.1.13.

1.2 Applicable Contract

This TOPR is issued under the USFS California Regional Vault and Septic Pumping Services IDIQ. All parent contract terms and conditions remain in effect unless expressly modified herein.

2. PERIOD OF PERFORMANCE

2.1 Start and End Dates

• Start Date: On or before 08/07/2026

• End Date: 08/31/2027

The PoP must comply with IDIQ Section H.1.2, including:

• Not to exceed 365 days

• Multiple Year order are prohibited

• Must fall within the IDIQ ordering period

2.2 Notice to Proceed

Work may begin only upon receipt of a properly executed Task Order or a written notice to proceed, with the schedule coordinated and approved by the FS CO, CS/Agent or personnel designated in writing by the CO (e.g.

COR).

TO Solicitation No.: 127EAS26R0003 Parent IDIQ No.: TBD Forest: Six Rivers National Forest (SRF) TO No.: TBD TO Project Title: SRF FY26 Smith River NRA Vault Pumping

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 2 of 12

3. RESPONSE REQUIREMENTS

3.1 Scheduling

The Contractor shall provide a scheduled service date within 5 business days of COR request.

3.2 Performance

• Routine pumping requests: Begin service within 72 hours of COR/CO/GTM request.

• Emergency requests: Begin service within 48 hours, consistent with the IDIQ PWS.

These requirements supplement, but do not replace, PWS Section C.2.3.

4. LOCATIONS OF WORK

All sites and estimated quantities for this Task Order are identified in Attachment A — SOI (Excel).

4.1 Location Identification

Work under this Task Order includes vault/septic pumping and associated services across the following:

• Forest: Six Rivers National Forest (SRF)

• Ranger District(s): Gasquet Ranger District

• Site Types: Campgrounds/Trailheads/River Access

• Place of Performance Counties: Del Norte County

4.2 Vault Coordinates

Coordinates for each site shall be included in:

• Attachment B.1 - B.4— Maps

• Attachment C — Coordinates Table

The SOI will identify:

• Unit quantities

• Estimated vault volumes

• Any unique access or equipment conditions

5. PROJECTSPECIFIC REQUIREMENTS

Insert Project Specific Requirements Below (if any):

5.1 Access and Site Conditions

Vault toilets with exterior access hatch doors shall be pumped from the exterior cleanout.

A Forest Service key may be needed to unlock the hatch door. If so, transfer of the key will be arranged by the COR.

Vault toilets without exterior access shall be pumped from the interior directly through the toilet riser following the procedures listed below. Sites are accessible by a variety of road types including paved, chip-sealed, gravel and dirt.

5.2 Pumping Requirements

Reserved

5.3 Hours of Operation

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 3 of 12

Work shall be scheduled so that it is accomplished between the hours of 8:00 A.M. and 7:00 P.M.; emergency pumping may occur outside of these hours.

5.4 Spill Response

Reserved

5.5 Equipment Requirements

Must be capable of accessing sites on paved, gravel, dirt, muddy, snow, or ice covered roads; vehicles must support chains when required.

5.6 Public Interaction and Conduct

Reserved

5.7 Service Ordering and Completion

5.7.1 Travel Application for Multiple Sites, Multiple Dumps, and On-Call Services

5.7.1.1 General Rule – Parent IDIQ Round Trip Definition

Travel shall be priced using the IDIQ travel tiers and represents one (1) round trip (RT) from the Contractor’s established place of business to the service location(s), to the disposal facility as required, and return to the place of business. Travel tier selection and CTR Round Trip Frequency shall be entered for each applicable travel tier in the SOI. Travel must be invoiced according to the IDIQ Schedule of Items (SOI) travel tier for the applicable performance year.

5.7.1.2 Multiple Vaults/Septic Tanks in One Run

When the Contractor services multiple vaults, septic tanks, or portable toilets on a single mobilization, and is able to complete all work and disposal within a single RT, the Contractor shall price one (1) RT, regardless of the number of units serviced.

5.7.1.3 Multiple Disposal Trips

If the Contractor must off-load waste before completing all assigned units, each required disposal trip constitutes an additional RT, to be priced at the applicable IDIQ travel tier.

The Contractor shall record the number of required disposal trips in the SOI under “CTR Round Trip Frequency,” and provide disposal manifests supporting each dump.

5.7.1.4 Contractor Responsibility for Determining Round Trips The Contractor is solely responsible for determining and proposing the CTR Round Trip Frequency required to complete the services under this Task Order. The COR is not required to estimate or validate the Contractor’s travel time, travel distance, disposal‑site routing, or the number of required mobilizations. The Contractor shall base its proposed RT frequency on:

• Its place of business,

• Its disposal facility selection and capacity constraints,

• Anticipated tank volumes and pumping requirements,

• Site access conditions, and

• Any mid‑route dumping requirements.

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 4 of 12

The Government will evaluate the Contractor’s proposed RT frequency for reasonableness and consistency with known site conditions. The Contractor shall allocate CTR Round Trip Frequency across travel tiers in the SOI based on the estimated distribution of service calls, pumping frequencies, and site distances.

Please note that the COR may identify the anticipated number of service calls (reference 5.7.1.5); however, the COR does not estimate or prescribe the number of Contractor round trips. All RT estimation remains the responsibility of the Contractor.

5.7.1.5 On-Call Services

For on‑call services initiated by the Government during the period of performance, each Contractor mobilization constitutes one (1) Round Trip (RT). The Contractor is responsible for determining and proposing the number of RTs required for each on‑call response, including any additional RTs required due to disposal‑site limitations or tank‑capacity constraints. The COR is not required to estimate travel time, determine Contractor routing, or project the number of RTs needed for any on‑call action. All travel pricing for on‑call services shall be based on the Contractor‑proposed CTR Round Trip Frequency documented in the SOI.

5.7.1.6 Proposal Requirement – Round Trip Frequency

The Contractor shall propose, in the SOI, the total CTR Round Trip Frequency required for the full scope of the Task Order, including:

1. Number of mobilizations required,

2. Number of required disposal trips (if applicable),

3. Identification of factors necessitating additional trips (e.g., tank capacity limits, remote sites, disposal‑site routing).

The Government may negotiate the proposed RT frequency where it is inconsistent with known site conditions;

however, the Contractor is responsible for establishing the RT estimate in its proposal.

5.7.2 Limits on Additional Pumping

The Contractor shall perform services only for the vaults, septic tanks, and locations listed in the Task Order Schedule of Items (SOI). Each vault or septic tank listed in the SOI has an associated pumping quantity representing the number of pumping events ordered for the period of performance. A pumping event, whether completed in a single mobilization or in multiple trips due to tank capacity limitations, shall be counted as one (1) pumping event against the ordered quantity for that specific vault or septic tank.

The Contractor is not authorized to pump additional vaults or septic tanks beyond those quantities ordered in the SOI, even if remaining tank capacity exists after servicing assigned units. Performing pumping services for unlisted units—or for listed units in excess of the ordered quantity—constitutes work outside the scope of this Task Order.

If the Government determines that additional pumping is required, the Government may, at its sole discretion, increase the quantity for a listed vault or septic tank, or add new pumping quantities for other listed units, through a written modification issued by the Contracting Officer or an authorized ordering official. The Contractor shall not perform any additional pumping beyond the awarded SOI quantities until such written direction is issued.

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 5 of 12

Optional COR Information:

The COR may identify that additional units appear to require service; however, the COR shall not authorize, direct, or permit the Contractor to pump beyond the awarded SOI quantities. Any additional pumping can only be ordered through a Contracting Officer issued modification that adjusts the SOI quantities.

Note: All procedures in the PWS remain in effect. If conflicts arise, the PWS governs.

6. DELIVERABLES

6.1 Required

The Contractor shall provide the following deliverables to the Government for this Task Order:

1. Service Documentation, including:

o pumping logs o volumes pumped, o dates/times of service, o debris removal notes, and o any other contractor-generated records supporting performance and service completion.

2. Waste Manifests / Disposal Receipts including:

Documentation from the disposal facility identifying o Facility name o date, o load number, and o any pertinent information confirming legal disposal.

3. Incident or Spill Reports (if applicable)

Submitted within 24 hours, consistent with IDIQ Section H.8.1.

Note:

The Forest Service COR will complete and retain the Service Report referenced in IDIQ Section E.1.2 as part of the Government’s inspection and acceptance procedures. Contractors are not required to generate the Service Report form.

7. WAGE DETERMINATION

The appropriate SCA Wage determination(s) shall be incorporated into the award in accordance with IDIQ Section H.1.12.

WD(s) Incorporated:

List WD numbers and revision dates

If additional counties are identified during performance, the Contracting Officer will incorporate the appropriate Wage Determinations by modification. The Contractor shall comply with the Wage Determination

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 6 of 12 applicable to the county in which each service is performed and is responsible for ensuring wage and fringe benefit compliance for each covered location.

8. TRAVEL

Travel will be reimbursed according to IDIQ travel tiers. The Contractor shall price travel using the TOPR SOI, which includes separate travel tier line items.

All contractor travel must comply with FMCSA driving regulations.

9. GOVERNMENT FURNISHED INFORMATION (GFI)

• Access keys (if required)

• Maps (Attachment B)

• Any Forest specific supplemental instructions

10. CONTRACTOR KEY PERSONNEL

• IDIQ-level: Contractor Representative only

• Task Order level: Contractor must identify the Task Order POC prior to NTP

TO Point(s) of Contact (to be identified prior to award and the issuance of the NTP)

11. ADMINISTRATIVE

All administrative processes—including invoicing, inspection, acceptance, subcontract approvals, modifications, and COR/GTM responsibilities—shall follow IDIQ Section G.

12. ATTACHMENTS

• A – SOI (Excel)

• B.1- B.4 – Maps (for TO location)

• C – Project Coordinates

• D – Wage Determination (for TO location)

• E – FS630011 Subcontractor Approval Form (only applicable if subcontracting)

13. PROPOSAL SUBMISSION INSTRUCTIONS (ORDER LEVEL)

Proposals are due by: July 26, 2026 no later than 2359 PST.

Submit proposals to:

CO: klenise.wallace@usda.gov

Required Submission Items:

• Ability to meet required start date

• Approach to servicing the locations

• Staffing and equipment availability

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 7 of 12

• TO Point of Contact

• FS-6300-11 (if subcontracting)

Incomplete submissions may be deemed non-responsive.

14. ORDER-LEVEL EVALUATION (BEST VALUE UNDER FAR 16.505)

Evaluation shall follow IDIQ Section M, including:

• Responsiveness

• Technical Capability

• Experience & Past Performance

• Price

• Compliance with representations, bio-based requirements, etc.

Comparative evaluation will be conducted per FAR 12.602 and 13.106-2(b).

The Government may select a higher priced proposal if it provides higher confidence or lower performance -risk.

15. QUESTIONS

Questions must be submitted in writing to the CO and COR by: July 23, 2026, no later than 1300 PST.

Only written responses from the CO/COR (or CO designated personnel) are binding.

END OF TOPR DETAILS

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 8 of 12

ATTACHMENT A

(External – SOI (Excel))

See Attachment J18.

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 9 of 12

ATTACHMENT B

External

B.1 Six Rivers Map – Overview

B.2 Six Rivers Map – North Toilets B.3 Six Rivers Map – East Toilets B.4 Six Rivers Map – West Toilets

SarahBelcher Text Box

B.1

B.2

Map B.3

B.4

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 10 of 12

ATTACHMENT C

(TO Project Coordinates)

Location details, to include driving directions, will be defined at the time of actual project development and validation.

(TO Project Coordinates) SRF FY26 Smith River NRA Vault Pumping TO

Vault Name Site Type Latitude Longitude Driving Directions

CHIMNEY FLAT PICNIC SITE 41.6972000 -123.9030500

DRY LAKE FISHING SITE 41.7418000 -123.8765000

SAND CAMP TRAILHEAD 41.7416000 -123.9811000

SOUTH KELSEY TRAILHEAD 41.6544444 -123.8625000

STEVEN BRIDGE BOATING SITE 41.6930478 -123.9306174

FORKS BOAT RAMP BOATING SITE 41.7994444 -124.0538889

BIG FLAT CAMPGROUND 41.6875000 -123.9080556

BEAR BASIN BUTTE LOOKOUT/CABIN 41.8090510 -123.7421890

DOE FLAT TRAILHEAD 41.8144444 -123.7066667

MADRONA DAY USE AREA 41.8572222 -123.8838889

GRASSY FLAT CAMPGROUND 41.8566667 -123.8869444

PANTHER FLAT PICNIC PICNIC SITE 41.8427778 -123.9316667

MARGIES RIVER ACCESS BOATING SITE 41.8441667 -123.9947222

MARY ADAMS PEACOCK DAY USE AREA 41.8425000 -124.0116667

MYRTLE BEACH DAY USE AREA 41.8021100 -124.0540800

SANDY BEACH DAY USE AREA 41.8633000 -123.8587000

SHELLY CREEK DAY USE AREA 41.9019000 -123.8545000

NORTH FORK CAMPGROUND 41.9783000 -123.9607000

NORTH FORK RIVER ACCESS BOATING SITE 41.9822700 -123.9604700

PATRICK CREEK CAMPGROUND 41.8723000 -123.8459900

PATRICK CREEK PICNIC PICNIC SITE 41.8724000 -123.8446000

PANTHER FLAT CAMPGROUND 41.8430556 -123.9288889

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 11 of 12

ATTACHMENT D

(TO Wage Determination(s))

No applicable SCA Wage Determination currently exists for some counties included in this Task Order. The contractor shall review all place-of-performance counties during proposal preparation. If the contractor determines that the applicable WD does not contain a required classification for the services performed, the contractor shall be prepared to submit an SF 1444 Conformance Request immediately upon receipt of award and Notice to Proceed.

To avoid delays in project start-up, the contractor is encouraged to pre-identify the anticipated labor classifications and prepare draft SF-1444 materials in advance. The Government will incorporate the appropriate WD(s) as soon as they become available via modification; however, performance may begin under pending conformance in accordance with IDIQ Section H.1.12 and the Davis-Bacon/SCLS conformance procedures.

Instruction to pull Wage Determinations

• Go to SAM.gov>Wage-Determinations (https://sam.gov/wage-determinations). Select Service Contracts.

• Use carrot to select state.

• County/Independent City?

• You will need to select the applicable county for each area.

• Previously Performed? Yes, but in a different locality.

• Non-Standard Services? Yes;

• Select Non-Standard Service>Use carrot to select Hazardous Waste Pickup and Disposal Services.

• Status? Active

Government Intent Note: The instructions above describe how the contractor is to identify the applicable Wage Determination for each place of performance. If, after following these steps, an appropriate Wage Determination is not available or does not contain a required labor classification, the contractor shall be prepared to submit an SF-1444 Conformance Request immediately upon award and Notice to Proceed. This clarification is provided to avoid delays in establishing the required conformed rate(s).

https://sam.gov/wage-determinations

Request For Authorization Of Additional Classification And Rate

Instructions: The Contractor shall complete items 3 through 16, keep a pending copy, and submit the request, in quadruplicate, to the Contracting Officer.

1. To:

Administrator, Wage And Hour Division U.S. Department Of Labor Washington, DC 20210

2. From: (Reporting Office)

3. Contractor 4. Date Of Request

5. Contract Number 6. Date Bid Opened (Sealed Bidding)

7. Date Of Award

8. Date Contract Work Started

9. Date Option Exercised (If Applicable) (Service Contract Only)

10. Subcontractor (If Any)

11. Project And Description Of Work (Attach Additional Sheet If Needed)

12. Location (City, County, And State)

13. In Order To Complete The Work Provided For Under The Above Contract, It Is Necessary To Establish The Following Rate(s) For The Indicated Classification(s) Not Included In The Department Of Labor Determination

Number: Dated:

a. List In Order: Proposed Classification Title(s); Job

Description(s); Duties; And Rationale For Proposed Classifications (Service contracts only)

b. Wage Rate(s) c. Fringe Benefits Payments

(Use reverse or attach additional sheets, if necessary)

14. Signature And Title Of Subcontractor Representative (If Any)

15. Signature And Title Of Prime Contractor Representative

STANDARD FORM 1444 (REV. 10/2023)

Prescribed by GSA-FAR (48 CFR) 53.222(f)

Check Appropriate Box Service Contract Construction Contract

OMB Control Number: 9000-0066 Expiration Date: 5/31/2027

Authorized For Local Reproduction Previous Edition Is Not Usable

Paperwork Reduction Act Statement

This information collection meets the requirements of 44 U.S.C. § 3507, as amended by section 2 of the

Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0066. We estimate that it will take .5 hours to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S. General Services

Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

To Be Completed By Contracting Officer (Check As Appropriate - See FAR 22.1019 (Service Contract Labor Standards) Or FAR 22.406-3 (Construction Wage Rate Requirements))

The Interested Parties Agree And The Contracting Officer Recommends Approval By The Wage And Hour Division. Available Information And Recommendations Are Attached.

The Interested Parties Cannot Agree On The Proposed Classification And Wage Rate. A Determination Of The Question By The Wage And Hour Division Is Therefore Requested. Available Information And Recommendations Are Attached.

(Send 3 copies to the Department of Labor)

Date SubmittedTitle And Commercial Telephone Number

Signature Of Contracting Officer Or Representative

DisagreeAgree

Check Appropriate Box - Referencing Block 13.

Title16. Signature Of Employee Or Representative

STANDARD FORM 1444 (REV. 10/2023) BACK

SF 1444 Additional Information

� Block 11 — Project and Description of Work

This request applies to vault toilet pumping, septic tank pumping, portable toilet pumping, vault structure cleaning, debris removal, waste transport, waste disposal, reporting, spill response, remote/winter access, and compliance with Federal, State, Tribal, county, and local wastewater handling and transportation regulations, as required under USFS California Regional Vault and Septic Pumping Services IDIQ 127EAS26R0003 (Sections B and C).

These duties include operation of pump trucks, DOT compliant wastewater hauling vehicles, PPE use per 29 CFR 1910.120, required waste manifests, and compliance with environmental, health, and transportation regulations.

� Block 13 — Classification Requested

Proposed Classification Title: Vault/Septic Pumping Technician

Job Description & Duties:

Performs vault toilet pumping, septic tank pumping, portable toilet servicing, vault cleaning, debris removal, and pumping operations using specialized pump trucks.

Handles, transports, and disposes of sewage, graywater, septage, and associated waste in compliance with Federal, State, Tribal, county, and local regulations.

Operates DOT-regulated wastewater hauling vehicles; completes waste manifests;

performs spill response; uses PPE meeting 29 CFR 1910.120; provides documentation and reporting as required by the USFS Performance Work Statement (Attachment J2).

Work includes remote-access and winter-access pumping, emergency response capability, and safe operation on National Forest lands.

Rationale for Proposed Classification:

No existing SCA classification adequately captures the combination of specialized pumping equipment operation, regulated wastewater handling, environmental compliance duties, PPE/hazmat-related requirements, and DOT-regulated wastewater hauling required under the IDIQ.

The duties do not align with 23370 (General Maintenance Worker), which does not include regulated waste handling or specialized equipment operation.

The duties do not align with 23810 (Plumber, Maintenance), which covers plumbing craft work such as repair and installation, not sewage pumping and regulated waste transportation.

Therefore, an additional classification is required for lawful compliance with the Service Contract Labor Standards.

USFS California Regional Vault and Septic Pumping Services IDIQ | Page 12 of 12

ATTACHMENT E

(FS-6300-11, Subcontractor Approval Form)

USDA – Forest Service FS-6300-11 (10/81)

SUBCONTRACTOR

APPROVAL

REQUEST

SOLICITATION NUMBER CONTRACT NUMBER

UNIT

PROJECT TITLE

PRIME CONTRACTOR NAME, ADDRESS AND POC+EMAIL

APPROVAL IS HEREBY REQUESTED TO SUBCONTRACT WORK ON ABOVE REFERENCED CONTRACT.

SUBCONTRACTOR DETAILS

SUBCONTRACTOR NAME:

SUBCONTRACTOR UEI NO:

SUBCONTRACTOR ADDRESS:

SUBCONTRACTOR TAX ID (IF NO UEI NO.):

WORK DETAILS

TYPE OF WORK TO BE SUBCONTRACTED:

% OF WORK TO BE SUBCONTRACTED:

PRIME CONTRACTOR CONTACT NAME/ TITLE PRIME CONTRACTOR DIGITAL / WET SIGNATURE DATE (wet signature only)

STOP. BELOW TO BE COMPLETED BY USDA FOREST SERVICE CONTRACTING OFFICER ONLY.

APPROVER NAME/ TITLE APPROVER DIGITAL / WET SIGNATURE DATE APPROVED (wet signature only)

INSTRUCTIONS:

Complete and return to Forest Service.

Service Contract: On
Construction Contract: Off
2 From Reporting Office: USDA - Procurement Operations

Ordering Contracting Officer - NAME Enter Order CO Division

3 Contractor: To be completed by the awarded contractor
4 Date Of Request:
5 Contract Number: Enter Parent No.
6 Date Bid Opened Sealed Bidding:
7 Date Of Award:
8 Date Contract Work Started:
9 Date Option Exercised If Applicable Service Contract Only:
11 Project And Description Of Work Attach Additional Sheet If Needed:
11 Project Title: Enter Task Order Project title
12:
City: Enter City of Work Performance
State: California
b Wage RatesUse reverse or attach additional sheets:
1:
41:
3:
2:
5:
6:
c Fringe Benefits PaymentsUse reverse:
1:
6:
5:
4:
3:
2:
5 Task Number:
11:
Project Description: See Additional Sheet
12 County: Enter County of Work Performance
a:
Classification:
1: Vault/Septic Pumping Technician
2: Sanitation Worker
3:
4:
5:
6:
Title:
Agree: Off
Disagree: Off
The Interested Parties Agree And The Contracting Officer Recommends Approval By The Wage: Off
The Interested Parties Cannot Agree On The Proposed Classification And Wage Rate A: Off
Contracting Officer Title:
Date Submitted:
STANDARD FORM 1444 REV 102023 BACK:
Contracting Officer Telephone Number:
SOLICITATION NUMBER: 127EAS26R0003
CONTRACT NUMBER:
UNIT: USFS California National Forests
PROJECT TITLE: USFS California Regional Vault and Septic Pumping Services IDIQ
PRIME CONTRACTOR NAME ADDRESS AND POCEMAIL:
PRIME CONTRACTOR CONTACT NAME TITLE:
DATE wet signature only:
APPROVER NAME TITLE:
DATE APPROVED wet signature only:
Text1:
Text2:
Text3:
Text4:
Text5:
Text6:

File details come from the government source that posted it. Updated .