VA PROJECT NUMBER
VA CONTRACT NUMBER
VA TASK ORDER NUMBER
635-456
VA101F-17-D-2913
36C10F20N0048
PROJECT NAME OKCVAMC OR & SICU DB Package
OVERALL PROJECT SUMMARY
This structural narrative is intended as a Design-Build (DB) RFP narrative for completing the construction of the 7th and 8th floors, totaling approximately 32,274 GSF. The 7th floor will be renovated into three new operating rooms and the recently installed vertical addition of the 8th floor will be new Surgical Intensive Care Unit (SICU) space.
The majority of structural work for the vertical addition was completed by a previous contractor.
Therefore, the Level 1 requirements identified in the Department of Veterans Affairs A/E
Submission Instructions for Design-Build Projects are not pertinent or were provided as part of the original SICU vertical addition project.
However, numerous items must still be addressed by the DB Contractor to finalize the project.
No structural drawings will be included in the DB RFP bridging documents.
SITE VISIT
A site visit was conducted on June 25, 2020, to review the existing conditions and to identify structural related items that must be addressed by the DB Contractor.
1. Excess concrete and/or drywall mud was observed 2. A ventilation fan that was on the old roof is still on the floor. This must be removed and the floor installed within a room on the new 8th floor. This must leveled. be removed, relocated and the opening infilled.
36C10F20N0048 Construct Surgical Intensive Care & Renovate Operating Rooms
VA TASK ORDER NUMBER
635-456
VA101F-17-D-2913
3. The demolition of the existing framing and the 4. The concrete infill on the stair treads is cracked installation of the new framing at the existing elevators and the stair treads deflect downward significantly and machine room must be completed. under applied pressure and must be removed and replaced or repaired.
5. The weld quality of the weld connecting the stair 6. The quality of the stair landings must be inspected treads to the stringers must be inspected and repaired and repaired as needed. Excess bolt length as needed. No welds were observed connecting the protruding from the wall must be cut neatly.
riser to the tread above.
VA TASK ORDER NUMBER
635-456
VA101F-17-D-2913
7. The vertical expansion of the columns in the 8. The expansion joint along gridline 10 should be southeast stairway should be inspected for compliance inspected for continuity and installation completed.
with the original design drawings and corrected as necessary. The unneeded fur-out should be removed.
9. The spray-applied fireproofing was missing in areas on beams and the underside of the metal deck throughout both levels and must be repaired.
During our site visit, no removal of finishes was completed and, therefore, other conditions may exist that need to be corrected or completed once uncovered.
VA TASK ORDER NUMBER
635-456
VA101F-17-D-2913
ANTI-TERRORISM/FORCE PROTECTION
According to the Department of Veterans Affairs Physical Security Design Manual, “Design and construction standards are provided for the physical security of new buildings, additions, and major alterations. The manual further defines major alterations as “a project where the area of renovation, including any associated addition, is equal to or greater than 50 percent of the area in the building in which the work is to be performed.”
This 32,274 GSF project is below the 50 percent threshold and, therefore, not subject to the requirements of the Physical Security Design Manual.
36C10F20N0048