Various Base Improvements Mihail Kogalniceanu Air Base, Romania
Solicitation number
W912GB-17-R-0020
Issued by

About this file

Solicitation Amendment 06

View the file

Other files

File Type Posted
W912GB-17-R-0020_0013.pdf PDF
W912GB-17-R-00020_0012.pdf PDF
ATTACHMENT_4_Price_schedule_Revised_29_Aug_2017.xlsx XLSX spreadsheet
Conformed_Section_00_10_00_Solicitation_CLIN_Schedule.pdf PDF
A.07.23_Atch_1_Experience_Overview_Sheet_Revised_08_August_17.docx DOCX document
Attachment_15_URBANISM_CERTIFICATIE_01011401[1].pdf PDF
W912GB-17-R-0020-00011.pdf PDF
Attachment H3 FSC 001-FSC X002.pdf PDF
Attachment H5 170809.MI GE 001 Scope Modification.pdf PDF
Attachment_14_SOW_Track_Changes.pdf PDF
Attachment H6 170814.MI RB 001 RB X001 RB X002 Modification_Annex 1.pdf PDF
Attachment H2 FSC 001-FSC X001.pdf PDF
Attachment H1 FSC 001-FSC 001.pdf PDF
Attachment H4 170809.MI GC 001 Scope Modification.pdf PDF
ATTACHMENT_4_Price_schedule.xlsx XLSX spreadsheet
Conform_Copy_W912GB-17-R-0020.pdf PDF
W912GB-17-R-0020-0010_(Post-Closing).pdf PDF
DRAWING_C0003-CIVIL_DETAIL.pdf PDF
W912GB-17-R-0020_0009.pdf PDF
SF1442_Section_00_10_00_Solicitation_Contract_Line_Item_Number_Schedule_Conformed.pdf PDF
W912GB-17-R-0020_0008.pdf PDF
01_SOW_Revised_19_July_2017.pdf PDF
Amendment_07.pdf PDF
Attachment_4_ERI_Revised_Price_Schedule_23_June_17_REVISED_1_JULY_2017.xlsx XLSX spreadsheet
SOW_5July2017.pdf PDF
AW_78-24-27.pdf PDF
Contingency_Design_Program.PDF PDF
MK_MI_SOW-A_DA.docx DOCX document
MK_FSC_SOW-A_DA.docx DOCX document
CX007-CX200.pdf PDF
W912GB-17-R-002005.pdf PDF
A.07.23_Atch_1_Experience_Overview_Sheet_Revised_23_June_17.docx DOCX document
RETENTION_POND_LOCATION__DRAWINGS_REVISED_23_June_17.pdf PDF
A.07.23_Atch_5_Resume_Revised_23Jun17.docx DOCX document
A.07.23_Attachment_4_ERI_Revised_Price_Schedule_23_June_17.xlsx XLSX spreadsheet
W912GB-17-R-0020-0004_FBO.pdf PDF
A.07.23_Attachment_4_ERI_Revised_Price_Schedule_13_June_17.xlsx XLSX spreadsheet
Att._12_Pre_Proposal_Conference_W912GB-17-R-0020_MK_Romania_-_6_June.ppt PPT presentation
Att._13_Pre_Proposal_Sign_In_Roster.pdf PDF
W912GB-17-R-0020-0003.pdf PDF
PPSV_Agenda__Logistic_Plan_with_Project_Site_Plan.pdf PDF
W912GB-17-R-0020_Amendment_02.pdf PDF
A.07.23_Attachment_4_ERI_Revised_Price_Schedule_24_MAY_17.xlsx XLSX spreadsheet
A.07.24_W912GB-17-R-0020_Amendment_01_23_May_2017.pdf PDF
SOW_Attachment_E1-E3_Design_Drawings_35_.zip ZIP file
A.01.13_USACE_Specifications_09_May_17.pdf PDF
A.07.23_W912GB-17-R-0020_Solicitation_9_May_17.pdf PDF
Instruction_to_Offerors_Attachments_1-11.zip ZIP file
SOW_Attachments_A-G.zip ZIP file
A.02.02 Atch_5_DRAFT PRE-SOL_FUEL STORAGE CAPACITY.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Provide responses to RFIs.

Extend the solicitation close date for Volume I (Technical) to 14 July 2017. Volume II (Price) close date is extended to 21 July 2017.

Provide an updated Scope of Work dated 5 July 2017.

Provide an updated bid schedule.

Provide updated Multimodal Improvments Design Analysis and FSC Design Analysis.

Provide AW 78-24-27 and Center of Contingency Booklet A.

Provide updated draw ing CX009.

Point of contact for this amendment is: Kristina Morrow at kristina.morrow @usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

1 72

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Jul-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912GB-17-R-0020

X 9B. DATED (SEE ITEM 11)

09-May-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Jul-2017

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

KONRAD ADENAUER RING 39

D-65187 WIESBADEN GERMANY

WIESBADEN 65187

W912GB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912GB-17-R-0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIRMENTS

SUMMARY OF CHANGES

SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIRMENTS

The standard size code $15,000,000 has been added.

The required response date/time has changed from 13-Jul-2017 10:00 AM to 16-Jul-

2017 04:00 PM.

The required performance has changed from Project: Various Base Improvements Mihail Kogalniceanu (MK) Air Base, Romania1. Construction Magnitude is between $25,000,000.00 to $100,000,000.002. NAICS Code is 236220 -- Commercial and Institutional Building Construction3. Proposals are due on 13 July 2017 by 10:00 Hours Central European Summer Time (CEST). Proposals shall be received at U.S. Army Corps of Engineers – Europe District, Contracting Division in accordance with solicitation.Contractors are required to submit all questions to Mr. Jefferey Ball via email at Jefferey.A.Ball@usace.army.mil and Mr.

Dean DeFord at Dean.P.DeFord@usace.army.mil and Mr. Robert Corkrum at Robert.E.Corkrum@usace.army.mil. See Section 00 00 00 – Site Visit for specific details required for the Pre-proposal Site Visit/ Briefing. to Project: Various Base Improvements Mihail Kogalniceanu (MK) Air Base, Romania1. Construction Magnitude is between $25,000,000.00 to $100,000,000.002. NAICS Code is 236220 -- Commercial and Institutional Building Construction3. Proposals are due on 16 July 2017 by 16:00 Hours Central European Summer Time (CEST). Proposals shall be received at U.S. Army Corps of Engineers – Europe District, Contracting Division in accordance with solicitation.Contractors are required to submit all questions to Mr. Jefferey Ball via email at Jefferey.A.Ball@usace.army.mil and Mr. Dean DeFord at Dean.P.DeFord@usace.army.mil and Mr. Robert Corkrum at Robert.E.Corkrum@usace.army.mil. See Section 00 00 00 – Site Visit for specific details required for the Pre-proposal Site Visit/ Briefing. .

The following have been modified:

AMENDMENT 01

The purpose of Solicitation Amendment 01 is to change and add the following:

Changes:

1. SF 1442 Block 13A Proposal Due Date is Extended to No Later Than 15:00 Central European Summer Time 15 June 2017.

2. SF 1442 Section 00 21 00 Instructions “Instruction to Offerors” is changed. Changes are identified in red text. Red text with strike through means the text no longer applies. Red text without strike through are additions and hereby applies to this solicitation..

3. SF 1442 Section 00 22 00 Supplementary Instructions “Instruction to Offerors” is changed. Changes are identified in red text. Red text with strike through means the text no longer applies. Red text without strike through are additions and hereby applies to this solicitation.

4. SF 1442 00 10 00 Solicitation Contract Line Item Number Schedule. Contract Line Item Numbers (CLINs) and Sub Contract Line Item Numbers (SCLINs) delivery terms are changed from AFATA (After First Article Test Approval) to ANP (After Notice to Proceed). Delivery Durations remain the same.

Additions:

1. SF 1442 Section 00 21 16 Instructions to Proposers RFI Amendment 01 – Added questions submitted by potential offerors with Government answers and establishes a Request for Information due date.

SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

SUBCLIN 1001AA

The NAICS code has changed from 238990 to 236220.

SUBCLIN 1001BA

SUBCLIN 1001CA

SUBCLIN 1001CB

SUBCLIN 1001CC

SUBCLIN 1001CD

SUBCLIN 1001DA

SUBCLIN 1001DB

SUBCLIN 1001EA

The CLIN extended description has changed from:

Additional Blast/Exhaust Deflector(s) (Design option) -All work, materials, and labor required to design additional Blast/Exhaust Deflector(s) Refer to plan(s) CX002-CX006All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed.

To:

Additional Blast/Exhaust Deflector(s) (Design) -All work, materials, and labor required to design additional Blast/Exhaust Deflector(s) Refer to plan(s) CX002-CX006All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed.

SUBCLIN 1001FA

Enlarge Fixed Wing Parking Apron (Design option): -All work, materials, and labor required to design Fixed Wing Parking Apron Refer to plan(s) CX002-CX006All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed.

Enlarge Fixed Wing Parking Apron (Design): -All work, materials, and labor required to design Fixed Wing Parking Apron Refer to plan(s) CX002-CX006All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed.

SUBCLIN 1002AA

SUBCLIN 1002BA

SUBCLIN 2001AA

SUBCLIN 2001BA

SUBCLIN 2001CA

SUBCLIN 2001CB

Aircraft Fuel Storage Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Storage Facility containing: Aircraft Fuel Storage Tank, Fuel Containment System, 2 Tanks 1.893M Liters / 500.000 Gallon each), and Alt. Fuel Delivery Connection. Including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs and Gutters, Storm Drainage Site Improvement, Information Systems.All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed.

Aircraft Fuel Storage Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Storage Facility containing: Aircraft Fuel Storage Tank, Fuel Containment System, 2 Tanks 1.892M Liters / 499,985 Gallon each), and Alt. Fuel Delivery Connection. Including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs and Gutters, Storm Drainage Site Improvement, Information Systems.All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed.

SUBCLIN 2001CC

SUBCLIN 2001CD

SUBCLIN 2001DA

SUBCLIN 2001DB

SUBCLIN 3001AA

SUBCLIN 3001BA

SUBCLIN 3001CA

SUBCLIN 3001CB

SUBCLIN 3001CC

SUBCLIN 3001CD

SUBCLIN 3001DA

SUBCLIN 3001DB

SUBCLIN 3001DC

SUBCLIN 3001DD

SUBCLIN 3001EA

SUBCLIN 3001EB

SUBCLIN 3001EC

SUBCLIN 3001ED

SUBCLIN 3001FA

SUBCLIN 3001GA

Fencing System for the Staging Marshalling Area (Design option) All work and labor required to design Fencing System for the Staging Marshalling Area at the RailheadAll work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

Fencing System for the Staging Marshalling Area (Design) All work and labor required to design Fencing System for the Staging Marshalling Area at the RailheadAll work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

SUBCLIN 3001HA

Alternative water Connection (Design option): All work and labor required to design Alternative Water Connection to the PFOS.All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

Alternative water Connection (Design): All work and labor required to design Alternative Water Connection to the PFOS.All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

SUBCLIN 3001JA

Backup Generator (Design option): All work and labor required to design Backup Generator for Rail Head, Fueling Area and Cargo Apron.All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

Backup Generator (Design): All work and labor required to design Backup Generator for Rail Head, Fueling Area and Cargo Apron.All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

SUBCLIN 3001KA

Alternative Electrical Utility Connection (Design option): All work and labor required to design alternative electrical utility connection of Transformer Station to existing Electrical Sub Station on PFOS in lieu of the requirement to connect to transformer in base bid. All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

Alternative Electrical Utility Connection (Design): All work and labor required to design alternative electrical utility connection of Transformer Station to existing Electrical Sub Station on PFOS in lieu of the requirement to connect to transformer in base bid. All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

SUBCLIN 3001LA

Enlargement of service lane, movement platform and railway (Design option): All work and labor required to design enlargement of service lane, movement platform and railwayAll work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

Enlargement of service lane, movement platform and railway (Design): All work and labor required to design enlargement of service lane, movement platform and railwayAll work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed.

SUBCLIN 3001MA

SUBCLIN 3002AA

Fencing System for the Staging Marshalling Area at the Railhead (Construction): All work, materials, and labor required to construct Fencing System for the Staging Marshalling Area at the Railhead.The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work.

Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.

Fencing System for the Staging Marshalling Area at the Railhead (Construction): All work, materials, and labor required to construct Fencing System at the Railhead.The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.

SUBCLIN 3002BA

SUBCLIN 3002CA

SUBCLIN 3002DA

SUBCLIN 3002EA

SUBCLIN 1002BB is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

1002BB

Demolition of Existing Structures

FFP

All work, materials, and labor required to remove any existing structures as outlined in the scope of work.

FOB: Destination

NET AMT

CLIN 2002 is added as follows:

OPTION Demolition of Existing Structures

FFP

(Construction) - All work, materials, and labor required to remove any existing structures as outlined in the scope of work.

SUBCLIN 3002EB is added as follows:

3002EB

OPTION Demolition of Existing Structures

FFP

(Construction) - All work, materials, and labor required to remove any existing structures as outlined in the scope of work.

SUBCLIN 3002EC is added as follows:

3002EC

OPTION Relocate two (2) Above Ground Fuel Lines

FFP

All work, materials, and labor required to relocate two (2) above ground existing, active fuel lines as outlined in the scope of work.

SECTION 00 22 16 - SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS

The following have been modified:

REQUEST FOR INFORMATION

REQUEST FOR INFORMATION

Points of Contact:

Primary Contract Specialist: Robert Corkrum Email: robert.e.corkrum@usace.army.mil

PLEASE NOTE: MR. ROBERT CORKRUM SHALL BE INCLUDED ON ALL CORRESPONDENCE

EFFECTIVE 20 JUNE 2017.

Primary Contract Specialist: Jefferey Ball Email: jefferey.a.ball@usace.army.mil

Secondary Contract Specialist: Dean DeFord Email: dean.d.deford@usace.army.mil

Questions shall be submitted no later than 20 June 2017 at 1400hrs Central European Summer Time (CEST).

Questions submitted after this date will be answered at the discretion of the Contracting Officer. For any questions concerning the solicitation or preparation of your proposal, you may contact the Contract Specialist via email at the above email addresses. All questions must be submitted in writing. No questions will be acknowledged or answered verbally.

Request For Information Government Responses Amendment 01:

Q1. GENERAL QUESTION: Of the four technical factors, only Factor 3 Management Approach has a page limitation of 50 pages. Are there page limitations to the other three technical factors: FACTOR 1 EXPERIENCE, FACTOR 2 PAST PERFROMANCE or FACTOR 4 DESIGN CAPABILITY?

A1. In accordance with the solicitation there are no page limitations to technical factors: Factor 1 Experience, Factor 2 Past Performance, and Factor 4 Design Capability. There is a limitation of 50 pages for Factor 3 Management Approach.

Q2. GENERAL QUESTION: Are there any Design or Construction firms which are excluded from participation?

A2. In Accordance with FAR 36.209, the contract will not be awarded to any firm or its subsidiaries or affiliates that prepared the 35% design. Furthermore, award will not be made to any firms that are currently excluded from working with the U.S. Federal Government.

Q3. Paragraph 1.1.1.1.1.1.7 FACTOR 3: MANAGEMENT APPROACH; (page 43 of 161) states: “NOTE:

Maximum allowable page limit for Factor 3 Management Approach is 50 pages. Any additional pages over 50 will not be evaluated by the government.” This paragraph goes on to further require the inclusion of Attachment 4 "Resume Forms" for four (4) identified Specifically Identified Personnel as well as for all key subcontractors signed letters of commitment in this factor.

QUESTION: Do the resume forms and signed letters of commitment count against the 50 page limitation for

MANAGEMENT APPROACH?

A3. Please see Solicitation Amendment 01 SF 1442 Section 00 21 00 Instructions “Instruction to Offerors” under Factor 3 Submission Requirements. The following has been added: “The Organization Chart, Resumes, and Letters of Commitment shall not count towards the 50 page maximum for this Factor.”

Q4. Paragraph 4.1.1.1.3 FACTOR 1: EXPERIENCE: Subparagraph 1 a. (page 50 of 161) states: All projects submitted shall demonstrate work experience performed within Romania or the European Union (EU).

QUESTION: This criteria is overly restrictive and prevents firms with significant US/worldwide DoD/USACE design/build construction management experience from submitting a competitive proposal. It appears this will significantly reduce competition and/or lead to potential proposers' protests? We recommend that this criteria be changed to allow all world-wide DoD/USACE project experience that meets the other criteria requirements.

Subparagraph 4. already states “Projects demonstrating experience in Romania are considered more relevant.” This would seem to appropriately recognize local performance.

A4. Please see Solicitation Amendment 01 SF 1442 Section 00 22 00 Supplementary Instructions “Instruction to Offerors” under Factor 1 Experience. The language has been changed.

Q5. Paragraph 4.1.1.1.3 FACTOR 1: EXPERIENCE: Subparagraph 1. d. (page 51 of 161) states: “Projects consider relevant shall be completed within the last six (6) years from the date of the solicitation or at least 50% complete by the date of the solicitation.” Subparagraph 4. Also states “Projects older than six (6) years may be considered but will be considered less relevant.” Paragraph 4.1.1.1.5 FACTOR 2 : PAST PERFORMANCE states: Past Performance will be evaluated for projects completed in the last five (5) years from the date of the solicitation”

QUESTION: Should the Past Performance statement be "from the last six (6) years before the date of the solicitation" to match the EXPERIENCE statement?

A5. Please see Solicitation Amendment 01 SF 1442 Section 00 22 00 Supplementary Instructions “Instruction to Offerors” under Factor 2 Past Performance. The language has been changed from “…the last six (6) years from the date of this solicitation….” To “…the last five (5) years from the date of this solicitation….”

Q6. Will there be an extension to the due date? Currently, the proposals are due June 9th which is 3 days after the site visit that is schedule on June 6th. The solicitation also requires all questions from the site visit to be submitted in writing. I would like to propose a 4 week extension to the current due date considering the number of questions expected on a RFP of this size, time required for USACE to provide answers/clarifications/updates to the site visit written questions, and the additional time needed for contractors to incorporate those changes/clarifications/updates resulting from the site visit written questions.

When is the cut off to submit RFI’s to USACE on this solicitation?

A6. Please see Amendment 01 SF 1442 Block 13A Proposal Due Date is Extended to no later than 15:00 Central European Summer Time (CEST) 15 June 2017. Please see Solicitation Amendment 01 SF 1442 Section 00 21 16

Instructions to Proposers RFI Amendment 01 – Establishes a Request for Information due date of no later than 08 June 2017 at 1400hrs Central European Summer Time (CEST).

Q7. We will have a rental vehicle for the site visit, so the vehicle details are unknown to complete the Commercial Vehicle Access Form. Will there be transportation options provided by the base/USACE onto MK Airbase for the site visit, or can we submit the Commercial Vehicle Access Form to MK Airbase security on the day of the site visit?

A7. The Commercial Vehicle Access form is not required. Site Visit Attendees will meet at the designated location illustrated on Attachment 7 Camp MK Location provided in the solicitation. Transportation will be provided from the meeting point to the site.

Q8. Solicitation, SF1442, Block 10. Block 10, Item 3, states, “Proposals are due on 09 June 2017 by 15:00 Hours Central European Summer Time (CEST).” However, as the Pre-proposal Site Visit and Briefing is to be held on 06 June 2017 additional time will be needed to fully review the information provided at the site visit and to prepare reasonable technical and cost proposals. Please advise if an extension to the proposal due date can be granted.

A8. Please see Amendment 01 SF 1442 Block 13A Proposal Due Date is Extended to no later than 15:00 Central European Summer Time (CEST) 15 June 2017.

Q9. Is there a deadline for questions and what should we expect as the turn-around time for responses to questions submitted?

A9. Please see Solicitation Amendment 01 SF 1442 Section 00 21 16 Instructions to Proposers RFI Amendment 01

– Establishes a Request for Information due date of no later than 08 June 2017 at 1400hrs Central European Summer Time (CEST).

Q10. Section 00 21 00, 4.1.1.1.3 FACTOR 1: EXPERIENCE, Item 1, paragraph d (page 51), states that projects considered relevant shall be completed within the last six (6) years from the date of the solicitation; 4.1.1.1.5 FACTOR 2: PAST PERFORMANCE (page 53) states that past performance will be evaluated for projects completed in the last five (5) years from the date of the solicitation. Please clarify if relevancy is five years or six as this impacts both Factors 1 and 2.

A10. Please see Solicitation Amendment 01 SF 1442 Section 00 22 00 Supplementary Instructions “Instruction to Offerors” under Factor 2 Past Performance. The language has been changed from “…the last five (5) years from the date of this solicitation….” To “…the last six (6) years from the date of this solicitation….”

Q11. Section 00 21 00, FACTOR 5: PRICE, Item 6 (page 47) states “Executed Bid Bond or Bank Letter of Assurance (to be submitted hard copy, notarized original); and a copy of the agent’s authority to sign bonds/BLA for the surety company shall accompany the bid bond/BLA.” Since submission is to occur via AMRDEC, please provide instructions on submitting the required hard copy of the Bid Bond or Bank Letter of Assurance.

A11. Please see Solicitation Amendment 01 SF 1442 Section 00 21 00 Factor 5: Price Item 6. Line six has been updated to read:

Executed Bid Bond or Bank Letter of Assurance (to be submitted hard copy, notarized original via delivery service to the address below); and a copy of the agent’s authority to sign bonds/BLA for the surety company shall accompany the bid bond/BLA. The Executed Bid Bond or BLA shall also be provided as a copy along with the electronic proposal. The hardcopy must be delivered prior to the proposal due date.

U.S. Army Corps of Engineers, Europe District W912GB-17-R-0020 Attn: Jefferey Ball Konrad Adenauer Ring 39 65187 Wiesbaden

Or

Department of the Army CMR 410 Box 7 Attn: Contracting – Jefferey Ball

APO, AE 09049

Q12. FACTOR 2: PAST PERFORMANCE - Will the USACE consider accepting Past Performance Questionnaires that have been recently completed for previous solicitations?

A12. Yes, this is acceptable provided that the previous Past Performance Questionnaires meets all the requirements stated in the solicitation.

Request For Information Government Responses Amendment 02:

Request for Information

Various Base Improvements Mihail Kogalniceanu Air Base, Romania Amendment 02

Q13. Page 15 of 34 mentions “The DELTA Taxiway should be provided to permit the safe and expeditious surface movement of aircrafts. Thus, the taxiway will have L = 200.00 m W = 22.50m (according to UFC 3-260-01 Airport planning design and B1-SC-85-5 page 40 – width of Taxiway” Drawings (and all calculations) show:

W = 18.00 m Please clarify.

A13. Please refer to article 2.4 CA-2: Fixed Wing Taxiway, 2.4.1 Fixed Wing DELTA Taxiway – Taxiway pavement design input, from Design Analyses document page 17 from 33, where at paragraph 2 has been specified the characteristics of the pavement grades and geometrics that should be in accordance with ETL 97-9, Bi-SC D 85-5, NATO Approved Criteria and Standards for Airfield, meaning that the width of the Taxiway DELTA should be 18m.

Q14. Page 15 of 34 mentions “The site will be cleared and prepared to the point of rough grading by the Romanian government in advance of construction” that means decontaminations too. Do the MOD will provide a report for decontamination?

A14. The SOW states the following, "The Contractor is required to notify of critical issues that may affect the contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, changes in critical personnel, and finding unexploded ordnance (UXO)."

Q15. If the MOD will not provide a report for decontamination, must the contractor to estimate the cost for site investigations and soil contamination report?

A15. The DB contractor must provide an estimate for an environmental and geotechnical survey at the proposed construction sites. This will be part of the design effort and the Host Nation approval process to obtain an Urbanism Certificate.

Q16. Is the area dedicated for construction of the Multimodal Improvement Ready building area (≈14000 m2) cleared and decontaminated?

A16. The area is cleared of unexploded ordinance and graded. No environmental remediation was applied.

Q17. Are there equipped spare cells (switchgears) in the existing 20 kV electrical substations located on TFOS and

PFOS?

A17. There are no spare cells installed in the existing 20 kV network.

Q18. What is the distance from the existing 20 kV electrical substation located on TFOS/PFOS to the new 20/0.4 kV Transformer Station?

A18.Please refer to the General Electrical Installations Layout GE001, W912GB-15-D-0011-0002, 03/04/2017, in the General Notes table is an approximate length of the MV lines from the last manhole in the southwest of the roundabout to ETS1 (approx.. 320m) and to ETS2 (approx. 600m) respectively.

Q19. Should the local norm I7-2011 be used for the grounding system of the Fuel Storage Capacity? I7-2011 has specific requirements for hazardous areas?

A19. Where applicable and not contrary to U.S. norms and standards local norms can be applied. It must be checked which is the more stringent one and required to obtain the Host Nation approval for the Urbanism Certificate.

Q20. In the RFP specification section 01 45 01 Quality Control Part 3.2.1.a states that Construction Quality Control (CQC) system manager reports to the project superintendent. CQC system manager usually reports to an officer in the headquarter office not to a site personnel. Please confirm who CQC will report to.

A20. This is our internal construction spec so the language should be left as stated in the spec. The spec states the CQC manager should report to the superintendent.

Q21. In the Price schedule document, in item 2001CB, it is written that there are 2 Tanks 1,419M Liters / 375.000 Gallon each, whereas in Attachment A-Design Analysis report in FSC part item 2.2.1 Fuel Tanks Storage, fuel tanks are given as 2x1.893M Liters / 500.000 Gallon each. Please confirm the required fuel tank volume.

A21. The capacity of the Fuel Tanks will be 1.893M Liters / 500.000 Gallon each. Please see revised Price Schedule dated 24 May 2017 that is attached with this solicitation amendment 02.

Q22. Section 00 70 00, FAR 52.236-1, states that the Contractor shall perform on the site, and with its own organization, work equivalent to at least 25% of the total amount of work to be performed under the contract. How is the 25% to be calculated? Is it based on the total overall cost of execution (including field office overhead) minus home office overhead, profit and bonding cost?

A22. Contract clause 52.236-1 has been included in the contract to assure adequate interest in and supervision of all work involved in the completion of this project by the Prime contractor. The contracting officer has discretion in calculating the percentage performed by the Prime contractor, however, generally speaking the calculations will be based on the number and value of activities assigned to the Prime contractor in the schedule submissions and updates.

Q23. Section 00 70 00, FAR 52.236-1. This clause states that the Contractor shall perform on the site, and with its own organization, work equivalent to at least 25% of the total amount of work to be performed under the contract.

We interpret "work" to mean physical work activities, involving any of the trades required to directly place the construction required by the contract. It also includes physical activities that directly support the work, such as: (1) warehousing; (2) maintenance of equipment; (3) procurement and transportation of supplies or construction materials to the site for use by the contractor; (4) procuring, transporting and providing equipment for use by the contractor; (5) logistical activities that directly support the contractor's employees; and (6) similar activities. Please confirm our interpretation.

A23. Please see Question 22.

Q24. Section 00 70 00, FAR 52.236-1. This clause states that the Contractor shall perform on the site, and with its own organization, work equivalent to at least 25% of the total amount of work to be performed under the contract.

We interpret "on site" to mean the area within the construction limits depicted or described in the contract drawings or specifications. Activities such as transportation, maintenance and logistics that take place outside of the construction limits depicted or described are still "on the site," if in direct support of activities within the construction limits. Please confirm our interpretation.

A24. This interpretation is correct.

Q25. Section 00 70 00, FAR 52.236-1. This clause states that the Contractor shall perform on the site, and with its own organization, work equivalent to at least 25% of the total amount of work to be performed under the contract.

We interpret "its own organization" to include, consistent with the definition of "contractor" in FAR 44.101, work performed by an affiliate to the prime contractor. Please confirm our interpretation.

A25. The work must be performed by the prime contractor, not an affiliate.

Request For Information Government Responses Amendment 04:

Amendment 04

Q26. Attachment 4 Price Schedule, 08 May 2017; Sub-CLINs 1001EA and 1001FA are both described as Design Options yet the price for these items are totaled in the line item for Total base Line Items Cargo Apron. Please confirm that Sub-CLINs 1001EA and 1001FA are to be totaled as a base line item number even though they are listed as options.

A26. Yes, Sub-CLINs 1001EA and 1001FA are to be totaled as a base line item number. Please see Revised Attachment 4 Price Schedule dated 13 June 2017 attached with this amendment 04.

Q27. Attachment 4 Price Schedule, 08 May 2017; The line item entitled TOTAL OPTIONAL AND BASE LINE ITEMS MULTIMODAL IMPROVEMENTS appears to have an incorrect formula that does not capture the cost of all of the options. Please clarify.

A27. Please see Revised Attachment 4 Price Schedule dated 13 June 2017 attached with this amendment 04.

Formula corrected under line item entitled TOTAL OPTIONAL AND BASE LINE ITEMS MULTIMODAL IMPROVEMENTS or Cell D329.

Q28. RFP Document- A.07.23_W912GB-17-R-0020_Solicitation_9_May_17 (page 33 of 161); ITEM NO 3002 (pg 33 of 161) options the construction of certain Multimodal Improvements. The design for these items is included under 3001 above, and is not optional. Question: If after 120-days from NTP, the option to construct one or more of 3002 items is not exercised, does that mean the design for those items will not be required?

A28. No the design for these items will be required regardless if the option is exercised or not.

Q29. RFP document “A.07.23_W912GB-17-R-0020_Solicitation_9_May_17”, Section 11.2.2, paragraph 4 on page 150; RFP document titled “A.07.23_W912GB-17-R-0020_Solicitation_9_May_17”, Section 11.2.2, paragraph 4 on page 150, states the following: “The contractor shall complete design and construction of Priority 1 and Priority 3 prior to Priority 2 and 4.”

RFP document titled “A.01.38 SOW Attachment A-Design Analysis”, Section 1.2 - Priorities and Phasing, para. 2, states the following: ”The completion of the Railhead and Utilities infrastructure shall have Priority 1. Within the Multimodal Improvements – the design and construction of the utilities and roads and Railhead shall have priority, followed by the Ready Building (Priority 2). The Cargo Apron shall have Priority 3, but it is expected to be completed in approximately the same time as the Ready Building in order to ensure complementary functionality.

The Fueling Area shall be Priority 4, but shall be started as early as possible after completion of the utility and roadwork provided with the Multimodal Improvements project.”

Please clarify the priorities and phasing of the facilities listed in the RFP.

A29. The phasing priorities are as stated in “A.01.38 SOW Attachment A-Design Analysis”

Q30. RFP document “A.07.23_W912GB-17-R-0020_Solicitation_9_May_17”, Section 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE; RFP document titled “A.07.23_W912GB-17-R- 0020_Solicitation_9_May_17”, Section 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE. The CLIN Items 1001, 1002, 2001, 3001, 3002, state the following: “Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.”

RFP document titled “A.07.23_W912GB-17-R-0020_Solicitation_9_May_17”, Section 11.2.2 – Design Submittal, para. 3, pg 150 of 161 states the following:” The Romanian MOD will review both the 65% and 100% design submittals with a review time of 120 calendar days for EACH review.”

Please clarify whether only the 100% design submittals will be reviewed by the Romanian MOD for a period up to 120 days as outlined in the CLIN Items, or both the 65% and 100% design submittals will be reviewed by the Romanian MOD for a period up to 240 days.

A30. Only the 100% design will be reviewed by the Romanians for 120 days.

Q31. Section 00 70 00; Due to time constraints, we have not been able to obtain commitments from subcontractors to attain competition to the maximum practical extent as required by the conditions of the contract reference FAR 52.244-5 Competition In Subcontracting, therefore, it is requested that the proposal due date be extended to 30 June 2017.

A31. Proposal Due Date is extended to 13 July 2017. See this Amendment 04 for details (Note: Proposals due time has also changed from 15:00 hours to 10:00 hours Central European Summer Time).

Q32. An Entrance Gate was shown on the key plans, and it was coded as M1.8, however we could not locate any explanation in the Design Analysis Report and other related documents. Is it only a gate, or will there be an Access Control Facility. More information is required about the gate and suggested control activities.

A32. The proposed gate has to fulfill AT/FP and UFC requirements as outlined in the scope. It is a gate only, not an Access Control Facility. In addition coordination with the Command Safety Officer from the Romanian MOD is needed to ensure site specific operating accessories, warning devices, and safety systems. Gate operation guidance is provided in UFC 4-022-01.

Q33. In paragraph 2.2 of the Design Analysis Report of the Cargo Apron, it states that the site will be cleared and prepared to the point of rough grading by Romanian Government. Under these circumstances the topographical survey works should be conducted after the completion of the clearing and grading works. What is the estimated period of works that will be conducted by the Romanian Government? Their schedule may have an impact on the schedule of the topographical survey, consequently on the design and the construction works.

A33. We are currently working with the local representative to get a schedule for the completion of this work by the Romanian Government. Some site preparation by the Romanians have already been completed.

Q34. On sheets GP003 thru GP005, the sanitary sewer network was shown to run under the road. This solution may lead to future maintenance and traffic flow problems. Is it possible to relocate it to clear the road and run it in native soil after the shoulder?

A34. The design is based on the current site layout and available space. If the relocation of the sewer lines is feasible and in accordance with related UFC and Host Nation requirements, the future D/B Contractor may propose such a modification in the design.

Q35. The suggested roof solution and roof structure of the building may make it hard to get the LEED credits. Is it possible to suggested different systems that would be more convenient for the climate and architectural solutions?

A35. The general concept and the geometry of the roof will not be altered in any way. The only acceptable change for improvement refers to possibly superior insulating materials and their performances, an improved solution/material for the translucent area of the roof (and the associated hatch) as well as the joints and connection details.

Q39. We understand that, as requested by the Design Analysis for the Ready Building, Anti-terrorism and Force Protection (AT/FP) requirements referring to UFC 4-010-01 will be applicable for the curtain wall. Please confirm.

A39. Yes this is correct

Q40. For the new apron and taxiway, Airfield Lighting Vault (ALV) location and SOW requirements are not clear.

ALV would normally require control connections to the existing Air Traffic Control Tower (ATCT) . Please clarify the SOW intent for ALV and interconnection to ATCT.

A40.The proposed tap in point is located at the Ops Building situated at the Helipad. The successful offeror needs to verify the location of the connectivity.

Q41. Electric Utility Connection of this project to an existing MK-FOS 20kV ring system substation would require a 20kV feeder breaker cubicle to be available as spare at the existing substation MV Switchgear Lineup. Please verify the existence of this spare cubicle.

A41. A spare cubicle is not situated at this location.

Q42. For the Ready Building (Drwg A009 and A010): Can we change the structural solution: From: In situ RC foundation pads + steel cross columns with foam in-situ Core to: Precast concrete solution for foundation pad & column, with the similar external dimension for the column and keeping the same structural grid of 10x10m?

A42. The proposed solution is acceptable for the foundation pad (required that all applicable norms are respected), but not for the columns. The columns, beams and other superstructure elements shall be designed and executed according to the tender design released.

Q43. For the Ready Building (Drwg A007)- Can we change the ground laid slab reinforcement: From: Upper and lower reinforcement on both directions as per the drawings To: Steel Fiber Reinforcements. – This is a generally used solution on ground laid concrete slabs in industrial and commercial applications in Romania and Europe.

A43. The solution is acceptable provided that the norms and regulations for floating slabs (with deepened and reinforced perimeters) are respected.

Q44. For the Ready Building – Can we change the structural type of the roof however keeping the same idea and geometry?

A44. The roof structure (concept and geometry) will not be altered excepting for minor adjustments resulting from the detail design process/calculation in order to comply with all norms and regulations in force.

Q45. For the Ready Building - Buried Fire Water Tank together with the pumping station: - Can the Tank be moved to above ground and can they be relocated on the site?

A45. The Fire Tank has been buried due to AT/FP restrictions (set back required from the building, visibility and accessibility constraints etc.) AT/FP requirements described in the UFC regulations are to be followed and the technical solutions must be designed accordingly in order to meet antiterrorism standards for buildings.

Q46. Foam extinguishing is required for Fuel Tank storage and Airplanes. Since a foam system is not in the contract documents can we assume we only provide the water hydrants and tank and foam is provided by firefighting trucks with foaming agents that connect to the hydrants or use their own water reserves?

A46. Firefighting measures are currently provided by the Romanian MoD and the Civilian Airport. An additional foam system is not part of this contract.

Q47. Is it allowed to use precast RC elements for the retention wall (Drwg CX200) of the railway unloading platforms?

A47. Due to the expected weights and dynamics at the loading platform pre-cast elements are not feasible.

Q48. What level (if any) of a LEED certification is required for the Ready Building?

A48. The target is LEED Silver.

Q49. Can we have an alternative heating and cooling solution for the Ready Building – replacing the VRVs (M-drawings) with a different type of system?

A49. The VRV solution has been chosen due to the following:

- It is a compact integrated solution (provides heating and cooling in the same time), not requiring extensive technical space dedicated to it as other solutions are likely to need;

- The electric supply was considered the most viable solution since other potential sourcing (gas/water) is not available.

The VRV solution will therefore be kept.

Q50. Can Performance Bond requirements be changed to 30% of the awarded Contract Amount similar to the BLG percentage amount?

A50. No.

Q51. Can the BLG amount be reduce to 10%? That is usually the maximum percentage for BLGs required in Romania.

A51. No.

Q52. Due to difficulties in obtaining the BLA/Bid Bond a few days before the Proposal Due date in time to mail it to Europe District by the Proposal due date, I request that the BLA/Bid bond be uploaded with the proposal by the due date and the hard copy be received in the USACE Office by 3 business days AFTER the proposal due date.

A52. See Amendment 04 the BLA hardcopy requirement of submitting the no later than proposal due date has been changed to BLA hardcopy must be submitted and received in the government office no later than 5 calendar days after the proposal due date. Furthermore, firms are reminded that they shall also include a digital copy of the BLA in their electronic proposal submission.

Q53. RFP Solicitation page 150 of 161. The RFP states: “The Romanian MOD will review both the 65% and 100% design submittals with a review time of 120 Calendar Days for EACH review.” Should the 100% submittal be the 95% submittal in this sentence? Can the MOD review time be shortened to 45 calendar days?

A53. The Romanians will review at the 100%. Their review will be 120 days.

Q54. Will USACE have site offices located at the laydown area? If so, please clarify the details of the site offices.

A54. As per specification 00 73 15.01 the contractor is to provide trailers for the government.

Q55. Q23 / A23 Section 00 73 00; The Government's response to Q23 states that "work" is defined as labor to meet the 25% performance of work requirement. To maintain compliance with host nation labor regulations and legislation, please clarify if the use of temporary labor agencies providing workers to perform on-site activities, under the direct supervision of the Prime Contractor, qualifies to meet the 25% performance of work requirement.

A55. No.

Q56. Is it possible to mail the hardcopy of the bank letter of assurance at the proposal due date (June 15)? USACE would probably receive the letter next day. We can e-mail the WAYBILL document for proofing.

A56. See RFI Answer 52.

Q57. Since Romania is not a DBA exempt country, will we need to purchase DBA Insurance for every Romanian worker on the construction site, even if they have Romanian Worker’s Insurance through their company.

A57. Yes.

Q58. With the combination of all three projects into one solicitation resulting in an estimated range of $25-$100 million, this presents a bid guarantee / bond difficulty. With a 30% bid guarantee/bond requirement and a maximum $100 million requirement, this means a company must come up with the $30 million bid bond or letter of credit which is very difficult for any company. Since the purpose of a bid guarantee as to ensure either the signing of the resultant contract and receipt of payment and performance bonds, or cover the cost of securing a follow-on contract if the selected proposer is not able to provide the required bonding, it appears that the amount of the bid guarantee could be reduced to the range of 1 to 5% which would still be $1-$5 million and would probably cover any re-solicitation / contract execution costs. Please consider reducing the amount of the bid guarantee from the now stated 30% of the bid price to 1 to 5%?

A58. The BLA and BLG percentages remain unchanged.

Q59. As the actual Site Visit scheduled for the 6th of June was not able to be carried out and potential Offerors were not able to access the Base and observe the site conditions due to circumstances not in the control of the Offerors, will a subsequent Site Visit be scheduled? If so when?

A59. Yes, see solicitation Amendment 03.

Q60. Will the time period for questions be extended in light of the inability to visit the as originally scheduled on June 6th to at least two days following a subsequent scheduled Site Visit?

A60. Yes, see solicitation Amendment 03.

Q61. Will a list of those attempting to visit the site on June 6th and attending the Proposal Conference Meeting that was held at the meeting point be released?

A61. Yes, see solicitation Amendment 03.

Q62. Is experience in Romania considered more relevant than experience in the European Union?

A62. In accordance with the evaluation criteria under Factor 1 Experience Projects demonstrating experience in EU and/or Romania are considered more relevant. These characteristics do impact relevancy; however, in no order of importance.

Q63. If the Bidder is a Joint Venture, the Bank Letter of Assurance/Bid Bond has to be in the name of the JV or can be divided between the partners of the Joint Venture?

A63. It must be in the name of the Joint Venture.

Q64. Section 00 21 00 – INSTRUCTION TO OFFERORS Criteria for evaluation factors 4.1.1.1.3 Factor 1:

Experience

„Projects with minimum cost of €5,000,000 and a maximum cost of €40,000,000.”

Please clarify if each project presented should be within the range of 5,000,000 Euro and 40,000,000 Euro, or all projects together can be in this range?

A64. Each project shall be in the range of €5,000,000.00 and €40,000,000.00.

Q65. According with point 1.1.1.1.1.1.5 Submission Requirements from Factor 2: Past experience : „Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.”

From our understanding, you will consider these reference projects without being necessary to present PPQs previously submitted for other RFPs. Please confirm if our understandig is correct and please clarify how you will evaluate these projects?

A65. All offerors shall submit a PPQ for each project submitted under factor 1 Experience for this solicitation. The Government reserves the right to review PPQs submitted for other solicitations to help with its past performance evaluation.

Q66. Section 00 21 00 – INSTRUCTION TO OFFERORS Factor 3- Management approach, point 1.1.1.1.1.1.9 „Specifically Identified Personnel Submission Requirements: The Offeror is required to provide a Resume Form for the four (4) identified Specifically Identified Personnel, provided as Attachment 4, “Resume Form,” to document the experience of each of their Specifically Identified Personnel.” On the other hand, in Attachment 4 are nine (9) SIP.

Please clarify if we have to present Resume Form (Attachment 4) for all 9 SIP or only for the four identified Specifically Identified Personnel.

A66. In accordance with the solicitation the offeror is required to submit attachment 5 resume forms for the four identified Specifically Identified Personnel.

Q67. Due to the fact that this procedure is for a design and build project…