| BASE LINE ITEMS CARGO APRON (CA) MK AIR BASE ROMANIA | | | |
| Line Item | Description | Unit | Amount |
| 1001 | Cargo Apron (CA) MK Air Base, Romania Base Line Items | Job | BLANK |
Base Line Items: The following base line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
| Liquidated Damages: Liquidated damages shall be assessed in the amount of €3.166,00 per calendar day of delay beyond the required completion date of the contract. | |
| 1001AA | A/E-provided Service: All work and labor required to provide a Geotechnical Survey for the project site. | € |
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| Total: | 0.00 € |
1001BA A/E-provided Service: All work and labor required to provide a Topographical Survey for the project site. €
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| Total: | 0.00 € |
1001CA Fixed Wing Parking Apron, Fixed Wing Taxiway, and Blast/Exhaust Deflector (Design): All work and labor required to design Fixed Wing Parking Apron, Fixed Wing Taxiway and Blast/Exhaust Deflector. €
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| 1001CB | Fixed Wing Parking Apron (Construction): All work, materials, and labor required to construct Fixed Wing Parking Apron containing: Hardscape, Drainage, Base Courses, Shoulders, Marking, Grounding / Mooring, and Lighting. Including supporting facilities: Electric Service, Storm Drainage, and Site Improvement Refer to plan(s) C002-C006 | € |
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| 1001CC | Fixed Wing Taxiway (Construction): All work, materials, and labor required to construct Fixed Wing Taxiway including supporting facilities: Hardscape, Drainage, Base Courses, Shoulders, Marking, and Lighting. Including supporting facilities: Electric Service, Storm Drainage, Site Improvement. | € |
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| 1001CD | Blast/Exhaust Deflector (Construction): All work, materials, and labor required to construct Blast/Exhaust Deflector. Refer to plan(s) C002-C006 | € |
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| Total: | 0.00 € |
1001DA Airfield Lighting Vault (ALV) (Design): All work and labor required to design Airfield Lighting Vault (ALV). €
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| 1001DB | Airfield Lighting Vault (ALV) (Construction): All work, materials, and labor required to construct Airfield Lighting Vault (ALV), including: Electric Service. | € |
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| Total: | 0.00 € |
1001EA Additional Blast/Exhaust Deflector(s) (Design option) -All work, materials, and labor required to design additional Blast/Exhaust Deflector(s) Refer to plan(s) CX002-CX006 €
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| Total: | 0.00 € |
1001FA Enlarge Fixed Wing Parking Apron (Design option): -All work, materials, and labor required to design Fixed Wing Parking Apron Refer to plan(s) CX002-CX006 €
| All work on this base line item shall be completed within 780 calendar days from the date of the Notice to Proceed. | |
| Total: | 0.00 € |
Total Base Line Items Cargo Apron: 0.00 €
| OPTIONAL LINE ITEMS CARGO APRON (CA) MK AIR BASE, ROMANIA | | | |
| Line Item | Description | Unit | Amount |
| 1002 | Cargo Apron (CA) MK Air Base, Romania Optional Line Items | | BLANK |
Optional Line Items: The following optional line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government reserves the right to award any options within 120 calendar days following issuance of Notice to Proceed (NTP) for the base work. If an option is exercised, it must be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €3.166,00 per calendar day of delay beyond the required completion date of the contract.
| 1002AA | Additional Blast/Exhaust Deflector(s) (Construction) -All work, materials, and labor required to construct | € |
| OPTION | additional Blast/Exhaust Deflector(s) Refer to plan(s) CX002-CX006 | |
| Should the Government exercise this optional line item all work shall be completed within 780 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
| 1002BA | Enlarge Fixed Wing Parking Apron (Construction): -All work, materials, and labor required to construct Fixed Wing Parking Apron Refer to plan(s) CX002-CX006 | € |
| OPTION | | |
| Should the Government exercise this optional line item all work shall be completed within 780 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total | 0.00 € |
| Total Optional Line Items Cargo Apron: | 0.00 € |
| Total Optional & Base Line Items Cargo Apron: | 0.00 € |
| BASE LINE ITEMS FUEL STORAGE CAPACITY (FSC) MK AIR BASE ROMANIA | | | |
| Line Item | Description | | Amount |
| 2001 | Fuel Storage Capacity (FSC) MK Air Base Romania Base Line Items | Job | BLANK |
Base Line Items: The following base line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €3.166,00 per calendar day of delay beyond the required completion date of the contract.
2001AA A/E-provided Service: All work and labor required to provide a Geotechnical Survey for the project site. €
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
2001BA A/E-provided Service: All work and labor required to provide a Topographical Survey for the project site. €
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
2001CA Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area (Design): All work and labor required to design Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area. €
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001CB | *Aircraft Fuel Storage Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Storage Facility containing: Aircraft Fuel Storage Tank, | € |
| Fuel Containment System, 2 Tanks 1.892M Liters / 499,985 Gallon each), and Alt. Fuel Delivery Connection. | |
| Including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs and Gutters, Storm Drainage | |
| Site Improvement, Information Systems. | |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001CC | Aircraft Fuel Truck Loading Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Truck Loading Facility containing: Distribution Piping, Pipe Bollards including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs and Gutters, Storm Drainage, Site Improvement, Information Systems. | € |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001CD | Fuel Truck Parking Area (Construction) All work, materials, and labor required to construct Fuel Truck Parking Area including supporting facilities: Water, Sewer | € |
| Paving, Walks, Curbs and Gutters, Storm Drainage, and | |
| Site Improvement. | |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
2001DA Fueling/POL, Support Building (Design): All work and labor required to design Fueling/POL, Support Building. €
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001DB | Fueling/POL,Support Building (Construction): All work, materials, and labor required to construct Fueling / POL, Support Building including supporting facilities: Vapor Barrier, Electric Service, Water, Sewer, Storm Drainage, and Information Systems. | € |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
Total Base Line Items Fuel Storage Capacity: 0.00 €
| BASE LINE ITEMS MULTIMODAL IMPROVEMENTS (MI) MK AIR BASE, ROMANIA | | |
| CLIN | | Amount |
| 3001 | Multimodal Improvements (MI) MK Air Base, Romania Base Line Items | BLANK |
Base Line Items: The following base line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €3.166,00 per calendar day of delay beyond the required completion date of the contract.
3001AA A/E-provided Service: All work and labor required to provide a Geotechnical Survey for the project site. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
3001BA A/E-provided Service: All work and labor required to provide a Topographical Survey for the project site. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
3001CA Site Roads, Utilities and Transformer Station (Design): All work and labor required to design Site Roads, utilities and and transformer station and connection to existing Substation on the TFOS €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001CB | Site Roads, Streets and Walkways (Construction): All work, materials, and labor required to construct Site Roads including: Paving, Walks, Curbs, and Gutter, and Site Improvement. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001CC | Site Utilities (Construction): All work, materials, and labor required to construct Site Utilities including: Electric Service, Water, Sewer, Storm Drainage, and Information Systems. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001CD | Transformer Station and Connection to existing Substation | € |
| on the TFOS (Construction): All work, materials, and labor required to construct Transformer Station including: | |
| Electric Service. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001DA | Rail load /off-load facility (Railhead), Vehicle Wash | € |
| Facility and Entrance Gate, (Design): All work and labor required to design Railhead and Vehicle Wash Facility. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001DB | Rail load /off-load facility Railhead (Construction): All work, materials, and labor required to construct Railhead containing: RR Tracks w/Ties and Ballast, Railhead Apron/Service Lane, Concrete Hardstand, Loading/Unloading Dock/Ramp, At-Grade Rail Crossing, and Rail Switch.ncluding supporting facilities: Electric Service, Water, Sewer, Storm Drainage, Site Improvement, and Information Systems. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001DC | Entrance Gate (Construction) All work, materials, and labor required to construct Entrance Gate including supporting facilities: Electric Service, Site Improvement, and Information Systems. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001DD | Vehicle Wash Facility (Construction) All work, materials, and labor required to construct Vehicle Wash Facility containing of: Vehicle Wash Facility, Wash Support Building, Wash Support Bldg. Vapor Barrier, Wash Facility Apron, Gravity Oil/Grease Sep., and Water and Grit Separator | € |
| Including supporting facilities: Electric Service, Water, Sewer, and Storm Drainage. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001EA | Ready Building (Design): All work and labor required to design one building (referred to as the Ready Building) containing all functions of: | € |
| -Ready Building-A/DACG with Overhead Protection | |
| -Shipping and Receiving and Cargo Operations Building | |
| -Overhead Protection, Pallet Area | |
| -Staging Marshalling Area | |
| and an exterior: | |
| -Open Storage Area, Installation and Generator Station | |
All work on this base line item shall be completed within 1050 calendar days from the date of the issuance of the Notice to Proceed.
| 3001EB | Ready Building (Construction): All work, materials, and labor required to construct one building containing all functions of: | € |
| -Ready Building-A/DACG with Overhead Protection | |
| -Shipping and Receiving and Cargo Operations Building | |
| -Overhead Protection, Pallet Area | |
| including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs, and Gutter, Storm Drainage, | |
| Site Improvement, Information Systems. | |
| All work on this base line item shall be completed within 1050 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001EC | Open Storage Area, Installation (Construction): All work, materials, and labor required to construct Open | € |
| Storage Area, Installation, including supporting facilities: Storm Drainage. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001ED | Staging Marshalling Area (Construction): All work, materials, and labor required to construct a staging marshalling area | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
3001FA A/E-provided Service: All work and labor required to provide LEED Services for the Ready Building (Enhanced Commissioning) €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
3001GA Fencing System for the Staging Marshalling Area (Design option) All work and labor required to design Fencing System for the Staging Marshalling Area at the Railhead €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
3001HA Alternative water Connection (Design option): All work and labor required to design Alternative Water Connection to the PFOS. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
3001JA Backup Generator (Design option): All work and labor required to design Backup Generator for Rail Head, Fueling Area and Cargo Apron. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
3001KA Alternative Electrical Utility Connection (Design option): All work and labor required to design alternative electrical utility connection of Transformer Station to existing Electrical Sub Station on PFOS in lieu of the requirement to connect to transformer in base bid. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
3001LA Enlargement of service lane, movement platform and railway (Design option): All work and labor required to design enlargement of service lane, movement platform and railway €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
| 3001MA | A/E provided Service (LEED Services): All work and labor required to provide LEED Services for the Ready Building | € |
| (v4 Base Services in Design and Construction Phases incl. | |
| Pre Assessment, Energy Modeling, Fundamental | |
| Commissioning, Fees, etc.) | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
Total Base Line Items Multimodal Improvements: 0.00 €
| OPTIONAL LINE ITEMS MULTIMODAL IMPROVEMENTS (MI) MK AIR BASE ROMANIA | | |
| CLIN | Description | Amount |
| 3002 | Multimodal Improvements (MI) MK Air Base, Romania Optional Line Items | BLANK |
Optional Line Items: The following optional line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government reserves the right to award any options within 120 calendar days following issuance of Notice to Proceed (NTP) for the base work. If an option is exercised, it must be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €3.166,00 per calendar day of delay beyond the required completion date of the contract.
| 3002AA OPTION | Fencing System for the Staging Marshalling Area at the | € |
| Railhead (Construction): All work, materials, and labor required to construct Fencing System for the Staging Marshalling Area at the Railhead. | |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
3002BA OPTION Alternative Water Connection (Construction) All work, materials, and labor required to construct Alternative Water Connection to the PFOS. Refer to plan GE001. €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
3002CA OPTION Backup Generator (Construction) All work, materials, and labor required to provide Backup Generator Station for Rail Head, Fueling Area and Cargo Apron. €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
| 3002DA OPTION | Alternative Electrical Utility Connection (Construction): All work, materials, and labor required to construct | € |
| alternative electrical utility connection of Transformer | |
| Station to existing Electrical Sub Station on PFOS in lieu of the requirement to connect to transformer in base bid. Refer to plan GE001. | |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
| 3002EA | Enlargement of service lane, movement platform and railway (Construction): All work and labor required to construction enlargement of service lane, movement platform and railway | € |
| OPTION | | |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
| Total Optional Line Items Multimodal Improvements: | 0.00 € |
| Total Optional & Base Line Items Multimodal Improvements: | 0.00 € |
| Total Contract All Base Line Items: | 0.00 € |
| Total Contract All Optional Line Items | 0.00 € |
| Total Contract All Base and Optional Line Items: | 0.00 € |
PRICE SCHEDULE
FY15 European Reassurance Initiative (ERI) Various Base Improvements: Multi Modal Improvements, Cargo Apron and Fuel Storage Capacity Mihail Kogalniceanu Air Base, Romania
14 April 2017 Revised 24 May 2017
Line Items: The following Line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government reserves the right to award any options within 120 calendar days following issuance of Notice to Proceed (NTP) for the base work. If an option is exercised, it must be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed.
Cargo Apron (CA) MK Air Base, Romania Fuel Storage Capacity (FSC) MK Air Base Romania (see CLIN 2001CB) Multimodal Improvements (MI) MK Air Base, Romania
Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €3.166,00 per calendar day of delay beyond the required completion date of the contract.