Section 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
CLIN Deleted
FFP
CLIN Deleted
NET AMT
1001AA 1
SCLIN Deleted - Do Not Price
FFP
SCLIN Deleted - Do Not Price FOB: Destination
1001BA 1
SCLIN Deleted - Do Not Price
FFP
1001CA 1
SCLIN Deleted - Do Not Price
FFP
1001CB 1
SCLIN Deleted - Do Not Price
FFP
1001CC 1
SCLIN Deleted - Do Not Price
FFP
1001CD 1
SCLIN Deleted - Do Not Price
FFP
1001DA 1
SCLIN Deleted - Do Not Price
FFP
1001DB 1
SCLIN Deleted - Do Not Price
FFP
1001EA 1
SCLIN Deleted - Do Not Price
FFP
1001FA 1
SCLIN Deleted - Do Not Price
FFP
CLIN Deleted
FFP
CLIN Deleted
1002AA 1
SCLIN Deleted - Do Not Price
FFP
1002BA 1
SCLIN Deleted - Do Not Price
FFP
1002BB
SCLIN Deleted - Do Not Price
FFP
Base Items Fuel Storage Capacity
FFP
Fuel Storage Capacity (FSC) MK Air Base Romania Base Line Items
NOTE: For all line items listed below, the Contractor shall refer to the "Summary of Scope RevisionsExplanation of Variances" and revised drawings which illustrate the changes between the initial project design and the reduced scope quantities.
Base Line Items: The following Line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €849.00 per calendar day of delay beyond the required completion date of the contract.
2001AA 1 Job SCLIN Deleted - Do Not Price
FFP
2001BA 1 Job SCLIN Deleted - Do Not Price
FFP
2001CA 1 Job Aircraft Fuel Storage Facility Design
FFP
Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area (Design): All work and labor required to design Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area, including all work and labor required to complete Geotechnical Survey and Topographical Survey. This only includes the revisions for the Base design items as clarified in the "Explanation of Variances" and drawing FSC 001 for the Fuel Storage Capacity.
All work on this base line item shall be completed within 430 calendar days from the date of the issuance of the Notice to Proceed.
2001CB 1 Job Aircraft Fuel Storage Fac (Construction)
FFP
Aircraft Fuel Storage Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Storage Facility containing: Aircraft Fuel Storage Tank, Fuel Containment System, 2 Tanks at +/- .945M Liters (+/- 250,000 gallons), and Alt. Fuel Delivery Connection. Including supporting facilities:
Electric Service, Water, Sewer, Paving, Walks, Curbs and Gutters, Storm Drainage Site Improvement, Information Systems. This includes the revisions for the Base design items as clarified in the "Explanation of Variances" and drawing FSC 001 for the Fuel Storage Capacity.
All work on this base line item shall be completed within 1090 calendar days from
2001CC 1 Job Aircraft Fuel Truck LoadFac Construction
FFP
Aircraft Fuel Truck Loading Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Truck Loading Facility containing: Distribution Piping, Pipe Bollards including supporting facilities and all utilities. This includes the revisions for the Base design items as clarified in the "Explanation of Variances" and drawing FSC 001 for the Fuel Storage Capacity.
All work on this base line item shall be completed within 1090 calendar days from
2001CD 1 Job Fuel Truck Parking Area (Construction)
FFP
Fuel Truck Parking Area (Construction) All work, materials, and labor required to construct Fuel Truck Parking Area with 12 spaces including supporting facilities:
Water, Sewer Paving, Walks, Curbs and Gutters, Storm Drainage, and Site Improvement. This includes the revisions for the Base design items as clarified in the "Explanation of Variances" and drawing FSC 001 for the Fuel Storage Capacity. All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed.
2001DA 1 Job Fueling/POL, Support Building (Design)
FFP
Fueling/POL, Support Building (Design): All work and labor required to design Fueling/POL, Support Building.
All work on this base line item shall be completed within 430 calendar days from
2001DB 1 Job Fueling/POL,Support Bldg (Construction)
FFP
Fueling/POL,Support Building (Construction): All work, materials, and labor required to construct Fueling / POL, Support Building including supporting facilities: Vapor Barrier, Electric Service, Water, Sewer, Storm Drainage, and Information Systems.
All work on this base line item shall be completed within 1090 calendar days from
Option Items FSC MK Air Base
FFP
NOTE: For all line items listed below, the Contractor shall refer to the "Summary of Scope RevisionsExplanation of Variances" and revised drawings which illustrate the changes between the initial project design and the reduced scope quantities.
Option Items: The following Line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government will award any options at the time of award of the base work. If an option is exercised, it must also be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of
2002AA
OPTION Deleted Do Not Price
FFP
Deleted Do Not Price
2002BA
OPTION Demolition (Design/Construction)
FFP
Demolition of Existing Structures(Design & Construction)-All work, materials and labor required to remove any existing structures as outline in Scope of Work. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 500 calendar days from the date of the issuance of the Notice to Proceed for the base items.
2002CA
OPTION 1 add tank at +/- 250,000g Design/Constr
FFP
One (1) additional tank at +/- 250,000 gallons each (Design & Construction) - All work, materials and labor required to furnish and install an additional tank with approximatley 250,000 gallon capacity, bringing the overall storage capacity of the project to three (3) 250,000 gallon tanks, or approximately 750,000 gallons total as described in the Summary of Scope Revisions document and drawing FSC X001.
Should the Government exercise this optional line item all work shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed for the base items.
2002DA
OPTION 1 add tank at +/- 250,000g Design/Constr
FFP
One (1) additional tank at +/- 250,000 gallons each (Design & Construction) - All work, materials and labor required to furnish and install an additional tank with approximatley 250,000 gallon capacity, bringing the overall storage capacity of the project to four (4) 250,000 gallon tanks, or approximately 1,000,000 gallons total as described in the Summary of Scope Revisions document and drawing FSC X002. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed for the base items.
Base Items Mutimodal Improvements
FFP
Multimodal Improvements (MI) MK Air Base, Romania Base Line Items
NOTE: For all line items listed below, the Contractor shall refer to the "Summary of Scope RevisionsExplanation of Variances" and revised drawings which illustrate the changes between the initial project design and the reduced scope quantities.
Base Line Items: The following Line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of
3001AA 1 Job Deleted Do Not Price
FFP
3001BA 1 Job Deleted Do Not Price
FFP
3001CA 1 Job Site Roads Utilities Transformer Design
FFP
Site Roads, Utilities and Transformer Station (Design): All work and labor required to design Site Roads, utilities and and transformer station and electrical connections as described in drawing MI GE 001, including all work and labor required to complete Geotechnical Survey and Topographical Survey.
All work on this base line item shall be completed within 330 calendar days from
3001CB 1 Job Site Roads Streets Walkways Construction
FFP
Site Roads, Streets and Walkways (Construction): All work, materials, and labor required to construct Site Roads including: Paving, Walks, Curbs, and Gutter, and Site Improvement. The road will consist of three layers: aggregate subbase courses, Portland cement-stabilized base courses and aggregate base courses (crushed and compacted stone, best mix) as described for the base in "Summary of Scope Revisions" for the Multi Modal Improvements.
All work on this base line item shall be completed within 810 calendar days from
3001CC 1 Job Site Utilities (Construction)
FFP
Site Utilities (Construction): All work, materials, and labor required to construct Site Utilities including: Electric Service, Water, Sewer, Storm Drainage, and Information Systems as described in the Summary of Scope Revisions and drawing
MI GE 001.
All work on this base line item shall be completed within 810 calendar days from
3001CD 1 Job SCLIN Deleted - Do Not Price
FFP
3001DA 1 Job RLOLF, VWF, EG (Design)
FFP
Rail load /off-load facility (Railhead), Vehicle Wash Facility and Entrance Gate, (Design): All work and labor required to design Railhead and Vehicle Wash Facility.
All work on this base line item shall be completed within 330 calendar days from
3001DB 1 Job Rail load /off-load fac Construction
FFP
Rail load /off-load facility Railhead (Construction): All work, materials, and labor required to construct Railhead containing: RR Tracks w/Ties and Ballast, Railhead Apron/Service Lane, Concrete Hardstand, Loading/Unloading Dock/Ramp, At- Grade Rail Crossing, and Rail Switch.ncluding supporting facilities: Electric Service, Water, Sewer, Storm Drainage, Site Improvement, and Information Systems.
All work on this base line item shall be completed within 810 calendar days from
3001DC 1 Job Entrance Gate (Construction)
FFP
Entrance Gate (Construction) All work, materials, and labor required to construct Entrance Gate including supporting facilities: Electric Service, Site Improvement, and Information Systems.
All work on this base line item shall be completed within 810 calendar days from
3001DD 1 Job Vehicle Wash Facility (Construction)
FFP
Vehicle Wash Facility (Construction) All work, materials, and labor required to construct Vehicle Wash Facility containing of: Vehicle Wash Facility, Wash Support Building, Wash Support Bldg. Vapor Barrier, Wash Facility Apron, Gravity Oil/Grease Sep., and Water and Grit Separator Including supporting facilities: Electric Service, Water, Sewer, and Storm Drainage.
All work on this base line item shall be completed within 810 calendar days from
3001EA 1 Job Ready Building (Design)
FFP
Ready Building (Design): All work and labor required to design one building (referred to as the Ready Building) containing all functions of: -Ready Building- A/DACG with Overhead Protection -Shipping and Receiving and Cargo Operations Building -Overhead Protection, Pallet Area -Staging Marshalling Area and an exterior: -Open Storage Area, Installation and Generator Station Reference drawings MI RB 001, MI RB X001 and MI RB X002 for clarifications.
All work on this base line item shall be completed within 390 calendar days from
3001EB 1 Job Ready Building (Construction)
FFP
Ready Building (Construction): All work, materials, and labor required to construct one building containing all functions of:
-Ready Building-A/DACG with Overhead Protection -Shipping and Receiving and Cargo Operations Building -Overhead Protection, Pallet Area including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs, and Gutter, Storm Drainage, Site Improvement, Information Systems.
All work on this base line item shall be completed within 1050 calendar days from
3001EC 1 Job Open Storage Area Install (Construction)
FFP
Open Storage Area, Installation (Construction): All work, materials, and labor required to construct Open Storage Area, Installation, including supporting facilities: Storm Drainage. Site Improvement, Information Systems. Reference drawing MI RB 001 for clarification.
All work on this base line item shall be completed within 810 calendar days from
3001ED 1 Job Staging Marshalling Area (Construction)
FFP
Staging Marshalling Area (Construction): All work, materials, and labor required to construct a staging marshalling area Reference drawing MI RB 001 for clarification.
All work on this base line item shall be completed within 810 calendar days from
3001FA 1 Job SCLIN Deleted - Do Not Price
FFP
3001GA 1 Job SCLIN Deleted - Do Not Price
FFP
3001HA 1 Job SCLIN Deleted - Do Not Price
FFP
3001JA 1 Job A/E provided Service (LEED Services)
FFP
A/E provided Service (LEED Services): All work and labor required to provide LEED Services for the Ready Building (v4 Base Services in Design and Construction Phases incl. Pre Assessment, Energy Modeling, Fundamental Commissioning, Fees, etc.)
All work on this base line item shall be completed within 1050 calendar days from
3001KA 1 Job SCLIN Deleted - Do Not Price
FFP
3001LA 1 Job SCLIN Deleted - Do Not Price
FFP
3001MA 1 Job SCLIN Deleted - Do Not Price
FFP
Option Items Multimodal Improvements
FFP
Multimodal Improvements (MI) MK Air Base, Romania Optional Line Items
NOTE: For all line items listed below, the Contractor shall refer to the "Summary of Scope RevisionsExplanation of Variances" and revised drawings which illustrate the changes between the initial project design and the reduced scope quantities.
Option Items: The following Line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government will award any options at the time of award of the base work. If an option is exercised, it must also be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of
3002AA 1 Job OPTION Fencing (Design/Construction)
FFP
FFencing System to include entrance gate Around the Concrete Hardstand at the Railhead (Design AND Construction): All work, materials, and labor required to design and construct a Fencing System to include entrance gate Around the Concrete Hardstand. Refer to drawing CX007.
The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.
3002BA 1 Job OPTION Alt water Connect (Design/Construction)
FFP
Alternative Water Connection (Design AND Construction) All work, materials, and labor required to design and construct Alternative Water Connection to the PFOS. Refer to plan GE001.
The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base
3002CA 1 Job OPTION Backup Generator (Design/Construction)
FFP
Backup Generator (Design & Construction): All work and labor required to design 1 diesel generator of 500kVA for the ready building
The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base
3002DA 1 Job SCLIN Deleted - Do Not Price
FFP
3002EA 1 Job OPTION Enlargement service lane Design/Construc
FFP
Enlargement of service lane, movement platform and railway (Design & Construction): All work and labor required to design and construct enlargement of service lane, movement platform and railway
The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base
3002EB
OPTION Demolition Structures (Design/Constructi
FFP
Demolition of Existing Structures(Design & Construction)-All work, materials and labor required to remove any existing structures as outlined in Scope of Work. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 500 calendar
3002EC
OPTION Relocate 2 Fuel Lines (Design/Constructi
FFP
Relocating two above ground active fuel lines(Design & Construction)- All work, materials and labor rwquired to remove any two above ground existing active fuel lines as outlined in the Scope of Work. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.
3002ED
OPTION Electr connect ETS1(Design/Construction)
FFP
Electrical connection to ETS1(Design & Construction): All work, material and labor of the electrical connection for the Railhead Area in the manhole south of the Fuel Storage Capacity project to ETS1 and the electrical connection of the NTS to ETS1. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar
3002EE
OPTION Electr connect ETS2 (Design/Construction
FFP
Electrical connection to ETS2 (Design & Construction): All work, material and labor of the electrical connection for the Railhead Area in the manhole south of the Fuel Storage Capacity project to ETS2 and the electrical connection of the NTS to ETS1. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.
3002EF
OPTION A/E-provided Service
FFP
A/E-provided Service: All work and labor required to provide LEED Services for the Ready Building (Enhanced Commissioning) The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
3002EG
OPTION Add Rows 4 Umbrellas Design/Construction
FFP
Additional Row of Four Umbrellas (Design and Construction): All work, material and labor required to add one additional row of four (4) umbrellas to the South Side of the Ready Building (400 additional sqm). The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
3002EH
OPTION Two Additional Row of Four Umbrellas (De.
FFP
Two Additional Row of Four Umbrellas (Design and Construction): All work, material and labor required to add two additional rows of four (4) umbrellas each to the South Side of the Ready Building (800 additional sqm) The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items.
3002EJ
OPTION Concrete Pave Finish Design/Construction
FFP
Concrete Pavement Finish (Design and Construction): All work, material and labor required provide a fully paved, concrete finished access road. The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar