| BASE LINE ITEMS FUEL STORAGE CAPACITY (FSC) MK AIR BASE ROMANIA | | | |
| Line Item | Description | | Amount |
| 2001 | Fuel Storage Capacity (FSC) MK Air Base Romania Base Line Items | Job | BLANK |
Base Line Items: The following base line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €849.00 per calendar day of delay beyond the required completion date of the contract.
2001CA Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area (Design): All work and labor required to design Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area, including all work and labor required to complete Geotechnical Survey and Topographical Survey. This includes the revisions for both only the Base design items as clarified in the "Explanation of Variances" and drawing FSC 001 for the Fuel Storage Capacity. €
| All work on this base line item shall be completed within 310 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001CB | *Aircraft Fuel Storage Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Storage Facility containing: Aircraft Fuel Storage Tank, | € |
| Fuel Containment System, 2 Tanks at +/- .945M Liters (+/- 250,000 gallons), and Alt. Fuel Delivery Connection. | |
| Including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs and Gutters, Storm Drainage | |
| Site Improvement, Information Systems. | |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001CC | Aircraft Fuel Truck Loading Facility (Construction): All work, materials, and labor required to construct Aircraft Fuel Truck Loading Facility containing: Distribution Piping, Pipe Bollards including supporting facilities and all utilities. | € |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001CD | Fuel Truck Parking Area (Construction) All work, materials, and labor required to construct Fuel Truck Parking Area with 12 spaces including supporting facilities: Water, Sewer | € |
| Paving, Walks, Curbs and Gutters, Storm Drainage, and | |
| Site Improvement. | |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
2001DA Fueling/POL, Support Building (Design): All work and labor required to design Fueling/POL, Support Building. €
| All work on this base line item shall be completed within 310 calendar days from the date of the issuance of the Notice to Proceed. | |
| 2001DB | Fueling/POL,Support Building (Construction): All work, materials, and labor required to construct Fueling / POL, Support Building including supporting facilities: Vapor Barrier, Electric Service, Water, Sewer, Storm Drainage, and Information Systems. | € |
| All work on this base line item shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| Total Base Line Items Fuel Storage Capacity: | 0.00 € |
| OPTIONAL LINE ITEMS FUEL STORAGE CAPACITY (FSC) MK AIR BASE ROMANIA | | |
| Line Item | Description | Amount |
| Fuel Storage Capacity MK Air Base, Romania Optional Line Items | |
Optional Line Items: The following optional line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government reserves the right to award any options within 120 calendar days following issuance of Notice to Proceed (NTP) for the base work. If an option is exercised, it must be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €849.00 per calendar day of delay beyond the required completion date of the contract.
| 2002AA OPTION | Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area (Design & Construction): All work and labor required to design and construct Aircraft Fuel Storage Facility, Aircraft Fuel Truck Loading Facility, and Fuel Truck Parking Area, including all work and labor required to complete Geotechnical Survey and Topographical Survey. This includes the revisions for both only the Base design items as clarified in the "Explanation of Variances" and drawing FSC 001 for the Fuel Storage Capacity. | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total | 0.00 € |
| 2002BA OPTION | Demolition of Existing Structures(Design & Construction)-All work, materials and labor required to remove any existing structures as outline in Scope of Work | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 500 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total | 0.00 € |
| 2002CA OPTION | One (1) additional tank at +/- 250,000 gallons each (Design & Construction) - All work, materials and labor required to furnish and install an additional tank with approximatley 250,000 gallon capacity, bringing the overall storage capacity of the project to three (3) 250,000 gallon tanks, or approximately 750,000 gallons total as described in the Summary of Scope Revisions document and drawing FSC X001. | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total | 0.00 € |
| 2002DA OPTION | One (1) additional tank at +/- 250,000 gallons each (Design & Construction) - All work, materials and labor required to furnish and install an additional tank with approximatley 250,000 gallon capacity, bringing the overall storage capacity of the project to four (4) 250,000 gallon tanks, or approximately 1,000,000 gallons total as described in the Summary of Scope Revisions document and drawing FSC X002. | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 1090 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total | 0.00 € |
| Total Optional Line Items Cargo Apron: | 0.00 € |
| Total Optional & Base Line Items Cargo Apron: | 0.00 € |
| BASE LINE ITEMS MULTIMODAL IMPROVEMENTS (MI) MK AIR BASE, ROMANIA | | |
| CLIN | | Amount |
| 3001 | Multimodal Improvements (MI) MK Air Base, Romania Base Line Items | BLANK |
Base Line Items: The following base line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €849.00 per calendar day of delay beyond the required completion date of the contract.
3001AA A/E-provided Service: All work and labor required to provide a Geotechnical Survey for the project site. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
3001BA A/E-provided Service: All work and labor required to provide a Topographical Survey for the project site. €
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
3001CA Site Roads, Utilities and Transformer Station (Design): All work and labor required to design Site Roads, utilities and and transformer station and electrical connections as described in drawing MI GE 001, including all work and labor required to complete Geotechnical Survey and Topographical Survey. €
| All work on this base line item shall be completed within 210 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001CB | Site Roads, Streets and Walkways (Construction): All work, materials, and labor required to construct Site Roads including: Paving, Walks, Curbs, and Gutter, and Site Improvement. The road will consist of three layers: aggregate subbase courses, Portland cement-stabilized base courses and aggregate base courses (crushed and compacted stone, best mix) as described for the base in "Summary of Scope Revisions" for the Multi Modal Improvements. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001CC | Site Utilities (Construction): All work, materials, and labor required to construct Site Utilities including: Electric Service, Water, Sewer, Storm Drainage, and Information Systems as described in the Summary of Scope Revisions and drawing MI GE 001. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001DA | Rail load /off-load facility (Railhead), Vehicle Wash | € |
| Facility and Entrance Gate, (Design): All work and labor required to design Railhead and Vehicle Wash Facility. | |
| All work on this base line item shall be completed within 210 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001DB | Rail load /off-load facility Railhead (Construction): All work, materials, and labor required to construct Railhead containing: RR Tracks w/Ties and Ballast, Railhead Apron/Service Lane, Concrete Hardstand, Loading/Unloading Dock/Ramp, At-Grade Rail Crossing, and Rail Switch.ncluding supporting facilities: Electric Service, Water, Sewer, Storm Drainage, Site Improvement, and Information Systems. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001DC | Entrance Gate (Construction) All work, materials, and labor required to construct Entrance Gate including supporting facilities: Electric Service, Site Improvement, and Information Systems. | € |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001DD | Vehicle Wash Facility (Construction) All work, materials, and labor required to construct Vehicle Wash Facility containing of: Vehicle Wash Facility, Wash Support Building, Wash Support Bldg. Vapor Barrier, Wash Facility Apron, Gravity Oil/Grease Sep., and Water and Grit Separator | € |
| Including supporting facilities: Electric Service, Water, Sewer, and Storm Drainage. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001EA | Ready Building (Design): All work and labor required to design one building (referred to as the Ready Building) containing all functions of: | € |
| -Ready Building-A/DACG with Overhead Protection | |
| -Shipping and Receiving and Cargo Operations Building | |
| -Overhead Protection, Pallet Area | |
| -Staging Marshalling Area | |
| and an exterior: | |
| -Open Storage Area, Installation and Generator Station | |
| Reference drawings MI RB 001, MI RB X001 and MI RB X002 for clarifications. | |
| All work on this base line item shall be completed within 270 calendar days from the date of the issuance of the Notice to Proceed. | |
| 3001EB | Ready Building (Construction): All work, materials, and labor required to construct one building containing all functions of: | € |
| -Ready Building-A/DACG with Overhead Protection | |
| -Shipping and Receiving and Cargo Operations Building | |
| -Overhead Protection, Pallet Area | |
| including supporting facilities: Electric Service, Water, Sewer, Paving, Walks, Curbs, and Gutter, Storm Drainage, | |
| Site Improvement, Information Systems. | |
| Reference drawing MI RB 001 for clarification. | |
| All work on this base line item shall be completed within 1050 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001EC | Open Storage Area, Installation (Construction): All work, materials, and labor required to construct Open | € |
| Storage Area, Installation, including supporting facilities: Storm Drainage. | |
| Reference drawing MI RB 001 for clarification. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001ED | Staging Marshalling Area (Construction): All work, materials, and labor required to construct a staging marshalling area | € |
| Reference drawing MI RB 001 for clarification. | |
| All work on this base line item shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total: | 0.00 € |
| 3001JA | A/E provided Service (LEED Services): All work and labor required to provide LEED Services for the Ready Building | € |
| (v4 Base Services in Design and Construction Phases incl. | |
| Pre Assessment, Energy Modeling, Fundamental | |
| Commissioning, Fees, etc.) | |
| All work on this base line item shall be completed within 1050 calendar days from the date of the issuance of the Notice to Proceed. | |
| Total | 0.00 € |
| Total Base Line Items Multimodal Improvements: | 0.00 € |
| OPTIONAL LINE ITEMS MULTIMODAL IMPROVEMENTS (MI) MK AIR BASE ROMANIA | | |
| CLIN | Description | Amount |
| 3002 | Multimodal Improvements (MI) MK Air Base, Romania Optional Line Items | BLANK |
Optional Line Items: The following optional line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government reserves the right to award any options within 120 calendar days following issuance of Notice to Proceed (NTP) for the base work. If an option is exercised, it must be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed. Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €849.00 per calendar day of delay beyond the required completion date of the contract.
| 3002AA OPTION | Fencing System to include entrance gate Around the Concrete Hardstand at the Railhead (Design AND Construction): | € |
| All work, materials, and labor required to design and construct a Fencing System to include entrance gate Around the Concrete Hardstand. Refer to drawing CX007. | |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
3002BA OPTION Alternative Water Connection (Design AND Construction) All work, materials, and labor required to design and construct Alternative Water Connection to the PFOS. Refer to plan GE001. €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
3002CA OPTION Backup Generator (Design & Construction): All work and labor required to design 1 diesel generator of 500kVA for the ready building €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
| 3002EA OPTION | Enlargement of service lane, movement platform and railway (Design & Construction): All work and labor required to design and construct enlargement of service lane, movement platform and railway | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | |
| Total: | 0.00 € |
| 3002EB OPTION | Demolition of Existing Structures(Design & Construction)-All work, materials and labor required to remove any existing structures as outlined in Scope of Work. | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 500 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
| 3002EC OPTION | Relocating two above ground active fuel lines(Design & Construction)- All work, materials and labor rwquired to remove any two above ground existing active fuel lines as outlined in the Scope of Work. | € |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
| 3002ED OPTION | Electrical connection to ETS1(Design & Construction): All work, material and labor of the electrical connection for the Railhead Area in the manhole south of the Fuel Storage Capacity project to ETS1 and the electrical connection of the NTS to ETS1. | |
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
3002EE OPTION Electrical connection to ETS2 (Design & Construction): All work, material and labor of the electrical connection for the Railhead Area in the manhole south of the Fuel Storage Capacity project to ETS2 and the electrical connection of the NTS to ETS1.
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
3002EF OPTION A/E-provided Service: All work and labor required to provide LEED Services for the Ready Building (Enhanced Commissioning) €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
3002EG OPTION Additional Row of Four Umbrellas (Design and Construction): All work, material and labor required to add one additional row of four (4) umbrellas to the South Side of the Ready Building (400 additional sqm). €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
3002EH OPTION Additional Row of Four Umbrellas (Design and Construction): All work, material and labor required to add two additional rows of four (4) umbrellas each to the South Side of the Ready Building (800 additional sqm) €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
3002EJ OPTION Concrete Pavement Finish (Design and Construction): All work, material and labor required provide a fully paved, concrete finished access road. €
| The Government reserves the right to exercise this option within 120 calendar days of issuance of the Notice to Proceed for the base items work. Should the Government exercise this optional line item all work shall be completed within 810 calendar days from the date of the issuance of the Notice to Proceed for the base items. | € |
| Total: | 0.00 € |
| Total Optional Line Items Multimodal Improvements: | 0.00 € |
| Total Optional & Base Line Items Multimodal Improvements: | 0.00 € |
| Total Contract All Base Line Items: | 0.00 € |
| Total Contract All Optional Line Items | 0.00 € |
| Total Contract All Base and Optional Line Items: | 0.00 € |
PRICE SCHEDULE
FY15 European Reassurance Initiative (ERI) Various Base Improvements: Multi Modal Improvements and Fuel Storage Capacity Mihail Kogalniceanu Air Base, Romania
Revised 14 August 2017 NOTE: For all line items listed below, the Contractor shall refer to the "Summary of Scope Revisions" and revised drawings which illustrate the changes between the initial project design and the reduced scope quantities.
Line Items: The following Line items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation / Request for Proposal, and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, regulatory, permitting and safety requirements. All work shall be performed in accordance with these documents.
Award of Options: The Government will award any options at the time of award of the base work. If an option is exercised, it must also be completed within the number of calendar days stated in the optional line item being exercised.
Period of Performance: A single Notice to Proceed will be issued for all awarded work. All work shall be completed within the number of calendar days indicated in each line item from the date of the Notice to Proceed.
Included in the total Period of Performance is a period of up to 120 calendar days during which the host nation Ministry of Defense will review the 100% design submittals and provide review comments to the US government. Only upon completion of the host nation Ministry of Defense (MOD) review, will the designs be approved for construction.
Liquidated Damages: Liquidated damages shall be assessed in the amount of €849.00 per calendar day of delay beyond the required completion date of the contract.