This is a permit authorization request letter submitted to the New York State Department of Environmental Conservation (NYSDEC) for the Wheeler-Sack Army Airfield Runway 03-21 Airfield Lighting Repair Project at Fort Drum. The project involves soil disturbance exceeding five acres and requires prior authorization under General Permit II.D.3 (GP-0-25-001). The requestor, Jacobs Civil Consultants, Inc., is seeking departmental approval to proceed with the project, which is designed with phasing to minimize runway downtime on the active military airfield while limiting overall disturbance.

The erosion control and environmental protection measures outlined include: conducting qualified inspector site visits at least twice every seven calendar days while disturbance exceeds five acres with minimum two-day intervals between inspections; initiating soil stabilization measures by the next business day when disturbance ceases and completing them within seven days, in accordance with New York State Standards and Specifications for Erosion and Sediment Control; preparing a detailed phasing plan identifying maximum disturbed areas per phase with required cuts and fills; installing additional water quality protection measures as needed; and incorporating all requirements into the Stormwater Pollution Prevention Plan (SWPPP) and project drawings. The letter was prepared by Colin O'Neill, P.E., SWPPP Preparer at Jacobs Civil Consultants, Inc., dated April 17, 2026.

View the file

Other files

File Type Posted
Amendment 13 - W912DS25RA003.pdf PDF
Ft_Drum_Pre-Award_Re-Phasing_Specifications.pdf PDF
Ft Drum Pre-Award Re-Phasing Drawings_041726.pdf PDF
FortDrum_SWPPP_Rephasing_Stamped_R1-20 Apr 26.pdf PDF
Amendment 12 - W912DS25RA003.pdf PDF
Amendment 11 W912DS25RA003.pdf PDF
Amendment 10 - W912DS25RA003.pdf PDF
Phasing and Schedule Market Research.pdf PDF
Basis of Award W912DS25RA003 18Dec2025.pdf PDF
Amendment 9 W912DS25RA003.pdf PDF
GC101 - Phasing and Schedule Market Research.pdf PDF
Amendment 8 - W912DS25RA003.pdf PDF
Amendment 7 - W912DS25RA003.pdf PDF
Electric and Water Utilities on the Concrete Batch Plant Site.pdf PDF
Basis of Award W912DS25RA003 12Nov2025.pdf PDF
Amendment 6 - W912DS25RA003.pdf PDF
32 12 15.13.pdf PDF
Amendment 5 - W912DS25RA003.pdf PDF
Basis of Award W912DS25RA003 22Oct2025.pdf PDF
Amendment 4 W912DS25RA003.pdf PDF
Amendment 2 W912DS25RA003.pdf PDF
Amendment 0003 Specs - Ft Drum Runway Lighting Repair (WSAAF).pdf PDF
Ft_Drum_SWPPP_FINAL_04252025_UPD07OCT25.pdf PDF
Amendment 3 - W912DS25RA003.pdf PDF
Sign-in Sheet.pdf PDF
Amendment 2 - W912DS25RA003.pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans (109-217).pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans (1-54).pdf PDF
Ft_Drum_RTA_Specifications_Reprint.pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans (55-108).pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans (218-326).pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans (327-433).pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans 25 APR 2025(55-108)_UPD23SEP25.pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans 25 APR 2025(327-433)_UPD23SEP25.pdf PDF
Ft_Drum_RTA_Specifications_Reprint_UPD23SEP25.pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans 25 APR 2025(218-326)_UPD23SEP25.pdf PDF
WSAAF Lighting Upgrade JA - Monaco Fire Alarm_signed-_Redacted.pdf PDF
Bidder Walkthrough Visitor Pass Instructions R1.pdf PDF
WSAAF Lighting Upgrade JA - Trane Tracer Ensemble_Redacted.pdf PDF
Solicitation Amendment W912DS25RA0030001 SF 30.pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans 25 APR 2025(1-54)_UPD23SEP25.pdf PDF
Ft Drum Runway Lighting Repair - Final RTA Plans 25 APR 2025(109-217)_UPD23SEP25.pdf PDF
Ft_Drum Runway Lighting Repair RTA Specs 25 Apr 25.pdf PDF
Basis of Award - W912DS25RA003.pdf PDF
Bidder Walkthrough Plan.pdf PDF
Bidder Walkthrough Visitor Pass Instructions.pdf PDF
Ft Drum Map (WSAAF Bidder Walkthrough).pdf PDF
Solicitation - W912DS25RA003.pdf PDF
IMDR-ES_Form_2_APPLICATION_FOR_SPONSORSHIPv7.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 17, 2026

NYSDEC

Division of Environmental Permits – Bureaeu of Energy Project Management

625 Broadway, 4th Floor

Albany, NY 12233-0001

Subject: Wheeler-Sack Army Airfield – Runway 03-21 Airfield Lighting Repair Project

Authorization from the Department for a disturbance of greater than 5 acres

(General Permit II.D.3.)

To whom it concerns, The Wheeler-Sack Army Airfield – Runway 03-21 Airfield Lighting Repair Project at Fort

Drum may include > 5 acres of disturbance. Due to the nature of the site being an active airfield on an active army base, phasing has been planned around limiting the duration of the runway being taken offline, but disturbance will be limited as much as practical and no areas will be left disturbed with no active work for an extended period of time.

In accordance with Part II.D.3 of the General Permit (GP-0-25-001), the following erosion control measures will be implemented:

a. A qualified inspector will conduct at least two (2) site inspections in accordance with the Permit every seven (7) calendar days for so long as greater than five (5) acres of soil remain disturbed and will allow two (2) calendar days between inspections.

b. In areas where soil disturbance activity has temporarily or permanently ceased, the application of soil stabilization measures will be initiated by the end of the next business day and completed within seven (7) days from the date the current soil disturbance activity ceased. The soil stabilization measures selected will be in conformance with the techincal standard, New York State Standards and

Specifications for Erosion and Sediment Control.

c. Preparation of phasing plan that defines the maximum disturbed area per phase and shows required cuts and fills.

d. Installation of any additional measures needed to protect water quality.

e. Inclusion of the requirements above in the SWPPP and Project Drawings.

We are requesting prior authorization from the Department for this activity.

Sincerely, Jacobs Civil Consultants, Inc.

Colin O’Neill, P.E.

SWPPP Preparer