Solicitation Amendment W912DS25RA0020004 SF 30.pdf
PDF 3 MB Posted
- Solicitation number
- W912DS25RA002
About this file
This is a Standard Form 30 (SF-30) Amendment of Solicitation/Modification of Contract for a repair project for Building 606, issued by the U.S. Army Corps of Engineers (W2SSD Contracting Division). The amendment (Number 0004) extends the proposal due date from 03 October 2025 to 17 October 2025 at 2:00 PM EDT and provides additional responses and new drawings/attachments.
The amendment modifies the list of drawing sheets, adding four new contract documents (A-124_AM 4, A-564_AM 4, A-601_AM 4, and A-602_AM 4), each with one page. The project involves a comprehensive repair of Building 606, with multiple specification manual volumes and drawing sets dated between May and September 2025. The contract includes various technical drawings covering architectural, civil, electrical, structural, and mechanical aspects, with reference number W912DS19C0034 and Project Number 94078.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section 00 01 15 - List of Drawing Sheets
The attachments table has changed from:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
W912DS19C0034
PN 94078 Repair building 606 REV.
RTA Specification Manual Volume 1
Specification
W912DS19C0
034 PN 94078
Repair building 606
REV.RTA
Specification Manual Volume 1
13 May 2025 1395 Attachment No
0010 A-121 Drawings A-121 03 Sep 2025 1 Attachment No
0011 A-122 Drawings A-122 03 Sep 2025 1 Attachment No
0012 A-319 Drawings A-319 03 Sep 2025 1 Attachment No
0013 A-406 Drawings A-406 03 Sep 2025 1 Attachment No
0014 C-101 Drawings C-101 03 Sep 2025 1 Attachment No
0015 E-513 Drawings E-513 03 Sep 2025 1 Attachment No
0016 S-112 Drawings S-112 03 Sep 2025 1 Attachment No
0017 S-318 Drawings S-318 03 Sep 2025 1 Attachment No
0018 01 30 00-_AM3 Specification 01 30 00-
_AM3
21 Aug 2025 Attachment No
0019 01 91 19_AM3 Specification 01 91 19_AM3 23 Apr 2025 Attachment No
W912DS19C0034
PN 94078 Repair building 606 REV.
RTA Specification Manual Volume 2
Specification
W912DS19C0
034 PN 94078
Repair building 606
REV.RTA
Specification Manual Volume 2
13 May 2025 1172 Attachment No
E-512 - Details - Electrical AM3
Drawings E-512 - Details
- Electrical
AM3
17 Sep 2025 Attachment No
E-601- Diagrams - One Line AM3
Drawings E-601- Diagrams - One Line AM3
17 Sep 2025 Attachment No
E-618 Panelboard Schedules AM3
Drawings
E-618 Panelboard Schedules
AM3
17 Sep 2025 Attachment No
HP802 HVAC
Plumbing and Electrical Coordination Schedule AM3
Drawings
HP802 HVAC
Plumbing and Electrical Coordination Schedule AM3
17 Sep 2025 Attachment No
0024 M 303 AM3 Drawings M 303 AM3 17 Sep 2025 Attachment No
0025 MS 100 AM3 Drawings MS 100 AM3 17 Sep 2025 Attachment No
W912DS19C0034
PN 94078 Repair building 606 REV.
RTA Specification Manual Volume 3
Specification
W912DS19C0
034 PN 94078
Repair building 606
REV.RTA
Specification Manual Volume 3
13 May 2025 1181 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA
Drawings
W912DS19C0
034 PN 94078
Repair Building 606
13 May 2025 118 Attachment No
W912DS25RA0020004
Drawings - Volume
Revised RTA Drawings - Volume 1
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 2
13 May 2025 236 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 3
13 May 2025 188 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 4
13 May 2025 177 Attachment No
0008 07 60 00 Specification 07 60 00 03 Sep 2025 21 Attachment No
0009 A-120 Drawings A-120 03 Sep 2025 1 Attachment No
To:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
W912DS19C0034
PN 94078 Repair building 606 REV.
RTA Specification Manual Volume 1
Specification
W912DS19C0
034 PN 94078
Repair building 606
REV.RTA
Specification Manual Volume 1
13 May 2025 1395 Attachment No
0010 A-121 Drawings A-121 03 Sep 2025 1 Attachment No
0011 A-122 Drawings A-122 03 Sep 2025 1 Attachment No
0012 A-319 Drawings A-319 03 Sep 2025 1 Attachment No
0013 A-406 Drawings A-406 03 Sep 2025 1 Attachment No
0014 C-101 Drawings C-101 03 Sep 2025 1 Attachment No
0015 E-513 Drawings E-513 03 Sep 2025 1 Attachment No
0016 S-112 Drawings S-112 03 Sep 2025 1 Attachment No
0017 S-318 Drawings S-318 03 Sep 2025 1 Attachment No
0018 01 30 00-_AM3 Specification 01 30 00-
_AM3
21 Aug 2025 19 Attachment No
0019 01 91 19_AM3 Specification 01 91 19_AM3 23 Apr 2025 10 Attachment No
W912DS19C0034
PN 94078 Repair building 606 REV.
RTA Specification Manual Volume 2
Specification
W912DS19C0
034 PN 94078
Repair building 606
REV.RTA
Specification Manual Volume 2
13 May 2025 1172 Attachment No
E-512 - Details - Electrical AM3
Drawings E-512 - Details
- Electrical
AM3
17 Sep 2025 1 Attachment No
E-601- Diagrams - One Line AM3
Drawings E-601- Diagrams - One Line AM3
17 Sep 2025 1 Attachment No
E-618 Panelboard Schedules AM3
Drawings
E-618 Panelboard Schedules
AM3
17 Sep 2025 1 Attachment No
HP802 HVAC
Plumbing and Electrical Coordination Schedule AM3
Drawings
HP802 HVAC
Plumbing and Electrical Coordination Schedule AM3
17 Sep 2025 1 Attachment No
0024 M 303 AM3 Drawings M 303 AM3 17 Sep 2025 1 Attachment No
0025 MS 100 AM3 Drawings MS 100 AM3 17 Sep 2025 1 Attachment No
0026 A-124_AM 4 Drawings A-124_AM 4 25 Sep 2025 1 Attachment No
0027 A-564_AM 4 Drawings A-564_AM 4 25 Sep 2025 1 Attachment No
0028 A-601_AM 4 Drawings A-601_AM 4 25 Sep 2025 1 Attachment No
0029 A-602_AM 4 Drawings A-602_AM 4 25 Sep 2025 1 Attachment No
W912DS19C0034
PN 94078 Repair building 606 REV.
RTA Specification Manual Volume 3
Specification
W912DS19C0
034 PN 94078
Repair building 606
REV.RTA
Specification Manual Volume 3
13 May 2025 1181 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 1
13 May 2025 118 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 2
13 May 2025 236 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 3
13 May 2025 188 Attachment No
W912DS19C0034
PN 94078 Repair Building 606 Revised RTA Drawings - Volume
Drawings
W912DS19C0
034 PN 94078
Repair Building 606 Revised RTA Drawings - Volume 4
13 May 2025 177 Attachment No
0008 07 60 00 Specification 07 60 00 03 Sep 2025 21 Attachment No
0009 A-120 Drawings A-120 03 Sep 2025 1 Attachment No
The following contract documents were added:
A-124_AM 4
A-564_AM 4
A-601_AM 4
A-602_AM 4
The following contract documents Page Counts were changed:
DOCUMENT PAGE COUNTS
DOCUMENT NAME FROM TO
A-124_AM 4 none 1
A-564_AM 4 none 1
A-601_AM 4 none 1
A-602_AM 4 none 1
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0004 |
| EffDate: 25 SEP 2025 |
| ReqNo: |
| ProjNo: PANNAD-25-P-0000 000139 |
| IssCode: W912DS |
| AdmCode: |
| IssuedBy: W2SD ENDIST NEW YORK |
KO CONTRACTING DIVISION, 696 VIRGINIA ROAD
CONCORD, MA 01742-2751
UNITED STATES
BRIAN WINTERS, EMAIL: BRIAN.H.WINTERS@USACE.ARMY.MIL TELEPHONE: 917-790-8083
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912DS25RA002 |
| SolDate: 08 AUG 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: AMENDMENT 0004 PROVIDES THE FOLLOWING UPDATES: |
1. PROPOSAL DUE DATE CHANGE: DUE DATE HAS BEEN EXTENDED FROM "03 OCTOBER 2025" TO "17 OCTOBER 2025" AT 2:00 PM EDT.
2. PROVIDES ADDITIONAL RESPONSES TO RFIS.
3. PROVIDES ADDITIONAL DRAWINGS/ATTACHMENTS.
| ContNameTitle: |
| CoNameTitle: NICHOLAS EMANUEL |
| ContDate: |
| CODate: 26 SEP 2025 |
File details come from the government source that posted it. Updated .