This document is a Contract Data Requirements List (CDRL) outlining reporting requirements for a requirements contract to provide Stryker vehicle Retrofit, Reset/Refurbishment, and Damage Repair services. The U.S. Army Contracting Command, Warren, Michigan will issue a sole source Request for Proposal to General Dynamics Land Systems by 30 September 2018 for a 5 year contract. The CDRL requires the contractor to submit monthly Funds and Man-Hours Expenditure Reports no later than 25 working days after each accounting month end, with cumulative costs to date and labor hours and costs broken down by contract and CLIN. The reports must be provided in the contractor's flat-file format and made available using the Government's Integrated Data Environment. Intra-company and inter-company costs over 5% of a CLIN's value or $25,000 must be reported separately.

Not Listed

View the file

Other files

File Type Posted
A013- Hazardous Materials Management Program Report.docx DOCX document
Attachment_0036_GDLS-C_Field_Weld_Repair_Procedure_F-4000_Rev_L.pdf PDF
New_Compressed_(zipped)_Folder.zip ZIP file
Attachment_0027_-_FSRR_Repair_Tasks.docx DOCX document
B002 - Technical Inspection —
Attachment_0032_-_Double_V_Hull_Stryker_Corrosion_inspection_check_list.xlsx XLSX spreadsheet
Attachment_0037_-_DVH_StrykerTire_Criteria_MI-_BCT-0105_REV_B__6_June_2013.pdf PDF
Attachment_0005_-_EIA_649-1_Tailoring.docx DOCX document
Attachment_0022_-_Program_of_Instruction_(POI)_for_Bench_Stock_-_14SEPT2....docx DOCX document
B017 - Forecast of FY19-24 - 14SEPT2016.docx DOCX document
Attachment_0034_-_D17000_Recorded_Joint_Welding_Procedure.docx DOCX document
A009 - RFV.DOCX DOCX document
Attachment_0013_-_Mandatory_Replacement_Parts_-_05JAN2018.xlsx XLSX spreadsheet
R001 - Property Accountability Reporting.docx DOCX document
B011 - Consumed Items Report - 25JAN2018.doc DOC document
Attachment_0019_-_Reset-Refurb_Kit_Determination_-_14SEPT2016.xlsx XLSX spreadsheet
Attachment_0018_-_ANAD_Reset-Refurb_Closeout_Disposition_Instructions_-_....xlsx XLSX spreadsheet
Attachment_0029_-_Crash_Damage_Closeout_Disposition_Instructions_-_18JAN....xlsx XLSX spreadsheet
B006 - Refurbishment Order of March —
Attachment_0020_-_ANAD_Reset-Refurb_Closeout_Timeline_-_14SEPT2016.docx DOCX document
Attachment_0009_-_Government_Furnished_List_(GFX)_-_14SEPT2016.xlsx XLSX spreadsheet
Attachment_0004_-_Stryker_STS_HMMP_Plan.docx DOCX document
B003- 6.0 Driveline and C9 FUPP training instructions.doc DOC document
A004 - AT Level 1 Training.docx DOCX document
Attachment_0025_-_Labor_Split_For_Reset-Refurb_at_ANAD_-_05JAN2018.xlsx XLSX spreadsheet
S002 - DVHA1 Repair Weldments and Fixture Drawings.doc DOC document
Attachment_0030_-_Crash_Damage_Closeout_Disposition_Instructions_-_18JAN....xlsx XLSX spreadsheet
Attachment_0002_-_Retrofit_Install_Tasks.xlsx XLSX spreadsheet
Attachment_0038_-_3126_FUPP_Technical_Inspection_Rev_1_(003).pdf PDF
Attachment_0001_-_Scheduled_Government_Furnished_Property.xlsx XLSX spreadsheet
A002 - CSDR Flexfile.doc DOC document
B001 - Removed Deployment Kit Inventories - 03MAR2018.docx DOCX document
Attachment_0021_-_Bench_Stock_Management_Plan_-_14SEPT2016.docx DOCX document
A010 - RDT.DOC DOC document
A001 - OPSEC Awareness Training Report.docx DOCX document
Attachment_0003_-_PM_SBCT_OPSEC_Plan.pdf PDF
Attachment_0015_-_Specified_Components_Inspection_and_Repairs__-_13FEB20....xlsx XLSX spreadsheet
Attachment_0012__-_Removal_of_BFT_and_OSRVT_Components_-_16MAY13.pdf PDF
S001 Structural Repair Instructions.docx DOCX document
Attachment_0031_-_Flat_Bottom_Stryker_Corrosion_inspection_check_list.xlsx XLSX spreadsheet
S006 Consumed Items Report.doc DOC document
Attachment_0016_-_Customer_Support_Form_-_Jan_2018.xlsx XLSX spreadsheet
S009 Final Acceptance Report.docx DOCX document
A0014 - RFV.DOCX DOCX document
Attachment_0028_-_Retrofit_and_Repair_CSDR_Plan.pdf PDF
B016 - Technical Inspection —
A008 - PLER.DOC DOC document
Attachment_0011_-_FY19-24_Stryker_Technical_Inspection_-_16JAN2018.xlsx XLSX spreadsheet
A007 - MRR.DOCX DOCX document
B008 - Government Owned Drawdown Property Inventory Analysis Report - 25....docx DOCX document
Show 40 more

Latest 50 of 70 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item) Form Approved

OMB NO. 0704-D188

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188) Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. Contract Line Item No.

B. Exhibit:

C. Category:

TDP |_| TM |_| OTHER |_|

D. System/Item:

Stryker Family of Vehicles

E. Contract/Pr No.

F. Contractor:

General Dynamics Land Systems

1. Data Item No.:

A006

2. Title of Data Item:

Funds and Man-Hours Expenditure Report

3. Subtitle:

17. Price Group:

4. Authority (Data Acquisition Document No.):

DI-FNCL-80331A /T

5. Contract Reference:

C.3.4; C.9.3.2.1.1; C.11.10.7: C.11.13:

6. Requiring Office:

SFAE-GCS-SB

18. Estimated Total Price:

7. DD 250 Req:

LT

9. Dist. Statement Required:

FOUO

1. Frequency:

Monthly

12. Date of First Submission:

See Block 16

14. Distribution

8. APP Code:

11. As of Date:

See Block 16

13. Date of Subsequent Submission:

See Block 16

a. Addressee:

b. Copies:

Draft
Final
Reg
Repro

16. Remarks:

BLK 4: DI-FNCL-80331A is tailored as follows:

1. Paragraph 2 is deleted.

2. Paragraph 4 is deleted.

BLK 11: Last day of contractor’s monthly accounting period.

BLK 12: Due NLT 25 working days after the end of the first complete monthly accounting period subsequent to the contracting officer’s authorization to proceed.

BLK 13: Subsequent submissions are due NLT 25 working days after the contractor’s accounting month end date. Submissions shall continue until all labor tasks have been completed and all anticipated remaining expenditures are only for the settlement and adjustment the contractor’s pricing rates. The contractor shall indicate final submission of the report in the document’s filename and on the first tab of the document.

BLK 14: The contractor shall make the Funds and Man-Hours Expenditure Report available to the Government PMO using the Government managed Integrated Data Environment.

BLK 16: The report shall contain cumulative costs to date and be delivered in the contractor’s flat-file format. When the report is prepared for Contractor Support to Government Testing efforts, the contractor shall include a narrative in contractor format describing the test activities supported.

The contractor formatted report shall contain the following data fields: Contract Number, Delivery Order Number, Contract Line Item Number (CLIN) Top Task, CLIN, CLIN Description, Work Order, Work Order Description, Account Number, Account Description, Expenditure Category, Labor Department Number, Labor Department Name, Plant Code, Labor Cluster, Report As of Date, Labor Hours, Cost (USD), Cost of Money (USD), Profit/Fee (USD), Grand Total (USD).

For delivery orders managed though contract work directives, the contractor shall provide a separate table identifying by contract work directive its associated CLINs.

The contractor shall report intra-company and inter-company costs whenever intra-company and intercompany costs are expected to account for greater than 5% of a CLIN’s total value or if the total expected intra-company and intercompany costs on a CLIN exceed $25,000. Intra-company and inter-company costs shall be reported on a separate tab in the submission in contractor format and shall, at a minimum, include the following data: Contract Number, Delivery Order Number, CLIN, Labor Hours, Labor Dollars (USD), Material Dollars (USD), Other Direct Costs Dollars (USD), Overhead/Indirect Dollars (USD), and Profit/Fee (USD).

https://gcscdrl.tacom.army.mil/ext/
15. TOTAL

G. Prepared By:

H. Date:

I. Approved By:

J. Date:

DD Form 1423-1, JUN 90 (EF) PREVIOUS EDITIONS ARE OBSOLETE Page of Pages image1.emf image2.emf