This is a Fugitive Dust Control Plan Form 14 template for construction and demolition trenching activities at Dugway Proving Ground (DPG). The form requires contractors to document trenching operations and select best management practices (BMPs) to control fugitive dust emissions during long, narrow excavations performed with track or wheel-mounted equipment such as excavators, shovels, backhoes, or trenchers.
Contractors must complete general information fields including location, start and end dates, point of contact information, and site description. For fugitive dust emission control, at least one BMP must be selected from three critical mitigation areas: presoak soils prior to trenching (BMP 14-01: pre-water surface), stabilize surface soils where equipment operates (BMPs 14-02 through 14-04: pre-water/maintain, apply chemical stabilizers, or limit mileage and speed), and stabilize soils after trenching (BMPs 14-05 and 14-06: apply and maintain water or chemical stabilizers on excavated soil). When suppression methods are used, contractors must maintain logbooks documenting the date, time, suppression type, amount in gallons, purpose, and application location. Additionally, contractors must comply with Utah Administrative Code R307-205-6(2) trackout prevention requirements by preventing material deposition on paved roads and promptly cleaning any materials deposited. Completed forms and corresponding logbook entries must be submitted to the Environmental Program's Air Program Manager at boyd.roberts.civ@mail.mil upon operation completion or annually by calendar year end, whichever occurs first.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Environmental Programs FDCP-14 Air Quality Program Revision 0
Dugway Proving Ground Fugitive Dust Control Plan Form 14 Construction & Demolition
Trenching Activity Description: A long, narrow excavation in the ground using a track or wheel mounted excavator, shovel, backhoe or trencher.
General Information
Location(s): Start Date: End Date:
Point of Contact: Email: Phone Number:
Description of site:
Fugitive Dust Emission Control Techniques Select at least one best management practice (BMP) for each critical mitigation area:
Presoak soils prior to trenching activities
BMP 14-01 Pre-water surface.
Stabilize surface soils where trenching equipment, support equipment and vehicles will operate
BMP 14-02 Pre-water and maintain surface soils in a stabilized condition.
BMP 14-03 Apply and maintain a chemical stabilizer to surface soils. (Name of chemical: ) BMP 14-04 Limit mileage and speed.
Stabilize soils after trenching
BMP 14-05 Apply and maintain water on excavated soil.
BMP 14-06 Apply and maintain chemical stabilizer on excavated soil. (Name of chemical: )
Logbook Requirement If suppression is used, a logbook is required, at minimum, it must contain: the date, time, type of suppression used (i.e. water/chemical suppressant), amount (in gallons), purpose and location applied.
Trackout Prevention In accordance with Utah Administrative Code R307-205-6(2), any person(s) performing fugitive dust emission activities will to the maximum extent possible, keep material from being deposited onto any paved road other than a designated deposit site. Any such person(s) who deposits materials that may create fugitive dust on a paved road shall clean the road promptly.
*By signing you attest that you have read and understand the requirements of the DPG FDCP and will follow the BMPs you have selected.
Signature Date This form is to be completed and kept on record according to the requirements found in the Dugway Proving Ground (DPG) Fugitive Dust Control Plan (FDCP). Copies of form(s) and corresponding logbook entries (if applicable) shall be provided to EP, Air Program Manager, upon the completion of operation(s) and/or annually at the end of each calendar year whichever occurs first. Submit completed form and applicable logbook entries in hardcopy or electronically, via email to Environmental Program’s (EP) Air Program Manager: boyd.roberts.civ@mail.mil
| Text1: |
| Text2: |
| Text3: |
| Text4: |
| Text5: |
| Text6: |
| Text7: |
| Text8: |
| Check Box1: Off |
| Check Box2: Off |
| Date: |
| Text9: |
| Check Box3: Off |
| Check Box4: Off |
| Check Box5: Off |
| Check Box6: Off |
File details come from the government source that posted it. Updated .