This is a Fugitive Dust Control Plan form template for hauling materials at Dugway Proving Ground. The form applies to transportation of aggregate materials to and from job sites and requires contractors to implement best management practices (BMPs) to control fugitive dust emissions.

Contractors must select at least one BMP from each of three critical mitigation areas: limiting visible dust opacity from vehicular operations (applying water/chemical suppressants or limiting vehicle mileage and speed), stabilizing materials during transport (using tarps or applying water prior to transport), and cleaning wheels and undercarriage of haul trucks (cleaning wheels or sweeping/watering haul roads). All aggregate hauling operations require a logbook documenting the date and amount of material hauled, and if suppressants are used, additional entries must record the date, time, type and amount of suppressant in gallons, purpose, and location applied. The form requires compliance with Utah Administrative Code R307-205-6(2) regarding trackout prevention, mandating that contractors keep material from being deposited on paved roads other than designated sites and promptly clean any roads where material is deposited. Completed forms and corresponding logbook entries must be submitted to the Environmental Program's Air Program Manager at boyd.roberts.civ@mail.mil upon operation completion or annually at year-end, whichever occurs first. The form requires contractor signature attesting to understanding and compliance with the Fugitive Dust Control Plan requirements.

View the file

Other files

File Type Posted
Attachment 2 Dugway Proving Ground Paving IDIQ Virtual Site Visit.pptx PPTX presentation
TE-01 Contract Line Items Proposal Template Base plus 4 Year.xlsx XLSX spreadsheet
TE-04 Standard Drawings.pdf PDF
TE-09b Fugitive Dust Control Form 02-Screening.pdf PDF
TE-09f Fugitive Dust Control Form 06-Backfilling.pdf PDF
TE-09j Fugitive Dust Control Form 10-Demolition.pdf PDF
TE-09m Fugitive Dust Control Form 13-Sawing-Cutting.pdf PDF
TE-09r Fugitive Dust Control Form 18-Traffic.pdf PDF
TE-02 Standard Specification Book Rev 9 June 2025.pdf PDF
TE-07 Quality Management Plans 5 June 2025.pdf PDF
TE-09a Fugitive Dust Control Form 01-Crushing.pdf PDF
TE-09c Fugitive Dust Control Form 03-Stockpiles.pdf PDF
TE-09l Fugitive Dust Control Form 12-Disturbed Land.pdf PDF
TE-10 Asphalt Slurry Seal.pdf PDF
TE-11 Existing Asphalt Core Sampling FY27 -FY31 Paving 12 March 2026.pdf PDF
1442-Solicitation W911S627BA001 DPG Horizontal Construction 101426.pdf PDF
TE-05 Materials Manual of Instruction.pdf PDF
TE-08 Work Zones.pdf PDF
TE-09 Dust Control Forms 5 June 2025.pdf PDF
TE-09e Fugitive Dust Control Form 05-Staging Areas.pdf PDF
TE-09g Fugitive Dust Control Form 07-Site Preparation.pdf PDF
TE-09n Fugitive Dust Control Form 14-Trenching.pdf PDF
TE-09o Fugitive Dust Control Form 15-Loading.pdf PDF
TE-09p Fugitive Dust Control Form 16-Paving.pdf PDF
TE-09q Fugitive Dust Control Form 17-Trackout.pdf PDF
Attachment 1 Scope of Work W911S6 Construction Horizontal FY27 - FY 31.pdf PDF
DPG_Paved_Roads_2026.pdf PDF
TE-03 Paving IDIQ Airfield Specifications.pdf PDF
TE-06 Min Sampling an Testing.pdf PDF
TE-09i Fugitive Dust Control Form 09-Site Grading.pdf PDF
TE-09k Fugitive Dust Control Form 11-Disturbed Soil.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Environmental Programs FDCP-04 Air Quality Program Revision 0

Dugway Proving Ground Fugitive Dust Control Plan Form 04 Storage, Hauling and Handling of Aggregate Material

Hauling Materials Activity Description: The transportation of materials to or from a site.

General Information

Location(s): Start Date: End Date:

Point of Contact: Email: Phone Number:

Description of site:

Fugitive Dust Emission Control Techniques Select at least one best management practice (BMP) for each critical mitigation area:

Limit visible dust opacity from vehicular operations

BMP 04-01 Apply and maintain water/chemical suppressant to operational areas and haul routes. (Name of chemical: ) BMP 04-02 Limit vehicle mileage and speed.

Stabilize materials during transport on site

BMP 04-03 Use tarps or other suitable enclosures on haul trucks.

BMP 04-04 Apply water prior to transport.

Clean wheels and undercarriage of haul trucks prior to leaving construction site

BMP 04-05 Clean wheels.

BMP 04-06 Sweep or water haul road.

Logbook Requirement All aggregate hauling operations require a logbook to be kept, at minimum, it must contain: the date and amount of aggregate material hauled.

If suppression is used, additional logbook entries are required, at minimum, entries must contain: the date, time, type of suppression used (i.e.

water/chemical suppressant), amount (in gallons), purpose and location applied.

Trackout Prevention In accordance with Utah Administrative Code R307-205-6(2), any person(s) performing fugitive dust emission activities will to the maximum extent possible, keep material from being deposited onto any paved road other than a designated deposit site. Any such person(s) who deposits materials that may create fugitive dust on a paved road shall clean the road promptly.

*By signing you attest that you have read and understand the requirements of the DPG FDCP and will follow the BMPs you have selected.

Signature Date This form is to be completed and kept on record according to the requirements found in the Dugway Proving Ground (DPG) Fugitive Dust Control Plan (FDCP). Copies of form(s) and corresponding logbook entries (if applicable) shall be provided to EP, Air Program Manager, upon the completion of operation(s) and/or annually at the end of each calendar year whichever occurs first. Submit completed form and applicable logbook entries in hardcopy or electronically, via email to Environmental Program’s (EP) Air Program Manager: boyd.roberts.civ@mail.mil

Text8:
Text1:
Text2:
Text3:
Text4:
Text5:
Text6:
Text7:
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Date: