AF Form 3064 - Contract Progress Schedule

This document is a template and instructions for the Air Force Contract Progress Schedule (AF IMT 3064), used to track contractor performance against planned work elements throughout a contract period. The form requires contractors to submit three copies to the contracting officer at times specified in the contract, with all copies dated and signed by the contractor or authorized representative.

The form captures essential contract identification information including contract number, starting date, completion date, project title, purchase request number, and project number, along with actual starting and completion dates. Contractors must identify major work elements (such as excavation, concrete work, carpentry, engineering, or equipment installation) in logical sequence and assign each element a percentage of total job completion. The schedule uses a 14-week column format (Columns D through Q) to display planned periodic progress, with contractors entering percentage completion figures for each work element by week. All weekly progress figures are totaled and used to create overlay graphs for performance tracking. If contract modifications alter the work schedule, completion date, or scope, contractors must submit revised schedules labeled accordingly. Additionally, contractors must submit AF Form 3065 (Contract Progress Report) at intervals established by the contracting officer, reporting actual percentage of work accomplished for each element. The instructions emphasize that accurate reporting is critical for contract administration and partial payment approvals, and contractors must immediately notify the contracting officer of any anticipated delays.

View the file

Other files

File Type Posted
FA500026R0001_AMENDMENT_ 0002 _SF30 Signed.pdf PDF
FA500026R0001_AMENDMENT_0001_SF30 Signed.pdf PDF
Attachment 2_Relevant Experience Project Template R1 Amendment 01.docx DOCX document
Attachment 1_2026 JBER MACC SOW R1 Amendment 01.pdf PDF
Attachment 5_Self-Scored Worksheet R1 Amendment 01.xlsx XLSX spreadsheet
2026 MACC Pre-Proposal Sign-In Sheet.pdf PDF
Attachment 8_2026 JBER MACC Q and A.pdf PDF
JBER MACC Pre-Proposal Conference-20260331_163518UTC-Meeting Recording.mp4 MP4 file
Attachment 4_Technical Definitions R1 Amendment 0001.pdf PDF
SOW App 001 AF IMT 3000 Submittal.pdf PDF
SOW App 004 Contractors Fire Safety Guide Rev 14 September 2017.pdf PDF
SOW App 008 Dig Permit Fillable Template.pdf PDF
SOW App 013 Environmental Precon Checklist 21JAN2025.pdf PDF
SOW App 015 JBER Hazardous Waste Management Plan 26MAR2025.pdf PDF
SOW App 016 JBER Integrated Hazardous Material Plan 31MAY2025.pdf PDF
SOW App 017 JBER Telecom Standards 20AUG2025.pdf PDF
Attachment 2_Relevant Experience Project Template.pdf.docx DOCX document
Attachment 6_NAF Standard Clauses.pdf PDF
SOW App 003 AF IMT 3065 Progress Report.pdf PDF
SOW App 006 Dig Permit Custom Map Elmendorf.pdf PDF
SOW App 007 Dig Permit Custom Map Richardson.pdf PDF
SOW App 014 JBER Environmental Protection and Solid Waste Management Specs 18FEB2026.pdf PDF
Attachment 3_Wage Determination_20260102.pdf PDF
Attachment 7_Price Proposal.xlsx XLSX spreadsheet
FA500026R0001_20260323.pdf PDF
SOW App 005 DD Form 1354.pdf PDF
SOW App 009 JBER IFS Vol 1. Elmendorf.pdf PDF
SOW App 010 JBER IFS Vol 2. Richardson.pdf PDF
SOW App 011 JBER Asbestos Management and Operating Plan 23FEB2021.pdf PDF
SOW App 012 JBER CAD GIS RECORD DRAWING AS BUILT STANDARD 2024_FINAL.pdf PDF
Attachment 1_2026 JBER MACC SOW.pdf PDF
Attachment 4_Technical Definitions.pdf PDF
Attachment 5_Self-Scored Worksheet Final.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT PROGRESS SCHEDULE Form Approved OMB NO. 0704-0188(See Contractor's Instructions on Reverse)

Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information, Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302, and to the Office of Management and Budget Paperwork Reduction Project 0704-0188, Washington DC 20503. Please DO NOT RETURN your form/questionnaire to either of these addresses. Send your completed form/questionnaire to : SAF/AQCP, 1060 Air Force Pentagon, Washington DC 20330-1060

DATE SIGNED

DATE SIGNED CONTRACTING OFFICER'S SIGNATURE

CONTRACTOR'S NAME (Last, First, Middle Initial)

1. CONTRACT NO. 8. PROJECT TITLE

3. COMPLETION DATE

4. PURCHASE REQUEST NO.

LINE

NO

A

WORK ELEMENTS

B

C

WEEKS

D E F G H I J K L M N O P Q

10. APPROVAL RECOMMENDED BY:

DATE SIGNED

2. STARTING DATE

INSTALLATIONS ENGINEER'S SIGNATURE

5. PROJECT NO.

6. ACTUAL STARTING DATE

7. ACTUAL COMPLETION DATE

9. SUBMITTED BY:

ADDRESS (Street, City, State, Zip Code)

CONTRACTOR'S SIGNATURE 11. APPROVED BY:

AF IMT 3064, 20030901, V1 PREVIOUS EDITIONS ARE OBSOLETE

INSTRUCTIONS TO CONTRACTORS

1. Prepare three copies of AF Form 3064, in accordance with these instructions, and submit to the contracting officer at the time stated in the contract or as established by the contracting officer.

2. Blocks 1, 2, and 3. Enter the contract number, starting date, and completion date as shown on the contract.

3. Block 8. Enter the title of the project as shown on the contract.

4. Block 9. Enter name and address of your firm. The three copies submitted to the contracting officer must be dated and signed by the contractor or an authorized representative of the firm.

5. Lines 1 through 12. Major elements of work (whether unit price or lump sum contract) such as excavation, concrete work, carpentry, engineering, installation of communication electronic facilities, etc., will be shown in Column B in logical sequence and in sufficient detail to identify the element. If the contract calls for more than 11 work elements, additional copies of the AF Form 3064 may be used as a continuation for the work elements.

6. The percentage of each listed work element to the complete job will be shown opposite each element in Column C. As an example, if 3 work elements are shown: excavation, concrete work, and backfill, and it is estimated that excavation is 50% of the total job, concrete 30%, and backfill 20%, these percentages will be shown opposite each element. The total must equal 100%.

7. Columns D through Q will be used to show planned periodic progress, as required by the contracting officer, during the period of the contract. Only the top half of the space under these columns will be used by contractors. Using the example cited above and assuming that the contract period for performance is 8 weeks, and it is planned to accomplish 10% of the excavation work the 1st week and 20% each week until excavation is complete, 10 would be shown in the upper half of Line 1 under Column D, 20 under Column E, and 20 under Column F for a total of 50%. If it is planned to accomplish the concrete work during the 4th, 5th, and 6th weeks in equal amounts, 10 would be entered under Columns G, H, and I on Line 2. Assuming the backfill will be accomplished during the 7th and 8th weeks, 10 would be entered under Columns J and K on Line 3. If the contract extends beyond 14 weeks, additional copies of AF Form 3064 may be used as a continuation of performance record.

8. Total amount of work planned at intervals as shown in Columns D through Q will be totaled and entered in the top half of the space under the appropriate column of Line 12. Again, using the example cited above, the totals under Columns D through K would read 10, 20, 20, 10, 10, 10, 10, 10 for a total of 100%. These totals will be used to plot an overlay graph using Lines 4 through 11, beginning with Column D and extending to the right the number of columns (weeks) authorized by the contract for performance time.

9. In the event the contract is modified by the contracting officer under terms of the contract, changing the progress of work as originally scheduled, adding or deleting work or changing the original completion date, a revised progress schedule will be prepared and submitted to the contracting officer for approval. In preparing the revised schedule, the amount of work completed will be considered, together with the changed new completion date set forth in the contract modification. Considering these factors, the work under the contract will be rescheduled over the new total performance time in the same manner that the original schedule was prepared. The new completion date will be entered in Block 3. "First Revised Schedule," "Second Revised Schedule," etc., will be entered to the left of the form title. Time of submission of the revised schedule will be determined by the contracting officer.

10. At such intervals as may be established by the contracting officer, the contractor will submit to the contracting officer AF Form 3065, "Contract Progress Report," indicating the percentage of work accomplished for each work element during the established reporting period. Accurate reports are of the utmost importance to the contractor and to the Government, since the percentage of completion, or progress, thus reported is used in administration of the contract and may be used in connection with approval of partial payments under the contract. Care should be taken to plan the work in such manner that it can be accomplished as stated in this schedule. If, for any reason, it becomes known that any part of the progress under this contract will be delayed, this fact should be reported to the contracting officer immediately.