This is a template for AF Form 3064 and Form 66, which are Air Force progress schedule and contract material submittal forms used for construction project tracking and documentation.
The template includes two primary sections: AF Form 3064 for contract progress scheduling, containing fields for contract number (FA441725F0267), project title (Replace 25 IS HVAC), starting and completion dates, purchase requisition number, project number, and actual start/completion dates. The form includes line items for work elements with columns for tracking percentages and weekly/cumulative progress totals across multiple time periods. The second section is Form 66, a Schedule of Material Submittals form, which documents required submittals for project CP 1026752 (Repair Command Post Bldg 90208, Contract FA441720C0002). This form tracks various submittal types including shop drawings, manufacturer's data, samples, certifications, performance test reports, delivery tickets, warranties, O&M manuals, installation procedures, and schedules/plans. The form includes columns for line item descriptions, submittal types, date received, approval status (approved/disapproved), contractor resubmittal requirements, and remarks. Line items listed cover standard construction elements such as backfill, aggregate base course, Portland cement base, asphaltic concrete paving, site water lines, sodding, landscape planting, concrete work, and expansion joints. The template is designed for use by project engineers and contract administrators to monitor contractor progress and material submissions throughout a construction project lifecycle.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Combined RFIs - With Answers - FINAL 13 Apr 2026.xlsx | XLSX spreadsheet | |
| FA441726B00010004 - Solicitation Amendment - Released New RFIs.pdf | ||
| FA441726B00010003 - Solicitation Amendment SF 30 - Released.pdf | ||
| FA441726B00010002 - Solicitation Amendment - RELEASED.pdf | ||
| PWS - Demo Facility 90326 - No. of Days Corrected - 3 Mar 26.pdf | ||
| Asbestos LBP Survey Bldg. 90326 - Jan 2009.pdf | ||
| Combined RFIs - With Answers - FINAL.xlsx | XLSX spreadsheet | |
| FA441726B00010001 - Solicitation Amendment SF 30.pdf | ||
| Site Visit Minutes - Demo Reef Facility - 24 Mar 26 - Signed.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Form Approved | ||||||||||||||
| OMB No. 0704-0188 | ||||||||||||||
| Public reporting for the collection of informationis estimated to average 15 minutes per response, inlcuding the time for reviewing instructions, searching exisiting data sources, gathering the data, completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of the collection of information, including suggestions for reducing this burden to the Department of Defense, Washington Headquarters Services. Directorate for Information, Operations and Reports, 1215 Jefferson Davis Highway Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget Paperwork Reduction Project 0704-0188, Washington, DC 20503. Please DO NOT RETURN your (form questionnaire) to either of these addresses. Send your completed (form questionnaire) to: SAF AQCO Washington, DC 20330-1000. | ||||||||||||||
| 1. Contract No.: | 8. Project Title | 10. Approval Recommended by: | ||||||||||||
| FA441725F0267 | Replace 25 IS HVAC | |||||||||||||
| 2. Starting Date: | ||||||||||||||
| 3. Completion Date: | 9. Submitted by: | 11. Approved By: | ||||||||||||
| 4. Purchase Req No.: | Date Signed | Contractor's Signature | Date Signed | Contracting Officer's Signature | ||||||||||
| 5. Project No.: | ||||||||||||||
| 6. Actual Starting Date: | ||||||||||||||
| 7. Actual Completion Date: | ||||||||||||||
| Line No. | Work Elements | % | ||||||||||||
| A | B | C | ||||||||||||
| 1 | ||||||||||||||
| 2 | ||||||||||||||
| 3 | ||||||||||||||
| 4 | ||||||||||||||
| 5 | ||||||||||||||
| 6 | ||||||||||||||
| 7 | ||||||||||||||
| 8 | ||||||||||||||
| 9 | ||||||||||||||
| 10 | ||||||||||||||
| 11 | ||||||||||||||
| 12 | ||||||||||||||
| 13 | ||||||||||||||
| 14 | ||||||||||||||
| 15 | ||||||||||||||
| 16 | ||||||||||||||
| 17 | ||||||||||||||
| 18 | ||||||||||||||
| 19 | ||||||||||||||
| 20 | ||||||||||||||
| 21 | ||||||||||||||
| 22 | ||||||||||||||
| 23 | ||||||||||||||
| Item Totals | 0% | |||||||||||||
| Weeky Total | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | ||
| Cumulative Total | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| Line No. | Work Elements | % |
| A | B | C |
| 1 | ||
| 2 | ||
| 3 | ||
| 4 | ||
| 5 | ||
| 6 | ||
| 7 | ||
| 8 | ||
| 9 | ||
| 10 | ||
| 11 | ||
| 12 | ||
| 13 | ||
| 14 | ||
| 15 | ||
| 16 | ||
| 17 | ||
| 18 | ||
| 19 | ||
| 20 | ||
| 21 | ||
| 22 | ||
| 23 |
| Weeky Total | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| Cumulative Total | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
CONTRACT PROGRESS SCHEDULE
Form 66
| PROJECT NO. | PROJECT TITLE | SOLICITATION/CONTRACT # | |||||||||||||||||||||
| SCHEDULE OF MATERIAL SUBMITTALS | CP 1026752 | Repair Command Post Bldg 90208 | FA441720C0002 | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | ||||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | SHOP DRAWINGS | MANUFACTURER'S DATA | SAMPLES | CERTIFICATE/CERTIFICATION | PERF. TEST REPORTS | SAMPLE FOR TESTING | DELIVERY TICKETS | WARRANTY FORM/FORMS | MIX DESIGN | INSTALLATION PROCEDURES | EXTRA STOCK | O & M MANUAL & LEGAL REQ'S | SCHEDULES & PLANS | MANF. / INSTALLER QUAL. | DATE RECEIVED | DATE TO CIVIL ENGINEERING | SUBMITTAL NUMBER | APPROVED | DISAPPROVED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
| 01010 DD Form 1354 | |||||||||||||||||||||||
| 01010 Photos | 1 digital copy on CD | ||||||||||||||||||||||
| 01010 AF Form 3064 Schedule | |||||||||||||||||||||||
| 01540 Green Procurement | 4 | 4 | 4 | 4 | 4 | ||||||||||||||||||
| 01560 Environment Protection | 4 | 4 | 4 | 4 | 4 | ||||||||||||||||||
| 01570 Traffic Regulation | 4 | 4 | |||||||||||||||||||||
| 01700 Contract Closeout | 4 | ||||||||||||||||||||||
| 02223 Backfill | 1 | 4 | |||||||||||||||||||||
| 02231 Aggregate Base Course | 1 | 4 | 4 | ||||||||||||||||||||
| 02238 Portland Cement Base | 1 | 4 | 4 | 4 | |||||||||||||||||||
| 02510 Asphaltic Conc Paving | 4 | 4 | 4 | ||||||||||||||||||||
| 02667 Site Water Lines | 4 | 4 | 1 | ||||||||||||||||||||
| 02938 Sodding | 1 | 4 | 4 | 4 | |||||||||||||||||||
| 02950 Landscape Planting | 4 | 4 | 4 | ||||||||||||||||||||
| 03100 Concrete Formwork | 4 | ||||||||||||||||||||||
| 03200 Concrete Reinforcement | 4 | 4 | |||||||||||||||||||||
| 03251 Expansion Joints | 1 | 4 | |||||||||||||||||||||
| 03300 Concrete | 4 | 4 | 4 | ||||||||||||||||||||
| 03370 Concrete Curing | 4 | 4 |