FA500026R0001_AMENDMENT_ 0002 _SF30 Signed.pdf

PDF 374 KB Posted

Attached to
Amendment 002***Multiple Award Construction Contract (MACC), Joint Base Elmendorf-Richardson (JBER), AK – Solicitation
Solicitation number
FA500026R0001
Issued by

About this file

This is Standard Form 30 Amendment No. 0002 to solicitation FA500026R0001, issued by the Air Force on April 21, 2026. The amendment addresses additional questions received from offerors and provides the complete answer to question 77 from attachment 8.

The amendment clarifies key submission requirements: offerors must use the Government-provided templates without recreation or formatting modifications; if the instruction page cannot be deleted as directed, it may be submitted as-is without counting against page limits. For Appendix 1 (Project Specific Statements of Work), offerors must submit official contract documentation between the offeror and their client in original format to substantiate self-scores, including SOWs, modifications, and RFIs. The amendment also provides terminology clarification regarding project location categories: "Projects on a Military Base/Federal Government Facility in the United States (excluding Alaska)" should be read as "Projects on a Military Base/Federal Government Facility in the United States south of the 60th parallel," and "Projects in Alaska but not on a Military Base/Federal Government Facility" should be read as "Projects in Alaska and north of the 60th parallel, but not on a Military Base Federal Government Facility." The updated scoresheet from Amendment 0001 contains the proper terminology, and the proposal due date remains unchanged. Cross-references to contract documents, including SOWs, must be included in the 2-page narrative section of the REP attachment, not in individual backup documents.

View the file

Other files

File Type Posted
Attachment 4_Technical Definitions R1 Amendment 0001.pdf PDF
Attachment 8_2026 JBER MACC Q and A.pdf PDF
JBER MACC Pre-Proposal Conference-20260331_163518UTC-Meeting Recording.mp4 MP4 file
Attachment 1_2026 JBER MACC SOW R1 Amendment 01.pdf PDF
Attachment 5_Self-Scored Worksheet R1 Amendment 01.xlsx XLSX spreadsheet
2026 MACC Pre-Proposal Sign-In Sheet.pdf PDF
FA500026R0001_AMENDMENT_0001_SF30 Signed.pdf PDF
Attachment 2_Relevant Experience Project Template R1 Amendment 01.docx DOCX document
Attachment 1_2026 JBER MACC SOW.pdf PDF
Attachment 4_Technical Definitions.pdf PDF
Attachment 5_Self-Scored Worksheet Final.xlsx XLSX spreadsheet
FA500026R0001_20260323.pdf PDF
SOW App 002 AF IMT 3064 Progress Schedule.pdf PDF
SOW App 005 DD Form 1354.pdf PDF
SOW App 009 JBER IFS Vol 1. Elmendorf.pdf PDF
SOW App 010 JBER IFS Vol 2. Richardson.pdf PDF
SOW App 011 JBER Asbestos Management and Operating Plan 23FEB2021.pdf PDF
SOW App 012 JBER CAD GIS RECORD DRAWING AS BUILT STANDARD 2024_FINAL.pdf PDF
SOW App 003 AF IMT 3065 Progress Report.pdf PDF
SOW App 006 Dig Permit Custom Map Elmendorf.pdf PDF
SOW App 007 Dig Permit Custom Map Richardson.pdf PDF
SOW App 014 JBER Environmental Protection and Solid Waste Management Specs 18FEB2026.pdf PDF
Attachment 3_Wage Determination_20260102.pdf PDF
Attachment 7_Price Proposal.xlsx XLSX spreadsheet
SOW App 001 AF IMT 3000 Submittal.pdf PDF
SOW App 004 Contractors Fire Safety Guide Rev 14 September 2017.pdf PDF
SOW App 008 Dig Permit Fillable Template.pdf PDF
SOW App 013 Environmental Precon Checklist 21JAN2025.pdf PDF
SOW App 015 JBER Hazardous Waste Management Plan 26MAR2025.pdf PDF
SOW App 016 JBER Integrated Hazardous Material Plan 31MAY2025.pdf PDF
SOW App 017 JBER Telecom Standards 20AUG2025.pdf PDF
Attachment 2_Relevant Experience Project Template.pdf.docx DOCX document
Attachment 6_NAF Standard Clauses.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required) See Section G

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Continuation Page.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Brian Barcelona, Acquisition Flight Chief

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

2. AMENDMENT/MODIFICATION NUMBER

PAGE OF PAGES

1 3

6. ISSUED BY CODE FA5000 7. ADMINISTERED BY (If other than Item 6)

5. PROJECT NUMBER (If applicable)

JBER MACC

CODE

FA5000 673 CONS

10480 SIJAN AVE STE 242, CP 907 552 5614

JBER, AK 99506-2501

UNITED STATES

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NUMBER

FA500026R0001

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE

(X)

4. REQUISITION/PURCHASE REQUISITION NUMBER 3. EFFECTIVE DATE

04/21/2026

1. CONTRACT ID CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE SUMMARY OF CHANGES

Block 14, Description of Amendment/Modification:

The purpose of this amendment is to:

a. Provide answers to additional questions received by the Government.

b. Provide the complete answer to question 77 of attachment 8.

a. Provide answers to additional questions received by the Government.

Q: Please confirm that Offerors may recreate their own relevant experience templates that contains all information included in Attachment 2, so that we can add headers/footers, create bold/underlined subheadings in the project narrative section, and perform small edits for clarity (Missing letters, inconsistent italics/bolding, etc.), and create headings for a table of contents. The current document is locked and even the first page – which we are instructed to delete and not submit – cannot be deleted.

A: No, please use provided templates. If the first page cannot be deleted as instructed, please submit as is and the instruction page will not be counted against the total.

Q: If the Government wants offerors to use their original template, please release an unlocked version so that headers/footers and small formatting edits such as bold/underline/etc. can be added.

A: Please use provided templates.

Q: Many of the original SOW files we will be submitting have their own pagination on the bottom, which will not correspond to the total combined Appendix page count. Will the Government allow for subsections within Appendix 1 (i.e. Appendix 1 Section A.1 –Category 1 Project 1, Section B.2 -Category 2 Project 2) to simplify SOW page number and section references and ensure ease of evaluating the project criteria?

A: Please follow the instructions for cross-referencing relevant experience documentation as indicated in Section L, L-2, 1.8.2.6 of the solicitation.

Q: Will the Government allow for additional official reference documents (such as drawings, modifications, change orders, etc.) beyond the SOW, as many project criteria are contained in these additional documents and not in the original SOW – or the documents are titled something other than a SOW/PWS.

A: See attachment 8, question number 86.

Q: Other Scorecard-style RFPs have requested that the SOW/contract documentation be marked with comments in the pdf to highlight the project criteria and make for easy evaluation. Would the Government consider allowing this instead of or in addition to references within the narrative to ensure all project criteria are noted?

A: No, offerors are to cross-reference contract documents, including SOWs as indicated in Section L, L-2, L-2, 1.8.2.6 of the solicitation in the REP narrative. Any comments should be included in the 2-page narrative section of the REP attachment not in the individual back-up documents.

Q: Would the Government please revise the REP to match the revised language in Amendment 1 and provide a 1-week extension to allow respondents time to re-do the forms in the revised amended REP template?

A: No revision will be made to the REP Template. Anywhere "Projects on a Military Base/Federal Government Facility in the United States (excluding Alaska)" is found, read it as "Projects on a Military Base/Federal Government Facility in the United States south of the 60th parallel". Anywhere "Projects in Alaska but not on a Military Base/Federal Government Facility" is found, read it as “Projects in Alaska and north of the 60th parallel, but not on a Military Base Federal Government Facility". The updated scoresheet from Amend 0001 contains the proper terminology. The proposal due date will remain unchanged.

Q: Attachment 5, which is the scorecard does not match Attachment 2. In the Q&A it says to use the scorecard, but what do we do in Attachment 2 as we are supposed to check a box. Should this not match with attachment 2?

A: See answer to previous question.

b. Provide the complete answer to question 77 of attachment 8.

Q: Regarding the above-referenced solicitation, please clarify what is to be included in Appendix 1, Project Specific Statements of Work. Is the format at our discretion?

A: Appendix 1 is for Statements of Work any official contract documentation between the offeror and their Client that substantiates the offeror's self-score (e.g. a modification, RFI adding or clarifying work, etc.) for the submitted REPs. See Solicitation Sec. L-2,1.8.2.4.

The Government expects SOWs and other documents in Appendix 1 to be included in their original format.

FA500026R0001_AMENDMENT_0001_SF30 Signed.pdf
L-2 PROPOSAL PREPARATION INSTRUCTIONS

SECTION SF 30 BLOCK 14 CONTINUATION PAGE SUMMARY OF CHANGES.pdf

1 CONTRACT ID CODE:
4 REQUISITIONPURCHASE REQUISITION NUMBER:
FA5000:
5 PROJECT NUMBER If applicable JBER MACCRow1:
undefined:
9B DATED SEE ITEM 11:
undefined_2:
10A MODIFICATION OF CONTRACTORDER NUMBER:
CODE:
10B DATED SEE ITEM 13:
undefined_3:
A THIS CHANGE ORDER IS ISSUED PURSUANT TO Specify authority THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A:
undefined_4:
undefined_5:
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
undefined_6:
D OTHER Specify type of modification and authority:
is not: Off
is required to sign this document and return: Off
copies to the issuing office:
14 DESCRIPTION OF AMENDMENTMODIFICATION Organized by UCF section headings including solicitationcontract subject matter where feas:
ble:
15A NAME AND TITLE OF SIGNER Type or print:
16A NAME AND TITLE OF CONTRACTING OFFICER Type or print Brian Barcelona Acquisition Flight Chief:
15C DATE SIGNED:
16C DATE SIGNED: 4/21/2026
2026-04-21T16:12:44-0800
BARCELONA.BRIAN.ALEXANDER.1246753403
Text4: x
Text5: