This document contains an AF Form 3064 Contract Progress Schedule template and instructions for its use, as well as details of Solicitation Number FA480922B0001. The solicitation is for a Simplified Acquisition of Base Engineer Requirements indefinite-delivery/indefinite-quantity multiple award contract set aside for 8(a) small businesses. Work will encompass maintenance, repair, alteration, and minor construction projects at Seymour Johnson Air Force Base, Fort Fisher Military Recreation Area, and Dare County Bombing Range in North Carolina across trades such as concrete, electrical, and asbestos abatement. Interested parties should register at SAM.gov for solicitation information and submit questions by October 4th, 2022. The IDIQ base year is twelve months with four twelve-month option periods and a six-month extension, to be performed at Seymour Johnson AFB, Fort Fisher, and Dare County Bomb Range in North Carolina.

The AF Form 3064 is a template for contractors to submit a Contract Progress Schedule to the contracting officer for approval. It includes instructions for contractors to list work elements by percentage, planned completion dates, and actual progress. Contractors will also submit periodic Contract Progress Reports using AF Form 3065.

View the file

Other versions and copies of AF Form 3064

File Revision Posted Attached to
Attachment C - AF Form 3064.xlsx Revision not stated Airfield Blast Shield
AF Form 3064.xlsx Revision not stated Demo B5276 & B8129 Amendment 0001
Attachment F BLANK SAMPLE AF Form 3064.xlsx Revision not stated Robins AFB Paving Multi-Award IDIQ
Template - AF IMT 3064 and 66 Fillable - Progress Schedule.xlsx Revision not stated Demo Reef Dining Facility, Bldg 90326
SOW App 002 AF IMT 3064 Progress Schedule.pdf Revision not stated Amendment 002***Multiple Award Construction Contract (MACC), Joint Base Elmendorf-Richardson (JBER), AK – Solicitation
FNWZ 17-0021A - Att E - AF Form 3064.xlsx Revision not stated Demo B6142
FNWZ 21-0071 - Att E - AF Form 3064.xlsx Revision not stated Demo B6119
Attachment 16 - AF FORM 3064 Contract Progress Schedule.xlsx Revision not stated SABER IDIQ - Dover AFB
SOW Attach 9 - AF Form 3064 PSFB.xlsx Revision not stated Peterson SFB Bldg 3 Soil Erosion Repair
Attachment 3_AF IMT 3064_2003091_VI_Progress Schedule.pdf Revision not stated Hazardous Materials Abatement Contract - IDIQ
Attachment 9 - BLANK SAMPLE AF Form 3064.xlsx Revision not stated Dismantling of Modular Facility & Storage Racks
Attachment 2.7 - AF Form 3064 Schedule Template.xlsx Revision not stated Multiple Award Basic Ordering Agreement for Construction Services at Cannon AFB, NM
Attachment 12 - AF Form 3064 Contract Progress Schedule - Sample.xlsx Revision not stated Civil Works IDIQ 2024 - Hurlburt Field, FL
Attachment 12 - Af Form 3064 Contract Progress Schedule-Sample.xlsx Revision not stated Civil Works IDIQ 2024 - Hurlburt Field, FL
Attah 15 - AF Form 3064.xlsx Revision not stated SABER IDIQ - Hurlburt Field FL
ATCH L4 - Contract Progress Schedule_AF Form 3064 - Fillable.xlsx Revision not stated ADDITION TO CDC WEST BLDG 90306, CP1024656
Attachment 1k Mini-MACC SOW AF IMT 3064 Progress Schedule.pdf Revision not stated JBER Mini-MACC
BLANK SAMPLE AF Form 3064.xlsx Revision not stated Civil Engineering Multiple Award Construction Contract III, IDIQ
Atch BLANK SAMPLE AF Form 3064.xlsx Revision not stated Design/Build ANG ACS Weapons Facility
Attachment 07 - AF Form 3064.pdf Revision not stated Construct/Repair LOX Canopies
Show all 20

Who attaches AF Form 3064

Other files

File Type Posted
FA480922B0001 - Bid Record - 14-Dec-22 (2 pages).pdf PDF
FA480922B0001 Abstract - Bid Opening 14-Dec-22 (4 pages).pdf PDF
Solicitation Amendment - FA480922B00010006 (Conformed) (83 pages) posted 7-December-2022.pdf PDF
Solicitation Amendment FA480922B00010006 SF 30 (4 pages) dated 7-December-22.pdf PDF
25. Min Rqmnt Proj (VKAG 20-1040) SOO (10 pgs) Rev 3 dtd 6-Dec-2022.pdf PDF
FA480922B00010005 Request for Information dated 5-December-2022.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) Statement of Objectives (REVISION 02) (10 pages) dated 1-November-2022.pdf PDF
Solicitation Amendment - FA480922B00010005 (Conformed) (87 pages) dated 28-November-2022.pdf PDF
Solicitation Amendment FA480922B00010005 SF 30 (13 pages) dated 28-November-2022.pdf PDF
2. SABER XI Statement of Work (67 pages) Revision 3 dated 26Oct22.pdf PDF
28. Section 271000 Building Telecommunications Cabling System (13 pages) dated 27-Oct-22.pdf PDF
Solicitation Amendment FA480922B00010004 SF 30 (3 pages) dated 14-October-2022.pdf PDF
Solicitation Amendment FA480922B00010003 SF 30 (10 pages) dated 27-September-2022.pdf PDF
2. SABER XI Statement of Work (66 pages) Revision dated 24-Sept-22.pdf PDF
26. Minimum Requirement Project (VKAG 20-1040) Drawings (Full Set) (8 pages) Revision dated 9-Sept-22.pdf PDF
Solicitation Amendment FA480922B00010002 SF 30 (9 pages) dated 22-September-2022.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) Statement of Objectives (9 pgs) Revision dtd 22-Sept-22.pdf PDF
SABER XI Requests for Information (RFIs) and Responses (19 pages) 20 September 2022.pdf PDF
Solicitation Amendment FA480922B00010001 SF 30 (2 pages) dated 9-September-2022.pdf PDF
12. AF Form 66 Schedule of Material Submittals - VKAG 22-1200 SABER Basic XI (1 page) Revision dated 6-September-22.pdf PDF
SABER XI PreBid Conference and Site Visit Meeting Minutes with Attachments (18 pages) dtd 30 Aug 22.pdf PDF
10. SJAFB Standard Engineering Drawing Preparation and Support (CAD Standards) (71 pages) dated 1-Dec-22.pdf PDF
23. SABER XI IDIQ Bid Schedule (2 pages) - BLANK.pdf PDF
18. Request for Information (1 page) - BLANK.pdf PDF
14. AF Form 103 Base Civil Engineering Work Clearance Request (2 pages) - BLANK.pdf PDF
12. AF Form 66 Schedule of Material Submittals - VKAG 22-1200 SABER Basic XI (1 page) dated 24-May-22.pdf PDF
Solicitation - FA480922B0001 - SJAFB SABER (Posted 19-Aug-22).pdf PDF
19. Contractor Production Report (QC Report) (8 pages) - EXAMPLE.pdf PDF
5. Environmental Management System Site-Specific Training (15 pages) dated April-22.pdf PDF
7.Section 02821 Centipede Grass Hydro-Seeding (10 pages) dated 24-May-22.pdf PDF
22. Wage Determinations (51 pages) dated 25-Feb-22.pdf PDF
13. AF Form 66 Schedule of Material Submittals (1 page) - BLANK.pdf PDF
2. SABER XI Statement of Work (65 pages) dated 12-Aug-22.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) - Statement of Objectives (5 pages) dated 9-May-22.pdf PDF
15. AF Form 3000 Material Approval Submittal (2 pages) - BLANK.pdf PDF
27. Pre-Proposal Conference and Site Visit Location Map (2 pages).pdf PDF
4. Section 01560 Environmental Management Supplement SJAFB Contractors (2 pages) dated 5-Jul-22.pdf PDF
26. Minimum Requirement Project (VKAG 20-1040) Drawings (Full Set) (7 pages) dated 1-Nov-20.pdf PDF
20. SJAFB Access Request Application (2 pages) - EDITABLE.pdf PDF
6. Section 02051 Asbestos Removal, Cleanup and Disposal, Facility Demolition (2 pages) dated 24-May-22.pdf PDF
24. Determination of Contractor Responsibility (3 pgs) - BLANK.pdf PDF
21. Climatic Data Summary for SJAFB (2 pages) dated 13-May-22.pdf PDF
11. Installation Development and Design (ID2) SJAFB (90 pages) dated Mar-11.pdf PDF
1. Nonapropriated Fund (NAF) Standard Clauses (21 pages) dated 2-Jun-22.pdf PDF
9. Seymour Johnson Mass Notification System Message Script (2 pages) dated 24-May-22.pdf PDF
8. Section 02938 Sod (2 pages) dated 24-May-22.pdf PDF
16. AF Form 3065 Contract Progress Report (1 page) - BLANK.pdf PDF
3. Section 01560 Environmental Protection (8 pages) dated 1-Jul-22.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT NO. 8. PROJECT TITLE 10. APPROVAL RECOMMENDED BY:

2. STARTING DATE 31-May-19 DATE SIGNED Government PM Signature:

3. COMPLETION DATE 29-Aug-19 9. SUBMITTED BY:

4. PURCHASE REQUEST NO. DATE SIGNED Contractor's Name (Last, First, Middle Initial) CONTRACTOR'S SIGNATURE 11. APPROVED BY

5. PROJECT NO. Address (Street, City, State, Zip Code) DATE SIGNED CONTRACTING OFFICER'S SIGNATURE

6. ACTUAL STARTING DATE

7. ACTUAL COMPLETION DATE

LINE NO. WORK ELEMENTS %

A B C 3.00% 1.00% 2.00% 3.00%

Bonds & Submittals 100.00% 1.00% 5.00% 5.00% 5.00% 5.00% 5.00% 15.00% 20.00% 30.00% 9.00% 100.00% 5.00% 5.00% 5.00%

6.00% 1.00% 1.00% 1.00% 1.00% 1.00% 1.00% 6.00%

27.00% 2.00% 5.00% 5.00% 5.00% 5.00% 5.00% 27.00%

38.00% 3.00% 7.00% 7.00% 7.00% 7.00% 7.00% 38.00%

16.00% 5.00% 5.00% 6.00% 16.00%

5.00% 3.00% 2.00% 5.00%

1.00% 2.00% 11.00% 13.00% 13.00% 13.00% 18.00% 18.00% 9.00% 2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% CUMULATIVE TOTAL: 100.00% 1.00% 3.00% 14.00% 27.00% 40.00% 53.00% 71.00% 89.00% 98.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

1.00% 5.00% 5.00% 5.00% 5.00% 5.00% 15.00% 20.00% 30.00% 9.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% CUMULATIVE TOTAL ACTUAL PROGRESS 100.00% 1.00% 6.00% 11.00% 16.00% 21.00% 26.00% 41.00% 61.00% 91.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

0.00% 3.00% -3.00% -11.00% -19.00% -27.00% -30.00% -28.00% -7.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

31-Oct 15-Nov 30-Nov 15-Dec 31-Dec15-Aug 31-Aug 15-Sep 30-Sep 15-Oct31-May 15-Jun 30-Jun 15-Jul 31-Jul

PREVIOUS EDITIONS ARE OBSOLETE

AF IMT 3064, 20030901. V1

DIFFERENCE:

FA303019FA039

CONTRACT PROGRESS SCHEDULE

ORIGINAL

PCU Roofing

Closeout7

Wood Nailers

Roof Insulation

Mobilization2

Sheet Metal Flashings

FA480922B0001

Attachment 17

1.00% 3.00%

14.00%

27.00%

40.00%

53.00%

71.00%

89.00%

98.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

1.00%

6.00%

11.00%

16.00%

21.00%

26.00%

41.00%

61.00%

91.00%

100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

31-May 15-Jun 30-Jun 15-Jul 31-Jul 15-Aug 31-Aug 15-Sep 30-Sep 15-Oct 31-Oct 15-Nov 30-Nov 15-Dec 31-Dec

FA480922B0001

INSTRUCTIONS TO CONTRACTORS

1. Prepare three copies of AF Form 3064, in accordance with these instructions, and submit to the contracting officer at the time stated in the contract or as established by the contracting officer.

2. Blocks 1, 2, and 3. Enter the contract number, starting date, and completion date as shown on the contract.

3. Block 8. Enter the title of the project as shown on the contract.

4. Block 9. Enter name and address of your firm. The three copies submitted to the contracting officer must be dated and signed by the contractor or an authorized representative of the firm.

5. Lines 1 through 12. Major elements of work (whether unit price or lump sum contract) such as excavation, concrete work, carpentry, engineering, installation of communication electronic facilities, etc., will be shown in Column B in logical sequence and in sufficient detail to identify the element. If the contract calls for more than 11 work elements, additional copies of the AF Form 3064 may be used as a continuation for the work elements.

6. The percentage of each listed work element to the complete job will be shown opposite each element in Column C. As an example, if 3 work elements are shown: excavation, concrete work, and backfill, and it is estimated that excavation is 50% of the total job, concrete 30%, and backfill 20%, these percentages will be shown opposite each element. The total must equal 100%.

7. Columns D through Q will be used to show planned periodic progress, as required by the contracting officer, during the period of the contract. Only the top half of the space under these columns will be used by contractors. Using the example cited above and assuming that the contract period for performance is 8 weeks, and it is planned to accomplish 10% of the excavation work the 1st week and 20% each week until excavation is complete, 10 would be shown in the upper half of Line 1 under Column D, 20 under Column E, and 20 under Column F for a total of 50%. If it is planned to accomplish the concrete work during the 4th, 5th, and 6th weeks in equal amounts, 10 would be entered under Columns G, H, and I on Line 2. Assuming the backfill will be accomplished during the 7th and 8th weeks, 10 would be entered under Columns J and K on Line 3. If the contract extends beyond 14 weeks, additional copies of AF Form 3064 may be used as a continuation of performance record.

8. Total amount of work planned at intervals as shown in Columns D through Q will be totaled and entered in the top half of the space under the appropriate column of Line 12. Again, using the example cited above, the totals under Columns D through K would read 10, 20, 20, 10, 10, 10, 10, 10 for a total of 100%. These totals will be used to plot an overlay graph using Lines 4 through 11, beginning with Column D and extending to the right the number of columns (weeks) authorized by the contract for performance time.

9. In the event the contract is modified by the contracting officer under terms of the contract, changing the progress of work as originally scheduled, adding or deleting work or changing the original completion date, a revised progress schedule will be prepared and submitted to the contracting officer for approval. In preparing the revised schedule, the amount of work completed will be considered, together with the changed new completion date set forth in the contract modification. Considering these factors, the work under the contract will be rescheduled over the new total performance time in the same manner that the original schedule was prepared. The new completion date will be entered in Block 3. "First Revised Schedule," "Second Revised Schedule," etc., will be entered to the left of the form title. Time of submission of the revised schedule will be determined by the contracting officer.

10. At such intervals as may be established by the contracting officer, the contractor will submit to the contracting officer AF Form 3065, "Contract Progress Report," indicating the percentage of work accomplished for each work element during the established reporting period. Accurate reports are of the utmost importance to the contractor and to the Government, since the percentage of completion, or progress, thus reported is used in administration of the contract and may be used in connection with approval of partial payments under the contract. Care should be taken to plan the work in such manner that it can be accomplished as stated in this schedule. If, for any reason, it becomes known that any part of the progress under this contract will be delayed, this fact should be reported to the contracting officer immediately.

AF IMT 3064, 20030901, V1 PREVIOUS EDITIONS ARE OBSOLETE

FA480922B0001

SOW Attch 15. AF IMT 3064 (Blank)
AF3064

AF3064.xfdl_