This is a Statement of Work (SOW) for the 2026 Joint Base Elmendorf-Richardson (JBER) Multiple Award Construction Contract (MACC), an Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract issued by the Department of the Air Force Pacific Air Forces. The MACC is designed to supplement the Civil Engineer's in-house capability to perform construction, facility repair/alteration, and real property repair/alteration projects on an as-needed basis, primarily targeting repair and alteration work but also including new construction. The contractor shall provide all materials, equipment, labor, and general conditions to accomplish design, repair, and construction projects across various trades including carpentry, hazardous materials abatement, demolition, mechanical, electrical, plumbing, concrete masonry, welding, and paving. Work is geographically scoped to properties and facilities within JBER's jurisdiction in Alaska. The SOW establishes that task orders will be issued on a firm-fixed-price basis following Fair Opportunity Proposal Request (FOPR) procedures with competitive awards. Design efforts are anticipated at 65%, 95%, or 100% completion levels, with contractors responsible for providing design documentation including drawings, scope of work, cost estimates, and submittals. Contractors must have in-house design staff or hire a design firm, provide project management, on-site superintendence, safety, environmental compliance, quality control, and administration for all task order efforts.

The SOW incorporates extensive operational, environmental, safety, and quality control requirements. All construction shall comply with the Unified Facilities Guide Specifications (UFGS), Elmendorf Architectural Compatibility Standards, Richardson Installation Design Guide, and applicable federal, state, and local regulations including OSHA standards and EPA environmental requirements. Key personnel requirements include a Program Manager with minimum 10 years of commercial construction experience, Project Managers with 10 years of documented experience, a Site Superintendent with 5 years of experience required on-site during work, and a Site Safety and Health Officer with 5 years of experience and 30-hour OSHA certification. The contractor must establish and maintain a Quality Control Management Plan approved by the government prior to task order award, with daily quality control inspections and documentation. Environmental protection requirements are extensive, including submission of an Environmental Protection Plan within 15 working days of Notice to Proceed, Erosion and Sediment Control Plans for projects disturbing one or more acres, hazardous materials tracking and management, spill prevention and response procedures, and waste management in accordance with federal regulations for large quantity generators. Performance and payment bonds equal to 100% of task order price are required for awards exceeding $35,000, due within 10 days of task order award. Pre-construction conferences are mandatory, and contractors must submit submittals including material specifications, shop drawings, construction schedules, and operations and maintenance manuals. The SOW includes detailed appendices providing templates for erosion control plans, hazardous material tracking forms, spill reporting documents, hazardous waste management plans, and waste disposal worksheets.

View the file

Other files

File Type Posted
FA500026R0001_AMENDMENT_ 0002 _SF30 Signed.pdf PDF
Attachment 4_Technical Definitions R1 Amendment 0001.pdf PDF
Attachment 8_2026 JBER MACC Q and A.pdf PDF
JBER MACC Pre-Proposal Conference-20260331_163518UTC-Meeting Recording.mp4 MP4 file
Attachment 1_2026 JBER MACC SOW R1 Amendment 01.pdf PDF
Attachment 5_Self-Scored Worksheet R1 Amendment 01.xlsx XLSX spreadsheet
2026 MACC Pre-Proposal Sign-In Sheet.pdf PDF
FA500026R0001_AMENDMENT_0001_SF30 Signed.pdf PDF
Attachment 2_Relevant Experience Project Template R1 Amendment 01.docx DOCX document
Attachment 4_Technical Definitions.pdf PDF
Attachment 5_Self-Scored Worksheet Final.xlsx XLSX spreadsheet
FA500026R0001_20260323.pdf PDF
SOW App 002 AF IMT 3064 Progress Schedule.pdf PDF
SOW App 005 DD Form 1354.pdf PDF
SOW App 009 JBER IFS Vol 1. Elmendorf.pdf PDF
SOW App 010 JBER IFS Vol 2. Richardson.pdf PDF
SOW App 011 JBER Asbestos Management and Operating Plan 23FEB2021.pdf PDF
SOW App 012 JBER CAD GIS RECORD DRAWING AS BUILT STANDARD 2024_FINAL.pdf PDF
SOW App 003 AF IMT 3065 Progress Report.pdf PDF
SOW App 006 Dig Permit Custom Map Elmendorf.pdf PDF
SOW App 007 Dig Permit Custom Map Richardson.pdf PDF
SOW App 014 JBER Environmental Protection and Solid Waste Management Specs 18FEB2026.pdf PDF
Attachment 3_Wage Determination_20260102.pdf PDF
Attachment 7_Price Proposal.xlsx XLSX spreadsheet
SOW App 001 AF IMT 3000 Submittal.pdf PDF
SOW App 004 Contractors Fire Safety Guide Rev 14 September 2017.pdf PDF
SOW App 008 Dig Permit Fillable Template.pdf PDF
SOW App 013 Environmental Precon Checklist 21JAN2025.pdf PDF
SOW App 015 JBER Hazardous Waste Management Plan 26MAR2025.pdf PDF
SOW App 016 JBER Integrated Hazardous Material Plan 31MAY2025.pdf PDF
SOW App 017 JBER Telecom Standards 20AUG2025.pdf PDF
Attachment 2_Relevant Experience Project Template.pdf.docx DOCX document
Attachment 6_NAF Standard Clauses.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JBER MACC SOW

Table of Contents

18 Mar 2026

MULTIPLE AWARD CONSTRUCTION CONTRACT

(MACC)

Joint Base Elmendorf-Richardson, Alaska

ATTACHMENT 1

STATEMENT OF WORK GENERAL

CONTRACT PROVISIONS

Revised 18 March 2026

Section 01000 General Contract Requirements

1. Contract Description

2. Contract Requirements

3. Contractor Organization

4. Ordering Procedures

5. Working Hours

6. Submittals

7. Project Status Updates (Partnering)

8. Interruption of Work

9. Project Coordination

Section 01100 General Site Requirements

1. Regulations

2. Standard Products

3. Safety

4. Operations and Storage Areas

5. Vehicles, Pass & Identification, Security Requirements

6. Security Requirements

7. Contractor’s Telephone

8. Employee Standards

9. Prohibited Items

10. Materials and Equipment

12. Work

13. Roadways

14. Airfield Requirements

15. Work in Restricted Areas

16. Utilities Services (FAR 52.236-14)

17. Survey Markers

18. Recording and Preserving Historical and ArchaeologicalFinds

Section 01200 General Design and Regulations Requirements

1. General Design Section

Section 01300 Task Order Execution

1. Notification of Work/Inspection

2. Closeout

3. Warranties

4. Contractor-Furnished Equipment Data

Section 01400 Contractor’s Quality Control and Program Management

1. General

2. Quality Control Plan

3. Program Management Section 01500 Environmental Protection on JBER Section 01600 Management of Hazardous and Solid Waste - JBER

APPENDICES

APPENDIX A EROSION SEDIMENTATION AND CONTROL PLAN TEMPLATE

APPENDIX B JBER CONTRACTOR HAZARDOUS MATERIAL TRACKING FORM

APPENDIX C SPILL REPORTING DOCUMENTS

APPENDIX D HAZARDOUS WASTE MANAGEMENT PLAN TEMPLATE

APPENDIX E SOLID AND HAZARDOUS WASTE FORMS

APPENDIX F LIST OF ADDITIONAL REFERENCED DOCUMENTS

Section 01000 General Contract Requirements

1. Contract Description

1.1. The Multiple Award Construction Contract (MACC) is an Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract for execution that supplements Civil Engineer’s (CE) in-house capability to perform construction, facility repair/alteration, and real property repair/alteration projects on an as needed basis. This requirement is geared primarily towards repair/alteration projects but may also be used to perform new construction projects. The contractor shall provide all material, equipment, labor and general conditions to accomplish design, repair, and construction projects in an expeditious manner. The work may include facility upgrades, utility work, airfield pavement, roads, roofs and other assorted repair and alteration projects. The construction work includes tasks in various trades such as carpentry, hazardous materials abatement/removal, demolition, mechanical, electrical, plumbing, concrete masonry, welding, and paving.

Design as used in this acquisition means project estimating and preparation of complete designs. All construction/design shall be in compliance with the Elmendorf Architectural Compatibility Standards, the Richardson Installation Design Guide and Section 1200 General Design Section.

1.2. Design Build: MACC contractor shall develop project design documentation including drawings, Scope of

Work, cost estimate broken out by CSI division and submittals representative of up to a 65% design effort (unless specified that higher design levels be submitted in Task Order) as adequate to perform the construction. Upon completion of design, and upon acceptance by the Government, construction execution shall commence and be completed in accordance with Task Order requirements. See Section 01200 for specific requirements related to Design.

1.3. Construction Only: MACC contractor shall provided completed design document drawings, Scope of

Work and available specifications to initiate and complete construction execution in accordance with Task Order requirements. The MACC contractor will then develop a price proposal and a schedule to complete project.

1.4. The geographic scope of this contract includes the property and facilities located within the jurisdiction of Joint Base Elmendorf Richardson (JBER).

2. Contract Requirements

2.1 The Contractor shall furnish all management, supervision, labor, materials, equipment, and incidentals required for a broad range of maintenance, repair, and minor/new construction work on various real property facilities covered under this contract, including design and engineering services incidental to construction. The Contracting Officer (CO) will conduct negotiations with the Contractor and issue individual Task Orders (TO) for maintenance, repair and minor construction projects identified by the Base Civil Engineer (BCE) as part of this MACC program.

2.2 MACC Master Specifications

2.2.1 This contract will utilize the Unified Facilities Guide Specifications (UFGS). UFGS standard specifications can be obtained from the Whole Building Design Guide website: https://www.wbdg.org/dod/ufgs. The Unified Facilities Guide Specifications (UFGS) are hereby incorporated into the solicitation and any resultant contract. Each TO will remain under the UFGS version that was in effect at the time of TO award or through any supplements issued by the Government when individual TO’s are modified to add additional work. Only the additional work may be applicable to the current UFGS.

2.2.2 Specifications are numbered and organized in accordance with the Construction Specification Institute’s

(CSI) Master Format. All specifications are filed in Division 2 through 48 per CSI guidelines.

2.2.3 In accordance with FAR 36.101 the order of precedence specified in FAR Clause 52.236-21 shall take https://www.wbdg.org/dod/ufgs precedence over FAR 52.215-8; in the case of difference between drawings and specifications the specifications shall govern.

2.2.4 The Government will identify the required elements of work in the project Scope of Work and Drawings.

Following the project award, the successful contractor shall utilize the UFGS Guide Specs and apply the elements of work identified by the Government to develop the project specific specification to be submitted to the Government for approval.

2.3 Bona Fide Need Requirement. All Task Orders awarded near the end of the fiscal year shall satisfy a bona fide need on or before 31 December of the same calendar year. To satisfy bona fide need the Contractor shall meet either the physical onsite evidence requirement or the documentation evidence requirement, at the CO’s discretion:

2.3.1 Physical Onsite Evidence: A visual inspection of the work site discloses meaningful work has been accomplished, or contractor employees are actively engaged in work performance (no further verification is necessary); or

2.3.2 Documentary Evidence: If physical onsite evidence of performance does not exist, and to prevent unwarranted default proceedings, the CO may request documentary evidence that cost has been incurred, or material has been ordered to allow performance of the task order.

3. Contractor Organization

3.1. The contractor shall have available an in-house design staff or hire a design firm for the development of task orders requiring design efforts up to the 65% or beyond effort to respond to the requirements of this multi-discipline MACC type contract. The contractor shall also provide project management, incidental project design/engineering, on-site superintendence, safety, environmental compliance, quality control and administration for all task order efforts.

4. Ordering Procedures

4.1 As the need arises for performance under the terms of this contract, the CO or authorized representative will issue a Fair Opportunity Proposal Request (FOPR). Orders placed will be competitively awarded using FAR 16.505(b)(1) fair opportunity processes with specific instructions provided within each FOPR.

4.2 Orders shall be issued on a Firm-Fixed Price (FFP) basis. The Contract Line Item Number (CLIN) structure on each order will reflect the FFP for each line item and will strictly follow the CLIN structure outlined in the IDIQ contract. Order competition for subsequent award is as follows:

4.3 Fair Opportunity Proposal Request (FOPR)

4.3.1 The ordering CO will initiate the FOPR process by sending a FOPR letter and attachments (herein referred to as the FOPR package) to IDIQ holders following FAR 16.505.

- The FOPR letter may include the following information

- Date of package

- Proposal due date and name/email address of POC to submit proposal

- Date, time, and location of pre-proposal site visit

- Magnitude of construction estimate IAW FAR 36.204

- Project specific statement of work/performance work statement/statement of objectives

- Estimated Period of Performance (PoP)/Estimated Completion Date (ECD)

- Work schedule

- Other requirement documents

- Bonding requirements

- Identification of liquidated damages rate, if applicable

- Identification of Government furnished property/equipment available, if applicable

- Identification of Superintendent, SSHO and QC requirements

- Other pertinent data such as planned closures for other base-related restriction periods

4.3.2 For each FOPR, the CO will provide the Contractor with one (1) copy of the Government’s Statement of Work (SOW) and requirements package.

4.3.3 Although the Contractor may be given a preliminary or complete design package, it is still the Contractor’s responsibility under FAR 52.236-3 to investigate the site and conditions affecting the work prior to proposal submission. The Contractor may reproduce the drawings and specifications at the Contractor’s own expense if additional copies are needed. The Contractor shall check all drawings and specifications for discrepancies upon receipt and notify the CO or their designated representative immediately of any discrepancies via a written Request for Information (RFI). The RFI shall be forwarded to the CO for review and in-turn forwarded to the assigned MACC Project Manager(s) for review, clarification and response. Enlarged plans and details shall govern where the same work is shown at smaller scales. The Contractor shall compare all drawings and verify the installation before laying out the work and shall be responsible for any errors which might have been avoided thereby.

4.3.4 Brand Name Descriptions: The Statement of Work (SOW), drawings and the Technical Provisions of the specifications may, in some instances, refer to certain items of equipment, material, or article by trade name/brand name. References of this type shall not be construed as limiting competition, but shall be regarded as establishing the physical, functional and performance needs in order to meet the minimum level of quality or reliability desired. These brand name references are not intended to limit materials or services to only the brand name UNLESS a Justification and Approval (J&A) is included with the FOPR. If there are any questions regarding the Government’s definition of minimum quality or reliability standards, in reference to a brand name, a request for additional information shall be requested in writing to the CO within five (5) business days of receiving the FOPR.

4.3.5 Task Order Site Superintendent, Quality Control, and Site Safety and Health Officer requirements.

Each SOW will identify the manning requirements for the above three functions. Depending on job magnitude and complexity, the Government, at its sole discretion, will specify whether one person can perform all three functions, whether two people can perform the three functions or whether a single individual per function are required on the job site.

4.3.6 When one, two or three individuals are required per task order the following personnel mixes are acceptable:

− One Person: Superintendent/QC/SSHO performed by single qualified individual − Two Person: Superintendent + QC/SSHO (dual role) or Superintendent/SSHO (dual role) + QC − Three Person: Superintendent + QC + SSHO

4.3.7 The site superintendent is always required on site IAW FAR 52.236-6 and shall not dual role as the QC unless the task order has been designated as one person IAW 4.3.6 & 4.3.7.

4.3.8 QC and SSHOs are required to attend all construction sites daily to perform their functions unless the task order requires three individuals at which point all three positions are required onsite during performance of work.

4.3.9 If an individual FOPR does not identify the number of required personnel, the default will be “two persons” unless changed in writing by the CO.

4.4 Pre-Proposal Site Visit

4.4.1 After the release of a FOPR, the Government and the Contractors will schedule and conduct a pre-proposal site visit for the project. Interchanges held during the site visit may include, but are not limited to scope of work, method of construction, sequence of operations, progress schedule, means of access to project site, delivery and storage of materials and equipment, work restrictions, coordination requirements, project goals, liquidated damages and potential difficulties/problems. The Contractor shall comply with the requirements of the clause at FAR 52.236-3, Site Investigation and Conditions Affecting the Work.

4.4.2 Any questions asked during the site visit or identified after the site visit shall be submitted by the prime contractor in writing as a Request for Information (RFI) to the CO and designated Contract Specialist within three (3) business days after the site visit unless a shorter timeframe is specified in the FOPR.

Questions received after the deadline may be answered at the sole discretion of the CO. The CO will provide a finalized SOW by amendment (if necessary) to the FOPR following submission of the site visit questions, unless determined otherwise by the CO. The CO will provide a proposal deadline five (5) business days after Government responses to Q&A/RFI’s are posted unless otherwise identified in the

FOPR.

4.4.3 As part of meeting the requirements of FAR 52.236-3, Site Investigation and Conditions Affecting the

Work, the Government shall provide the as-built and other drawings they believe are necessary to support the contractor’s needs and perform the scope of work. Following Task Order (TO)award Contractors may access additional historical drawings related to the project site or facility. Historical records and drawings (if they are available) are located in the 673d CES Civil Engineer Squadron, Bldg. 724, drawing vault.

Contractors will be required to bring a copy of the TO signed by the CO to the drawing vault in order to be authorized access. Contractors shall not use the drawing vault to research any building/project for which they do not have a signed TO or contract/task order. Contractors found violating this policy may have their access to the drawing vault restricted and/or have further administrative actions levied.

4.5 Proposal Submission Process

4.5.1 All Contractors are highly encouraged to submit a proposal for every FOPR under this contract. Failure to propose as a meaningful participant may result in the Contractor’s off-ramping from the MACC program via termination IAW the On/Off Ramp Procedures contained in Section H of the contract. The CO will conduct an annual review on all current MACC contractors to ensure meaningful participation is occurring.

If the CO believes a MACC contractor is not a meaningful participant, a meeting will be established to discuss the Governments concerns.

4.5.2 Normal Response Requirements: If the requirement is determined to be a normal response requirement by the CO, the contractor shall submit a Task Order Proposal to fulfill the requirement within fourteen (14) calendar days or the time specified in the TO, whichever is later. Additional time may be allowed at the discretion of the CO.

4.5.3 Quick Response Requirements: If the requirement is determined to be a quick response requirement by the CO, the contractor shall submit a Task Order Proposal to fulfill the requirement within a maximum of seven (7) calendar days from written notification.

4.5.4 If no proposals or only one proposal is received, the Government, at its discretion, may revalidate the FOPR requirement. The validation process may include interchanges of information with some or all the Contractors to determine whether there are concerns about the FOPR requirement. Should the requirement be validated, the FOPR package may be reissued.

4.5.5 The Contractor’s proposal shall be submitted to the ordering CO on or before the time and date specified in the FOPR letter. Pricing on task order proposals shall be valid for a minimum of 90 calendar days after the required submission date unless otherwise specified in the individual FOPR.

4.5.6 Proposals may be requested and processed up to the point of award in advance of funding, then held, for the entire period specified in the FOPR. If funding becomes available after proposed prices expire IAW the timeline given in the FOPR, all Contractors who submitted a proposal will be offered an opportunity to update their pricing. The CO may cancel a FOPR at CO discretion. After cancellation, a a new FOPR may be issued. It is the government’s intent to award a task order for each proposal processed up to the point of award; however, due to changes in the construction program, congressional budget changes or world events, some projects may be canceled. No compensation for cancelled FOPRs will be granted to the contractor.

4.6 Project Proposal

For FOPRs associated with a new task order, the Contractor shall provide a written proposal describing the Contractor’s approach to the proposed project work described in the Government’s SOO/SOW and project drawings (if any) or a price only proposal may be requested. The proposal shall include at a minimum, a cover letter and a completed pricing schedule.

The FOPR may require all or some of the following additional documents: a narrative describing the approach to the proposed project as described in the Government’s SOO/SOW to include all major components of the project; an AF Form 66 Schedule of Material Submittals identifying any supplemental submittals in addition to those identified by the government; a detailed project schedule in Microsoft Project (will be in Adobe .pdf format), or equivalent, that includes all major components of the project, and their associated percentage of effort; and any other information as needed to demonstrate a complete and thorough understanding of construction effort. The minimum requirements will be identified in each individual FOPR based on the COs discretion, taking into account such factors as complexity, urgency, historical knowledge or other factors affecting the individual FOPR.

The Government intends to make proposals minimally burdensome with the majority being price only or price and technical narrative. The CO at their sole discretion may amend a FOPR at any time to include additional requirements as they become necessary for the Government to ensure clear understanding of a requirement.

4.6.1 Cover Page. The cover page or pages shall include project title, total project cost, list of assumptions, list of requirements, performance period, material long-lead times, any exclusions and any special considerations such as phasing of construction. The contractor’s proposals shall be complete and concise.

4.6.2 Technical Narrative. Upon verbal or written request of the CO, the Contractor shall provide a technical narrative. The written narrative shall describe the Contractor’s approach and shall document the Contractor’s basic design solution to the subject project. The Contractor shall not simply re-state the goals of the Government SOO/SOW but provide sufficient information to demonstrate to the Government a complete and thorough understanding of the requirement and all applicable codes and regulations. The technical narrative shall be no longer than five pages unless otherwise specified in the FOPR.

4.6.3 Price Proposal. The Contractor shall provide their proposed price by completely filling out the pricing requested in the FOPR for all identified Contract Line Items (CLIN’s). Contractors shall be requested to provide a lump sum cost per CLIN. All CLINS shall be added to determine the total proposed price.

4.6.3.1 Detailed Price Proposal (Cost Breakdown). Upon verbal or written request of the CO, the Contractor shall submit a detailed cost breakdown of their proposal within 2 business days of request. The cost breakdown shall include a breakout of costs and quantities for all labor, materials, equipment, overhead, and profit for the prime contractor and all subcontractors. The breakout shall be organized by division of work and include sub-line items of work, provided in a clear and concise format, to enable a straightforward evaluation of the proposal by the Government.

4.6.3.2 The Government anticipates the detailed cost breakdown will be required infrequently in response to

FOPRs. They may be requested for a variety of reasons, including but not limited to establishing price reasonableness or to evaluate pricing when only one offer is received. Detailed breakdowns may also be requested if the Government deems it necessary to reasonably determine the Contractor’s understanding of the project. Detailed breakdowns are required in most cases for modification proposals.

4.7 Task Order Proposal Evaluation

4.7.1 Task orders issued under each contract award are subject to the requirements of Federal Acquisition Regulation (FAR) 16.505, Orders under Multiple Award Contracts. All contractors will be given a fair opportunity to be considered for each order. Contractors shall follow the procedures outlined above in section 4.6 to be considered for award. The CO will select one contractor to receive the task order award.

No protest under FAR subpart 33.1 is authorized in connection with the issuance or proposed issuance of a delivery order, except as authorized by FAR 16.505(a)(10)(i).

4.7.2 Each task order will be awarded to the Offeror whose task order proposal is determined to represent the best value to the Government considering price and any other factor(s) identified in the FOPR. Selection for task order award will normally be based on either Lowest Price Technically Acceptable (LPTA) or Price-Only evaluation, at the discretion of the CO with concurrence of the Government Project Manager. The Government reserves the right to utilize Technical or Past Performance Tradeoffs at the CO’s discretion.

Each FOPR will identify the evaluation criteria and selection procedures to be used. IAW FAR 16.505(b)(7), the CO will exercise broad discretion in selecting the Contractor.

4.7.2.1 LPTA: When LPTA is identified as the evaluation and selection procedures in a FOPR, task order award will be made to the lowest priced proposal determined technically acceptable. A proposal will be determined technically acceptable when it demonstrates complete understanding of the task order requirements. Inconsistencies, incomplete proposals, and/or a lack of sufficient detail may cause task order proposals to be determined technically unacceptable.

4.7.3 Factors considered when evaluating proposals and selecting an awardee may include but are not limited to the following:

- Completeness of proposal

- Design

- Construction methodology

- Scheduling

- Past performance

- Quality of deliverables

4.7.4 After considering the above factors the CO may conduct interchanges with offerors to discuss any aspect of their proposals. Interchanges may be conducted with some, all, or none of the offerors at the CO’s discretion.

4.7.5 Award: Each task order award will include the following information:

- Effective date of the task order

- Contract number and task order number. Item number and description, quantity, and unit prices

- Task order price, delivery or performance data

- Accounting and appropriation data

- Liquidated Damages, if applicable

- Design, if applicable

- Sketches/Drawings, if applicable

- Government’s Statement of Work and Specifications

- Required Completion (normally as Days After NTP)

- Applicable Construction Wage Rates

4.8 Post Task Order Award Documentation Requirements ***Design After Award***

4.8.1 Drawings. When required, design drawings submitted by the Contractor shall show the basic layout and planning of work. Shop drawings shall show in detail the proposed fabrication and assembly of structural elements and/or the installation (i.e., form fit, and attachment details) of materials or equipment. Drawings will have sufficient detail to enable both the Contractor and the Government to understand the work to be accomplished.

4.8.1.1 For the purpose of this requirement, the term drawings includes actual construction drawings, shop drawings, fabrication drawings, erection drawings, diagrams, layouts, schematics, descriptive literature, illustrations, room finish schedules, lighting/panel schedules, lighting level analysis plans, load/distribution schedules/calculations, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions as may be required by an individual task order.

4.8.1.2 The Government may indicate minimum drawings that are necessary for each individual task order project.

Typical types of drawings required on task orders include the following: Title/Location/Legend/Index Sheets, Site Plans, Grading/Landscaping Plans, Underground Utility Plan and Profiles, Demolition Floor Plans, New Work Floor Plans, Wall Sections, Building Section, Finish Schedules, Window and Door Schedules, Mechanical Plans and Equipment Schedules, Plumbing Plans and HVAC Riser Diagrams, Electrical Plans and Wiring Diagrams, Electrical Equipment and Panel Schedules, Lighting Plans and Schedules, Communications Plans, Fire Protection Plans, Structural Plans, Roofing Plans, Wall and Roof Sections, Reflected Ceiling Plans, Elevations (Interior and Exterior), and Associated details.

4.8.2 Design Calculations. The Contractor shall provide, as part of the proposal, design calculations to substantiate appropriate equipment or material selection/sizing, component assembly, proposed layout and sizing of utilities and structural elements (i.e. HVAC Loads, Lighting, Platform Supports, etc.). The Contractor shall supply the following calculations per each task order project, as applicable:

4.8.2.1 Mechanical: HVAC load analysis and unit sizing, pipe sizing and duct sizing.

4.8.2.2 Electrical: Electrical system capacity, conductor, conduit, protective devices, and other equipment sizing.

4.8.2.3 Structural: Structural system and foundation sizing.

4.8.2.4 Pavement/Site Work: Area run-off quantities, drainage capacities and grading slopes.

4.8.2.5 Lighting: Lighting level analysis and lumen/foot-candle levels for each room or area.

4.8.2.6 Energy: Provide energy savings and Return on Investment (ROI).

4.8.3 Schedule of Material Submittals. The Contractor shall provide as a minimum, all submittals identified in the AF Form 66, Schedule of Material Submittals. Additional submittal requirements are identified in paragraph 6. Submittals. The submittals shall include all reports, construction materials, and documentation that have a material effect on the construction effort including but not limited to large purchase items; long-lead items; required reports; and as-built drawings.

4.8.4 Construction Schedules. The progress schedules for Task Orders under this contract shall be prepared using AF Form 3064 Project Schedule, Microsoft Project, or equivalent industry standard progress schedules as indicated in the FOPR instructions.

4.8.4.1 Progress Schedules shall be prepared IAW FAR Clause 52.236-15 for all projects that exceed the Simplified Acquisition Threshold, as defined in FAR 2.201, and whose actual performance is greater than 60 days. Progress Schedules shall break down the project into distinct tasks, identifying major work elements such as electrical, site work, etc., show which tasks will be accomplished simultaneously, and indicate the critical path. It shall identify all major tasks of construction effort and their associated percentage of the work effort. It shall demonstrate a logical progression of the work effort from award to close-out. The purpose of the submitted project schedules is to aid in the determination of the construction period. Following the start work date, the Contractor shall provide bi-monthly construction progress updates on an AF Form 3065 Progress Report, to the Contract Specialist and Project Manager.

4.8.5 Schedules may be requested by the Government for projects below the SAT or whose performance period is less than 60 days when deemed necessary.

4.8.6 Progress Payments/Reports. Progress Payments are allowable and shall be requested IAW FAR Clause 52.232-16 Progress Payments. Progress reports shall be prepared for all projects when progress payments are requested. Air Force Form 3065 (Progress Report), or CO approved equivalent, in electronic format is the form that shall be used when requesting progress payments, or final payment, to justify work completion.

4.8.6.1 When requesting progress payments, the completed AF 3065, or approved equivalent, shall be submitted to the Government’s Project Manager and Inspector for verification of claimed work completion percentages.

Following Government signature, the AF 3065 shall be submitted to the CO and Specialist for final approval. Once completed the AF 3065 shall be attached to the invoice in Wide Area Workflow (WAWF).

Invoices submitted without a completed AF 3065 will be rejected.

4.9 Construction Wage Rate Requirements (Formerly known as Davis-Bacon Act): The most current

Construction Wage Rate Requirements Statute wage determination will be attached to each FOPR and incorporated into each task order award, remaining in effect for the duration of the task order unless changed by modification by the CO.

4.10 Performance and Payment Bonds – Applicable to Individual TOs

4.10.1 Contractors shall furnish Performance and Payment Bonds (Standard Form 25/25A) with good and sufficient surety or sureties, acceptable to the Government on all TOs over $35,000. Bid bonds are not anticipated for use on task orders.

4.10.1.1 Performance Bond. Unless the CO determines that a lesser amount is adequate for the protection of the Government, the penal sum of the performance bonds (Standard Form 25) shall equal one hundred percent (100%) of the task order price.

4.10.1.2 Payment Bond. Shall equal 100% of the contract price for each TO. One of the following is required:

- A payment bond; or

- An irrevocable letter of credit (ILC); or

- A tripartite escrow agreement. The prime contractor establishes an escrow account in a federally insured financial institution and enters into a tripartite escrow agreement with the financial institution, an escrow agent, and all the suppliers of labor and material. The escrow agreement shall establish the terms of payment under the contractor’s escrow account, and the escrow agent distributes the payments in accordance with the agreement, or triggers the disputes resolution procedures if required

- Certificates of deposit. The contractor provides certificates of deposit from a federally insured financial institution with the CO, in an acceptable form, executable by the CO

- Other Deposits. A deposit of the types of security listed in FAR 28.204.

4.10.1.3 Performance and payment bonds are due no later than 10 days after task order award.

4.11 Meetings and Conferences

4.11.1 Pre-Construction Conference: The Contractor shall attend a pre-construction conference prior to issuing a start work notice on any project unless the requirement is waived by the Government in writing. The Contractor shall reach out to the Project Manager and Contract Specialist assigned to the project to schedule the meeting. The Government Project Manager will coordinate attendance of the Project Inspector, Base Environmental, the customer and any other applicable government parties. The meeting shall be Government led and will discuss all aspects of the required work for a task order, including the presence of previously identified hazardous and toxic materials. Base Environmental shall provide a copy of the most current contact list to the Contractor during the Pre-Construction Conference. At a minimum there shall be a review of material submittals, drawings, SOW review, schedule review, safety and accident protection, coordination required, base, local, state, and federal environmental regulatory requirements applicable to the task order. At minimum, the environmental brief shall cover natural and cultural resource protection, water quality, air quality, management and disposal of non-hazardous, universal, and hazardous waste, hazardous materials management, toxic materials and spill prevention. The environmental brief shall also cover toxic materials, identification, abatement, management and disposal for asbestos, PCBs, and lead-based paint if applicable to the task order. Administrative issues, traffic control, as-built criteria, performance requirements, security procedures, and any questions the Contractor may have shall be covered in the Pre-Construction Conference and current contact information will be exchanged.

4.11.2 Following the pre-construction conference, the Contract Specialist shall provide all attendees with written

(e-mailed) meeting minutes from the conference to include the list of all in attendance for the meeting, any identified issues or concerns, identified due outs and responsible party to address them and the date, time, and location of the meeting.

4.11.3 Proposals may be requested and processed up to the point of award in advance of funding, then held, for the entire period specified in the FOPR. If funding becomes available after proposed prices expire IAW the timeline given in the FOPR, all Contractors who submitted a proposal will be offered an opportunity to update their pricing. The CO may cancel a FOPR at CO discretion. After cancellation, a new FOPR may be issued. It is the government’s intent to award a task order for each proposal processed up to the point of award; however, due to changes in the construction program, congressional budget changes or world events, some projects may be canceled. No compensation for cancelled FOPRs will be granted to the contractor.

5. Working Hours

5.1 Standard Working Hours. Monday through Friday, 7:30 a.m. to 4:30 p.m., excluding Saturdays, Sundays, and Federal Holidays. Unless waived in the task order SOW, if the contractor desires to work during non-standard working hours, Government inspection forces may be required. The contractor shall notify the CO and Inspector in writing by email, three working days in advance of his/her intention to work during periods other than standard working hours.

5.1.1 This notification shall allow the inquiry into the availability of additional Government Inspectors. If the CO confirms that additional Government Inspectors are reasonably available, the CO may authorize the contractor to perform work during periods other than standard working hours. However, if the Government Inspectors are required to perform in excess of their normal duty days solely for the benefit of the contractor, the actual cost of inspection at overtime rates may be charged to the contractor.

5.2 Non-Standard Working Hours. Will be defined on individual task orders and shall be outside the definition of the standard working hours and not in controlled areas.

5.3 Standard and Non-standard Work in Controlled Areas. Will be specified in each affected task order.

All work in restricted areas is assumed to be within standard working hours. All work inside of controlled areas may be subject to brief delays due to security processing (30 minutes time each process on and off per visit to the controlled area) or interruption to the normal work schedule to permit the completion of mission essential operations. Such interruptions, if required, will be given on short notice and expeditious action will be required. The contractor shall not be compensated for said delays.

6. Submittals

6.1. Upon issuance of a Task Order, the contractor shall provide submittals as required by the specifications.

The CO may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

6.2. All submittals shall be submitted on an Air Force Form 3000 Material Approval Submittal (20030901 or most current version). All submittals shall be signed by the Quality Control Manager with a statement that the CQM has verified that the submitted items meet or exceed the requirements of the task order.

6.2.1. The contractor shall fill out the AF Form 3000 for all of equipment and materials that are required. This This maybe all-inclusive and additional submittals may be required. Submit the material submittals and shop drawings to the CO for approval within the timeframe identified on the AF66. If additional time is required by the contractor to provide specific submittals, the contractor shall identify the submittals requiring the time extension and request an extension from the CO; including the reason for the needed time extension and the date the submittals will be provided. The extension will be approved by the CO.

6.3. Submittals shall include items such as: contractor’s work plans / schedules, material submittal register, samples, brochures, manufacturers data, product data sheets, shop drawings and/or certificates of materials (relative to the construction execution), contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; Hazardous Materials Safety Data Sheets, and other such required submittals. All unrelated items and information on the submittal shall be crossed out.

6.4. Contractor shall plan for and submit all submittals requiring Government approval prior to the acquisition of the material or equipment covered thereby, in accordance with design criteria, specifications and FOPR requirements. If the material submittals provided are in variance from the design criteria and/or contract specifications, the contractor shall describe such variations in writing at the time of submission and request a variance from the design criteria and/or contract specifications in accordance with the terms and conditions of the contract. Failure to provide such notification will not relieve the contractor from their responsibility of meeting the design criteria and/or contract specifications regardless of whether the submittal is approved by the Government.

6.5. Material submittals shall be specified under each specification section and be submitted in electronic format. All the material submittals as indicated in the applicable specification section shall be submitted at the same time. If the submittal requirement is listed on the drawings, all material submittals of like work shall be submitted simultaneously along with all corresponding specification sections. A system of standard submittals for each contractor will be used to minimize the submittal requirement. Failure to submit all material submittals associated with an individual specification section at the same time may be cause for rejection.

6.6. Submittal Classifications: Submittals are classified as follows:

6.6.1. Government Approved: Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system will be checked, and other items as indicated on the Submittal Register or as designated by the CO. Within the terms of the Contract Clause entitled “Specifications and Drawings for Construction,” shall be considered “shop drawings”.

6.6.2. Re-Certification: Contractor shall provide the requested submittals for each task order unless otherwise specifically approved by the CO for the task order in question. If approved and the contractor intends to use previously approved materials or equipment, a letter certifying the specific material or equipment in lieu of a submittal is acceptable. Certification letter will contain the task order number and approved electronic copies of AF Form 3000 submittal.

6.6.3. Approved Submittals: The CO’s approval of submittals shall not be construed as a complete check but will indicate only that the general method of construction, materials, methods and other information are satisfactory. Approval will not relieve the contractor of the responsibility for any error that may exist, as the contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.

After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

6.6.4. Disapproved Submittals: The contractor shall make all corrections required by the CO and furnish a corrected submittal. Corrected submittals shall be submitted within three (3) business days, or as required by the disapproved submittal, after receipt of disapproval, in the form and number of copies specified for the initial submittal. If the contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause “Changes” shall be given promptly to the CO. Subsequent submissions of disapproved or updated submittals shall be formatted in a way to identify it is a subsequent submittal. (Ex. Submittal 1 was disapproved. The resubmittal would be labeled 1a or 1-1, with additional resubmissions lb, 1c, or 1-2, 1-3, etc. until final approval).

6.7. Submittal Scheduling: Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of fourteen (14) calendar days) shall be allowed for review and approval.

6.8. Submittal registers (AF Form 66): Submittal Registers shall be submitted by the contractor within fourteen (14) calendar days after issuance of the Notice to Proceed and prior to any material processing.

6.9. Government Approval (Submittals): Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval and dated. A digital copy of the submittal will be returned to the contractor.

6.10. The Contractor is responsible for tracking all open submittals and providing a monthly report to the

Government indicating the status of all open submittals. Open submittals are all submittals required by the AF-66 that have not been approved by the Project Manager/Inspector and the Contracting Office. This listing shall encompass all awarded TOs in the Contractor’s MACC portfolio with open submittals.

7. Project Status Updates (Partnering)

7.1. At a frequency determined by the CO, the contractor is required to attend project status update meetings for all active projects.

7.2. The Contractor shall ensure key management personnel participate in and provide briefings to the Base Civil Engineer (BCE), as required. The BCE will be represented by the MACC Program Manager, Project Manager(s), Project Inspector(s), CO’s Representative (CORs) and other authorized Government personnel, as needed. The Contractor's Program Manager and Project Manager(s), at a minimum, will attend. The purpose of these meetings is to discuss status of active projects, schedules, projections, problems, corrective actions, recommendations, etc., to accomplish project and program goals.

7.3. Project Tracking Spreadsheet. The Contractor shall produce a project tracking spreadsheet, provided to the CO by the fifth day of each month (or the first business day following, if the fifth falls on a weekend or holiday). At a minimum the spreadsheet shall include: Government project number (FXSB or HJHZ XX-XXXX), Task Order number, Contractor Project Manager initials, Government Project Manager initials, Government Inspector initials, Contract Specialist initials, a brief current project status, task order completion date, scheduled completion date, progress completed to date (shown as a percentage of the entire TO) and other pertinent remarks.

8. Interruption of Work

8.1. If it becomes necessary to interrupt work activities in buildings and/or areas for construction purposes

(except as otherwise described in the task order), the contractor shall request permission, in writing, from the CO no less than twenty-one (21) working days in advance. The contractor shall submit written requests for approved street closings no less than twenty-one (21) working days prior to closing of the street.

Requests shall stipulate the location of the work, the time at which the shutdown will occur, and the duration of the closure. Closures shall be kept to a minimum both in number and duration. Where multiple closures are required, as many as can be accurately scheduled shall be submitted as a group. Contractor shall receive written approval of any requested interruption or closure plan prior to implementing the requested closure.

9. Project Coordination

9.1. Final schedule(s) is/are due at the time of the pre-construction meeting.

9.2. Temporary construction. Any contractor-installed temporary construction intended to prevent interruption of normal work activity or loss of utility services is subject to approval of the Base Civil Engineer through the

CO.

9.3. Medical Facilities. The contractor shall coordinate all work in medical facilities through the CES PM with hospital staff liaison support to minimize interruption of service.

End of Section

Section 01100 General Requirements

Section 01100 General Site Requirements

1. Regulations

1.1. The contractor shall comply with all applicable Federal, State, Local, Air Force, Army, and DOD regulations, including supplements pertaining to safety, traffic control, and fire prevention.

2. Standard Products

2.1. Materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacture of such products, which are of a similar material, design, and workmanship. The standard products shall have been in satisfactory commercial and/or industrial use for 2 years prior to use. The 2-year use shall include applications of equipment and materials under similar circumstances and of similar size. The 2-year experience shall be satisfactorily completed by a product that has been sold or is offered for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures.

Products having less than a 2-year field service record will be acceptable, if a certified record of satisfactory field operation, for not less than 6,000 hours exclusive of the manufacturer's factory or laboratory tests, can be shown and approved by the Government. The contractor shall not purchase "close-out" products that are being discontinued by the manufacturer.

2.2. Recovered Materials Procurement: In accordance with FAR 23.4, and the authorities of FAR 23.402, the contractor shall use sustainable environmental materials, including acquisition of bio-based, environmentally preferable, energy- efficient, water-efficient, and recycled-content products. The materials shall be non-ozone depleting and non- toxic odorless products, where such products and services meet project performance requirements. The applicable materials are given by the U.S. EPA Comprehensive Procurement Guidelines and the USDA BioPreferred Catalog. Determination of feasibility of using these materials shall be in accordance with FAR 23.405.

3. Safety

3.1. Compliance with the current U.S. Army Corps of Engineers "Safety and Health Requirements Manual", (EM 385-1-1); Occupational Safety and Health Act (OSHA) standards, and current JBER safety regulations is mandatory. The prime contractor shall be held responsible to ensure that his/her workforce and any subcontractor or supplier workforce comply with the above safety requirements.

3.2. JBER has a hospital onsite should an injury occur; base medical staff can provide emergency medical treatment. Follow-on care after initial emergency treatment will not be provided. The contractor shall be required to reimburse the Government at an established rate for non-beneficiaries in accordance with DOD Regulation 6010.15-M.

3.3. Safety Assurance: The contractor shall prepare and submit a safety plan detailing the means and methods that will be implemented to ensure that there is full compliance with all safety regulations, practices, and standards.

3.3.1. Pre-construction Safety Meeting: The pre-construction safety meeting shall be conducted prior to the start of any new task order.

3.3.2. Hazardous Materials: The contractor shall bring to the attention of the CO any previously known material suspected of being hazardous which they encounter during execution of work. A determination will be made by the CO as to whether the contractor shall perform tests to determine if the material is hazardous. If the CO directs the contractor to perform tests, and/or if the material is found hazardous and additional protective measures are needed, a contract change may be required, subject to equitable adjustment under the terms of the contract.

3.3.3. Hazardous Material Handling: All work, including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1926/1910.