SECT-44_TESTING_OF_GRAVITY_SANITARY_SEWERS.docx

DOCX document 18 KB Posted

Attached to
Grant Funded Construction of Rummell Road Trail
Solicitation number
2025-131
Issued by
Polk County, Florida

About this file

This document is a technical specification section (Section 44) for testing gravity sanitary sewers, issued by a municipal engineering department. The specification outlines comprehensive testing requirements for sewer line installation, including cleaning, visual inspection, television testing, leakage testing, and deflection testing. Contractors are required to conduct these tests upon project completion, with a minimum 48-hour notice to the City Engineer, and must use equipment at their own expense. All testing must conform to UNI-BELL recommended practices, with specific guidelines for each testing method.

The specification mandates rigorous quality control measures, including visual inspections where the full pipe diameter must be visible between manholes, closed-circuit television inspections from manhole to manhole, and air-based leakage testing. The maximum allowable pipe deflection is set at 7%, with the City Engineer reserving the right to require random or comprehensive deflection testing. Contractors must repair or replace any sections of sewer that fail to meet the specified testing standards, with all remediation costs borne by the contractor. The testing protocols are designed to ensure the structural integrity, alignment, and leak-resistance of newly installed sanitary sewer lines.

View the file

Other files

File Type Posted
Grant_Funded_Construction_of_Rummell_Road_Trail_(Addendum_#1_Revision).pdf PDF
Sect-20_Special_Conditions_Rummell_Road_Trail_UPDATED.pdf PDF
Grant_Funded_Construction_of_Rummell_Road_Trail.pdf PDF
Sect-20_Special_Conditions_Rummell_Road_Trail.pdf PDF
Performance_Bond.pdf PDF
Payment_Bond.pdf PDF
[D]_Payment_And_ContractCompletion_Forms.pdf PDF
Sample_Certificate_of_Insurance.pdf PDF
[C]_Contractual_Documents.pdf PDF
FDEP_Agreement_Attachment_8.pdf PDF
SECT-39_GRASSING_AND_SEEDING.docx DOCX document
FDEP_Agreement_Attachment_9.pdf PDF
Insurance_Requirements_.pdf PDF
SECT-61_PAVEMENT_MARKING_REMOVAL_(THERMPLASTIC).docx DOCX document
FDEP_Agreement_Exhibit_H.pdf PDF
SECT-38_CONCRETE.docx DOCX document
SECT-59_REFLECTIVE_PAVEMENT_MARKERS.docx DOCX document
FDEP_Agreement_Exhibit_F.pdf PDF
SECT-36_PAVEMENT_REMOVAL_AND_RESTORATION.doc DOC document
SECT-56_CULVERTS_AND_STORM_SEWERS.docx DOCX document
Building_Fees_Schedule_2025-004R.pdf PDF
SECT-60_THERMOPLASTIC_TRAFFIC_STRIPES_AND_MARKINGS.docx DOCX document
FDEP_Agreement_Exhibit_G.pdf PDF
SECT-32_EXCAVATION_BACKFILL_COMPACTION_GRADING.docx DOCX document
SECT-31_SITE_PREP_SURF_REMOVE.docx DOCX document
SECT-58_HIGHWAY_SIGNING.docx DOCX document
SECT-37_ROADWAY_CONSTRUCTION_STANDARDS.doc DOC document
SECT-30_GENERAL.docx DOCX document
SECT-57_INLETS_MANHOLES_AND_JUNCTION_BOXES.docx DOCX document
PLANS_APPROVED-SDP23-0139_2025-02-27.pdf PDF
SECT-42_MANHOLES.docx DOCX document
SECT-34_PRESSURE_PIPE_RESTRAINT.docx DOCX document
SECT-52_VALVES_HYDRANTS_&_ACCESS_FOR_WATER_MAINS.DOC DOC document
SECT-41_GRAVITY_SEWER_PIPE_LAYING_JOINTING_AND_MISC_CONSTRUCTION_DETAILS.doc DOC document
SECT-55_VALVES_AND_ACCESS_FOR_RECLAIMED_WATER_MAINS.doc DOC document
SECT-49_Blank.DOC DOC document
SECT-50_WATER_DISTRIBUTION.DOC DOC document
SECT-35_PRESSURE_CONNECTION.doc DOC document
SECT-53_RECLAIMED_WATER_SYSTEMS.DOC DOC document
SECT-45_WASTEWATER_FORCE_MAINS.DOC DOC document
SECT-40_PIPE_MATERIAL_FOR_GRAVITY_SANITARY_SEWERS.docx DOCX document
SECT-51_PIPE_INSTALLATION_FOR_WATER_MAINS.DOC DOC document
SECT-54_PIPE_INSTALLATION_FOR_RECLAIMED_WATER_SYSTEMS.DOC DOC document
SECT-47_SUBMERSIBLE_WASTEWATER_PUMPS.DOC DOC document
SECT-33_BORING_&_JACKING.docx DOCX document
SECT-48_PUMP_STATION_ELECTRICAL_POWER_&_CONTROL_SYSTEM.DOC DOC document
SECT-43_SERVICE_LATERALS.docx DOCX document
SECT-46_SEWAGE_PUMPING_STATIONS.rtf RTF text file
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 44 - TESTING OF GRAVITY SANITARY SEWERS

Item No. Title

44.1TESTING
44.1.1General
44.1.2Cleaning
44.1.3Visual Test
44.1.4Television Test
44.1.5Leakage Test
44.1.6Deflection Testing

44.1 TESTING

44.1.1 GENERAL

All projects shall be tested upon completion of installation in the presence of the CITY ENGINEER or designee, representative(s) of the contractor, and/or other authorized agencies with a minimum forty-eight (48) hours advance notice (not including weekends or holidays). Testing shall conform with UNI-BELL recommended practice, UNI-B-5-78 and UNI-B-6-79, and the following requirements. All equipment for performing tests and making measurements shall be furnished by the contractor at his own expense, unless specified and agreed to otherwise in writing with the CITY ENGINEER or designee. Sections of sewer which fail to pass the required tests shall have the defects located and repaired or replaced and be retested until within the specified allowance at the contractor's own expense. Confirmation as to the type(s) and method(s) of testing required will be made at the pre-construction conference by the CITY ENGINEER or designee upon approval of the CITY ENGINEER or designee.

44.1.2 CLEANING

Prior to any tests, all sewer lines shall be cleaned and inspected for major defects. Pre-cleaning by appropriately sized sewer cleaning ball or by high velocity jet or other method may be necessary.

44.1.3 VISUAL TEST

All sewer lines shall be inspected visually to verify accuracy of alignment and freedom from debris and obstructions. The full diameter of the pipe for straight alignments shall be visible when viewed between consecutive manholes. The method of test shall be photography or visually lamping with mirrors and lights, unless a specific method is required by the special provisions.

44.1.4 TELEVISION TEST

It shall be the responsibility of the CONTRACTOR that all sewer lines shall be inspected by closed circuit television. Test shall be from manhole to manhole. Test shall stop at all laterals and inspect connection and lateral. Test shall also stop and inspect any deformations or inconsistencies. A copy of the final VHS inspection tape shall be remitted to the City. All VHS tapes shall be of high quality and a minimum of “Gold” standard by Kodak, Fuji, Memorex or approved equal. The tape label shall, at a minimum, state the project name, date, contractor, and manholes between which the pipe on the tape has been inspected. [Service lateral pipes from main pipe to lateral pipe terminus (clean-out) assembly may be required per City Engineer or his designee.]

44.1.5 LEAKAGE TEST

Points for leakage measurement and the method of testing will be selected by the CITY ENGINEER or designee. Method of test is low-pressure air exfiltration. Explicit instructions for the following methods of test will be supplied by the CITY ENGINEER or designee. Plugs, caps, and branch connections must be secured against blow-off during leakage test. (Infiltration or exfiltration leakage tests are not acceptable test methods.)

Air testing shall be completed as specified by “Uni-Bell Plastic Pipe Association UNI-B-6-82, Low-Pressure Air Testing of Installed Sewer Pipe,” or latest version, or 7 psi for 7 minutes between manholes, including service laterals.

44.1.6 DEFLECTION TESTING

Unless specified and approved otherwise, the maximum allowable pipe deflection (reduction in vertical inside diameter) shall be 7 ½%. The CITY ENGINEER or designee reserves the right to require the contractor to perform random deflection tests of pipe before final acceptance at construction locations between successive manholes where the construction encountered unstable trench walls or bottoms, heavy rainfall, high ground water levels, deep lines, or difficulty in achieving compaction. Should random test locations be unsatisfactory, then the contractor shall deflection test the entire sewer system. All locations with excessive deflection shall be excavated, and repaired by re-bedding and/or replacement of the pipe. Other devices for testing include: properly sized mandrel, sewer ball, or deflectometer.

File details come from the government source that posted it. Updated .