S02 - 695-19-107 Drawing Set Updated.pdf
PDF 38 MB Posted
- Solicitation number
- 36C25221B0002
About this file
This solicitation notice is for a construction project to renovate approximately 11,000 square feet of space on the 7th floor of Building 111 at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin for a relocated GI Procedure Clinic. The project scope includes demolishing existing interior spaces, renovating areas for the new clinic, and updating mechanical, electrical, plumbing, medical gas, fire protection, and pneumatic tube systems. The estimated value is between $2,000,000 and $5,000,000. The North American Industry Classification code is 236220 for construction of commercial and institutional buildings with a size standard of $39.5 million. The completion period is 515 calendar days from notice to proceed. This solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses. The solicitation and drawings are scheduled to be posted on SAM.gov on October 15, 2020 with a bid opening of November 16, 2020. A pre-bid conference will be held at the location.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTING OFFICER SIGNATURE
CONTRACTING OFFICER REPRESENTATIVE SIGNATURE
CHIEF ENGINEER SIGNATURE
LEAD USER SIGNATURE
DATE
DATE
DATE
DATE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1
.1
.1
R e n o v a te
A N d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/2
/2
:4
:5
P
M
GI000
COVER SHEET
GUIDON DESIGN INC.
1221 N. Pennsylvania St.
Suite 200
Indianapolis, Indiana 46202
317.800.6388
RING & DUCHATEAU, LLP.
17400 W. Capital Drive
Brookfield, WI 53045
414.778.1700
RENOVATE 7AN FOR
ENDOSCOPY LAB
5000 W National Ave, Milwaukee, WI 53295
695-19-107
08/21/2020 DV JDJ
695-19-107
RENOVATE 7AN FOR ENDOSCOPY LAB
CLEMENT J. ZABLOCKI VAMC
5000 W National Ave, Milwaukee, WI 53295
100% CONSTRUCTION DOCUMENTS
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SHEET LIST
SHEET
NUMBER SHEET NAME
REFERENCE
GUL101 FACILITY SIGNOFF
GUL102 GEN. INFO
GUL102.1 GEN. INFO
GUL103 ATTACHMENT
GUL104 PROJECT DETAILS
GUL104.1 PROJECT DETAILS
GUL104.2 PROJECT DETAILS
GUL104.3 PROJECT DETAILS
GUL104.4 PROJECT DETAILS
GUL105 GI ENODSCOPY - 7207
GUL106 SPECIAL EXAM RM - 7215
GUL107 FLUOROSCOPY - 7230
GUL109 PREP/RECOVERY - 7233
GUL110 GI ENDOSCOPY - 7236
GUL111 GI ENDOSCOPY 7244
GUL112 7TH FLOOR OVERALL
A-101 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
A-102 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
S-101 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
E-101 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
E-102 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
E-501 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
M-501 SIEMENS - ARTIS ZEE MULTI-PURPOSE SITE SPECIFIC DRAWING
SKYTRON--00 SKYTRON REFERENCE DRAWING
SKYTRON-00A SKYTRON REFERENCE DRAWING
SKYTRON-01A SKYTRON REFERENCE DRAWING
SKYTRON-02A SKYTRON REFERENCE DRAWING
SKYTRON-03A SKYTRON REFERENCE DRAWING
SKYTRON-A1 SKYTRON REFERENCE DRAWING
SKYTRON-A1.1 SKYTRON REFERENCE DRAWING
SKYTRON-A2 SKYTRON REFERENCE DRAWING
SKYTRON-A3 SKYTRON REFERENCE DRAWING
SKYTRON-A4 SKYTRON REFERENCE DRAWING
SKYTRON-B1 SKYTRON REFERENCE DRAWING
SKYTRON-B1.1 SKYTRON REFERENCE DRAWING
SKYTRON-B2A SKYTRON REFERENCE DRAWING
SKYTRON-B2B SKYTRON REFERENCE DRAWING
SKYTRON-B3 SKYTRON REFERENCE DRAWING
SKYTRON-B4A SKYTRON REFERENCE DRAWING
SKYTRON-B4B SKYTRON REFERENCE DRAWING
SKYTRON-B5A SKYTRON REFERENCE DRAWING
SKYTRON-B5B SKYTRON REFERENCE DRAWING
SKYTRON-C1 SKYTRON REFERENCE DRAWING
SKYTRON-C1.1 SKYTRON REFERENCE DRAWING
SKYTRON-S1A SKYTRON REFERENCE DRAWING
SKYTRON-S1B SKYTRON REFERENCE DRAWING
SKYTRON-S SKYTRON REFERENCE DRAWING
PT-2.07A SWISSLOG - PNEUMATIC TUBE ROUTE
SHEET LIST
SHEET
NUMBER SHEET NAME
GENERAL
GI000 COVER SHEET
GI101 LIFE SAFETY PLAN
GC101 INFECTION CONTROL/PHASING PLAN
HA101 HAZARDOUS MATERIAL REMOVAL PLAN
ARCHITECTURAL
AE001 ARCHITECTURAL SYMBOLS AND ABBREVIATIONS
AE002 WALL TYPES
AD101 SEVENTH FLOOR DEMOLITION PLAN
AD102 SIXTH FLOOR REFLECTED CEILING PLAN (DEMO/NEW WORK)
AE101 SEVENTH FLOOR ARCHITECTURAL PLAN
AE102 SEVENTH FLOOR DIMENSION PLAN
AE111 SEVENTH FLOOR REFLECTED CEILING PLAN
AE501 BUILDING DETAILS
AE502 LEAD SHIELDING DETAILS
AE601 DOOR AND WINDOW SCHEDULE
AI101 SEVENTH FLOOR FINISH AND WALL PROTECTION PLAN
AI201 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI202 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI203 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI204 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI205 INTERIOR ELEVATIONS AND ENLARGED PLANS
AI501 INTERIOR FINISH AND CASEWORK DETAILS
AI601 FINISH SCHEDULES
AI901 SIGNAGE PLAN
AI902 SIGNAGE TYPE
QH101 SEVENTH FLOOR FIXED EQUIPMENT FLOOR PLAN
IF101 SEVENTH FLOOR FURNITURE PLAN
IF102 SEVENTH FLOOR FURNITURE PLAN ELEVATIONS
FIRE PROTECTION
FP001 FIRE SUPPRESSION SYMBOLS, ABBREVIATIONS AND SHEET INDEX
FPD107 SEVENTH FLOOR DEMOLITION FIRE SUPPRESSION PLAN
FP107 SEVENTH FLOOR FIRE SUPPRESSION PLAN
PLUMBING
PS001 PLUMBING SYMBOLS, ABBREVIATIONS AND SHEET INDEX
PD106 SIXTH FLOOR DEMOLITION FLOOR PLAN
PD107 SEVENTH FLOOR DEMOLITION PLAN
DD107 SEVENTH FLOOR DEMOLITION MEDICAL GAS PLAN
PL106 SIXTH FLOOR PLUMBING PLAN
PL107 SEVENTH FLOOR PLUMBING PLAN
DG107 SEVENTH FLOOR MEDICAL GAS PLAN
PL300 MASH PLUMBING PLAN
PL400 PLUMBING ISOMETRICS
PL500 PLUMBING DETAILS AND SCHEDULES
MECHANICAL
MI000 MECHANICAL SYMBOLS, ABBREVIATIONS, SHEET INDEX
MD101 MECHANICAL DEMOLITION FLOOR PLAN - 7TH FLOOR
MD102 MECHANICAL DEMOLITION FLOOR PLAN - 6TH FLOOR
MH101 MECHANICAL DUCTWORK FLOOR PLAN - 7TH FLOOR
MH102 MECHANICAL DUCTWORK FLOOR PLAN - 8TH FLOOR
MP101 MECHANICAL PIPING FLOOR PLAN - 7TH FLOOR
MM400 ENLARGED PLANS AND SECTIONS
MM500 MECHANICAL DETAILS
MM501 MECHANICAL DETAILS
MM502 MECHANICAL DETAILS
MM600 MECHANICAL SCHEDULES
MM601 MECHANICAL SCHEDULES
MM602 MECHANICAL SCHEDULES
MM603 MECHANICAL SCHEDULES
ELECTRICAL
EI000 SYMBOLS, ABBREVIATIONIS AND SHEET INDEX
ED101 SEVENTH FLOOR - DEMOLITION
EL101 SEVENTH FLOOR PLAN - LIGHTING
EP100 SECOND FLOOR PLAN
EP101 SEVENTH FLOOR PLAN - OVERALL
EP102 SEVENTH FLOOR PLAN - POWER
EP103 PARTIAL ROOF PLAN - POWER
EP300 ENLARGED PLANS
EP301 ENLARGED PLANS
EP400 ONE-LINE SYMBOLS
EP401 POWER RISERS
EP500 DETAILS LIGHTING
EP501 DETAILS LIGHTING
EP510 DETAILS POWER
EP600 LIGHTING SCHEDULES
EP601 SCHEDULE POWER
EP602 SCHEDULES POWER
ET000 SYMBOLS, ABBREVIATIONS AND SHEET INDEX
ET101D SEVENTH FLOOR - TECHNOLOGY DEMOLITION
ET101 SEVENTH FLOOR PLAN - TECHNOLOGY
ET102 SEVENTH FLOOR PLAN - SYSTEMS
ET500 DETAILS TECHNOLOGY
ET501 DETAILS TECHNOLOGY
ET600 SCHEDULES
Contact:
CLEMENT J. ZABLOCKI
VA MEDICAL CENTER
5000 West National Ave.
Milwaukee, WI 53295
OWNER
GUIDON DESIGN INC.
David Vallandingham
Project Manager, Architect
1221 North Pennsylvania Street Suite 200 Indianapolis, IN 46202 p: 317.800.6388 x 130 e: dvallandingham@guidondesign.com
ARCHITECT
LOCATION MAP: NOT TO SCALE
CAMPUS MAP: NOT TO SCALE
N
N
Contact:
RING & DUCHATEAU, LLP.
Frank Lopez
Mechanical Engineer
MECHANICAL
17400 W. Capitol Drive Broookfield, WI 53045 p: 414.778.1700 x e: flopez@ringdu.com
Contact:
RING & DUCHATEAU, LLP.
Marcos Perez
Electrical Engineer
ELECTRICAL
Contact:
RING & DUCHATEAU, LLP.
Bob Wagner
Pluming Engineer
PLUMBING
p: 414.778.1700 x e: mperez@ringdu.com p: 414.778.1700 x e: rwagner@ringdu.com
17400 W. Capitol Drive Broookfield, WI 53045
17400 W. Capitol Drive Broookfield, WI 53045
PROJECT NORTH
Contact:
Milwaukee VA Medical Center p: 414.384.2000
TRUE NORTH
N
N
PROJECT NORTHTRUE NORTH
Revisions: Date:
Code Criteria General:
This summary of code requirements is based primarily on NFPA 101. Design features not addressed by NFPA 101 or documents referenced therein shall comply with the requirements of the latest edition of the IBC or as otherwise identified. For design features that in conflict between the NFPA and ICC standards, NFPA requirements shall rule.
Local Codes:
As an agency of the federal government, VA is not subject to local imposition of code enforcement procedures (drawing reviews, building permits, inspections, fees, etc.).
VA must function as the authority having jurisdiction (AHJ) and thus has the responsibility to guard public health and safety through enforcing its adopted codes.
Notes:
Conflicts between nationally recognized codes and standards and VA requirements – should a conflict exist between VA requirements and VA adopted nationally recognized codes and standards, the conflict shall be brought to the attention of VA. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure a consistency system wide.
Intervening Rooms: IBC: section 1014 exit access, 1014.2 egress through intervening spaces. Egress through intervening spaces shall comply with this section. 1. Egress from a room or space shall not pass through adjoining or intervening rooms or areas, except where such adjoining rooms or areas and the area served are accessory to one or the other.
Exit Route, IBC/NFPA conflict: suite exits directly into exit stair, allowed by NFPA.
Code Review The 2018 edition of the life safety code, NFPA 101, and the sixth edition of the department of veterans affairs fire protection design manual have been used to review this project for compliance with the fire and life safety requirements. For features not addressed by NFPA 101 and the referenced national fire codes, the 2018 edition of the international building code has been used.
Project Scope The existing Dialysis Clinic in the main hospital Building 111, 7th floor, A-wing is being remodeled to bring the suite to current healthcare standards. The clinic will serve inpatient and outpatient populations. Patients require egress assistance in an event of an emergency. The Inpatient and Outpatient area is a Group I, Institutional occupancy (IBC 2018). There is one waiting area which occupancy count will be reviewed as an A, assembly occupancy (2018 IBC). Based on verification provided by the VA, the suite is being reviewed against the requirements for a new Health Care occupancy, NFPA 101 chapter 18.
1. Occupancy type, I-2 hospital occupancy, IBC chapter 3. The 7th Floor A-wing floor shall be NFPA 101 Healthcare, chapter 18. No change from existing occupancy type.
2. Construction type, the building is assumed to be type 1-A based on allowable heights and area per IBC chapter 5, equivalent to NFPA 101 I (332). No change to overall building height or area.
3. Fire Resistive Ratings Type IA/ I (332) construction, chapter 6 IBC/NFPA 101:
1. Structural frame: Noncombustible, 3-hour fire resistive
2. Bearing walls
1. Exterior: Noncombustible, 3 hour fire resistive
2. Interior: Noncombustible, 3-hour fire resistive
3. Non-bearing walls and partitions
1. Exterior: Noncombustible, 0-1-hour fire resistive
2. Interior: Noncombustible, 0 hour fire-resistive
4. Floor: Noncombustible, 2-hour fire resistive
5. Roof: Noncombustible, 1-1/2-hour fire resistive
4. Structural design shall comply with chapter 16 of the IBC.
5. Allowable area: Based upon a I-2 occupancy and non-combustible, Type 1A: allowable area: unlimited (IBC, table 503)
6. Allowable Height: Unlimited (NFPA 101 table 18.1.6.1)
7. Occupancy Separation: Occupancy separation is not required.
8. Occupant Load are per NFPA 7.3.1.2 and IBC and outlined on the Life Safety Sheet.
9. Means of Egress section 18.2 (NFPA 101)
1. Clear width of corridors shall be clear 8 feet. Corridors not used by patients may be no less than 44 inches.
2. Door widths shall not be less than 41 ½” from treatment areas.
3. Not less than 2 exits shall be provided per floor.
4. Egress from smoke compartments shall be permitted through adjacent compartments but shall not require return through the compartment of fire origin.
5. Not less than 2 exits shall serve a smoke compartment.
6. Dead end corridors shall not exceed 30 feet.
7. Patient Care Non-Sleeping Suite does not exceed 12,500 sq.ft.
8. Maximum travel distance does not exceed 100 feet to exit a suite into an exit access corridor or horizontal exit.
10. Protection 18.3 (NFPA 101)
1. Hazardous Areas - Storage rooms and Soiled Rooms over 100sq.ft. shall be constructed with 1 hour fire rate partitions, rooms over 50 sq.ft. shall be constructed with smoke partitions.
2. Interior finish
1. Walls and Ceilings: shall be labeled as class A. Rooms with 4 or less occupants may have finishes labeled Class A and B.
2. Interior Floor Finish: critical radiant flux of at least 0.1W/cm2
3. Fire alarm system shall be provided. The system shall be by manual means.
4. Occupant notification shall be through automatic means.
5. Portable fire extinguishers shall be provided per NFPA 10.
6. Sprinkler in areas where cubicle curtains are installed shall be in accordance with NFPA 13. The sprinkler system shall be hydraulically designed in accordance with NFPA 13 and the Department of Veterans Affairs Fire Protection Design Manual, December 2015: minimum design requirements:
• Storage mechanical and electrical rooms shall be protected as:
• Ordinary hazard occupancy, group 1: 0.15 gpm/ft2 over 1,500 ft2.
• Hose stream allowance: 250 gpm
• All other areas shall be protected as:
• Light hazard occupancy: 0.10 gpm/ft2 over 1,500 ft2.
• Hose stream allowance: 100 gpm
• All sprinklers within the smoke zone shall be changed to quick response sprinklers.
11. Special provisions 8.4 (NFPA 101)
1. Alcohol Dispensers to be installed by owner and to meet this provision.
12. Building Services 18.5 (NFPA 101)
13. Reserve 18.6
14. Operating Features 18.7
1. Construction barriers constructed along means of egress shall be constructed and maintained per NFPA 241.
CODE ANALYSIS - NFPA 101, HEALTHCARE CHAPTER 18
CODE ANALYSIS LEGEND
TOTAL OCCUPANCY
FEC
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT SIGNAGE
FIRE EXTINGUISHER CABINET
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
2 HR - FIRE SEPARATION
1 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
B
1500 SF
NPFA, National Fire Protection Association full listing of current codes, including but not limited to:
NFPA 10 Standard for Portable Fire Extinguisher NFPA 13 Standard for the Installation of Sprinkler Systems NFPA 72 Fire Alarm Code NFPA 70, NEC National Electrical Code NFPA 80 Standard for Fire Doors and Fire Windows NFPA 88A Standard for Parking Structures NFPA 99 Healthcare Facilities Code NPFA 101 Life Safety Code NFPA 220 Standard on Types of Building Construction NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations
ICC Codes, International Code Council full listing of current codes, including but not limited to:
International Building Code International Plumbing Code International Mechanical Code International Fuel Gas Code International Fire Code International Energy and Conservation Code
ASHRAE Standards, as referenced within other codes including, but not limited to:
Standard 170-2017, Ventilation of Healthcare Facilities Standard 188-2018, Legionellosis: Risk Management for Building Water Systems
Accessibility Codes ADAAG, ADA Accessibility Guidelines VA Barrier Free Design Guide Pg-18-13, ABAAS
FGI, The Facility Guidelines Institute Guidelines for Design and Construction of Hospitals Guidelines for Design and Construction of Outpatient Facilities
Behavioral Health Design Guide
Systems relating to maintenance of facilities OSHA, Occupational, Safety and Health Administration Standards.
Codes and guidelines referenced within NFPA and ICC codes are to also be followed and applied to all design and construction. Refer to VA manual pg-18-3, specifications for additional codes, standards, guidelines and regulations. Contractor is responsible for constructing work compliant with OSHA, Occupational, Safety and Health Administration Standards.
VA Directives, Design Manuals, Master Specifications, VA National Cad Standard Application Guide, and other Guidance on the Technical Information Library (Til), www.cfm.va.gov/til/.
VA DESIGN GUIDES
ARCHITECTURAL
ASBESTOS ABATEMENT
CRITICAL PATH METHOD SCHEDULE & RISK MANAGEMENT FOR A/E
Volume 1 Volume 2
ELECTRICAL
ELEVATORS
EQUIPMENT
ESTIMATING
FIRE PROTECTION
HVAC
INTERIOR DESIGN
LIGHTING DESIGN
PHYSICAL SECURITY
Life Safety Protected Facilities Mission Critical Facilities Appendix Aa Appendix Ab Appendix Ac Appendix B
PLUMBING
SITE PARKING
Site Development Site Appendix
STEAM, HEATING, HOT WATER, AND OUTSIDE DISTRIBUTION SYSTEMS
Volume 1 Volume 2 Volume 3
STRUCTURAL
A. Ancillary Facility B. Energy Center C. Medical Unit D. Nursing Home E. Parking Structure F. Regional Office G. Seismic Retrofit
SUSTAINABILITY
TELECOMMUNICATIONS
VA DESIGN MANUALS PG-18-10:
GOVERNING CODES:
PROJECT AREAA
B
C
23 25222119 2016 171311 12109
A
B
C
D
E
H
K
L
M
J
DIAGONAL DISTANCE = 143'-3"
TRAVEL DISTANCE= 108'-0" EXIT
EXIT
PREP / RECOVERY
PREP / RECOVERY
PREP / RECOVERY
PREP / RECOVERY
PREP / RECOVERY
PREP / RECOVERY
MEDICATION
PHYSICIAN /
RESIDENT WORK
STATIONS
MECH.
PRIVATE TOILET
7233A
PREP / RECOVERY
PREP / RECOVERY
OFFICE
7216A
OFFICE
7216B
OPEN OFFICE
STAFF LOUNGE /
TRAINING
SPECIAL EXAM RM
PATIENT TOILET
7215A
CLEAN UTILITY
SCOPE STORAGE
ELECTRICAL
ELECTRICAL
ELECTRICAL
CONTROL ROOM
FLUOROSCOPY
GI ENDOSCOPY
CONSULT
WORKROOM
FAMILY TOILET
TEAM LEAD
RECEPTION
WAITING
F
E C
F E
C
STAIR
STAIR 7-5
LOCKERS
CORRIDOR
C7A02
CORRIDOR
C7A04
CORRIDOR
C7A01
GI ENDOSCOPY
9449 SF
10095
I
623 SF
I
PATIENT TOILET
GI ENDOSCOPY
EC
STAFF TOILET
7214B
ANESTHESIA WORK
RM
7239A
T R
A V
E L
D
IS
T A
N C
E
2'
-1
T R
A V
E L
D
IS
T A
N C
E
'-6
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
EXAM
TRAINING/CONSULT
PUBLIC TLT
RECEPTION
WAITING ROOM
CORRIDOR
C7A14
MSA
EC
RECEPTION
INTAKE
CORRIDOR
C7A13
SEP. ROOM
WATER TREATMENT
PATIENT TLT.
7135A PATIENT TLT.
7136A
SEP. ROOM
7135 ISO ROOM
EQUIP. ROOM
7209A
FEC
CO2 STORAGE
7206A
EXIT SEPARATION = 89'-5"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1
.1
.1
R e n o v a te
A N d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:3
P
M
GI101
LIFE SAFETY PLAN
GUIDON DESIGN INC.
1221 N. Pennsylvania St.
Suite 200
Indianapolis, Indiana 46202
317.800.6388
RING & DUCHATEAU, LLP.
17400 W. Capital Drive
Brookfield, WI 53045
414.778.1700
RENOVATE 7AN FOR
ENDOSCOPY LAB
5000 W National Ave, Milwaukee, WI 53295
695-19-107
08/21/2020 AWS DV
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1" = 100'-0"
KEY PLANN
SCALE: 3/32" = 1'-0"GI101
1 SEVENTH FLOOR LIFE SAFETY PLAN
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY : TYPE D
PATIENT RISK GROUP: MEDIUM
CLASS OF PRECAUTION MATRIX: IV
PROVIDE TEMPORARY 1 HR FIRE RATED WALL CONSTRUCTION PER NFPA 241.
REFER TO DETAIL 1/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH
CARD READER ACCESS. REFER TO ELEVATION 2/GI102.
EXISTING WALL PROVIDES A 1-HR CONSTRUCTION BARRIER. CONTRACTOR
TO MODIFY WALL AND PROVIDE FIRE CAULKING AS NEEDED TO PROVIDE
ENSURE 1-HR CONSTRUCTION BARRIER THROUGHOUT.
SEAL AND TAPE EXISTING DOOR TO PREVENT CONSTRUCTION DEBRIS FROM
PASSING THROUGH.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 01 01 10 AND 01 35 26.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE INFECTION CONTROL
WORKPLAN AND DRAWING TO COR FOR APPROVAL BEFORE ANY DEMOLITION.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CPM SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
SIXTH FLOOR ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE
HOURS OF 5:00 PM AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING
WORK WHERE CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED
AND STORED IN A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED.
DAMAGED AND BROKEN CEILING TILES SHALL BE REPLACED BY
CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE 24" X 36" STICK WALK-OFF MATT AT EACH TEMPORARY DOOR
LOCATION. MAT SHALL BE REPLACED OR CLEANED AS NECESSARY.
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART (SHARK TANK) FOR ABOVE CEILING ACCESS
OUTSIDE PROJECT BOUNDARY.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
INFECTION CONTROL GENERAL NOTES
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
CONTINUOUS FIRESAFE SEALANT
TOP AND BOTTOM, & BOTH SIDES
3 1/2" SOUND ATTENUATION
BATT.
5/8" TYPE X GYPSUM BOARD, BOTH
SIDES
3 5/8" METAL STUD @ 16" O.C.
WITH RUNNER CHANNELS ALONG
TOP AND BOTTOM
CONSTRUCTION
SIDE
PUBLIC
SIDE
6 MIL. FIRE RETARDANT VISQUEEN
MEMBRANE. CONTINUOUSLY
ADHERE TO THE STRUCTURAL DECK
ABOVE AND TO THE FLOOR BELOW
WITH TAPE.
UNDERSIDE OF STRUCTURAL DECK
UL LISTING:
U465
COORDINATE WITH EXISTING
CEILING
PUBLIC
SIDE
1 HOUR FIRE RATED METAL DOOR ASSEMBLY AND FRAME
WITH SEALS, CARD READER, HARDWARE AND CLOSER. VA
WILL PROVIDE CONSTRUCTION SFIC TO BE INSTALLED IN
CONTRACTOR-PROVIDED HARDWARE.
NEGATIVE AIR MONITOR (TRIATEK BASIS
OF DESIGN)
HAND SANITIZER
SEAL ALL EDGES WITH TAPE (SEE
SPECIFICATIONS)
SEAL ALL EDGES WITH TAPE
REFER TO TEMPORARY BARRIER TYPE
FOR REQUIRED CONDITION TO
STRUCTURE ABOVE
VA / OSHA TEMPORARY SIGNAGE
PROTECT EXISTING WALLS AND
FLOORING FROM TEMP.
CONSTRUCTION BARRIER.
EXISTING FINISHES DAMAGED
BY TEMP/IC/CN BARRIER SHALL
BE REPAIRED BY THE
CONTRACTOR.
23 25222119 2016 171311 12109
A
B
C
D
E
H
K
L
M
J
UP
WORKROOM
EXAM
EXAM
EXAM
EXAM
EXAM
OFFICE
OFFICE
WAITING AREA
OFFICE
MED RM
7210A
OFFICE
SOILED UTILITY
CLEAN UTILITY
EC
EC
EC
TREATMENT
LAB / TREATMENT
HAC
STAIR
7-5
EXAM
STORAGE
RESTROOM
BREAK
LAB
STORAGE
STORAGE
7250A
OFFICE
EXAM
OFFICE
OFFICE
EC
VP
7-33
ELEV
7-A-7
ELEV
7-A-8
PROCTO DO RM
7240A
WOUND RM
7240B
WOUND STAFF
7240C
WAITING RM
WAITING AREA
CORRIDOR
C7A01
CORRIDOR
C7A02
CORRIDOR
C7A03
CORRIDOR
C7A05
CORRIDOR
C7A04
CORRIDOR
C7A04A
CORRIDOR
C7A06
CORRIDOR
C7A07
CORRIDOR
C7A14
CLEAR MIN.
6' - 0"
C
LE
A R
M
IN
6'
2 1
4'
7' - 11 5/8"
PROJECT AREAA
B
C
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1
.1
.1
R e n o v a te
A N d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:2
P
M
GC101
INFECTION CONTROL/PHASING
PLANGUIDON DESIGN INC.
1221 N. Pennsylvania St.
Suite 200
Indianapolis, Indiana 46202
317.800.6388
RING & DUCHATEAU, LLP.
17400 W. Capital Drive
Brookfield, WI 53045
414.778.1700
RENOVATE 7AN FOR
ENDOSCOPY LAB
5000 W National Ave, Milwaukee, WI 53295
695-19-107
08/21/2020 DV DMC
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1 1/2" = 1'-0"GC101
1 TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL CONSTRUCTION NFPA 241
SCALE: 1/4" = 1'-0"GC101
2 TEMPORARY WALL CONSTRUCTION ELEVATION
SCALE: 1/8" = 1'-0"GC101
3 SEVENTH FLOOR PLAN INFECTION CONTROL N
SCALE: 1" = 100'-0"
KEY PLAN
SCALE: 1/4" = 1'-0"GC101
4 EXISTING DEMISING WALL PHOTO
SCALE: 1/4" = 1'-0"GC101
5 EXISTING DEMISING WALL PHOTO
PROJECT BOUNDARY
AREA FOR REMOVAL OF ASBESTOS-CONTAINING FLOORING
AND ASSOCIATED MASTIC
A. HAZMAT REMOVAL NOTES APPLY TO ENTIRE ROOMS. REMOVE ACCORDING
TO SAFETY STANDARDS. REFERENCE SPECIFICATION 02 82 11.
B. ALL HAZARDOUS MATERIALS SHALL BE REMOVED IN COMPLIANCE WITH
APPLICABLE CODES AND LAWS.
C. THE CONTRACTOR IS RESPONSIBLE TO VERIFY THE HAZARD(S) AND LEVEL
OF PROTECTION REQUIRED FOR ALL EMPLOYEES OR SUBCONTRACTORS
TO COMPLETE THE CONSTRUCTION WORK.
D. PROVIDE ABATEMENT OF VCT AND FLOORING MASTIC WITHIN HATCHED
AREA.
E. ALL FLOORING WILL REQUIRE ABATEMENT INCLUDING BUT NOT LIMITED TO
ALL 9X9 OR 12X12 VCT OR CERAMIC TILES.
F. PROVIDE COST FOR REMOVAL OF COUNTED AND UNFORESEEN MUD
FITTINGS ON FIBEGLASS INSULATED DOMESTIC WATER LINES. ASSUME 300
PLUMBING FITTINGS BETWEEN 1.5 INCH AND 6 INCH DIAMETER. PLUMBING
FITTING FOR ABATEMENT ARE LOCATED ON 7TH FLOOR AND CEILING OF
6TH FLOOR.
G. PROVIDE COST FOR REMOVAL OF COUNTED AND UNFORESEEN MUD
FITTING ON FIBERGLASS INSULATED PERIMETER HEATING AND COOLING
WATER LINES. ASSUME 300 HVAC PIPING FITTINGS BETWEEN 1.5 INCH AND 6
INCH DIAMETER. HVAC PIPING FITTINGS FOR ABATEMENT ARE LOCATED
PRIMARILY IN CEILING OF 6TH FLOOR AND ARE ASSOCAITED WITH EACH OF
THE WINDOW CABINET UNITS.
H. PROVIDE COST FOR REMOVAL OF ASBESTOS CONTAINING CABINET UNIT
HEATER BOXES. INSIDES OF UNITS ARE COATED WITH ACM. QUANITY 26.
I. PROVIDE COST FOR REMOVAL OF ASBESTOS CONTAINING 9X9 LVT, TILE
AND MASTIC, ASSUME 9,020 SF.
J. PROVIDE COST FOR REMOVAL OF ASBESTOS CONTAINING 4X4 WALL TILE,
MASTIC AND GROUT, ASSUME 1,816 SF.
K. PROVIDE COST FOR REMOVAL OF ASBESTOS CONTAINING 4X4 / 8X4 WALL
TILE BASE, ASSUME 132 LINEAR FEET.
L. PROVIDE COST FOR REMOVAL OF FLOURESCENT LIGHT TUBES AND CFL
BULBES, ASSUME 350 TOTAL.
M. PROVIDE COST FOR REMOVAL OF PDB CONTAINING BALLASTS FOR
FLUORESCENT LIGHTING FIXTURES, ASSUME 175 EACH.
N. BASED ON THE DATE OF THE EXISTING CONSTRUCTION AND
UNDERSTANDING OF THE FACILITY, LEAD PAINT IS WITHIN THE PROJECT
AREA. DO NOT PROVIDE LEAD PAINT ABATEMENT. CONTRACTOR TO
PERFORM DEMOLITION ACTIVITIES AFTER IMPLEMENTATION OF LEAD
STABILIZATION. CONTRACTOR TO USE MEASURES FOR PROTECTION AND
TO MINIMIZE PAINT DEBRIS.
1. DOMESTIC WATER RISERS
2. HVAC PIPING RISER
3. 4"X4" VERTICAL ASBESTOS-CONTAINING TILES AROUND SINK
HAZARDOUS MATERIAL REMOVAL GENERAL NOTES
HAZARDOUS MATERIAL REMOVAL PLAN NOTES
HAZARDOUS MATERIAL REMOVAL LEGEND
BEYOND PROJECT BOUNDARY
AREA FOR REMOVAL OF VERTICAL 4X4 ASBESTOS-CONTAINING
TILES
23 25222119 2016 171311 12109
A
B
C
D
E
H
K
L
M
J
UP
WORKROOM
EXAM
EXAM
EXAM
EXAM
EXAM
OFFICE
OFFICE
WAITING AREA
OFFICE
MED RM
7210A
OFFICE
SOILED UTILITY
CLEAN UTILITY
EC
EC
EC
541 SF
TREATMENT
LAB / TREATMENT
HAC
STAIR
7-5
EXAM
STORAGE
RESTROOM
BREAK
LAB
STORAGE
STORAGE
7250A
OFFICE
EXAM
OFFICE
OFFICE
EC
VP
7-33
ELEV
7-A-7
ELEV
7-A-8
STORAGE
OFFICE
OFFICE
VP
7-29
FC
PROCTO DO RM
7240A
WOUND RM
7240B
WOUND STAFF
7240C
WAITING RM
WAITING AREA
CORRIDOR
C7A01 CORRIDOR
C7A02
CORRIDOR
C7A03
CORRIDOR
C7A05
CORRIDOR
C7A04
CORRIDOR
C7A04A
CORRIDOR
C7A06
CORRIDOR
C7A14
1 1 1
1 1 1
2 2 2 2
33 33
PROJECT AREAA
B
C
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
NOT F
OR
CONSTRUCTIO
N
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1
.1
.1
R e n o v a te
A N d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:3
P
M
HA101
HAZARDOUS MATERIAL REMOVAL
PLANGUIDON DESIGN INC.
1221 N. Pennsylvania St.
Suite 200
Indianapolis, Indiana 46202
317.800.6388
RING & DUCHATEAU, LLP.
17400 W. Capital Drive
Brookfield, WI 53045
414.778.1700
RENOVATE 7AN FOR
ENDOSCOPY LAB
5000 W National Ave, Milwaukee, WI 53295
695-19-107
08/21/2020 AWS DV
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1/8" = 1'-0"HA101
1 SEVENTH FLOOR PLAN HAZMAT ABATEMENT PLAN
Revisions: Date:
SCALE: 1" = 100'-0"
KEY PLAN
N
ARCHITECTURAL ABBREVIATIONS
SECTION REFERENCE
DRAWING NUMBER
SHEET LOCATION
DRAWING NUMBER
SHEET
LOCATION
DETAIL REFERENCE
OBJECT
REFERENCED
OBJECT
REFERENCED
X
XXXX
X
XXXX
SCALE: ??
VIEW TITLE
N
NORTH ARROW
INCANDESCENT WALL MOUNTED LIGHTING
INCANDESCENT SURFACE MOUNT LIGHTING
SURFACE MOUNTED FLUORESCENT
RECESSED FLUORESCENT
HVAC RETURN AIR GRILLE
HVAC SUPPLY DIFFUSER
PENDANT LIGHT
ACCESS PANEL
EXIT LIGHTING
S
D
SPEAKER
SMOKE DETECTOR
INCANDESCENT RECESSED LIGHTING
A 9'-0"
CEILING TAG CEILING TYPE
FINISHED CEILING HEIGHT
REFER TO CEILING LEGEND FOR MORE
INFORMATION
EXTENT OF REVISION
REVISION SET
MECH/ELEC ITEMS: REFER TO MEP SHEETS AS APPLICABLE
PROJECT BOUNDARY
BEYOND PROJECT BOUNDARY, NIC
REFLECTED CEILING PLAN SYMBOLS
DETAIL/DRAWING SCALE
TITLE OF DETAIL/DRAWING
DETAIL/DRAWING NUMBER
SHEET NUMBER
A/C AIR CONDITION
A/E ARCHITECT/ENGINEER
AB ANCHOR BOLT
ABC AGGREGATE BASE COURSE
AC ASBESTOS CEMENT OR ASPHALTIC CONCRETE
ACS DR ACCESS DOOR
ACS FLR ACCESS FLOOR
ACS PNL ACCESS PANEL
ACST ACOUSTIC
ACT ACOUSTICAL CEILING TILE
AD AREA DRAIN
ADA AMERICANS WITH DISABILITIES ACT
ADC AUTOMATIC DOOR CLOSER
ADDL ADDITIONAL
ADDN ADDITION
ADH ADHESIVE
ADJ ADJACENT, ADJOINING, OR ADJUSTABLE
ADMIN ADMINISTRATION
AFC ABOVE FINISHED COUNTER
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AFS ABOVE FINISHED SLAB
AGGR AGGREGATE
AHJ AUTHORITY HAVING JURISDICTION
AHR ANCHOR
AHU AIR HANDLING UNIT
AIA AMERICAN INSTITUTE OF ARCHITECTS
AISC AMERICAN INSTITUTE OF STEEL CONSTRUCTION
ALT ALTERNATE
ALT NO ALTERNATE NUMBER
ALUM ALUMINUM
AMP AMPERE
AMT AMOUNT
ANOD ANODIZE
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
ANT ANTENNA
APPD APPROVED
APPROX APPROXIMATE
AR AS REQUIRED
ARCH ARCHITECT
ASB ASBESTOS
ASI ARCHITECT'S SUPPLEMENTAL INSTRUCTION
ASKLR AUTOMATIC SPRINKLER
ASPH ASPHALT
ASSN ASSOCIATION
ATCH ATTACHMENT
ATS AUTOMATIC TRANSFER SWITCH
AUTO AUTOMATIC
AUX AUXILIARY
AV AUDIO VISUAL
AVG AVERAGE
AW ACID WASTE
AWI ARCHITECTURAL WOODWORKING INSTITUTE
AWS AMERICAN WELDING SOCIETY
AWT ACOUSTICAL WALL TREATMENT
B PL BASE PLATE
BALC BALCONY
BAT BATTEN
BB BULLETIN BOARD
BD BOARD
BEV BEVEL
BI FLD DR BIFOLDING DOORS
BITUM BITUMINOUS
BKG BACKING
BLD BUILD
BLDG BUILDING
BLKG BLOCKING
BLKT BLANKET
BM BEAM OR BENCHMARK
BOT BOTTOM
BRCG BRACING
BRDG BRIDGING
BRG BEARING
BRKT BRACKET
BRZ BRONZE
BSMT BASEMENT
BTWN BETWEEN
BUR BUILT-UP ROOFING
C CELSIUS CHANNEL OR CHANNEL CELSIUS
C CONC CAST CONCRETE
C TO C CENTER TO CENTER
CAB CABINET
CB CORNER BEAD
CBB CEMENTITIOUS (BACKER) BOARD
CC CUBIC CENTIMETER
CCTV CLOSED CIRCUIT TELEVISION
CCW COUNTERCLOCKWISE
CEM CEMENT
CEM PLAS CEMENT PLASTER
CER CERAMIC
CF CONTRACTOR FURNISHED
CF/CI CONTRACTOR FURNISHED/CONTRACTOR INSTALLED
CF/OI CONTRACTOR FURNISHED/OWNER INSTALLED
CFLG COUNTERFLASHING
CFM CUBIC FEET PER MINUTE
CFMF COLD-FORMED METAL FRAMING
CFS CUBIC FEET PER SECOND
CG CORNER GUARD
CGSFU CERAMIC GLAZED STRUCTURAL FACING UNITS
CH BD CHALKBOARD
CHEM CHEMICAL
CHFR CHAMFER
CI CAST IRON
CIP CAST-IN-PLACE
CIR CIRCLE
CIRC CIRCULAR
CJ CONSTRUCTION JOINT OR CONTROL JOINT
CL CENTER LINE
CLDG CLADDING
CLG CEILING
CLR CLEAR
CMU CONCRETE MASONRY UNIT
CNR CORNER
CNTR COUNTER
CO CARBON MONOXIDE, CLEANOUT
CO₂ CARBON DIOXIDE
COL COLUMN
COM COMMON
COMB COMBINATION, COMBINED
COMM COMMUNICATION
COMP COMPONENT
CONC CONCRETE
COND CONDENSER OR CONDITION
CONF CONFERENCE
CONN CONNECT
CONSTR CONSTRUCTION
CONT CONTINUE
CONTR CONTRACTOR
COORD COORDINATE
CORR CORRIDOR
CPM CRITICAL PATH METHOD
CPRS COMPRESSIBLE
CPT CARPET
CRS COLD ROLLED STEEL
CS CAST CONCRETE STONE
CSB CONCRETE SPLASH BLOCK
CSG CASING
CSK COUNTER SUNK
CSMT CASEMENT
CSWK CASEWORK
CT CERAMIC TILE
CTB CERAMIC TILE BASE
CTF CERAMIC TILE FLOOR
CTG COATING
CTR CENTER
CTRL CONTROL
CTV CABLE TELEVISION
CU COPPER C
CU FT CUBIC FEET
CU IN CUBIC INCH
CU YD CUBIC YARD
CURT CURTAIN
CYL CYLINDER
CYL L CYLINDER LOCK
N NORTH
NA NOT APPLICABLE
NAT NATURAL
NATL NATIONAL
NC NOISE CRITERIA
NCOMBL NONCOMBUSTIBLE
NEG NEGATIVE
NEUT NEUTRAL
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NR NOISE REDUCTION
NRC NOISE REDUCTION COEFFICIENT
NRP NONREMOVABLE
NS NARROW STILE
NUM NUMERAL
O/O OUT TO OUT
O OXYGEN
OA OUTSIDE AIR OR OVERALL
OC ON CENTER
OCC OCCUPY
OCT OCTAGON
OD OUTSIDE DIAMETER OR OUTSIDE DIMENSION
OF/CI OWNER FURNISHED/CONTRACTOR INSTALLED
OFD OVERFLOW DRAIN
OFF OFFICE
OF/OI OWNER FURNISHED/OWNER INSTALLED
OH OVERHANG
OH DR OVERHEAD (COILING) DOOR
OPH OPPOSITE HAND
OPNG OPENING
OPP OPPOSITE
OPR OPERABLE
OPT OPTIONAL
OR OPERATING ROOM OR OUTSIDE RADIUS
ORD ORDNANCE OR OVERFLOW ROOF DRAIN
ORG ORGANIC
ORIG ORIGINAL
ORN ORNAMENTAL
OUT OUTLET
OZ OUNCE
PAR PARALLEL OR PARAPET
PART PARTIAL
PAT PATTERN
PB PUSHBUTTON
PBD PARTICLEBOARD
PC PIECE, POLYCARBONATE OR PORTLAND CEMENT
PCC PRECAST CONCRETE
PCCP CONCRETE PAVEMENT
PCD PAPER CUP DISPENSER
PCF POUNDS PER CUBIC FOOT
PCP PORTLAND CEMENT PLASTER
PED PEDESTAL
PEN PENETRATE
PEND PENDANT
PERF PERFORATED
PERIM PERIMETER
PERP PERPENDICULAR
PGBD PEGBOARD
PHS PHILLIPS HEAD SCREW
PKG PACKAGE
PL PLATE, PROPERTY LINE
PLAM PLASTIC LAMINATE
PLAS PLASTER OR PLASTIC
PLBG PLUMBING
PLYWD PLYWOOD
PMTL PAINTED METAL
PNEU PNEUMATIC
PNL PANEL
POLY POLYETHYLENE (PLASTIC)
PR PAIR
PRCST PRECAST
PREFAB PREFABRICATE
PREFIN PREFINISH
PRELIM PRELIMINARY
PREP PREPARATION
PRESS PRESSURE
PREV PREVIOUS
PRKG PARKING
PRMLD PREMOLDED
PROJ PROJECT
PROP PROPERTY
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT PAINT, PNEUMATIC TUBE, OR PRESSURE TREATED
PTD PAPER TOWEL DISPENSER
PTN PARTITION
PVC POLYVINYL CHLORIDE (PLASTIC)
PVG PAVING
PWR POWER
QA QUALITY ASSURANCE
QC QUALITY CONTROL
QRY QUARRY
QT QUARRY TILE
QTB QUARRY TILE BASE
QTF QUARRY TILE FLOOR
QTR QUARTER
QTY QUANTITY
QUAD QUADRANT
QUAL QUALITY
R RADIUS OR RISER
RA RETURN AIR
RAD RADIATOR
RB RESILIENT BASE OR RUBBER BASE
RB HK ROBE HOOK
RBM REINFORCED BRICK MASONRY
RBR RUBBER
RCP REFLECTED CEILING PLAN
RCVR RECEIVER
RD ROAD OR ROOF DRAIN
REC RECESSED
RECD RECEIVED
RECPT RECEPTACLE
RECT RECTANGLE
REF REFERENCE OR REFRIGERATOR
REFR REFRACTORY REFRIGERATION OR REFRIGERATION
REFRACTORY
REG REGISTER
REINF REINFORCE
REP REPAIR
REPL REPLACE
REQ REQUIRE
REQD REQUIRED
RESIL RESILIENT
RET RETURN
REV REVISION
RF RADIO FREQUENCY
RFG ROOFING
RFI REQUEST FOR INFORMATION
RFP REQUEST FOR PROPOSAL
RH RIGHT HAND
RHMS ROUND HEAD MACHINE SCREW
RHR RIGHT HAND REVERSE
RHWS ROUND HEAD WOOD SCREW
RL ROOF LEADER
RLG RAILING
RM ROOM
RND ROUND
RO ROUGH OPENING
ROW RIGHT OF WAY
RPM REVOLUTIONS PER MINUTE
RS ROUGH SAWN
RT RIGHT
RV ROOF VENT
RVS REVERSE
RWD REDWOOD
RWL RAIN WATER LEADER
W/ WITH
W/O WITHOUT
WARR WARRANTY
WBL WOOD BLOCKING
WC WALL COVERING OR WATER CLOSET
WC WL HNG WATER CLOSET, WALL HUNG
WCHR WATER CHILLER
WCL WL MTD WATER COOLER, WALL HUNG
WD WOOD
WDW WINDOW
WF WIDE FLANGE
WFAB WALL FABRIC
WFR WOOD FRAME
WFS WOOD FURRING STRIPS
WH WATER HEATER
WHSE WAREHOUSE
WLD WELDED
WM WIRE MESH
WP WATERPROOFING
WPD WATER PRESSURE DROP
WPM WATERPROOF MEMBRANE
WR WEATHER RESISTANT
WS WEATHERSTRIP
WSCT WAINSCOT
WT WEIGHT
WWF WELDED WIRE FABRIC
X BRACE CROSS BRACE
XPS EXTRUDED POLYSTYRENE BOARD (INSULATION)
YD YARD
YR YEAR
GENERAL CONSTRUCTION NOTES
1. THE CONTRACT DOCUMENT DRAWINGS HAVE BEEN PREPARED USING REVIT®
SOFTWARE IN A MICROSOFT WINDOWS ENVIRONMENT. A BUILDING INFORMATION
MODEL (BIM) HAS BEEN DEVELOPED FOR DESIGN COMMUNICATION. THE MODEL
DOES NOT CONTAIN COMPLETE INFORMATION FOR USE IN COST ESTIMATING,
SYSTEMS PERFORMANCE, COORDINATION, SCHEDULING, OR FACILITIES
MANAGEMENT.
2. THE CONTRACT DOCUMENT DRAWINGS HAVE BEEN PREPARED USING THE
CONSTRUCTION SPECIFICATIONS INSTITUTE'S UNIFORM DRAWING SYSTEM AND THE
NATIONAL CAD STANDARD AS GUIDES.
3. DISCREPANCIES IN THE CONTRACT DOCUMENTS SHALL BE IMMEDIATELY BROUGHT
TO THE ATTENTION OF THE ARCHITECT AND OWNER’S REPRESENTATIVE/COR.
CONTRACTOR SHALL PROVIDE THE HIGHER GRADE OF QUALITY AND/OR GREATER
QUANTITY OF WORK WHEN BIDDING IF A CLARIFICATION CAN NOT BE OBTAINED BY
THE BID DUE DATE.
4. CONTRACTOR IS RESPONSIBLE FOR COORDINATING SCOPE OF WORK WITH
OWNER’S REPRESENTATIVE/COR AND VARIOUS FACILITY PERSONNEL INVOLVED
WITH UTILITY SHUT DOWN, INFECTION CONTROLS, OCCUPANT/EMPLOYEE SAFETY,
ACCESS CONTROL, ETC.
5. ANY INDICATION OF PROJECT LIMITS OR BOUNDARY OF DEMARCATION ARE SHOWN
FOR THE CONVENIENCE OF THE CONTRACTOR, THE FULL SCOPE OF THE PROJECT
LIMIT OF BOUNDARY REQUIRES COORDINATION WITH THE DESIGN SCOPE OF WORK
AND ACCESS TO EXISTING UTILITIES FOR TIE IN.
6. DRAWINGS ARE PREPARED FROM FIELD VERIFICATION, EXISTING FACILITY DRAWING
BASE FILES, AND USING DIMENSIONS, CONFIGURATIONS AND DETAILS OF SPECIFIC
MANUFACTURERS AS A BASIS OF DESIGN. CONTRACTOR IS RESPONSIBLE FOR
VERIFICATION OF ACTUAL DIMENSIONS, THE COORDINATION OF THE DETAILS WITH
THE PRODUCTS WHICH ARE PROVIDED PER THE SCOPE OF THE SPECIFICATIONS
AND THE SURROUNDING CONSTRUCTION. CONTRACTOR SHALL VERIFY DIMENSIONS,
ROUGH-IN DIMENSIONS, CONNECTIONS, AND OVERALL INSTALLATION
REQUIREMENTS.
7. CONTRACTOR IS RESPONSIBLE FOR THE COMPLETION OF THE ENTIRE SCOPE OF
WORK OUTLINED IN THE CONTRACT DOCUMENTS. CONTRACTOR IS RESPONSIBLE
FOR THE COORDINATION OF ALL SUB-CONTRACTORS AND THE SCOPE OF WORK
THEY PROVIDE. SUB-CONTRACTORS ARE RESPONSIBLE FOR THEIR FULL SCOPE OF
WORK WITHIN THE CONTRACT DOCUMENTS, TRADES ARE NOT SEGMENTED TO ONLY
CERTAIN SHEETS AND SPECIFICATIONS, CROSS COORDINATION IS REQUIRED.
8. CONTRACTOR AND SUB-CONTRACTORS ARE BOTH RESPONSIBLE FOR
UNDERSTANDING INFORMATION OUTLINED IN THE SPECIFICATIONS, KEY NOTES,
GENERAL NOTES, LEGEND, CODES, ETC., PROVIDED IN THE CONTRACT DOCUMENTS.
9. CONTRACTOR AND SUB-CONTRACTORS ARE BOTH RESPONSIBLE FOR PROVIDING
AND MAINTAINING SMOKE/FIRE RATINGS OF NEW CONSTRUCTION AND EXISTING
CONSTRUCTION AS INDICATED ON DRAWINGS. THIS INCLUDES PATCHING
PENETRATIONS IN SHAFTS, WALLS, SLABS AND ROOF. ONLY U.L. APPROVED
METHODS, MATERIALS AND INSTALLATION ARE ACCEPTABLE.
10. MECHANICAL, PLUMBING, FIRE PROTECTION AND ELECTRICAL DRAWINGS SHOW
INFORMATION IN A DIAGRAMMATIC FASHION WITHOUT DIMENSIONING. THE GENERAL
CONTRACTOR IS TO COORDINATE THE LOCATIONS OF ALL MECHANICAL, PLUMBING
AND ELECTRICAL EQUIPMENT WITH RESPECT TO THE ARCHITECTURAL AND
STRUCTURAL DETAILING OF SHAFTS, CHASES, CEILING CONSTRUCTION, ETC.
11. CONTRACTOR IS RESPONSIBLE FOR VERIFYING DIMENSIONS IDENTIFIED AND NOT
IDENTIFIED IN THE CONTRACT DOCUMENTS WITH THE EXISTING AND NEW
CONSTRUCTION ELEMENTS. CONTRACTOR IS RESPONSIBLE FOR VERIFICATION
BETWEEN THE CONTRACT DOCUMENTS, INSTALLED AND UNINSTALLED
CONSTRUCTION BEFORE THE ORDERING OF MATERIALS AND EQUIPMENT. NOTIFY
ARCHITECT AND OWNER’S REPRESENTATIVE/COR OF ANY DISCREPANCIES OR
MISSING DIMENSIONS.
12. DO NOT SCALE THE DRAWINGS. DRAWING SCALES AS INDICATED ARE FOR GENERAL
ORIENTATION AND CONTEXT ONLY.
13. THE TERM "ALIGN" MEANS TO INSTALL DIFFERENT/SIMILAR COMPONENTS OF
CONSTRUCTION TO PROVIDE A FLUSH FINISH SURFACE.
14. ALL DIMENSIONS INDICATED ARE TO FACE OF EXISTING MEMBERS, FACE OF NEW
STRUCTURAL MEMBERS, FACE OF NEW MASONRY, FACE OF NEW STUDS OR COLUMN
GRID LINES UNLESS NOTED OTHERWISE.
15. FLOOR ELEVATION 100’-0” IS EQUAL TO THE FINISH FLOOR SLAB OF THE EXISTING
SLAB FLOOR CONSTRUCTION UNLESS OTHERWISE NOTED.
16. ROUGH OPENINGS SHALL ALLOW FOR SHIM SPACE.
17. CONTRACTOR TO PROVIDE WORK WHERE DETAILS AND NOTES ARE IDENTIFIED AS
“TYPICAL” OR “SIMILAR” EACH INSTANCE THAT IS THE SAME IN NATURE TO THE
DETAIL, AREA, OR ITEM REFERENCED.
18. PROVIDED WORK SHALL BE FURNISHED AND INSTALLED BY THE CONTRACTOR.
CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF DELIVERY, MOUNTING,
INSTALLATION, NECESSARY BLOCKING AND ROUGH-IN.
19. INSTALLED WORK IS THE CONTRACTOR INSTALLING OWNER FURNISHED MATERIALS
AND EQUIPMENT. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF MATERIAL
DELIVERY, MOUNTING, INSTALLATION AND ROUGH IN.
20. FURNISHED WORK IS THE CONTRACTOR FURNISHING THE MATERIALS AND
EQUIPMENT TO THE OWNER. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF
DELIVERY AND ROUGH-IN.
21. ALL PROVIDED WORK SHALL BE WITH NEW MATERIALS UNLESS SPECIFICALLY
CALLED OUT AS SALVAGED OR RELOCATED WITHIN THE CONTRACT DOCUMENTS.
22. ALL PERSONS DIRECTLY OR INDIRECTLY ASSOCIATED WITH THE PROJECT SHALL BE
FAMILIAR WITH THE RULES AND REGULATIONS OF THE OCCUPATIONAL SAFETY AND
HEALTH ACT, AND IMPLEMENT THOSE RULES AS THEY APPLY TO THIS PROJECT.
23. THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING AND PROTECTING ALL
UTILITY LINES. LOCATIONS SHOWN ARE APPROXIMATE. REPAIR ALL DAMAGE TO
UTILITY LINES CAUSED BY CONSTRUCTION OPERATIONS AT NO COST TO THE
OWNER.
24. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL TEMPORARY BRACING AND SHORING
REQUIRED DURING CONSTRUCTION.
25. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ADJACENT
CONSTRUCTION, FINISHES, EQUIPMENT, AND TRAVEL ROUTE TO AND FROM THE
CONSTRUCTION SITE. ANY DAMAGE OR UNACCEPTABLE WEAR BY THE
CONSTRUCTION TEAM SHALL BE REPAIRED/REPLACED BY THE CONTRACTOR AT NO
COST TO THE OWNER.
26. IN THE CASE OF CONFLICTS OR DISCREPANCIES WITHIN OR AMONG THE CONTRACT
DRAWINGS, THE BETTER QUALITY, MORE STRINGENT REQUIREMENTS OR GREATER
QUALITY OF WORK, AS DETERMINED BY THE COR, SHALL BE PROVIDED.
27. CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND COORDINATING HARDWARE,
ACCESS CONTROL AND AUTOMATIC OPERATORS ARE PROVIDED WITH COMPLETE
AND COMPATIBLE SYSTEMS REQUIRED FOR THEIR OPERATION. REFER TO DOOR
HARDWARE SCHEDULE, HARDWARE SPECIFICATIONS, AUTOMATIC OPERATOR
SPECIFICATIONS, ACCESS CONTROL SPECIFICATIONS AND ELECTRICAL DRAWINGS.
D DEPTH OR PENNY (NAIL)
D LABEL CLASS D DOOR
DAT DATUM
DB DECIBEL
DBL DOUBLE
DBL GLZ DOUBLE GLAZE
DC DIRECT CURRENT
DEG DEGREE
DEL DELETE
DEMO DEMOLITION
DEPT DEPARTMENT
DET DETAIL
DF DRINKING FOUNTAIN
DIA DIAMETER
DIAG DIAGONAL DIAGRAM OR DIAGRAM DIAGONAL
DIFF DIFFERENCE OR DIFFUSER
DIM DIMENSION
DIR DIRECTION
DISP DISPENSER
DIST DISTANCE
DIV DIVIDE OR DIVISION
DL DEAD LOAD
DOC DOCUMENT
DOZ DOZEN
DN DOWN
DR DOOR, DRAIN, DRESSING ROOM, OR DRIVE
DS DOWNSPOUT
DSGN DESIGN
DW DISHWASHER
DWG DRAWING
DWTR DUMBWAITER
E EAST
EA EACH
EFF EFFICIENCY
EFS EXTERIOR FINISH SYSTEM
EIFS EXTERIOR INSULATION AND FINISH SYSTEM
EJ EXPANSION JOINT
EL ELEVATION
ELAST ELASTOMERIC
ELEC ELECTRIC
ELEV ELEVATOR
EMER EMERGENCY
ENCL ENCLOSURE
ENGR ENGINEER
ENVIR ENVIRONMENT
EPA ENVIRONMENTAL PROTECTION AGENCY
EPDM ETHYLENE PROPYLENE DIENE MONOMER
EPO EMERGENCY POWER OFF
EPS EXPANDED POLYSTYRENE BOARD (INSULATION)
EQ EQUAL
EQL SP EQUALLY SPACED
EQUIP EQUIPMENT
EQUIV EQUIVALENT
ERD EXISTING ROOF DRAIN
ESC ESCAPE OR ESCUTCHEON
ESCAL ESCALATOR
EST ESTIMATE
ETC AND SO FORTH OR ET CETERA
ETS EXPOSE TO STRUCTURE
EW EACH WAY
EWC ELECTRIC WATER COOLER
EWS EYE WASH STATION
EXH EXHAUST
EXIST EXISTING
EXP EXPANSION OR EXPOSED
EXT EXTERIOR, EXTERNAL, OR EXTINGUISHER
F FAHRENHEIT OR FEMALE
FA FIRE ALARM
FAB FABRIC
FAC FACTOR
FACIL FACILITY
FAS FASCIA
FCO FLOOR CLEANOUT
FCTY FACTORY
FD FLOOR DRAIN
FDC FIRE DEPARTMENT CONNECTION
FDTN FOUNDATION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FF FINISH FACE
FF EL FINISH FLOOR ELEVATION
FF&E FURNITURE, FIXTURE, AND EQUIPMENT
FH FLAT HEAD OR FLAT HEAD SCREWS
FHC FIRE HOSE CABINET
FHMS FLAT HEAD MACHINE SCREW
FHP FULL HEIGHT PARTITION
FHWS FLAT HEAD WOOD SCREW
FIG FIGURE
FIL FILLET
FIN FINISH
FIXT FIXTURE
FL FLOORLINE
FLASH FLASHING
FLDG FOLDING
FLEX FLEXIBLE
FLG FLOORING
FLR FLOOR
FLUOR FLUORESCENT
FM FACTORY MUTUAL
FM-G FACTORY MUTUAL GLOBAL
FO FINISHED OPENING
FOC FACE OF CONCRETE OR FACE OF CURB
FOF FACE OF FINISH
FOM FACE OF MASONRY
FOS FACE OF SLAB OR FACE OF STUD
FOUNT FOUNTAIN
FOW FACE OF WALL
FP FIRE PROTECTION OR FIREPROOF
FPM FEET PER MINUTE
FPS FEET PER SECOND
FR FIRE RATING, FIRE RESISTANT, OR FRAME
FR SNK FLUSHING RIM SINK
FREQ FREQUENCY
FRMG FRAMING
FRP FIBER REINFORCED POLYESTER OR FIBERGLASS
REINFORCED PLASTIC
FRZ FREEZER
FS FEDERAL SPECIFICATION
FSTNR FASTENER
FT FEET OR FOOT
FTG FOOTING
FURG FURRING
FURN FURNISH OR FURNITURE
FUT FUTURE
FWC FABRIC WALLCOVERING
GA GAGE OR GYPSUM ASSOCIATION
GAL GALLON
GALV GALVANIC OR GALVANIZED
GALV STL GALVANIZED STEEL
GB GRAB BAR
GC GENERAL CONTRACTOR
GD GUARD
GDR GUARD RAIL
GEN GENERAL OR GENERATOR
GFRC GLASS-FIBER-REINFORCED CONCRETE
GFRG GLASS-FIBER-REINFORCED GYPSUM
GFRP GLASS-FIBER-REINFORCED PLASTIC
GI GALVANIZED IRON
GL GLASS
GLU LAM GLUED LAMINATED WOOD
GR FL GROUND FLOOR
GRAN GRANITE
GRTG GRATING
GSB GYPSUM SHEATHING BOARD
GSM GALVANIZED SHEET METAL
GSU GLAZED STRUCTURAL UNIT
GT GROUT
GUAR GUARANTEE
GUT GUTTER
GYP GYPSUM
H HIGH
H PLAM HIGH PRESSURE PLASTIC LAMINATE
HAZ MAT HAZARDOUS MATERIALS
HB HOSE BIBB
HC HOLLOW CORE
HCWD HOLLOW CORE WOOD DOOR
HDBD HARDBOARD
HDNR HARDENER
HDO HIGH DENSITY OVERLAY
HDR HEADER
HDW HARDWARE
HDWD HARDWOOD
HEPA HIGH EFFICIENCY PARTICULATE AIR (FILTER)
HEX HEXAGON
HF HIGH FREQUENCY
HGR HANGER
HM HECTOMETER OR HOLLOW METAL
HMD HOLLOW METAL DOOR
HMDF HOLLOW METAL DOOR AND FRAME
HMF HOLLOW METAL FRAME
HNDRL HANDRAIL
HO HOLD OPEN
HORIZ HORIZONTAL
HOSP HOSPITAL
HP HIGH PRESSURE OR HORSEPOWER
HS HEAT-STRENGTHENED (GLASS) OR HIGH STRENGTH
HSKPG HOUSEKEEPING
HST HOIST
HT HEIGHT
HVAC HEATING, VENTILATING, AND AIR CONDITIONING
HVY HEAVY
HW HOT WATER
HYD HYDRANT
HYDR HYDRAULIC
I INTERSTATE (HIGHWAY) OR MOMENT OF INERTIA
IAQ INDOOR AIR QUALITY
IBC INTERNATIONAL BUILDING CODE
ID IDENTIFICATION, INSIDE DIAMETER
ID NO IDENTIFICATION NUMBER
ILLUM ILLUMINATION
INCL INCLUDED
IND INDEPENDENT OR INDUSTRIAL
INFO INFORMATION
INSUL INSULATION
INT INTERIOR
INTERCOM INTERCOMMUNICATION
INTL INTERNATIONAL
IRMA INVERTED ROOF MEMBRANE ASSEMBLY
IWH INSTANTANEOUS WATER HEATER
JAN JANITOR
J-BOX JUNCTION BOX
JT JOINT
KD KILN DRIED OR KNOCKED DOWN
KIT KITCHEN
KO KNOCKOUT
KPL KICKPLATE
L ANGLE
LAB LABORATORY
LAD LADDER
LAM LAMINATE
LAM GL LAMINATED GLASS
LAU LAUNDRY
LAV LAVATORY
LBR LUMBER
LBS POUND
LD BRG LOAD-BEARING
LDR LEADER
LED LIGHT EMITTING DIODE
LF LINEAR FEET (FOOT)
LH LEFT HAND
LHR LEFT HAND REVERSE OR LEFT HAND REVERSE
LATENT HEAT RATIO
LIB LIBRARY
LIN LINEAR
LINO LINOLEUM
LIQ LIQUID
LKR LOCKER
LKR RM LOCKER ROOM
LKWASH LOCKWASHER
LL LEAD LINED
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LMST LIMESTONE
LNDSCP LANDSCAPE
LR LIVING ROOM
LRG LARGE
LRV LOUVERED ROOF VENT
LS LUMP SUM
LT LIGHT
LT GA LIGHT GAGE
LT WT LIGHTWEIGHT
LTG LIGHTING
LTNG LIGHTNING
LVD LOUVERED
LVR LOUVER
LWC LIGHTWEIGHT CONCRETE
LWIC LIGHTWEIGHT INSULATING CONCRETE
LYR LAYER
MACH MACHINE
MACH RM MACHINE ROOM
MAINT MAINTENANCE
MAN MANUAL
MATL MATERIAL
MATV MASTER ANTENNA TELEVISION SYSTEM
MAX MAXIMUM
MB MACHINE BOLT
MCB METAL CORNER BEAD
MD DECK
ME MECHANICAL ENGINEER
MEAS MEASURE
MECH MECHANICAL
MECH RM MECHANICAL ROOM
MED MEDICAL MEDIUM OR MEDIUM MEDICAL
MEK METHYL ETHYL KETONE
MEL MELAMINE
MEMB MEMBRANE
MEMO MEMORANDUM
MEZZ MEZZANINE
MF MILL FINISH
MFD MANUFACTURED
MFG MANUFACTURING
MFR MANUFACTURER
MFR REC MANUFACTURER'S RECOMMENDATION
MGT MANAGEMENT
MH MANHOLE
MIC MICROPHONE
MID MIDDLE
MIL STD MILITARY STANDARD
MIN MINIMUM MINUTE OR MINUTE MINIMUM
MIRR MIRROR
MISC MISCELLANEOUS
MIT MITER
MKR MARKER
ML METAL LATH
MLDG MOLDING (MOULDING)
MLWK MILLWORK
mm MILLIMETER
MO MASONRY OPENING OR MOTOR OPERATED
MOD MODEL, MODIFY OR MODULE
MOD BIT MODIFIED BITUMEN
MON MONITOR
MOPR MOP RACK
MR MOISTURE RESISTANT
MS MACHINE SCREW OR MOP SINK
MTD MOUNTED
MTG MOUNTING
MTL METAL
MULL MULLION
MW MICROWAVE
MWP MEMBRANE WATERPROOFING
ARCHITECTURAL SYMBOLS
X
X
XXXX
SHEET LOCATION
VIEW NUMBER
X X
X
SHEET LOCATION
VIEW NUMBER
XXXX
BUILDING SECTION REFERENCE
DRAWING NUMBER
SHEET LOCATION
BUILDING X
XXXX
X
XXXX
ELEVATION REFERENCES
NEW WALL
WALL TO BE
REMOVED
S3A.G
INDICATES STRUCTURAL MATERIAL
INDICATES NOMINAL SIZE
INDICATES STRUCTURE AND FINISH HEIGHTS
INDICATES QUALIFER
EXISTING WALL TO
REMAIN
TEMPORARY IC
BARRIER WALL
CONSTRUCTION
ROOM
ROOM TAG
NEW DOOR
EXISTING DOOR
DEMOLISHED DOOR
SA SUPPLY AIR
SALV SALVAGE
SAMP SAMPLE
SAN SANITARY
SAT SUSPENDED ACOUSTICAL TILE
SATC SUSPENDED ACOUSTICAL TILE CEILING
SB SPLASH BLOCK
SBS STYRENE BUTADIEN STYRENE
SBSTR SUBSTRATE
SC SHADING COEFFICIENT OR SOLID CORE
SCH SCHOOL
SCHED SCHEDULE
SCHEM SCHEMATIC
SCP SCUPPER
SCRN SCREEN
SCT STRUCTURAL CLAY TILE
SCWD SOLID CORE WOOD DOOR
SD SHOP DRAWINGS, SMOKE DETECTOR OR SOAP
DISPENSER
SDG SIDING
SECT SECTION
SEG SEGMENT
SEL SELECT
SEP SEPARATE
SF SQUARE FOOT (FEET)
SFTWD SOFTWOOD
SGD SLIDING GLASS DOOR
SGL SINGLE
SHR SHOWER
SHR HD SHOWER HEAD
SHRD SHOWER DRAIN
SHT SHEET
SHT MTL FLASH SHEET METAL (FLASHING)
SHTHG SHEATHING
SHV SHELVING
SIM SIMILAR
SJ SCORED JOINT
SK SKETCH
SKLT SKYLIGHT
SLD WDW HORIZONTAL SLIDING WINDOW
SLDG SLIDING
SLNT SEALANT
SM SHEET METAL
SMK SMOKE
SND SANITARY NAPKIN DISPENSER
SND INS SOUND INSULATION
S SOUTH
SNDU SANITARY NAPKIN DISPOSAL UNIT
SPEC SPECIFICATION
SPKLR SPRINKLER
SPKR SPEAKER
SPLY SUPPLY
SQ SQUARE
SQ IN SQUARE INCH
SQ YD SQUARE YARD
SS SANITARY SEWER OR SERVICE SINK
SST STAINLESS STEEL
ST STAIRS OR STREET
STC SOUND TRANSMISSION CLASS
STD STANDARD
STIF STIFFENER
STL STEEL
STL LNTL STEEL LINTEL
STL RF DK STEEL ROOF DECK
STL TB STEEL TUBE
STNLS STAINLESS
STOR STORAGE
STR STRINGERS
STRUCT STRUCTURAL
SUB SUBSTITUTE
SURF SURFACE
SUSP SUSPEND
SV SHEET VINYL
SW SWITCH
SWDR SWING DOOR
SYM SYMBOL
SYNTH SYNTHETIC
SYS SYSTEM
T TREAD
TA TOILET ACCESSORY
T&G TONGUE AND GROOVE
T&M TIME AND MATERIALS
TB THROUGH BOLT OR TOWEL BAR
TCA TILE COUNCIL OF AMERICA
TCP TELEPHONE CONTROL PANEL OR TEMPERATURE
CONTROL PANEL OR TRAFFIC CONTROL PLAN
TD TOWEL DISPENSER
TECH TECHNICAL
TEL TELEPHONE
TEMP TEMPERATURE OR TEMPORARY
TER TERRAZZO
THD THREAD
THERM THERMAL
THK THICKNESS
THRES THRESHOLD
THRU THROUGH
THRUOUT THROUGHOUT
TK BD TACKBOARD
TMPD TEMPERED
TN TRUE NORTH
TO TOP OF ___
TO FDN TOP OF FOUNDATION
TOB TOP OF BEAM
TOM TOP OF MASONRY
TOP TOP OF PARAPET
TOS TOP OF STEEL
TOW TOP OF WALL
TPD TOILET PAPER DISPENSER
TPH TOILET PAPER HOLDER
TR TOWEL RACK
TRANS TRANSOM
TRANS WD FIN TRANSPARENT WOOD FINISH
TRTD TREATED
TS TENSILE STRENGTH OR TUBE STEEL
TSTAT THERMOSTAT
TV TELEVISION
TYP TYPICAL
U HEAT TRANSFER COEFFICIENT
UC UNDERCUT
UCD UNDERCUT DOOR
UGND UNDERGROUND
UL UNDERWRITERS LABORATORIES
ULT ULTIMATE
UNFIN UNFINISH
UON UNLESS OTHERWISE NOTED
UPS UNINTERRUPTIBLE POWER SUPPLY
UR URINAL
UTIL UTILITY
UV ULTRAVIOLET
V VOLT
VAC VACUUM
VAR VARIES
VCT VINYL COMPOSITION TILE OR VITRIFIED CLAY TILE
VEH VEHICLE
VENT VENTILATION
VERT VERTICAL
VEST VESTIBULE
VFAT VINYL FACED ACOUSTICAL TILE
VIC VICINITY
VID VIDEO
VIF VERIFY IN FIELD
VNR VENEER
VOC VOLATILE ORGANIC COMPOUND
VOL VOLUME
VOLT VOLTAGE
VP VENEER PLASTER
VR VAPOR RETARDER
VTR VENT THROUGH ROOF
VWC VINYL WALL COVERING
VWF VINYL WALL FABRIC
REVISION TO PLAN CALLOUT
WALLS
DOOR TAG
KEY NOTE TAGS
WALL TAG : REFER TO WALL LEGEND FOR MORE INFORMATION
DOORS
PT-1
A
T
101 EQUIPMENT/FURNITURE TAG
FINISH INDICATION
FRAME / WINDOW
GLAZING1
1 PLAN NOTE
1 DEMOLITION NOTE
ALTERNATE/BID DEDUCT ITEM
KEY NOTE SYMBOLS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
NOT F
OR
CONSTRUCTIO
N
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1
.1
.1
R e n o v a te
A N d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:1
P
M
AE001
ARCHITECTURAL SYMBOLS AND
ABBREVIATIONSGUIDON DESIGN INC.
1221 N. Pennsylvania St.
Suite 200
Indianapolis, Indiana 46202
317.800.6388
RING & DUCHATEAU, LLP.
17400 W. Capital Drive
Brookfield, WI 53045
414.778.1700
RENOVATE 7AN FOR
ENDOSCOPY LAB
5000 W National Ave, Milwaukee, WI 53295
695-19-107
08/21/2020 AWS TAA
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
WALL TYPES LEGEND AND GENERAL NOTES
A. ALL WALLS WILL BE WALL TYPS S3C.G UNLESS OTHERWISE NOTED.
B. ALL WALL TYPE INDICATORS REFER TO THIS SHEET UNLESS OTHERWISE
NOTED.
C. REFER TO DIMENSION PLANS FOR PARTITION TYPE LOCATIONS.
PARTITIONS ARE DISTINGUSHED ON PLANS BY SYMBOL DESIGNATION
GRAPHIC DESIGNATION, OR A COMBINATION OF BOTH.
This is the start of the file's text. The full file is on GovTribe.