About this file

This document outlines a pre-solicitation notice for a federal contract opportunity to renovate space at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The contractor shall demolish existing interior spaces and renovate approximately 11,000 square feet for a relocated GI Procedure Clinic for between $2-5 million. Products and services include construction documents, drawings and specifications to complete mechanical, electrical, plumbing, nurse call, duress, CCTV, medical gas, fire protection and pneumatic tube systems. The North American Industry Classification Code is 236220 and the size standard is $39.5 million. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses and will be posted to beta.SAM.gov on October 15th, with a bid opening of November 16th. The project completion period is 515 calendar days from notice to proceed.

View the file

Other files

File Type Posted
36C25221B0002 0003.docx DOCX document
S06 - ET101 - SEVENTH FLOOR PLAN - TECHNOLOGY - Amd03.pdf PDF
S06 - Appendix E - Physicist Report.pdf PDF
S06 - AE501 - BUILDING DETAILS.pdf PDF
S06 - EP602 - SCHEDULES POWER.pdf PDF
S06 - ET101 - SEVENTH FLOOR PLAN - TECHNOLOGY.pdf PDF
S06 - DG107 - SEVENTH FLOOR MEDICAL GAS PLAN.pdf PDF
S06 - 08 71 13.11 - LOW ENERGY DOOR OPERATORS Amend No2.pdf PDF
S06 - 7AN_ShieldingReport_20200601.pdf PDF
S06 - AE002 - WALL TYPES.pdf PDF
S06 - AE101 - SEVENTH FLOOR ARCHITECTURAL PLAN.pdf PDF
S06 - ET501 - DETAILS - TECHNOLOGY.pdf PDF
S06 - 11 73 00 - CEILING MOUNT PATIENT LIFT Amend No2.pdf PDF
S06 - GC101 - INFECTION CONTROL_PHASING PLAN.pdf PDF
S06 - EP401 - POWER RISERS.pdf PDF
S04 - Site Visit Sign-In Sheet - 695-19-107.pdf PDF
36C25221B0002 0001.docx DOCX document
S02 - Wage Determination Effective 10.2.2020.pdf PDF
S02 - J_A 695-19-107_Door Hardware.pdf PDF
S02 - J_A 695-19-107_HVAC BAS.pdf PDF
S02 - 695-19-107_2020.09.24_Volume 2 Specifications 100percent.pdf PDF
S02 - 695-19-107_2020.09.24_Volume 1 Specifications 100percent.pdf PDF
S02 - J_A 695-19-107_Interior Signage.pdf PDF
S02 - J_A 695-19-107_Firestop Systems.pdf PDF
S02 - 695-19-107 Drawing Set Updated.pdf PDF
S02 - J_A 695-19-107_Medical Gas Systems.pdf PDF
36C25221B0002_1.docx DOCX document
S02 - J_A 695-19-107_Card Readers.pdf PDF
S02 - J_A 695-19-107_Nurse Call.pdf PDF
S02 - J_A 695-19-107_Fire Alarm System.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25221B0002 0002 SF30 Continuation Sheet

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 11/17/2020 695-21-1-6940-0001 695-19-107 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders

36C25221B0002 10-19-2020

X X X November 30, 12:00pm (Noon) Local Time See Continuation Page.

Continue to monitor Contract Opportunities at beta.SAM for any and all changes to this solicitation.

Stacy Hoover Contracting Officer Renovate 7AN for GIGU and Procedure Clinic Clement J. Zablocki VA Medical Center, Milwaukee, WI

I. The following changes are to be made to the solicitation:

a. BID OPENING IS EXTENDED:

1) The virtual bid opening is hereby extended to November 30, 2020.

*Receipt of Bids: Bid submissions are due via email at 12:00pm (Noon) Local Time on November 30, 2020. See block 11 of the SF30.

*The virtual bid opening will be held one hour after the bid receipt deadline. (1:00pm Local Time on November 30, 2020).

2) The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number;

a) https://teams.microsoft.com/l/meetup-join/19%3ameeting_N2NlMTk5MWItNTdlOC00MDZlLWJlY2MtOTRhZjEwODE1Y2M0%40thread.v2/0?context=%7b%22Tid%22%3a%22e95f1b23-abaf-45ee-821d-b7ab251ab3bf%22%2c%22Oid%22%3a%229c720dbb-6d20-4131-baf4-63f37f49469b%22%7d

b) Meeting will be available to be accessed 15 min prior to bid opening.

c) Meeting number (access code): 872-701-0185

d) Conference ID: 580 076 140#

3) IAW FAR 52.214-5 Submission of Bids and FAR 14.202-8 Electronic Bids; Bids shall be provided via email to the Contracting Officer at Stacy.Hoover2@va.gov on or before the date and time specified for receipt of bids. A hard copy submission is not required. Any bids received after the date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999).

4) Ensure your complete bid including bid bond are provided in your submission. The successful low bidder is required to furnish their original bid bond within five (5) days after award notification by the Contracting Officer.

5) It is highly recommended that Bidders submit their bid at least one-hour prior bid receipt deadline (see block 11 of the SF30) to avoid any transmission issues.

II. The following changes are made on project specifications:

1) Specification 08 71 13.11 – this specification was updated to include the requirement that motors be AC brushless type.

2) Specification 11 73 00 – this specification was updated to include the deleting of the integrated scale requirement and the clarification of the emergency manual lowering action.

III. The following changes are made on project drawings:

1) AE002 – Wall Type changes regarding lead lining and General Note A.

2) AE101 – Deletion of Section Detail 2/AE501.

3) AE501 – Deletion of Section Detail 2.

4) EP401 – Revised Keynote 8.

5) EP602 – Updated Equipment Schedule for CWP-7240.

6) ET101 – Additional Nurse Call equipment for Rooms 7205, 7236 and 7244.

7) ET501 – Updated Detail 3.

8) GC101 – Revised Infection Control General Note F.

9) DG107 – Revised tab nomenclature for ZVBs and MGAs.

IV. The following Questions and Answers / Clarifications are the result of bidders request(s) for information received to date:

1. The 117300-specification project calls for a ceiling lift motor with an integrated CLASS III scale that allows users to read weights off the hand control. Can the scale on the proposed motor be of a more standard classification in accuracy? If not, could the level of precision be defined? Also, if it’s found the scales must be CLASS III, do we need to provide pricing for the annual calibration necessary for weight read outs on this level of precision? Industry norms for patient lift scales are set at a notch below this requirement because in most care settings a scale of which to dose medication from (which is often what CLASS III scales are used for in medical practice), aren’t practical and that is the case in this project as well the CLASS III scale, as well as needing to read the weights off the hand control as opposed to anywhere else on the system, seem arbitrary to some extent for salient features. If there is justified reasoning for these, may this information be made available to bidders and vendors as to solidify that this specification is actually open to substitute products and nota a “disguised sole source” if so to speak?

Scales are not required for new ceiling lift equipment in 7AN. The specification has been modified and will be included as part of the Amendment.

2. Could you please tell me if the Presolicitation posted as solicitation number 36C25221B0002 will be a follow-on requirement to any work performed currently or in the past, or will this be a new requirement? If possible, can you please provide the most recent contract or task order number?

This is not a follow-on requirement; there is no recent contract or task order number.

3. Did you get all the bidders for Moving or furniture/finishes you need?

No bids have been received. See block 11 on the SF30 and information above for bid opening information.

4. Should we figure 2/AE501 or wall type F3A.Gi as the typical exterior wall detail? Please advise.

Wall type F3A.Gi will be the typical exterior wall detail. Detail 1/AE501 depicts the deeper exterior wall cavity condition underneath each window. The condition shown on 2/AE501 no longer exists and will be modified by amendment. F3A.Gi will align the finish side of the exterior wall furring with 1/AE501.

5. Please see attached substitution request [Record 8100 Series Door Operators; re: specification section 087113.11]. We are requesting your assistance in gaining approval for this project. Should this need to go elsewhere, please forward. Thank you. We can offer an equivalent operators with our record – USA 8100 Automatic Swing Operators. Along with our Doors being equivalent, we can offer a cost saving bid for all involved parties. We also offer a two-year warranty. We install and service our operators with AAADM certified technicians. Please let me know if you would like anything else for substitution acceptance. Thank you for your time and consideration.).

Equal product must include brushless AC motors and weight capacity of 500 lbs. Please refer to updated Specification 08 71 13.11 in the Amendment. See FAR 52.211-6 BRAND NAME OR EQUAL for submission of equal products.

6. Please provide a Physicist’s Report and Radiation Protection Specifications.

Reports are included. There are no “Radiation Protection Specifications”.

7. Page AE102 general note G defines the unless noted otherwise wall type as S3A.Gi. Page AE002 defines the unless noted otherwise wall type as S3C.G. Please clarify.

Sheet AE002 is incorrect and will be modified by amendment. All wall types to be S3A.Gi UNO as noted on AE102.

8. The loop for the addressable fire alarm devices needs to originate at the fire alarm closet 8B07 on the 8th floor, B-wing. There is no capacity in the existing space.

Agreed. The SLC circuit originating on the 8th floor is addressed in Keynote #4 on Sheet ET102.

9. Could you provide specification information for the nurse call "staff terminals" as identified on drawing ET000 legend and shown on drawing ET101 for rooms 7207, 7230, 7236, and 7244?

The staff terminal is intended to be equal to Jeron model 7927.

10. Are code blue buttons required in Procedure rooms 7236 and 7244?

Yes. Refer to updated drawings, Sheet ET101, reflecting this change.

11. The new Nurse Call cabinet, NCT, in room 7228 requires connection to the Nurse Call Network in room 7128. Are the (3) CAT6 connections to that room part of this project?

Yes, the CAT 6 connection to room 7128 shall be provided as part of this project.

12. Are any Nurse Call devices required in Family toilet room 7204?

No.

13. There is a dome light shown on the outside wall of room 7205 in corridor C7A02 without any call devices attached to it. Is it required?

Yes. Refer to updated drawings, Sheet ET101, reflecting this change.

14. The telecom closet was not available at the time of the walkthrough. Please provide photos of the telecom room including racks, wall fields, ceiling, ladder racking, penetrations & grounding equipment.

VA will no longer be providing pictures of our data/telecom closets to ensure operational security measures are met. Be advised space is available and new infrastructure – if required – will fit.

15. Spec section 270533 lists paging and nurse call as full raceway. Detail ET501/3 depicts J-hooks for paging and nurse call. Please confirm pathway type required.

Full pathway shall be provided to meet specifications. Detail 3 Sheet ET501 to be revised.

16. Spec section 274132 1.1.B describes using existing CATV backbone. 1.1.C describes reusing the existing CATV amplifier. 1.1.D describes new antennas, head-end equipment, etc. New splitting equipment between the amplifier and wall outlet is inherent to scope. Please define any required new antennas or head-end equipment or lightning protection required for this project.

Existing CATV backbone shall be reused and splitting equipment to be expanded as needed to accommodate new outlet quantities.

17. Spec section 274132 3.4.D describes 8 hours of MATC training for operations and performance and 8 hours for preventative maintenance. Please confirm that 16 hours of training is needed for this project.

Provide training in the amount stated in the specification.

18. Spec section 275116 & ET101 Detail Note D describes the speaker equipment as being an extension from an existing system. 255116 4.3.B.1 asks for (4) 1-hour training sessions of the paging system. Since the equipment and methods of paging are all existing, is 1-hour of training required on 4 separate occasions (closer to 8 hours of labor involved)?

Provide training in the amount stated in the specification.

19. Drawing EP300 Siemens drawing note 'A' states "The Electrical contractor shall include all costs associated with the installation of the electrical equipment and raceways indicated on the documents developed by Siemens dated 07/16/2020." Can you provide these drawings?

Siemens drawings are included in the Bid Set; sheet #s 95 through 101.

20. Is it acceptable to utilize Hospital Grade MC Cable for normal power in-wall rough-in where acceptable by NEC?

Per spec, Hospital Grade MC cable is only authorized in these three locations: ceiling whips for lighting (less than 6ft in length); custom furniture or millwork (power/lighting); and for desk lighting/ illumination for built-in, wall-mount furniture. MC cable is not allowed for branch circuits fed from an emergency source.

21. If panel origination matches, is it acceptable to utilize and extend existing circuits/conduit/wiring other than what is shown on the drawings?

No. Intent is to provide new branch circuiting to all new electrical devices in 7AN.

22. Drawing EP102, Note 2 states "Lighting Control Panel Furnished by VA Project 695-19-131. Provide all the necessary components as an expansion to the new system.” Can you provide a manufacturer/model # or cut sheet for this lighting control panel?

No. That project is now just starting construction. VA can provide an approved submittal as soon as it becomes available.

23. Please clarify drawing EP401, Note 8. Do we need to install this equipment as part of this project 695-19-107, or will this equipment be installed by project 695-19-131 electrical contractor?

Note 8 on Sheet EP401 has been revised. Note 8 refers to equipment installed as part of project 695-19-131 (Dialysis). The 7AN/Endoscopy electrical scope of work includes, however, additional components to this equipment.

24. Based on the walk thru, Panel LH-71-1 does not have all spare breakers shown on drawing EP601. There are enough existing breakers to cover the required circuits. Are we to include the correct amount of spare breakers to match the panel schedule shown on EP601?

No. These breakers are shown as existing because they will be provided as part of project 695-19-131 (Dialysis).

25. Drawing EP401, Note 8 shows panels EUL-Q-71-1 and EPH-Q-71-1 to be provided by project 695-19-131. It is more cost effective to order the required breakers with the panels. Will the new circuit breakers 'NCB' shown on drawing EP601 for these panels be provided under project 695-19-131, or should we provide these NCB breakers separately as a part of this project 695-19-017 (Contractor means 695-19-107)?

The new breakers indicated are to be provided as part of project 695-19-107.

26. Drawing EP602 Equipment Schedule shows a weatherproof disconnect for chilled water pump CWP-7240. Since this will be located indoors, is a NEMA 1 disconnect acceptable similar to the hot water pump disconnects?

Disconnect for equipment CWP-7240 can be rated with a NEMA 1 enclosure; Sheet EP602 will be revised in the Amendment.

27. Drawing EP300 shows special purpose outlets SC1 and PU1. These special purpose outlets are not listed in the equipment schedule shown on drawing EP602. Please confirm voltage, load, and type of connection or receptacle.

Special purpose outlets are dedicated to the Siemens equipment. These connections are shown on sheet EP401 and contain voltage, wire, & conduit information needed for equipment connection. Contractor is to confirm final connection requirements with Siemens final site-specific drawings.

28. Ref spec 01 35 26 part 1.7- A full time dedicated superintendent is required to be assigned to the project in addition to a SSHO and QC manager. Per 1.7,F the SSHO and QC manager must remain onsite during construction. Nowhere does the spec require the SSHO or QC manager to be designated only to the project. The spec as written puts the general contractor that is not onsite performing other contracts at a disadvantage due to increase cost for the SSHO and a QC manager which become full time direct costs only on the 7AN project. Other contractors onsite performing other contracts can share the expense which is unfair to other SDVOSB GCs who would like to earn an award for new contracted projects. Can the SSHO and QC manager duties be accomplished by the site superintendent? If not can the full time on site requirement be removed? If not is it possible to change the spec requiring the SSHO /QC manager designated to this specific project full time?

No – Superintendent may NOT perform roles of SSHO and QCM. Supt/QCM can be same person, or SSHO/QCM can be the same person.

No – Requirement for full-time onsite Superintendent will not be removed.

Yes – SSHO and/or QCM can be assigned to other projects (but cannot be assigned as a Superintendent on other projects), however this SSHO must be onsite during construction activities.

29. Ref specification 01 32 16.15 part 1.2- Can the contractor generate and maintain the CPM schedule with their own in house staff or is the contractor required to hire a 3rd party consultant to generate and maintain the schedule for the duration of the project?

Meet specification requirements – that means a 3rd party independent scheduling consultant.

30. Ref spec 09 05 16 part 3.2- Is it the intent to grind and level the entire floor space? Demolition general note L on drawing AD101 requires floor slabs to be filled and leveled. What thickness of floor leveling is required and is it required throughout the space? Will concrete floor infills be required at old clay tile walls?

Yes, the General Contractor is responsible for floor leveling throughout the entire project site (7AN). Note that the project site to the south (7AS/Dialysis) will also be floor leveled (prior to the 7AN/Endoscopy project). Both halves of the 7th floor A-wing, where they meet, should match. Because of significant mortar bed removals (refer to Note 15 AD101) and imperfections in the existing floor, leveling may be 0-inches in some areas and up to two (2) inches in other places. The VA is not aware of any “old clay tile walls”.

31. Ref drawing AD101- Based on site visit various rooms contain stored furniture & furnishings not shown on the drawing. Will the VA remove all stored items prior to project start?

Contractor should expect that loose items will be removed by VA prior to project start.

32. Ref drawing QH101 Eq Schedule- Mark A1001 is shown in room 7249. Similar symbols appear in other prep/recovery rooms. Are there other rooms that require item A1001?

All Prep/Recovery rooms will receive A1001. Details 4/AI204, 9/AI204, and 7/AI205 show the typical location for mounting A1001. Contractor to account for an A1001 in each Prep/Recovery room and coordinate and verify final mounting location with COR.

33. Ref drawing QH101 Eq Schedule and Drawing AI204- Detail 2 on drawingAI204 illustrates a symbol which appears as a clock but not identified with the item #A4015. How many clocks are required?

This symbol is a clock. Coordinate equipment item #A4015 with clock outlets on ET101. There are 22 clocks in this project.

34. Project includes demolition and renovation work in an existing building. Regardless of whether asbestos is present, or whether the scope of work includes asbestos removal, State and Federal law requires a survey for Asbestos Containing Materials (ACM) and Presumed Asbestos Containing Materials (PACM) be completed in accordance with DNR and OSHA requirements. A completed survey report number must be listed on the permit application submitted to the DNR (DNR Notification Form # 4500-113) prior to any demolition. This report can take (30) days or longer to complete and as such may impact the project schedule. Please clarify if this survey has been completed. If not, please indicate whether the Owner will commission said survey or if the bidding contractors will be required to provide by including costs in their bids.

7A is same construction at the same time (original building construction) as identical ward 8A which was renovated 18 months ago. A full hazardous materials survey was conducted on 8A prior to construction/renovation activities. This historical document, use of homogenous materials since constructed at the same time and other internal records for hazardous materials present in Building 111 were utilized to create HA101 and the list/quantities of hazardous materials for this project. There will not be another survey. Bidding contractors will not be required to provide survey cost in their bid.

35. Is detail 2/AE501 is the typical exterior wall detail (with dens) or should it be wall type F3A.Gi?

Wall type F3A.Gi is the typical exterior wall detail. Detail 2/AE501 will be removed.

36. Can we use galvanized sheet metal strapping in lieu of wood blocking and backing?

No. VA prefers fire-treated wood blocking and backing.

37. I have attached product data for an alternate manufacturer for the patient lifts. May these products be substituted?

Equal product must include two specific features: 1) The emergency manual lowering cord needs to be operated in such a way that users can apply continuous pull/downward force to the cord, and it will allow the patient to slowly descend. Additional steps or access to the motor during emergency manual lowering are not equal. 2) The lift motor and hanger bar must be approved for use with Guldmann Repositioning, High Back, Twin Turner and Limb Lifter loop slings. Please refer to updated Specification 11 73 00 in the Amendment. See FAR 52.211-6 BRAND NAME OR EQUAL for submission of equal products.

38. Is the general contractor responsible for the in-wall blocking and backing for the OF/OI furniture systems?

Yes. The GC is in the best position to install blocking for all items, including VA furnished and installed. Coordinate with the COR and review Sheet QH101 as well as items in the 12 59 00 specification.

39. Please confirm contractor is responsible for floor leveling is required for the entire floor surface that is getting demolished.

Yes, the General Contractor is responsible for floor leveling throughout the entire project site (7AN). Note that the project site to the south (7AS/Dialysis) will also be floor leveled (prior to the 7AN/Endoscopy project). Both halves of the 7th floor A-wing, where they meet, should match. Because of significant mortar bed removals and imperfections in the existing floor, leveling may be 0-inches in some areas and up to two (2) inches in other places.

40. Plan page AE111 notes for ‘ceiling mounted booms’. Are these to be provided by contractor? Can they be supported with a typical non-structural frame, or is structural steel required to be tied into the building? Will engineered calculations and drawings be required?

Booms (by Skytron) will be provided by a separate VA contract. General Contractor’s responsibility lies with only structural installation. Installation instructions are provided in the Bid Set per Skytron sheet A1.1. General Contractor is also required to get power, data and medical gasses to the booms per these drawings.

41. Please confirm that items labeled “flurio table” , “tech carts”, etc. on plan page AI202, will be furnished and installed by the VA. No items or labor is required from prime contractors.

Confirmed. Loose items in plan views for all four procedure rooms (7207, 7244, 7230 and 7236) are VA provided and installed. Wall-mount items (receptacles, sinks, desks, millwork, hangers, med gas outlets), including necessary blocking, are the responsibility of the General Contractor.

42. Is prime contractor responsible for furnishing and installing furniture as shown on IF101 and IF102?

Yes. Contact local Herman-Miller furniture representative BSI for a 7AN/Endoscopy bid proposal. It is the responsibility of the General Contractor to have this furniture installed. BSI may provide an installation cost as well. 262-955-6400; W222 N630 Cheaney Rd, Waukesha, WI 53186.

43. Please confirm if the work on 6th floor is going to be off hours due to it being an occupied space?

Work on the 6th floor – in each sub-phase – can be during regular working hours once COR approves workplan and infection control plan. In each of the General Contractor’s seven sub-phases (refer to Note B Sheet AD101), the VA will vacate and move personnel out so that Contractor has complete access for above ceiling work. This is addressed in the DEMOLITION GENERAL NOTES on Sheet AD101 and REFLECTED CEILING DEMOLITION PLAN GENERAL NOTES on Sheet AD102. Note F on GC101 has also been revised. The only work that must be off shift is work associated with outages.

44. There are ‘Skytron’ drawings included on the contract documents. Are these for reference only? Or is prime contractor to furnish and install the equipment according to these plans? What are the structural steel requirements for this equipment?

The General Contractor will be installing the structural portion only of Skytron boom equipment. This includes structural work to the concrete deck above. VA will provide and install booms via separate contract method. Refer to Skytron sheet A1.1 for structural installation instructions.

45. There are ‘guldmann’ drawings provided in the contract documents. Are these for reference only? Or is prime contractor to furnish and install the equipment according to these plans? Is this sole sourced?

No, Guldmann drawings are not for reference only. Yes, the Prime Contractor shall furnish and install the equipment according to these drawings. No, Guldmann ceiling lifts are not sole sourced. See FAR 52.211-6 BRAND NAME OR EQUAL for submission of equal products.

46. AE002 Detail 1 – references ‘lead lined schedule’. We don’t see a lead lined schedule in the specs or drawings, can this be provided?

Refer to Sheet AE502 for lead shielding details; there is no schedule. All lead-lined walls will receive 1/32nd-inch lead lining. Sheet AE002 has been revised. Additionally, radiation shielding reports and physicist reports are included in addition to these answers.

47. Please provide sizes for the furniture schedule. For example – what size markerboards, chalkboards, tackboards, etc.

There are no chalkboards or tackboards. Markerboards will be provided per design expectations with proposal from sole-sourced furniture provider Herman-Miller local representative (BSI). See response to Question # 42.

48. On AE111, room 7233 Prep/Recovery Room does not show a curtain system, is there supposed to be one in this room? For all areas, is the GC supposed to supply the curtain fabric?

Room 7233 does not get a curtain system. Review the door schedule Sheet AE601. This room will utilize door and frosted glass in lieu of curtain system. For all other curtain areas as shown in the drawings, the General Contractor is responsible for providing the curtain track system and the curtain fabric. See Specification section 10 21 23 and Specification section 01 01 10-SN page 22. Basis of Design for curtain track systems shall be Barrier-Free Curtain Track Rail Support System (CTRSS). Contact them direction for a proposal.

49. Is the pneumatic tubing system to be sole sourced?

Current system at hospital is SwissLog/Translogic. Equal products must align seamlessly with hardware and software (without need for outages for programming or work outside 7AN) in Building 111. See FAR 52.211-6 BRAND NAME OR EQUAL for submission of equal products.

50. Please confirm that the superintendent appointed to this project shall be only overseeing this project in its entirety. Please also confirm if there are (2) separate individuals needed to perform the work, one for the SSHO and one being the superintendent?

This project’s Superintendent shall oversee as Superintendent this project only. The Superintendent shall be employed by the General Contractor. Yes, a second and separate individual shall be also assigned by the General Contractor to act at the project’s SSHO. The SSHO shall be employed by the General Contractor. The SSHO and Superintendent may not be the same individual.

51. Is the demolition and abatement scope of work to be performed on OT due to noise constraints? Also, General Note B stated (7) sub phases. Is this for the work on the floor below only? Or is this assumed for the full demolition scope of work.

Demolition activities may commence during regular working hours. However, COR reserves the right to stop work for noise or vibration issues at any time. Contractor will then be responsible for shifting work hours earlier or later with COR approval. Refer to Bid Set Sheet GC101 Note H regarding work that is known to be very noisy or cause excess vibrations. Regular hours of work are defined in Specification section 01 01 10-SN paragraph 3.20. Regarding noise/vibration: please also refer to Specification section 01 00 00 paragraph 1.6E and Specification section 01 01 10-SN paragraph 3.26.

General Contractor shall bid seven (7) sub-phases of work on the 6th floor for plumbing and HVAC piping demolition, relocation and new work. After workplan and infection control plans for all seven (7) sub-phases are approved, the General Contractor can work unencumbered in unoccupied sub-phases on the 6th floor during regular working hours. Outages, however, must be completed off shift. Note F on GC101 has been revised. The only work that must be off shift is work associated with outages. Demolition on the 7th floor can be completed in one phase, coordinated of course with hazardous materials abatement activities.

52. Please confirm floor slab thickness of existing deck.

10”-13” thick slab per existing VA drawings 111-S 31 March 26, 1967.

53. Keynote CC Under General notes on plan page AI201 note “provide and install slat blinds at all exterior windows within scope.” Please confirm quantity / specification for this note.

General Contractor shall provide slat blinds at all exterior windows on the project. Refer to Specification section 12 24 00.

54. Per the equipment schedule on QH201, it notes “VFCI” for a few items. Where would the prime contractor receive these items? Do we need to account for unloading / uncrating after delivery of these items?

VA will provide these items to the 7th floor at a time convenient to both the General Contractor and the VA. The General Contractor does not need to account for any unloading or uncrating after delivery.

55. There is a fixed furniture specification. Is prime contractor to provide all furniture ‘Herman Miller Furniture’ type system? Or will this be by a separate contract?

General Contractor is responsible for providing (furnish and install) all fixed furniture per contract drawings and specifications. Contact local Herman-Miller furniture representative BSI for a 7AN/Endoscopy bid proposal which may or may not include delivery and installation. 262-955-6400; W222 N630 Cheaney Rd, Waukesha, WI 53186.

56. Please confirm the intent of the ACT scope on the 6th and 7th floor. Are we to remove the ceiling, grid, etc. in its entirety and re-install new?

The 7th floor A-wing North is a full remodel with a completely new ceiling. Work on the 6th floor includes only plumbing, piping and associated MEP/FP work above existing ceiling to support the new layout on the 7th floor. The Contractor is responsible for temporary ceiling demo on the 6th floor (sub-phases 1 through 7), protection of ceiling materials, and re-installation of the existing ceiling tiles and grid each evening and at the conclusion of each sub-phase. The VA does not desire new ceiling grid or tiles on the 6th floor unless the General Contractor damages or misplaces existing ceiling materials; in which case, the General Contractor is responsible for all new celling materials for the 6th floor.

57. Please confirm work hours for the project.

Regular hours of work are defined in Specification section 01 01 10-SN paragraph 3.20. Please also refer to Bid Set Sheet GC101

58. Please provide 6th floor and 7th floor As-Builts?

These as-builts are not available pre-bid, but additional documentation will be made available (as well as DWG/REVIT files of the construction drawings) to the General Contractor awarded the contract. Information has been provided in the construction documents to allow for bidding of the work required as part of this contract.

59. What are the infection control requirements for work in corridor outside of scope of work?

Infection Control (IC) requirements are defined in Specification section 01 35 26 paragraph 1.12. The General Contractor must meet IC requirements at every work location, regardless of the proposed IC as noted in the construction drawings. For work outside of the main project area (7AN) – including corridor work and the sub-phase work on the 6th floor – the General Contractor shall prepare an IC plan for VA Approval to achieve proper control of dust and construction debris. The VA will review the General Contractor’s plan and approve or reject based on the Infection Control requirements listed in Specification section 01 35 26 paragraph 1.12.

Note: the sub-phase work on the 6th floor will be allowed to take place behind properly installed IC plastic to include negative air machines and other IC prevention measures as outlined in each ICRA permit.

Work in the corridor may be proposed as well behind IC plastic or “shark tanks” (minty) depending on duration of the work.

60. Please confirm the VA is responsible for hiring the CxA?

The VA will contract separately with an outside entity to act as the Commissioning Agent. The General Contractor shall coordinate all activities and requirements between his sub-contracted MEP/FP contractors and the Commissioning Agent.

61. Per spec 01 35 26.1.7, do the employees designated for Superintendent, Site Safety and Health Officer (SSHO), and Quality Control Manager need to be employees of the General Contractor?

Yes.

62. Per spec 01 35 26.1.7.A, confirm the Superintendent designated for this project cannot supervise any other contracts on the VA campus.

Confirmed.

63. Per spec 01 35 26.1.7.A, confirm Superintendent may not perform any subcontractor competent person’s duties.

Confirmed.

64. Per spec 01 35 26.1.7, can the Superintendent perform a dual role as the SSHO and Superintendent?

No.

65. Please confirm that non-destructive examination of the piping welds as described in specification section 23 22 13, page 14, item “H” is a requirement for this project for the steam and condensate piping.

Confirmed.

66. Clarify who is responsible for motor controllers for HVAC equipment.

The General Contractor is responsible for providing all equipment. Coordinate with your sub-contractors.

67. Per Section 01 32 16.15, is a third-party scheduling consultant required on this project?

Yes.

68. Is the contractor required to clean all ducts including existing ductwork?

All existing ductwork is being demolished. An entire new system is being installed for 7AN only. There is no connection to existing ductwork. Therefore, there is no duct cleaning required on existing ductwork.

69. Can paint be sprayed on? Section 09 91 00 says spray application only upon approval from COR in writing.

No.

70. Detail 20 on AI201 shows countertops and brackets at the typical nurse’s station but there is nothing shown on the plan view or any of the elevations. Please provide the length of these countertops and verify locations (are these only at reception 7202 / Waiting 7200?).

These workstations are located in Corridor C7A04 between 7245/7247, between 7243/7241, and between 7233/7235. See elevation tag for 20/AI201 on AE101 for typical location. Dimensions of these spaces can be found on AE102.

71. On AI204 Detail 2, there appears to be a depiction of an electrical clock but no call out. Please confirm if this is an electric clock.

This symbol is a clock. Coordinate equipment item #A4015 with clock outlets on ET101. There are 22 clocks in this project.

72. On AI203 Detail 3, there appears to be a A1003 Wall Mounted Lead Apron Rack. Please verify.

Verified.

73. Is there a countertop in the control room?

Yes.

74. Are there countertops located between the prep rooms at the V Shaped walls?

Yes, see elevation 20/AI201 and corresponding section at 3/AI501. Dimensions to this space can be found on AE102. See also answer to question number 70.

75. Is any built-in casework needed at the Soiled Utility Room?

Yes, refer to the drawings.

76. Is furniture going to be removed prior to our occupancy of the space?

Yes.

77. Is Guldmann sole sourced for patient lifts?

No. Guldmann is the Basis of Design. Refer to Question/Answer #1, #37 and #45.

78. The GUL drawings say 10’-0”, but sheet GC101 suggests 12’-0” to the deck. Could you please confirm the correct deck height?

VA disagrees with your assertion that Sheet GC101 suggest 12’-0” to the deck. Deck height is 10’-0”.

79. Sheet AE002, wall type F3A.Gi shows a 3-5/8” stud wall. However, cuts 1 & 2/AE501 shows a 6” stud at the exterior walls. What it the correct thickness of these walls?

6” studs will be required under the windows where the existing fan coil units are being removed. The typical wall furring at the existing walls will be 3-5/8” stud. Detail 1/AE501 is accurate to show the typical condition under the windows. Detail 2/AE501 is incorrect and will be removed.

80. What are the dimensions of the exterior windows (1/AE501)?

Typical existing windows are 5’-7” tall x 3’-8” wide.

81. Please verify that all loose furniture, equipment and sharps will be removed from the work area prior to the start of construction.

Verified.

82. Has the VA tested the ductwork and mechanical systems scheduled for demolition or relocation for biohazards?

No. The ductwork and mechanical systems scheduled for demolition have not served processes, procedures, or medical work that produced biohazards.

83. Clarify who is responsible for motor controllers for HVAC equipment.

The General Contractor is responsible for providing all equipment. Coordinate with your sub-contractors. Refer to Question/Answer #66.

84. Reference 01 32 16.15.1.3: Does the contractor need to hire a third-party scheduling consultant for this project?

Yes.

85. There are multiple references to LEED requirements in the specifications. Do the LEED requirements apply to this project?

No.

86. Is there any existing duct work that needs to be cleaned as part of this project?

No. Refer to Question/Answer #68.

87. Per Section 07 84 00, is the contractor required to hire a 3rd party fire penetration inspector?

Yes.

88. IC Plan Note 3 on Sheet GC101 indicates to modify existing partitions to make 1-HR rated walls. Are the existing partitions drywalled on both sides of the studs to the deck? Are pictures of the existing partitions available to help determine the level of effort required to make these 1-HR partitions?

By the time this contract begins, the existing partitions between 7AS and 7AN will have been returned to 1-hour fire-rating by the Dialysis construction General Contractor. Coordinate with the VA and the Dialysis GC if questions exist regarding the 1-hour fire-rated construction barrier.

89. Does the General Contractor need to supply & install wall blocking for the office furniture per plan pages IF101 & IF102?

Yes.

90. Sheet QH101Equipment Schedule indicates CFCI for M0506 Samsung 4K TV. What is the model number of the TV required?

Provide model number: QN32Q50RAFXZA or similar. Submittal of selected tv to be installed is required.

91. Can the SSHO and the superintendent be the same person?

No.

92. There is Patcraft carpet tile on the finish schedule but none called out on the room finish schedule. Is carpet tile needed for this project?

No carpet is needed on the project. The finish schedule will be revised in the Amendment.

93. Further clarification is required clarifying which rooms are to receive 550 lbs. Hoist and which rooms are to receive 770 lbs. BARIATRIC Hoist per DIV 11.73.00 spec. Otherwise we have no way of knowing what quantity of each to include on this project. There are not labels on the room drawings designating Bariatric Rooms and thus 770 lbs. capacity to be utilized.

Bariatric lifts are required in the following locations: 7207, 7230, 7233 and 7233A.

94. Is there a construction schedule, or is the project still going through the approval and planning process? Are plans on hold for any reason? Who is the architect? Who will be the project's general contractor?

There is no construction schedule at this time. The plans are not on hold. The architect is Guidon Design, Inc. The contract has not been awarded; there is no general contractor at this time.

95. I received a message from another contractor stating that an amendment came out in regards to the above reference project. I can download the amendment from the contractor, but on beta I never received a notification, nor are there any documents on beta. The only attachment on beta is the presolication. Thanks.

Solicitation 36C25221B0002 (and all project documents) has been published on beta.SAM.gov https://beta.sam.gov/opp/ffd738e01cfe4739b724e4586ec78252/view?index=opp&sort=-relevance&page=1&keywords=36c25221b0002&date_filter_index=0&inactive_filter_values=false Contact the Federal Service Desk at: 866-606-8220 for beta.SAM.gov assistance.

96. Please confirm what time bids need to be turned in. If I was to email our bid at 12:55PM CST would you still accept it? May I suggest having bids due at 1:00PM CST for All Contractors, then, bids be publicly opened at 2PM CST? Otherwise, All bids due at Noon, then, be publicly announced at 1PM.

See block 11 of the SF30 and information above.

97. I was informed you are the point of contact regarding this project and I would certainly like to provide you or the correct person with our medical gas quote for the scope in this project. Please let me know if there is someone else I should be speaking with and I will be happy to do so.

All subcontractors wishing to participate in the project shall furnish proposals to SDVOSB firms intending to provide bids.

V. GENERAL INFORMATION:

None

See attached document: S06 - 7AN_ShieldingReport_20200601.

See attached document: S06 - 08 71 13.11 - LOW ENERGY DOOR OPERATORS Amend No2.

See attached document: S06 - 11 73 00 - CEILING MOUNT PATIENT LIFT Amend No2.

See attached document: S06 - AE002 - WALL TYPES.

See attached document: S06 - AE101 - SEVENTH FLOOR ARCHITECTURAL PLAN.

See attached document: S06 - AE501 - BUILDING DETAILS.

See attached document: S06 - Appendix E - Physicist Report.

See attached document: S06 - DG107 - SEVENTH FLOOR MEDICAL GAS PLAN.

See attached document: S06 - EP401 - POWER RISERS.

See attached document: S06 - EP602 - SCHEDULES POWER.

See attached document: S06 - ET101 - SEVENTH FLOOR PLAN - TECHNOLOGY.

See attached document: S06 - ET501 - DETAILS - TECHNOLOGY.

See attached document: S06 - GC101 - INFECTION CONTROL_PHASING PLAN.